EXCAVATION IN ALL ROCK.

Where the tunnel was all in good rock two distinct methods were used.

The first was the bottom-heading-and-break-up, and the second, the

top-heading-and-bench method. The first is illustrated by Figs. 1 and 2,

Plate LXIII. The bottom heading, 13 ft. wide and 9 ft. high, having

first been driven, a break-up was started by blasting down the rock,

forming a chamber the full height of the tunnel. The timber platform,

shown in the drawing, was erected in the bottom heading, and extended

through the break-up chamber. The plan was then to drill the entire face

above the bottom heading and blast it down upon the timber staging, thus

maintaining a passage below for the traffic from the heading and

break-ups farther down the line. Starting with the condition indicated

by Plate XIII, the face was drilled, the columns were then taken down

and the muck pile was shoveled through holes in the staging into muck

cars below. The face was then blasted down upon the staging, the drill

columns were set up on the muck pile, and the operation was repeated.

This method has the advantage that the bottom heading can be pushed

through rapidly, and from it the tunnel may be attacked at a number of

points at one time. It was found to be more expensive than the

top-heading-and-bench method, and as soon as the depression in the rock

at about Station 59 was passed, a top heading about 7 ft. high, and

roughly the segment of a 23-ft. circle, was driven to the next soft

ground in each of the four tunnels. The remainder of the section was

taken out in two benches, the first, about 4 ft. high, was kept about

15 ft. ahead of the lower bench, which was about the remaining 11 ft.

high.

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The East River Tunnels. Paper No. 1159 · 第 8 / 35 题