EXCAVATION IN EARTH AND ROCK.

About 2,500 ft. of tunnel, the roof of which was in soft ground, was

excavated in normal air by the mining-and-timbering method. In the

greater part of this the rock surface was well above the middle of the

tunnel. The method of timbering and mining, while well enough known, has

not been generally used in the United States.

[Illustration: PLATE LXIII]

Starting from the break-up in all rock, as described above, and

illustrated on Plate XIII, when soft ground was approached, a top

heading was driven from the rock into and through the earth. This

heading was about 7 ft. high and about 6 ft. wide. This was done by the

usual post, cap, and poling-board method. The ground was a running sand

with little or no clay, and, at first, considerable water, in places.

All headings required side polings. The roof poling boards were about

2-1/2 or 3 ft. above the outside limit of the tunnel lining, as

illustrated by Figs. 3, 4, and 5, Plate LXIII. The next step was to

place two crown-bars, _AA_, usually about 20 ft. long, under the caps.

Posts were then placed under the bars, and poling boards at right angles

to the axis of the tunnel were then driven out over the bars. As these

polings were being driven, the side polings of the original heading were

removed, and the earth was mined out to the end of these new transverse

polings. Breast boards were set on end under the ends of the transverse

polings when they had been driven out to their limit. Side bars, _BB_,

were then placed as far out as possible and supported on raking posts.

These posts were carried down to rock, if it was near, if not, a sill

was placed.

A new set of transverse polings was driven over these side bars and the

process was repeated until the sides had been carried down to rock or

down to the elevation of the sills supporting the posts, which were

usually about 4 ft. above the axis of the tunnel.

The plan then was to excavate the remainder of the section and build the

iron lining in short lengths, gradually transferring the weight of the

roof bars of the iron lining as the posts were taken out. This meant

that not more than four rings, and often only one ring, could be built

before excavation and a short length of cradle became necessary. Before

the posts under the roof bars could be built and the weight transferred

to the iron lining, a grout dam was placed at the leading end of the

iron lining, and grout was brought up to at least 45 deg. from the top. Such

workings were in progress at as many as eight places in one tunnel at

the same time. Where there was only the ordinary ground-water to contend

with, the driving of the top heading drained the ground very thoroughly,

and the enlarging was done easily and without a serious loss of ground.

Under these conditions the surface settlement was from 6 in. to 2 ft.

Under Borden Avenue, there was more water, which probably came from a

leaky sewer; it was not enough to form a stream, but just kept the

ground thoroughly saturated. There was a continued though hardly

perceptible flow of earth through every crevice in the timbering during

the six or eight weeks between the driving of the top heading and the

placing of the iron lining; and here there was a settlement of from 4 to

8 ft. at the surface.

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The East River Tunnels. Paper No. 1159 · 第 9 / 35 题