CHAPTER XIII.

THE GERMAN METHOD--EXCAVATING TUNNELS THROUGH SOFT GROUND (Continued);

BALTIMORE BELT LINE TUNNEL.

The German method of tunneling was first used in 1803 in constructing

the St. Quentin Canal. In 1837 the Königsdorf tunnel of the Cologne and

Aix la Chapelle R.R. was excavated by the same method. The success of

the method in these two difficult pieces of soft-ground tunneling led to

its extensive adoption throughout Germany, and for this reason it

gradually came to be designated as the German method. Briefly explained

the method consists in excavating first an annular gallery in which the

side walls and roof arch are built complete before taking out the center

core and building the invert.

[Illustration: FIG. 76.--Diagrams Showing Sequence of Excavation in

German Method of Tunneling.]

=Excavation.=--The excavation of tunnels by the German method is begun

either by driving two bottom side drifts or by driving a center top

heading. Fig. 76 shows the mode of procedure when bottom side drifts are

used to start the work. The two side drifts No. 1 are made from 7 ft. to

8 ft. wide, and about one-third the total height of the full section;

the width of each heading has to be sufficient for the construction of

the masonry and strutting, and for the passage of narrow spoil cars

alongside them. These drifts are increased in height to the springing

line of the arch by taking out the two drifts No. 2. Next the top center

heading No. 3 is driven, and finally the two haunch headings No. 4 are

excavated. The center core No. 5 is utilized to support the strutting

until the side walls and roof arch are completed, when it is broken down

and removed. In case of very loose material, where the first side drifts

cannot be carried as high as one-third the height of the section, it is

the common practice to make them about one-fourth the height, and to

take out the side portions of the annular gallery in three parts, as

shown by Fig. 76.

[Illustration: FIG. 77.--Diagram Showing Sequence of Excavations in

Water Bearing Material, German Method.]

The top center heading plan of commencing the excavation is usually

employed in firm materials or when a vein of water is encountered in the

upper part of the section. In the latter contingency a small bottom

drift _A_, Fig. 77, is first driven to serve as a drain; but in any case

the excavation proper of the tunnel consists in first driving the center

top heading No. 1, and then by working both ways along the profile

parts, Nos. 2, 3, 4, and 5 are removed. Part No. 6 is left to support

the strutting until the side walls and roof arch are built, when it is

also excavated.

=Strutting.=--When the excavation is begun by bottom side drifts these

drifts are strutted by erecting vertical posts close against the sides

of the drift and placing a cap-piece transversely across the roof of the

drift. The side posts are usually supported by sills placed across the

bottom of the drift. These frameworks of posts, cap, and sill are

erected at short intervals, and the roof, and, if necessary, the sides

of the drift between them, are sustained by means of longitudinal

poling-boards extending from one frame to the next. The cap-pieces of

the strutting for the bottom drifts serve as sills for the exactly

similar strutting of the heading next above. To support the additional

weight, and to allow the construction of the side walls, the strutting

of the bottom drifts is strengthened by inserting an intermediate post

between the original side posts of each frame. These intermediate posts

are not inserted at the center of the frames or bents, but close to the

wall masonry line as shown by Fig. 78. This eccentric position of the

post avoids any interference with the hauling, and also allows the

removal of the adjacent side post when the masonry is constructed.

[Illustration: FIG. 78.--Sketch Showing Work of Excavating and Timbering

Drifts and Headings.]

[Illustration: FIG. 79.--Sketch Showing Method of Roof Strutting.]

Two methods of strutting the soffit of the excavation are employed, one

being a modification of the longitudinal system employed in the English

method of tunneling described in a succeeding chapter, and the other a

modification of the Belgian system previously described. Fig. 79 shows

the method of employing the radial strutting of the Belgian system. At

the beginning the center top heading is strutted with rectangular bents

such as are employed for strutting the drifts. As this heading is

enlarged by taking out the haunch sections, radial posts are inserted,

as shown by Fig. 79, which also indicates the method of strutting the

side trenches when the excavation is carried downward from the center

top heading instead of upward from bottom side drifts.

=Masonry.=--Whatever plan of excavation or strutting is employed, the

construction of the masonry lining in the German method of tunneling

begins at the foundations of the side walls and is carried upward to the

roof arch. The invert, if one is required, is built after the center

core of earth is removed.

=Centering.=--Tunnel centers are generally employed in the German method

of tunneling, a common construction being shown by Fig. 80. It is

essentially a queen-post truss, the tie beam of which rests on a

transverse sill as shown by the illustration. The transverse sill is

supported along its central portion by the unexcavated center core of

earth, and at its ends either directly on the vertical posts or on

longitudinal beams resting on these posts. The diagonal members of the

queen-post truss form the bottom chords of small king-post trusses which

are employed to build out the exterior member of the center to a closer

approximation to the curve of the arch.

