LINE C, MANHATTAN.

--------------+-----------------+-------------------+-------------------------+

| | Station: | Date: |

| |---------+---------+------------+------------+

| | | | | |

Material. | Method. | From | To | From | To |

--------------+-----------------+---------+---------+------------+------------+

{|Top heading |107+79.03|107+69 |Dec. 20, '04|Dec. 27, '04|

{|Top heading |107+69 |107+23 |Jan. 1, '05|Jan. 15, '05|

Rock {|Excavating bench |107+79 |107+23 |Jan. 21, '05|Feb. 28, '05|

{|Bottom heading |107+23 |106+72 |Mar. 1, '05|Mar. 11, '05|

{|Bottom heading |107+23 |107+15 |Oct. 12, '05|Oct. 27, '05|

{| | | | | |

| | | | | |

Rock |Bottom heading |107+15 |106+62 |Nov. 6, '05|Dec. 2, '05|

| | | | | |

| | | | | |

Mixed |Bottom heading |106+62 |106+55 |Dec. 2, '05|Dec. 23, '05|

| | | | | |

| | | | | |

Mixed |Bottom heading |106+55 |106+17 |Feb. 12, '06|Mar. 22, '06|

| | | | | |

Mixed |Rock cut |106+17 |105+85 |Apr. 2, '06|Apr. 20, '06|

| | | | | |

Mixed |Rock cut |105+85 |105+55 |July 27, '06|Aug. 26, '06|

| | | | | |

| | | | | |

Earth |Breasting and |105+55 | 99+40 |Aug. 26, '06|Jan. 2, '07|

| poling | | | | |

| | | | | |

Mixed |Rock cut | 99+40 | 98+70 |Jan. 2, '07|Feb. 6, '07|

| | | | | |

Rock |Full face | 98+70 | 98+60 |Feb. 6, '07|Feb. 12, '07|

| | | | | |

Mixed |Bottom heading | 98+60 | 98+39 |Feb. 12, '07|Mar. 6, '07|

| | | | | |

Rock |Bottom heading | 98+39 | 98+17 |Mar. 6, '07|Mar. 15, '07|

| | | | | |

Mixed |Rock cut | 98+17 | 95+68 |Mar. 15, '07|July 30, '07|

| | | | | |

Rock |Middle heading | 95+68 | 94+61 |July 30, '07|Aug. 21, '07|

| | | | | |

Mixed |Rock cut | 94+61 | 93+56 |Aug. 21, '07|Oct. 3, '07|

| | | | | |

Rock |Middle heading | 93+56 | 92+73 |Oct. 3, '07|Nov. 11, '07|

| | | | | |

Mixed |Rock cut | 92+73 | 90+55 |Nov. 11, '07|Feb. 13, '08|

| | | | | |

Mixed |Rock cut | 90+55 | 90+44.4 |Feb. 25, '08|Mar. 3, '08|

--------------+-----------------+---------+---------+------------+------------+

--------------+------+--------+--------+--------------------------------------+

| | |Rate of | |

|Number| |progress| |

| of | Linear |in feet | |

Material. | days.| feet. |per day.| Remarks |

--------------+------+--------+--------+--------------------------------------+

{| 7} | | {|Stopped to brace portal. No work done |

{| 14} | | {|from March 12th to October 11th, 1905,|

Rock {| 38} | 54 | 0.77 {|except a little trimming in September.|

{| 10} | | {|All work up to this date done in |

{| 15} | | {|normal air. Heading advanced to 106+70|

{| } | | {|and bulkheaded. |

| | | | |

Rock | 26 | 53 | 2.04 | |

| | | | |

| | | {|Heading advanced to 106 + 40. Shut |

Mixed | 21 | 7 | 0.33 {|down in order that Line D might have a|

| | | {|lead. |

| | | | |

Mixed | 38 | 38 | 1.00 {|Shut down on account of air shortage. |

| | | | |

Mixed | 18 | 32 | 1.78 |Shut down on account of air shortage. |

| | | | |

Mixed | 30 | 30 | 1.00 |Shut down April 20th to July 27th, |

| | | |1906. |

| | | | |

Earth |127 | 615 | 4.84 | |

| | | | |

| | | | |

Mixed | 35 | 70 | 2.00 | |

| | | | |

Rock | 6 | 10 | 1.66 | |

| | | | |

Mixed | 22 | 21 | 0.95 | |

| | | | |

Rock | 9 | 22 | 2.44 | |

| | | | |

Mixed |110 | 249 | 2.26 |Heading advanced to 97+82. |

| | | | |

Rock | 49 | 107 | 2.18 | " " " 94+35. |

| | | | |

Mixed | 43 | 106 | 2.46 | |

| | | | |

Rock | 39 | 83 | 2.13 | |

| | | | |

Mixed | 94 | 218 | 2.32 |Shut down until Line D shields met. |

| | | | |

Mixed | 6 | 11 | 1.83 | |

--------------+------+--------+--------+--------------------------------------+

LINE D, MANHATTAN.

