RAISING THE ROOF.

Herr Brenner, the engineer of the Erdberg Works, gives a description of how

the roof of a house, 54.6 meters wide, for a gasholder in Berlin, was

raised to a height of 22 meters. In that instance the iron structure was

put together at the bottom of the tank, leaving the rafter ends and the

mural ring. The hoisting itself was effected by means of levers--one to

each rafter--connected with the ironwork below by means of iron chains. At

the top there were apertures at distances of about 26 mm. from each other,

and through these the hoisting was proceeded with. With every lift, the

iron structure was raised a distance of 26 mm.

[Illustration: FIG. 2.]

Herr Brenner had considerable hesitation in raising in the same way the

structure at Erdberg, which was much larger and heavier than that in

Berlin. The simultaneous elevation to 48 meters above the level, proposed

to be effected at forty different points, did not appear to him to offer

sufficient security. He therefore proposed to put the roof together on the

ground, and to raise it simultaneously with the building of the wall;

stating that this mode would be perfectly safe, and would not involve any

additional cost. The suggestion was adopted, and it was found to possess,

in addition, the important advantage that the structure could be made to

rest on the masonry at any moment; whereas this had been impossible in the

case at the Berlin Gasworks.