SPECIAL DIFFICULTIES.

The most serious difficulties of the work came near the start. In Tunnel

_D_ blows and falls of sand from the face were frequent after soft

ground was met in the top. About six weeks after entering the full sand

face, and before the shutters had been installed, the shield showed a

decided tendency to settle, carrying the tunnel lining down with it and

resulting in a number of badly broken plates in the bottom of the rings.

Notwithstanding the use of extremely high vertical leads,[D] the sand

was so soft that the settlement of the shield continued for about

fifteen rings, the maximum being nearly 9 in. below grade. The

hydrostatic head at mid-height of the tunnel was 32-1/2 lb., and the

raising of the air pressure to 37 lb., as was done at this time, was

attended with grave danger of serious blows, on account of the recent

disturbance of the natural cover by the pulling and re-driving of piles

in the reconstruction of the Long Island ferry slips directly above. It

dried the face materially, however, and the shield began to rise again,

and had practically regained the grade when the anticipated blow-outs

occurred, culminating with the entrance of rip-rap from the river bed

into the shield and the flooding of the tunnel with 4 ft. of sand and

water at the forward end. The escape of air was very great, and, as a

pressure of more than 28 lb. could not be maintained, the face was

bulkheaded and the tunnel was shut down for three weeks in order to

permit the river bed to consolidate.

This was the most serious difficulty encountered on any part of the

work, and, coming at the very start, was exceedingly discouraging.

During the shut-down the broken plates were reinforced temporarily with

steel ribs and reinforced concrete (Fig. 1, Plate LXXIII) which, on

completion of the work, were replaced by cast-steel segments, as

described elsewhere. Practically, no further movement of iron took

place, and the loss of grade caused by the settlement of the shield,

which was by far the largest that ever occurred in this work, was not

sufficient to require a change in the designed grade or alignment of the

track. Work was resumed with the shutters in use at the face as an aid

to excavation. The features of extreme seriousness did not recur, but

for two months the escape of air continued to be extremely large, an

average of 15,000 cu. ft. per min. being required on many days during

this period.

[Illustration: PLATE LXXIII, FIG. 1.--TEMPORARY REINFORCEMENT OF BROKEN

PLATES AND REMOVAL OF A PLATE IN SECTIONS.]

[Illustration: PLATE LXXIII, FIG. 2.--HEAVY CAST-STEEL PATCH ATTACHED TO

BENT SEGMENT OF CUTTING EDGE.]

[Illustration: PLATE LXXIII, FIG. 3.--INFLOW OF SOFT CLAY THROUGH

SHIELD.]

[Illustration: PLATE LXXIII, FIG. 4.--REINFORCEMENT OF BROKEN PLATE WITH

LONG POLT AND TWISTED STEEL RODS.]

In Tunnel _B_, after passing out from under the bulkhead line, in April,

1906, the loss of air became very great, and blow-outs were of almost

daily occurrence until the end of June. At the time of the blows the

pressure in the tunnel would drop from 2 to 8 lb., and it generally took

some hours to raise the pressure to what it was before the blow. During

that time regular operations were interrupted. In the latter part of

June a permit was obtained allowing the clay blanket to be increased in

thickness up to a depth of water of 27 ft. at mean low tide. The

additional blanket was deposited during the latter part of June and

early in July, and almost entirely stopped the blows.

By the end of the month the natural clay, previously described, formed

the greater portion of the face, and, from that time forward, played an

important part in reducing the quantity of air required. During April

and the early part of May the work was under the ferry racks of the Long

Island Railroad. The blanket had to be placed by dumping the clay from

wheel-barrows through holes in the decking.

In Tunnel _A_ a bottom heading had been driven 23 ft. in advance of the

face at the time work was stopped at the end of 1905. During the ten

months of inactivity the seams in the rock above opened. The rock

surface was only from 2 to 4 ft. below the top of the cutting edge for a

distance of about 60 ft. Over the rock there were large boulders

embedded in sharp sand. It was an exceedingly difficult operation to

remove the boulders and place the polings without starting a run. The

open seams over the bottom heading also frequently caused trouble, as

there were numerous slides of rock from the face which broke up the

breasting and allowed the soft material from above to run into the

shield. There were two runs of from 50 to 75 cu. yd. and many smaller

ones.

[Footnote D: The lead of the shield is the angular divergence of its

axis from the axis of the tunnel and, in this tunnel, was measured as

the offset in 23 ft. It was called + when the shield was pointed upward

from grade, and - when pointed downward.]

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The East River Tunnels. Paper No. 1159 · 第 25 / 35 题