--------------+-----------------+---------+---------+------------+------------+

{|Top heading |107+70.49|107+16 |Dec. 9, '04|Jan. 31, '05|}

{|Removing bench |107+70.49|107+35 |Jan. 1, '05|Jan. 27, '05|}

Rock {|Bottom heading |107+35 |106+80 |Jan. 30, '05|Feb. 10, '05|}

{|Trimming |107+70 |106+80 |Mar. 29, '05|Apr. 12, '05|}

{|Trimming |107+70 |106+80 |Aug. 31, '05|Sept 19, '05|}

| | | | | |

Rock |Bottom heading |106+80 |106+67 |Oct. 5, '05|Nov. 8, '05|

| | | | | |

Mixed |Bottom heading |106+67 |106+39 |Nov. 8, '05|Dec. 23, '05|

| | | | | |

|Sliding hood and | | | | |

Mixed |breasting. Rock |106+29 |105+70 |Dec. 23, '05|Jan. 24, '06|

|bench | | | | |

| | | | | |

Earth |Poling and |105+70 |104+61 |Jan. 24, '06|Feb. 27, '06|

|breasting | | | | |

| | | | | |

| | | | | |

Earth |Poling, breasting|104+61 |103+90 |Mar. 2, '06|Mar. 31, '06|

| and shutters | | | | |

| | | | | |

| | | | | |

Earth |Shutters |103+90 | 99+41 |Apr. 20, '06|Sept 3, '06|

| | | | | |

| | | | | |

Mixed |Bottom bench | 99+41 | 99+17 |Sept 3, '06|Sept 23, '06|

| | | | | |

Mixed |Bottom heading | 99+17 | 98+50 |Oct. 2, '06|Nov. 24, '06|

| | | | | |

| | | | | |

Rock |Bottom heading | 98+50 | 97+72 |Nov. 24, '06|Jan. 16, '07|

| | | | | |

Mixed |Bottom heading | 97+72 | 97+27 |Jan. 16, '07|Feb. 10, '07|

| | | | | |

Mixed |Rock cut | 97+27 | 95+72 |Feb. 10, '07|Apr. 23, '07|

| | | | | |

Rock |Middle heading | 95+72 | 95+57 |Apr. 23, '07|May 11, '07|

| | | | | |

Rock |Middle heading | 95+57 | 94+65 |May 23, '07|June 17, '07|

| | | | | |

| | | | | |

Mixed |Middle heading | 94+65 | 94+41 |June 17, '07|June 25, '07|

| | | | | |

Mixed |Rock cut | 94+41 | 94+03 |June 25, '07|July 13, '07|

| | | | | |

Rock |Middle heading | 94+03 | 92+64 |July 13, '07|Sept 12, '07|

| | | | | |

Mixed |Middle heading | 92+64 | 92+54 |Sept 12, '07|Sept 20, '07|

| | | | | |

Rock |Middle heading | 92+54 | 92+50 |Sept 20, '07|Sept 21, '07|

| | | | | |

Mixed |Rock cut | 92+50 | 90+38.66|Sept 21, '07|Jan. 8, '08|

--------------+-----------------+---------+---------+------------+------------+

--------------+------+--------+--------+--------------------------------------+

| | |Rate of | |

|Number| |progress| |

| of | Linear |in feet | |

Material. | days.| feet. |per day.| Remarks |

--------------+------+--------+--------+--------------------------------------+

{| | | | |

{| | | | |

Rock {|123 | 90 | 0.73 |In normal air. |

{| | | | |

{| | | | |

| | | | |

Rock | 34 | 13 | 0.40 |Bottom heading timbered. |

| | | | |

Mixed | 45 | 38 | 0.84 | |

| | | | |

| | | | |

Mixed | 32 | 59 | 1.84 | |

| | | | |

| | | | |

Earth | 31 | 109 | 3.41 | |

| | | | |

| | | | |

| | | |Three days' delay to set shutters in |

Earth | 29 | 71 | 2.45 |top. Shut down 20 days to permit |

| | | |consolidation of the river bed and to |

| | | |repair broken plates. |

| | | | |

Earth |136 | 449 | 3.40 |Four days of 136, delay account of |

| | | |flood. |

| | | | |

Mixed | 20 | 24 | 1.20 | |

| | | | |

Mixed | 53 | 67 | 1.27 |Thirteen days' shut-down to put on |

| | | |hood. |

| | | | |

Rock | 53 | 78 | 1.47 | |

| | | | |