[Illustration: FIG. 80.--Sketch Showing Roof Arch Centers and Arch

Construction.]

=Hauling.=--When the bottom side drift plan of excavation is employed,

the spoil from the front of the drift is removed in narrow-gauge cars

running on a track laid as close as practicable to the center core.

These same cars are also employed to take the spoil from the drifts

above, through holes left in the ceiling strutting of the bottom drifts.

The spoil from the soffit sections may be removed by the same car lines

used in excavating the drifts, or a narrow-gauge track may be laid on

the top of the center core for this special purpose. In the latter case

the soffit tracks are usually connected by means of inclined planes

with the tracks on the bottoms of the side drifts. Generally, however,

the separate soffit car line is not used unless the material is of such

a firm character that the headings and drifts can be carried a great

distance ahead of the masonry work. With the center top heading plan of

beginning the excavation, the car track has, of course, to be laid on

the top of the center core. The center core itself is removed by means

of car tracks along the floor of the completed tunnel.

=Advantages and Disadvantages.=--Like the Belgian method of tunneling,

the German method has its advantages and disadvantages. Since the

excavation consists at first of a narrow annular gallery only, the

equilibrium of the earth is not greatly disturbed, and the strutting

does not need to be so heavy as in methods where the opening is much

larger. The undisturbed center core also furnishes an excellent support

for the strutting, and for the centers upon which the roof arches are

built. Another important advantage of the method is that the

construction of the masonry lining is begun logically at the bottom, and

progresses upward, and a more homogeneous and stable construction is

possible. The great disadvantage of the method is the small space in

which the hauling has to be done. The spoil cars practically fill the

narrow drifts in passing to and from the front, and interfere greatly

with the work of the carpenters and masons. Another objection to the

method is that the invert is the very last portion of the lining to be

built. This may not be a serious objection in reasonably compact and

stable materials, but in very loose soils there is always the danger of

the side walls being squeezed together before the invert masonry is in

position to hold them apart. Altogether the difficulties are of a

character which tend to increase the expense of the method, and this is

the reason why to-day it is seldom used even in the country where it was

first developed, and for some time extensively employed. For repairing

accidents, such as the caving in of completed tunnels, the German method

of tunneling is frequently used, because of the ease with which the

timbering is accomplished. In such cases the cost of the method used

cuts a small figure, so long as it is safe and expeditious.

BALTIMORE BELT LINE TUNNEL.

In the last few years a modification of the German method was used in

this country for the construction of several railroad tunnels. The

modification consists in excavating the two-side drifts up to the

springing line of the arch of the proposed tunnel. Then a central

heading, which is afterward enlarged to the whole section of the tunnel,

is excavated close to the crown. At the same time the masonry is

constructed from the foundation up in the side drifts. From the floor of

the upper section already excavated and strutted, the top of the masonry

of the drifts is reached by means of small side cuts; thus the lining is

made continuous up to the keystone. The central nucleus or bench is

removed after the tunnel has been lined.

The most important tunnel excavated by this method was the Baltimore

Belt Line tunnel described as follows:

The Baltimore Belt Ry. Co. was organized in 1890 by officials of the

Baltimore & Ohio, and Western Maryland railways, and Baltimore

Capitalists, to build 7 miles of double track railway, mostly within the

city limits of Baltimore. This railway was partly open cut and

embankment, and partly tunnel, and its object was to afford the

companies named facilities for reaching the center of the city with

their passengers and freight. To carry out the work the Maryland

Construction Co. was organized by the parties interested, and in

September, 1890, this company let the contract for construction to Ryan

& McDonald of Baltimore, Md. The chief difficulties of the work centered

in the construction of the Howard-street tunnel, 8350 ft. long, running

underneath the principal business section of the city.

=Material Penetrated.=--The soil penetrated by the tunnel was of almost

all kinds and consistencies, but was chiefly sand of varying degrees of

fineness penetrated by seams of loam, clay, and gravel. Some of the

clay was so hard and tough that it could not be removed except by

blasting. Rock was also found in a few places. For the most part,

however, the work was through soft ground, furnishing more or less

water, which necessitated unusual precautions to avoid the settling of

the street, and consequent damage to the buildings along the line. A

large quantity of water was encountered. Generally this water could be

removed by drainage and pumps, and the earth be prevented from washing

in by packing the space between the timbering with hay or other

materials. At points where the inflow was greatest, and the earth was

washed in despite the hay packing, the method was adopted of driving

6-in. perforated pipes into the sides of the excavation, and forcing

cement grout through them into the soil to solidify it. These pipes

penetrated the ground about 10 ft., and the method proved very efficient

in preventing the inflow of water.

