HOISTING.

At a given signal from the foreman, two operatives, stationed at each of

the forty lifting points, with crowbars inserted in the holes provided for

the purpose, give the screws a simultaneous turn in the same direction. The

bars are then inserted in another hole higher up. The hoisting screws are

connected with the structure of the roof, and rise therewith. All that is

requisite for the hoisting from the next cross beam is to give a forward

turn to the screws. When the workmen had become accustomed to their task,

the hoisting to a distance of 1 meter occupied only about half to

three-quarters of an hour. At the outset, and merely by way of a trial, the

roof was lifted to a height of fully 2 meters, and left for some time

suspended in the air. The eighty men engaged in the operation carry on the

work with great regularity and steadiness, obeying the signal of the

foreman as soon as it was given.