SUMP AND PUMP CHAMBERS.

To take care of the drainage of the tunnels, a sump with a pump chamber

above it was provided for each pair of tunnels. The sumps were really

short tunnels underneath the main ones and extending approximately

between the center lines of the latter. They were 10 ft. 9-1/2 in. in

outside diameter and 44 ft. long. The water drops directly from the

drains in the center lines of the tunnels into the sumps. Above the

sumps and between the tunnels, a pump chamber 19 ft. 5 in. long was

built. Above the end of the latter, opposite the sump, a cross-passage

was constructed between the bench walls of the two tunnels. This passage

gives access from either tunnel through an opening in the floor to the

pump chamber and through the latter to the sump.

From the preliminary borings it was thought that the sumps were located

so that the entire construction would be in rock. This proved to be the

case on Tunnels _C_ and _D_, but not on Tunnels _A_ and _B_. The

position of the rock surface in the latter is shown by Fig. 3. After the

excavation was completed in Tunnel _B_, January 1st, 1908, the plates

were removed from the side of the tunnel at the cross-passage, and a

drift was driven through the earth above the rock surface across to the

lining of Tunnel _A_. The heading was timbered as shown by Fig. 3. There

was practically no loss of air from the drift, but the clay blanket had

been removed from over this locality and the situation caused some

anxiety. In order to make the heading as secure as possible, the 24-in.

I-beams, shown on Fig. 3, were attached to the lining of the two

tunnels. The beams formed a support for the permanent concrete roof arch

of the passage, which was placed at once. At the same time plates were

removed from the bottom in Tunnel _B_ over the site of the sump, and a

heading was started on the line of the sump toward Tunnel _A_. As soon

as the heading had been driven beyond the center line of the pump

chamber, a bottom heading was driven from a break-up westward in the

pump chamber and a connection was made with the cross-passage. The iron

lining of the pump chamber was next placed, from the cross-passage

eastward. The soft ground was excavated directly in advance of the

lining, and the ground was supported by polings in much the same manner

as described for shield work. On account of bad ground and seams of sand

encountered in the rock below the level of the cross-beams, the entire

west wall of the pump chamber was placed before enlarging the sump to

full size. This was also judicious, in order to support as far as

possible the iron lining of the tunnels. The sump was then excavated to

full size. The iron lining of the sump and the east wall of the pump

chamber were placed as soon as possible. The voids outside the iron

lining of the sump and the pump chamber were filled as completely as

possible with concrete, and then thoroughly grouted. Finally, the

concrete lining was put in place inside of the iron.

As shown by Fig. 3, the excavation of these chambers left a considerable

portion of the iron lining of the tunnels temporarily unsupported on the

lower inner quarter. To guard against distortion, a system of diagonals

and struts was placed as shown.

The floor of the pump chamber was water-proofed with felt and pitch in a

manner similar to that described for the caissons at Long Island City.

It was not possible to make the felt stick to the vertical walls with

soft pitch, which was the only kind that could be used in compressed

air, and, therefore, the surfaces were water-proofed by a wall of

asphalt brick laid in pitch melting at 60 deg. Fahr. Forms were erected on

the neat line, and the space to the rock was filled with concrete making

a so-called sand-wall similar to that commonly used for water-proofing

with felt and pitch. The bricks were then laid to a height of four or

five courses. The joints were filled with pitch instead of mortar.

Sheets of tin were then placed against the face of the wall and braced

from the concrete forms. As much pitch as possible was then slushed

between the brick and the sand-wall, after which the concrete in the

main wall was filled up to the top of the water-proofing course. The tin

was then withdrawn and the operation repeated. This method was slow and

expensive, but gave good results. Ordinary pitch could not be used on

account of the fumes, which are particularly objectionable in

compressed air. The 60 deg. pitch was slightly heated in the open air before

using.

[Illustration: FIG. 3.]

The sump and pump chamber on Tunnels _C_ and _D_ differed from the one

described only in minor details; but, being wholly constructed in rock,

presented fewer difficulties and permitted a complete envelope of

water-proofing to be placed in the top.

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The East River Tunnels. Paper No. 1159 · 第 33 / 35 题