Mixed | 25 | 45 | 1.40 | |

| | | | |

Mixed | 72 | 155 | 2.15 | |

| | | | |

Rock | 18 | 15 | 0.83 | |

| | | | |

Rock | 25 | 92 | 3.68 |Twelve days' delay to repair cutting |

| | | |edge. |

| | | | |

Mixed | 8 | 24 | 3.00 | |

| | | | |

Mixed | 18 | 38 | 2.11 | |

| | | | |

Rock | 61 | 139 | 2.28 | |

| | | | |

Mixed | 8 | 10 | 1.25 | |

| | | | |

Rock | 1 | 4 | 4.00 | |

| | | | |

Mixed |109 | 211.34| 1.94 | |

--------------+------+--------+--------+--------------------------------------+

Openings were made between the headings as follows:

Tunnel _D_, February 20th, 1908;

Tunnel _B_, March 3d, 1908;

Tunnel _C_, March 5th, 1908;

Tunnel _A_, March 18th, 1908.

It was necessary to cut away the projecting floors of the working

compartments before the cutting edges could be shoved together.

_Contractor's Organization._--Tunnel operations were carried on

continuously for thirteen days out of fourteen, regular work being shut

down for repairs on alternate Sundays. When the required pressure was

more than 32 lb., four gangs of laborers were employed, each gang

working two shifts of 3 hours each, with an intermission of 3 hours

between the shifts. When the pressure was less than 32 lb., three gangs

were employed, each gang covering 8 hours, but with an intermission of

about 1/2 hour in low pressure for lunch.

_Air Pressures Required._--During the greater portion of the work in

soft ground, pressure was maintained which would about balance the

hydrostatic head at the axis of the tunnel. This required a pressure

varying from 30 to 34 lb. per sq. in. above that of the atmosphere. In

Tunnels _B_ and _D_, at Manhattan, during the work in soft ground,

pressures as high as 37 lb. were maintained for considerable periods of

time; in the firm material near the reef 28 lb. was often sufficient.

While removing the broken plates, the pressure was raised for a short

time to 42 lb., and was maintained between 37-1/2 and 40 lb. for a

little more than one month.

_Air Supply._--For regular operation the contractor furnished four

compressors on each side of the river, each having a rated capacity of

5,000 cu. ft. of free air per minute delivered at 50 lb. above normal,

when running at the rate of 100 rev. per min. An additional compressor

of the same capacity was supplied on each side of the river, in

compliance with the requirement for 25% excess capacity; the additional

compressors had also high-pressure air cylinders which could be

connected at will, and in which the pressure could be increased to 150

lb., and the air used to supply rock drills, grouting machines, etc. The

entire combination on each side of the river, therefore, was rated at

25,000 cu. ft. of free air per minute, or a mean of 6,250 cu. ft. per

heading. Its safe working capacity was not far from 20,000 cu. ft. per

min.

The shields broke through rock surface in Tunnels _B_, _C_, and _D_, at

Manhattan, in November and December, 1905. The consumption of air in the

four tunnels soon exceeded 15,000 cu. ft. for 24 hours, and in Tunnel

_D_, on several occasions, it exceeded 7,000 cu. ft. for a like period.

