CHAPTER XII.

EXCAVATING TUNNELS THROUGH SOFT GROUND; GENERAL DISCUSSION; THE BELGIAN

METHOD.

GENERAL DISCUSSION.

It may be set down as a general truth that the excavation of tunnels

through soft ground is the most difficult task which confronts the

tunnel engineer. Under the general term of soft ground, however, a great

variety of materials is included, beginning with stratified soft rock

and the most stable sands and clays, and ending with laminated clay of

the worst character. From this it is evident that certain kinds of

soft-ground tunneling may be less difficult than the tunneling of rock,

and that other kinds may present almost insurmountable difficulties.

Classing both the easy and the difficult materials together, however,

the accuracy of the statement first made holds good in a general way.

Whatever the opinion may be in regard to this point, however, there is

no chance for dispute in the statement that the difficulty of tunneling

the softer and more treacherous clays, peats, and sands is greater than

that of tunneling firm soils and rock; and if we describe the methods

which are used successfully in tunneling very unstable materials, no

difficulty need be experienced in modifying them to handle stable

materials.

=Characteristics of Soft-Ground Tunneling.=--The principal

characteristics which distinguish soft-ground tunneling are, first, that

the material is excavated without the use of explosives, and second,

that the excavation has to be strutted practically as fast as it is

completed. In treacherous soils the excavation also presents other

characteristic phenomena: The material forming the walls of the

excavation tends to cave and slide. This tendency may develop

immediately upon excavation, or it may be of slower growth, due to

weathering and other natural causes. In either case the roof of the

excavations tends to fall, the sides tend to cave inward and squeeze

together, and the bottom tends to bulge or swell upward. In materials of

very unstable character these movements exert enormous pressures upon

the timbering or strutting, and in especially bad cases may destroy and

crush the strutting completely. Outside the tunnel the surface of the

ground above sinks for a considerable distance on each side of the line

of the tunnel.

=Methods of Soft-Ground Tunneling.=--There are a variety of methods of

tunneling through soft ground. Some of these, like the quicksand method

and the shield method, differ in character entirely, while in others,

like the Belgian, German, English, Austrian, and Italian methods, the

difference consists simply in the different order in which the drifts

and headings are driven, in the difference in the number and size of

these advance galleries, and in the different forms of strutting

framework employed. In this book the shield method is considered

individually; but the description of the Belgian, German, English,

Austrian, Italian, and quicksand methods are grouped together in this

and the three succeeding chapters to permit of easy comparison.

THE BELGIAN METHOD OF TUNNELING THROUGH SOFT GROUND.

[Illustration: FIGS. 68 and 68A.--Diagrams Showing Sequence of

Excavations in the Belgian Method.]

The Belgian method of tunneling through soft ground was first employed

in 1828 in excavating the Charleroy tunnel of the Brussels-Charleroy

Canal in Belgium, and it takes its name from the country in which it

originated. The distinctive characteristic of the method is the

construction of the roof arch before the side walls and invert are

built. The excavation, therefore, begins with the driving of a top

center heading which is enlarged until the whole of the section above

the springing lines of the arch is opened. Various modifications of the

method have been developed, and some of the more important of these will

be described farther on, but we shall begin its consideration here by

describing first the original and usual mode of procedure.

=Excavation.=--Fig. 68 is the excavation diagram of the Belgian method

of tunneling. The excavation is begun by opening the center top heading

No. 1, which is carried ahead a greater or less distance, depending upon

the nature of the soil, and is immediately strutted. This heading is

then deepened by excavating part No. 2, to a depth corresponding to the

springing lines of the roof arch. The next step is to remove the two

side sections No. 3, by attacking them at the two fronts and at the

sides with four gangs of excavators. The regularity and efficiency of

the mode of procedure described consist in adopting such dimensions for

these several parts of the section that each will be excavated at the

same rate of speed. When the upper part of the section has been

excavated as described, the roof arch is built, with its feet supported

by the unexcavated earth below. This portion of the section is excavated

by taking out first the central trench No. 4 to the depth of the bottom

of the tunnel, and then by removing the two side parts No. 5. As these

side parts No. 5 have to support the arch, they have to be excavated in

such a way as not to endanger it. At intervals along the central trench

No. 4, transverse or side trenches about 2 ft. wide are excavated on

both sides, and struts are inserted to support the masonry previously

supported by the earth which has been removed. The next step is to widen

these side trenches, and insert struts until all of the material in

parts No. 5 is taken out.

