CONCRETE LINING.

The placing of concrete inside the iron tube was done by an organization

entirely separate from the tunneling force. A mixing plant was placed in

each of the five shafts. The stone and sand bins discharged directly

into mixers below, which, in turn, discharged into steel side-dump

concrete cars. All concrete was placed in normal air.

The first step, after the iron lining was scraped clean and washed down

and all leaks were stopped, was the placing of biats, marked _B_ on

Plate LXXIV. These were made up of a 6 by 12-in. yellow pine timber, 17

ft. long, with two short lengths of the same size spliced to its ends by

pieces of 12-in. channels, 3 ft. 9 in. long, clamped upon the sides.

These biats were placed every 5 ft. along the tunnel in rings having

side keys. Next, a floor, 13 ft. wide, was laid on the biats and two

tracks, of 30-in. gauge and 6-1/2-ft. centers, were laid upon the floor.

There were three stages in the concreting. Fig. 2, Plate LXXIV, shows

the concrete in place at the end of the first, and Fig. 3, Plate LXXIV,

at the end of the second stage. The complete arch above the bench walls

was done in the last operation.

Two 3 by 10-in. soldiers (_SS_ in Figs. 1 and 2, Plate LXXIV) were

fastened to each biat and braced across by two horizontal and two

diagonal braces. To each pair of soldiers a floor template, _T_, was

then nailed. The form for the center drain was then suspended as shown

in Fig. 1, Plate LXXIV. Three pieces of shuttering, _FFF_, 20 ft. long,

were then nailed to the bottom of the soldiers. One is all that would

have been needed for the first concrete placed, but it was easier to

place them at this stage than later, when there was less room. Three

rough shutters were also nailed to the curved portion for the floor

template. Opposite each biat, a bracket, _bb_, was then nailed, which

carries a set of rough boards which formed the risers for the duct

steps. Everything was then ready for concreting except that, where

refuge niches occurred, a form for the portion of the niche below the

seat was nailed to the shuttering. This form is shown at _R_ in Fig. 1,

Plate LXXIV.

[Illustration: PLATE LXXIV]

The concrete was dumped down on each side from side-dump cars standing

on the track, and, falling between the risers for the duct steps, ran or

was shoveled under the forms and down into the bottom. The horizontal

surface on each side the center drain was smoothed off with a shovel.

The workmen became very skillful at this, and got a fairly smooth

surface. This concrete was usually placed in lengths of 45 or 60 ft.

After setting for about 24 hours, the brackets, _bb_, were removed,

together with the shuttering on the steps. The triangular pieces, _t_ in

Fig. 1, Plate LXXIV, were not removed until later. Instead, a board was

laid upon this lower step on which the duct layers could work. This and

the triangular piece were not removed until just before the bench

concrete was placed. This was important, as otherwise the bond between

the old and new concrete would be much impaired by dirt ground into the

surface of the old concrete. The ducts were then laid, as shown in Fig.

2, Plate LXXIV.

The remaining shutters for the face of the bench walls were then placed.

The remainder of the forms for the refuge niches, _RR_, in Fig. 1, Plate

LXXIV, were nailed to the shutters, the steel beam over the niche was

laid in place, the forms for the ladders, _L_ in Fig. 2, Plate LXXIV,

which occur every 25 ft., were tacked to the shutters, the shutters and

forms were given a coat of creosote oil, and then all was ready for

placing the bench concrete.

The specifications required a 2-in. mortar face to be placed on all

exposed surfaces and the remainder to be smoothed with a trowel and

straight-edge. After about 48 hours, the biats were blocked up on the

bench, and all forms between the bench walls below the working floor

were removed.

The centering for the arch concrete consisted of simple 5 by 3-1/2 by

5/16-in. steel-angle arch ribs, curved to the proper radius, spaced at

5-ft. intervals. Each rib was made up of two pieces spliced together at

the top. Two men easily handled one of these pieces. After splicing, the

rib was supported by four hanger-bolts fastened to the iron lining as

shown in Fig. 3, Plate LXXIV.

In the early part of the work, two additional bolts were used about half

way up on the side between the upper and lower hanger-bolts. It was soon

found that by placing the strut between the tunnel lining and the crown

of the rib, these hanger-bolts could be dispensed with. The lagging was

of 3-in. dressed yellow pine, 12 in. wide, and in 15-ft. lengths. Each

piece had three saw cuts on the back, from end to end, allowing it to be

bent to the curve of the arch; it was kept curved by an iron strap

screwed to the back. The arches were put in, either in 15, 30 or 45-ft.

lengths, depending on what was ready for concrete and what could be done

in one continuous working. The rule was that when an arch was begun, the

work must not stop until it was finished. An arch length always ended in

the middle of a ring. The lagging was placed to a height of about 6 ft.

above the bench before any concreting was done. When the concrete had

been brought up to that point, lagging was added, one piece at a time,

just ahead of the concrete, up to the crown, where a space of about 18

in. was left. When the lagging had reached the upper hanger-bolts, they

were removed, which left only the two bottom bolts fixed in the

concrete. Most of these were unscrewed from the eye and saved, as tin

sleeves were placed around them before concreting. Two cast-iron eyes

were lost for every 5 ft. of tunnel. To place the key concrete, a stage

was set up in the middle of the floor, and, beginning at one end, about

2 ft. of block lagging was placed. Over this, concrete was packed,

filling the key as completely as possible. This was done partly by

shoveling and using a short rammer, and partly by packing with the hands

by the workmen, who wore rubber gloves for the purpose. Another 2 ft. of

lagging was then placed, and the operation was repeated, and thus

working backward, foot by foot, the key was completed. This is the usual

way of keying a concrete arch, but in this case the difficulty was

increased by the flanges of the iron lining. It was practically

impossible to fill all parts of the pockets formed by these flanges. To

meet this difficulty, provision was made for grouting any unfilled

space. As the concrete was being put in, tin pipes were placed with

their tops nearly touching the iron lining, and their bottoms resting on

the lagging. Each pocket was intended to have two of these pipes, one to

grout through and the other to act as a vent for the escape of air. Each

center key ring had six pipes, and each side key had eight. The bottoms

of the pipes were held by a single nail driven half way into the

lagging. This served to keep the pipes in position and to locate them

after the lagging was taken down.

The cost of labor in the tunnels directly chargeable to concrete was

$1.80 per cu. yd. The top charges, exclusive of the cost of materials

(cement, sand, and stone), amounted to $3.92.

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The East River Tunnels. Paper No. 1159 · 第 34 / 35 题