| | Station: | Date: |
| |---------+---------+------------+------------+
| | | | | |
Material. | Method. | From | To | From | To |
--------------+-----------------+---------+---------+------------+------------+
{|Top heading |108+43 |107+74 |July 20, '05|Aug. 3, '05|
Rock {|Top lift of bench|108+43 |107+74 |Aug. 8, '05|Aug. 23, '05|
{|Bottom lift of |108+43 |107+74 |Aug. 30, '05|Sept 27, '05|
{| bench | | | | |
| | | | | |
Rock {|Bottom heading |107+74 |107+21 |Sept 27, '05|Oct. 23, '05|
{|Bottom heading |107+74 |107+21 |Nov. 30, '05|Dec. 29, '05|
| | | | | |
Mixed |Bottom heading |107+21 |106+99 |Oct. 26, '06|Nov. 20, '06|
| | | | | |
Mixed |Rock bench |106+99 |106+34 |Nov. 20, '06|Jan. 13, '07|
| | | | | |
Earth |Poling and |106+34 | 99+11 |Jan. 13, '07|Apr. 17, '07|
| breasting | | | | |
| | | | | |
Mixed |Rock cut | 99+11 | 93+96 |Apr. 17, '07|Oct. 24, '07|
| | | | | |
Rock |Bottom heading | 93+96 | 93+58 |Oct. 24, '07|Nov. 14, '07|
| | | | | |
Rock |Center heading | 93+58 | 92+42 |Nov. 14, '07|Dec. 27, '07|
| | | | | |
Rock |Bottom heading | 92+42 | 91+05 |Dec. 27, '07|Feb. 24, '08|
| | | | | |
Mixed |Rock cut | 91+05 | 90+57 |Feb. 24, '08|Mar. 20, '08|
--------------+-----------------+---------+---------+------------+------------+
--------------+------+--------+--------+--------------------------------------+
| | |Rate of | |
|Number| |progress| |
| of | Linear |in feet | |
Material. | days.| feet. |per day.| Remarks |
--------------+------+--------+--------+--------------------------------------+
{| 14} | | {|Excavation in normal air, and before |
Rock {| 15}57| 69 | 1.21 {|advance of shield. |
{| 28} | | {| |
{| | | {| |
| | | | |
Rock {| 26}55| 53 | 0.96 {|Bottom heading timbered to avoid the |
{| 29} | | {|possibility of a break. |
| | | | |
Mixed | 25 | 22 | 0.88 |Bottom heading timbered. |
| | | | |
Mixed | 54 | 65 | 1.20 | |
| | | | |
Earth | 94 | 723 | 7.69 | |
| | | | |
| | | | |
Mixed |190 | 515 | 2.71 | |
| | | | |
Rock | 21 | 38 | 1.81 | |
| | | | |
Rock | 46 | 116 | 2.52 | |
| | | | |
Rock | 59 | 137 | 2.32 | |
| | | | |
Mixed | 25 | 48 | 1.92 | |
--------------+------+--------+--------+--------------------------------------+
LINE B, MANHATTAN.
--------------+-----------------+-------------------+-------------------------+
| | Station: | Date: |
| |---------+---------+------------+------------+
| | | | | |
Material. | Method. | From | To | From | To |
--------------+-----------------+---------+---------+------------+------------+
{|Top heading |108+35 |107+87 |July 6, '05|July 27, '05|
{|Top lift of bench|108+35 |107+87 |Aug. 3, '05|Aug. 14, '05|
Rock {|Bottom lift of | | | | |
{| bench |108+35 |108+15 |Aug. 26, '05|Aug. 30, '05|
{|Bottom lift of | | | | |
{| bench |108+15 |107+87 |Sept 11, '05|Sept 26, '05|
| | | | | |
Rock |Bottom heading |107+87 |107+00 |Oct. 23, '05|Jan. 17, '06|
| | | | | |
Mixed |Bottom heading |107+00 |106+64 |Jan. 17, '06|Feb. 12, '06|
| | | | | |
Mixed |Rock bench |106+64 |106+31 |Feb. 12, '06|Mar. 1, '06|
| | | | | |
Earth |Poling and |106+31 |105+58 |Mar. 1, '06|Apr. 3, '06|
| breasting | | | | |
| | | | | |
|Shutters in | | | | |
Earth | contact with |105+58 | 99+19 |Apr. 9, '06|Nov. 1, '06|
| face | | | | |
| | | | | |
Mixed |Rock bench | 99+19 | 98+44 |Nov. 1. '06|Dec. 29, '06|
| | | | | |
Mixed |Bottom heading | 98+44 | 97+76 |Dec, 29, '06|Feb. 12, '07|
| | | | | |
Mixed |Rock cut | 97+66 | 93+84 |Feb. 12, '07|Aug. 6, '07|
| | | | | |
Rock |Full face | 93+84 | 93+21 |Aug. 6, '07|Sept 2, '07|
| | | | | |
Rock |Center Heading | 93+21 | 92+30 |Sept 2, '07|Oct. 12, '07|
| | | | | |
Rock |Bottom heading | 92+30 | 90+99 |Oct. 12, '07|Dec. 6, '07|
| | | | | |
Mixed |Rock cut | 90+99 | 90+49.6 |Dec. 6, '07|Jan. 3, '08|
--------------+-----------------+---------+---------+------------+------------+
--------------+------+--------+--------+--------------------------------------+
| | |Rate of | |
|Number| |progress| |
| of | Linear |in feet | |
Material. | days.| feet. |per day.| Remarks |
--------------+------+--------+--------+--------------------------------------+
{| 21} | | {| |
{| 11} | | {| |
Rock {| }51| 48 | 0.94 {|Excavation done in normal air and |
{| 4} | | {|before advance of shield. |
{| } | | {| |
{| 15} | | {| |
| | | | |
Rock | 86 | 87 | 1.01 | |
| | | | |
Mixed | 26 | 36 | 1.38 | |
| | | | |
Mixed | 17 | 33 | 1.94 | |
| | | | |
Earth | | | | |
| 33 | 73 | 2.21 | |
| | | | |
| | | | |
Earth |206 | 639 | 3.10 | |
| | | | |
| | | | |
Mixed | 58 | 75 | 1.30 | |
| | | | |
Mixed | 45 | 68 | 1.51 | |
| | | | |
Mixed |175 | 392 | 2.24 | |
| | | | |
Rock | 27 | 63 | 2.33 | |
| | | | |
Rock | 40 | 91 | 2.28 | |
| | | | |
Rock | 55 | 131 | 2.38 | |
| | | | |
Mixed | 28 | 49.4 | 1.76 | |
--------------+------+--------+--------+--------------------------------------+