When the material penetrated is firm enough to permit, the plan of

excavation illustrated by the diagram, Fig. 68A, is substituted for the

more typical one just described. The only difference in the two methods

consists in the plan of excavating the upper part of the profile, which

in the second method consists in driving first the center top heading

No. 1, and then in taking out the remainder of the section above the

springing lines of the arch in one operation, while in the first method

it is done in two operations. The distance ahead of the masonry to which

the various parts can be driven varies from 10 ft. to, in some cases,

100 ft., being very short in treacherous ground, and longer the more

stable the material is.

=Strutting.=--The longitudinal method of strutting, with the

poling-boards running transversely of the tunnel, is always employed in

the Belgian method of tunneling. In driving the first center top

heading, pairs of vertical posts carrying a transverse cap-piece are

erected at intervals. On these cap-pieces are carried two longitudinal

bars, which in turn support the saddle planks. As fast as part No. 2,

Fig. 68, is excavated, the vertical posts are replaced by the batter

posts _A_ and _B_, Fig. 69. The excavation of parts No. 3 is begun at

the top, the poling-boards _a_ and _b_ being inserted as the work

progresses. To support the outer ends of these poling-boards, the

longitudinals _X_ and _Y_ are inserted and supported by the batter posts

_C_ and _D_. In exactly the same way the poling-boards _c_ and _d_, the

longitudinals _V_ and _W_, and the struts _E_ and _F_, are placed in

position; and this procedure is repeated until the whole top part of the

section is strutted, as shown by Fig. 69, the cross struts _x_, _y_,

_z_, etc., being inserted to hold the radial struts firmly in position.

The feet of the various radial props rest on the sill _M N_. These

fan-like timber structures are set up at intervals of from 3 ft. to 6

ft., depending upon the quality of the soil penetrated.

[Illustration: FIG. 69.--Sketch Showing Radial Roof Strutting, Belgian

Method.]

[Illustration: FIG. 70.--Sketch Showing Roof Arch Center, Belgian

Method.]

=Centers.=--Either plank or trussed centers may be employed in laying

the roof arch in the Belgian method, but the form of center commonly

employed is a trussed center constructed as shown by Fig. 70. It may be

said to consist of a king-post truss carried on top of a modified form

of queen-post truss. The collar-beam and the tie-beam of the queen-post

truss are spaced about 7 ft. apart, and the posts themselves are left

far enough apart to allow the passage of workmen and cars between them.

The tie beam of the king-post truss is clamped to the collar-beam of the

queen-post truss by iron bands. On the rafters of the two trusses are

fastened timbers, with their outer edges cut to the curve of the roof

arch. These centers are set up midway between the fan-like strutting

frames previously described. They are usually built of square timbers.

The tie beams are usually 6 × 6 in., and the struts and posts 4 × 4 in.

timbers. The reason for giving the larger sectional dimensions to the

tie beams, contrary to the usual practice in constructing centers, is

that it has to serve as a sill for distributing the pressure to the

foundation of unexcavated soil which supports the center. Sometimes a

sub-sill is used to support the center upon the soil; and in any case

wedges are employed to carry it, which can be removed for the purpose of

striking the center. After the arch is completed, the centers may be

removed immediately, or may be left in position until the masonry has

thoroughly set. In either case the leading center over which the arch

masonry terminates temporarily is left in position until the next

section of the arch is built.