Blows had become frequent, and it was evident that the air plant was

inadequate for driving four tunnels at once in the open material east of

the Manhattan rock. Work in Tunnel _A_, therefore, was not resumed,

after the suspension on December 29th, for about ten months, and Tunnel

_C_ was also closed down for more than four months of the time between

December, 1905, and July, 1906. During this period the capacity of the

plant was increased from the rated 25,000 cu. ft. of free air per

minute, to 35,000. In Tunnel _D_ the material had gradually become

firmer, with more clay and less escape of air, as the Blackwell's Island

Reef was approached, and, at the end of the period, the rock surface was

within 3 ft. of the top of the shield; in Tunnel _B_, the rock of the

reef was still a little below the shield, but the overlying material

contained a large proportion of clay and held air very well. Tunnel _C_

was still in open material, but, with two lines safe and with the

increased air plant, it was deemed best to resume work in Tunnel _A_,

which was done on October 23d, 1906. Thenceforward work was continuous

in all headings until the meeting points with the Long Island shields

were reached.

This period, January to October, 1906, inclusive, was the most strenuous

of the entire work, particularly the first six months. With one and, at

times, two tunnels closed down, the consumption of air in the headings

from Manhattan was an average of more than 20,000 cu. ft. per min. for

periods of from 30 to 60 days; it was often more than 25,000 cu. ft. for

24 hours, with a maximum of nearly 29,000 cu. ft., and doubtless this

was exceeded considerably for shorter periods. On several occasions the

quantity supplied to a single tunnel averaged more than 15,000 cu. ft.

per min. for 24 hours. The greatest averages for 24 hours were obtained

later in Tunnel _A_, after the resumption of work there, and exceeded

19,000 cu. ft., but the conditions in the headings of the other lines

were then so favorable that the work was carried on continuously in all.

The deficiency in the original plant at Manhattan was so marked, and the

need of driving all headings from Long Island simultaneously so clear,

that it was decided to increase the rated capacity of the Long Island

compressor plant to 45,400 cu. ft. of free air per minute, which was

10,400 cu. ft. greater than the capacity of the Manhattan plant after

the latter had been augmented.

[Illustration: PLATE LXXII]

The earth encountered on emerging from rock, when driving westward from

Long Island, was far more compact and less permeable to air than on the

Manhattan side, but for a distance of from 400 to 600 ft. immediately

east of the reef, it was a clean open sand, and, while the shields were

passing through this, the quantity of air supplied to the four headings

seldom fell below 20,000 cu. ft. per min.; it was usually more than

25,000 cu. ft., with a recorded maximum of 33,400 cu. ft. Although this

was greater than ever used on the Manhattan side, it was more uniformly

distributed among the several headings, and in none equalled the maximum

observed on the Manhattan side, the largest having been 12,700 cu. ft.

per min. for 24 hours; it must be remembered, however, that at one time

only two tunnels were in progress in the bad material in the tunnels

from Manhattan.

From the foregoing experience, it would seem that the plant finally

furnished at Long Island, having a rated capacity of 45,400 cu. ft. of

free air per minute, would have been a reasonable compliance with the

original actual needs on the Manhattan side and _vice versa_; the plant

finally developed on the Manhattan side, having a rated capacity of

35,000 cu. ft. of free air per minute, would have sufficed for the Long

Island side.

The total quantity of free air compressed for the supply of the working

chambers of the tunnels and the Long Island caissons was 34,109,000,000

cu. ft., and, in addition, 10,615,000,000 cu. ft. were compressed to

between 80 and 125 lb. for power purposes, of which at least 80% was

exhausted in the compressed-air working chambers. The total supply of

free air to each heading while under pressure, therefore, averaged about

3,550 cu. ft. per min.

The quantity of air escaping during a sudden blow-out is apparently much

smaller than might be supposed. Investigation of a number of cases,

showing large pressure losses combined with a long stretch of tunnel

supplying a relatively large reservoir of air, disclosed that a maximum

loss of about 220,000 cu. ft. of free air occurred in 10 min. This

averages only a little more than 19,000 cu. ft. per min., the maximum

recorded supply to one tunnel for a period of 24 hours. Of this

quantity, however, probably from 30 to 40% escaped in the first 45

seconds, while the remainder was a more or less steady loss up to the

time when the supply could be increased sufficiently to maintain the

lowered pressure. Very few blows showed losses approaching this in

quantity, but the inherent inaccuracy of the observations make the

foregoing figures only roughly approximate.

[Footnote C: _Minutes of Proceedings_, Inst. C. E., Vol. CXXX, p. 50.]