=Excavation.=--The excavation was carried out according to the German

method of tunneling. Bottom side drifts were first driven, and then

heightened to the springing line of the roof arch. Next a center top

heading was driven, and the haunch sections taken out. The object of

beginning the excavations by bottom side drifts, was to drain the soil

of the upper part of the section. The center core was removed after the

side walls and roof arch were completed, its removal being kept from 50

ft. to 75 ft. to the rear of the advanced heading. The dimensions of the

side drifts proper were about 8 × 8 ft., but they were often carried

down much below the floor level to secure a solid foundation bed for the

side walls.

=Strutting.=--The side drifts were strutted by means of frames composed

of two batter posts resting on boards, and having a cap-piece extending

transversely across the roof of the drift. These frames were spaced

about 4 ft. apart. The excavation was advanced in the usual way by

driving poling-boards at the top and sides, with a slight outward and

upward inclination, so that the next frame could be easily inserted

leaving space enough between it and the sheeting to permit the next set

of poling-boards to be inserted. These poling-boards were driven as

close together as practicable so as to prevent as much as possible the

inflow of water and earth.

[Illustration: FIG. 81.--Sketch Showing Method of Excavating and

Strutting Baltimore Belt Line Tunnel.]

The center top heading was strutted in the same manner as were the side

drifts. The arrangement of the strutting employed in enlarging the

center top heading is shown clearly by Fig. 81, which also shows the

manner of strutting the side drifts and face of the excavation, and of

building the masonry.

=Centers.=--Both wood and iron centers were employed in building the

roof arch. The timber centering was constructed of square timbers, as

shown by Fig. 82. This construction of the iron centers is shown by Fig.

83. Each of the iron centers consisted of two 6 × 6 in. angles butted

together, and bent into the form of an arch rib. Six of these ribs were

set up 4 ft. apart. They were made of two half ribs butted together at

the crown, and were held erect and the proper distance apart by spacing

rods. The rearmost rib was held fast to the completed arch masonry, and

in turn supported the forward ribs while the lagging was being placed.

[Illustration: FIG. 82.--Roof Arch Construction with Timber Centers,

Baltimore Belt Line Tunnel.]

=Masonry.=--The side walls of the lining were built first in the bottom

side drifts, as shown by Fig. 81. They were generally placed on a

foundation of concrete, from 1 ft. to 2 ft. thick. As a rule the side

walls were not built more than 20 ft. in advance of the arch, but

occasionally this distance was increased to as much as 90 ft. The roof

arch consisted ordinarily of five rings of brick, but at some places in

especially unstable soil eight rings of brick were employed. The arch

was built in concentric sections about 18 ft. in length. All the timber

of the strutting above the arch and outside of the side walls was left

in place, and the voids were filled with rubble masonry laid in cement

mortar. It required about 125 mason hours to build an 18-ft. arch

section. Figs. 82 and 83 show various details of the masonry arch work.

[Illustration: FIG. 83.--Roof Arch Construction with Iron Centers,

Baltimore Belt Line Tunnel.]

Owing to the very unstable character of the soil, considerable

difficulty was experienced in building the masonry invert. The process

adopted was as follows: Two parallel 12 × 12 in. timbers were first

placed transversely across the tunnel, abutting against longitudinal

timbers or wedges resting against the side walls. Short sheet piles were

then driven into the tunnel bottom outside of these timbers, forming an

inclosure similar to a cofferdam, from which the earth could be

excavated without disturbing the surrounding ground. The earth being

excavated, a layer of concrete 8 ins. thick was placed, and the brick

masonry invert constructed on it. In less stable ground each of the

above described cofferdams was subdivided by transverse timbers and

sheet piling into three smaller cofferdams. Here the masonry of the

middle section was first constructed, and then the side sections built.

Where the ground was worst, still more care was necessary, and the

bottom had to be covered with a sheeting of 1¹⁄₄-in. plank held down by

struts abutting against the large transverse timbers. The invert masonry

was constructed on this sheeting. Refuge niches 9 ft. high, 3 ft. wide,

and 15 ins. deep were built in the side walls.

=Accidents.=--In this tunnel, owing to the quick striking of the

centers, it was found that the masonry lining flattened at the crown and

bulged at the sides. This was attributed to the insufficient time

allowed for the mortar to set in the rubble filling. Earth packing was

tried, but gave still worse results. Finally dry rubble filling was

adopted, with satisfactory results. There was necessarily some sinking

of the surface. This resulted partly from the necessity of changing and

removing of the timbers, and from the compression and springing of the

timbers under the great pressures. The crown of the arch also settled

from 2 ins. to 6 ins., due to the compression of the mortar in the

joints. The maximum sinking of the surface of the street over the tunnel

was about 18 ins.; it usually ran from 1 to 12 ins. Some damage was done

to the water and gas mains. This damage was not usually serious, but it

of course necessitated immediate repairs, and in some instances it was

found best to reconstruct the mains for some distance. At one point

along the tunnel where very treacherous material was found, the surface

settlement caused the collapse of an adjacent building, and necessitated

its reconstruction.

Tunneling: A Practical Treatise. · 第 13 / 18 章