LINE D, LONG ISLAND.

--------------+-----------------+-------------------+-------------------------+

| | Station: | Date: |

| |---------+---------+------------+------------+

| | | | | |

Material. | Method. | From | To | From | To |

--------------+-----------------+---------+---------+------------+------------+

Rock |Bottom heading | 68+50.6 | 69+77 |June 2, '06|Oct. 24, '06|

| | | | | |

Earth and rock|Bottom heading | 69+77 | 71+22 |Oct. 24, '06|Jan. 13, '06|

| | | | | |

All rock |Bottom heading | 71+23 | 72+00 |Jan. 13, '07|Mar. 3, '07|

| | | | | |

All rock |Center heading | 72+00 | 75+73 |Mar. 3, '07|July 10, '07|

| | | | | |

Earth and rock|Going out of rock| 75+73 | 77+63 |July 10, '07|Sept 25, '07|

| | | | | |

All earth |Soft ground | 77+63 | 90+38.6 |Sept 25, '07|Mar. 7. '08|

--------------+-----------------+---------+---------+------------+------------+

--------------+------+--------+--------+--------------------------------------+

| | |Rate of | |

|Number| |progress| |

| of | Linear |in feet | |

Material. | days.| feet. |per day.| Remarks |

--------------+------+--------+--------+--------------------------------------+

Rock |144 | 126.4 | 0.87 | |

| | | | |

Earth and rock| 81 | 145 | 1.79 | |

| | | | |

All rock | 49 | 78 | 1.59 | |

| | | | |

All rock |129 | 373 | 2.89 | |

| | | | |

Earth and rock| 77 | 190 | 2.47 | |

| | | | |

All earth |164 |1,275.6 | 7.78 | |

--------------+------+--------+--------+--------------------------------------+

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The East River Tunnels. Paper No. 1159 · 第 22 / 35 题