=Masonry.=--The masonry of the roof arch, which is the first part built,

is of necessity begun at the springing lines, and the first course rests

on short lengths of heavy planks. These planks, besides giving an even

surface upon which to begin the masonry, are essential in furnishing a

bearing to the struts inserted to support the arch while the earth below

them, part No. 5, Fig. 68, is being excavated. As the arch masonry

progresses from the springing lines upward, the radial posts of the

strutting are removed, and replaced by short struts resting on the

lagging of the centers, which support the crown bars or longitudinals

until the masonry is in place, when they and the poling-boards are

removed, and the space between the arch masonry and walls of the

excavation is filled with stone or well-rammed earth.

Considering now the side wall masonry, it will be remembered that in

excavating the part No. 5, Fig. 68, of the section, frequent side

trenches were excavated, and struts inserted to take the weight of the

masonry. These struts are inserted on a batter, with their feet near the

center of the tunnel floor, so that the side wall masonry may be carried

up behind them to a height as near as possible to the springing lines of

the arch. When this is done the struts are removed, and the space

remaining between the top of the partly finished side wall and the arch

is filled in. This leaves the arch supported by alternate lengths or

pillars of unexcavated earth and completed side wall. The next step is

to remove the remaining sections of earth between the sections of side

wall, and fill in the space with masonry. Fig. 71 is a cross-section,

showing the masonry completed for one-half and the inclined props in

position for the other half; and Fig. 72 is a longitudinal section

showing the pillars of unexcavated earth between the consecutive sets of

inclined struts and several other details of the lining, strutting, and

excavating work.

[Illustration: FIG. 71.--Sketch Showing Method of Underpinning Roof Arch

with the Side Wall Masonry.]

[Illustration: FIG. 72.--Longitudinal Section Showing Construction by

the Belgian Method.]

The invert masonry is built after the side walls are completed. This is

regarded as a defect of this method of tunneling, since the lateral

pressures may squeeze the side walls together and distort the arch

before the invert is in place to brace them apart. To prevent as much as

possible the distortion of the arch after the centers are removed, it is

considered good practice to shore the masonry with horizontal beams

having their ends abutting against plank, as shown by Fig. 71. These

horizontal beams should be placed at close intervals, and be supported

at intermediate points by vertical posts, as shown by the illustration.

Since the roof arch rests are for some time supported directly by the

unexcavated earth below, settlement is liable, particularly in working

through soft ground. This fact may not be very important so long as the

settlement is uniform, and is not enough to encroach on the space

necessary for the safe passage of travel. To prevent the latter

possibility the centers are placed from 9 ins. to 15 ins. higher than

their true positions, depending upon the nature of the soil, so that

considerable settlement is possible without any danger of the necessary

cross-section being infringed upon. In conclusion it may be noted that

the lining may be constructed in a series of consecutive rings, or as a

single cylindrical mass.

=Hauling.=--Since in this method of tunneling the upper part of the

section is excavated and lined before the excavation of the lower part

is begun, the upper portion is always more advanced than the lower. To

carry away the earth excavated at the front, therefore, an elevation has

to be surmounted; and this is usually done by constructing an inclined

plane rising from the floor of the tunnel to the floor of the heading,

as shown by Fig. 72. This inclined plane has, of course, to be moved

ahead as the work advances, and to permit of this movement with as

little interruption of the other work as possible, two planes are

employed. One is erected at the right-hand side of the section, and

serves to carry the traffic while the left-hand side of the lower

section is being removed some distance ahead and the other plane is

being erected. The inclination given to these planes depends upon the

size of the loads to be hauled, but they should always have as slight a

grade as practicable. Narrow-gauge tracks are laid on these planes and

along the floor of the upper part of the section passing through the

center opening mentioned before as being left in the centers and

strutting.

In excavating the top center heading there is, of course, another rise

to its floor from the floor of the upper part of the section. Where, as

is usually the case in soft soils, this top heading is not driven very

far in advance, the earth from the front is usually conveyed to the rear

in wheelbarrows, and dumped into the cars standing on the tracks below.

In firm soils, where the heading is driven too far in advance to make

this method of conveyance adequate, tracks are also laid on the floor of

the heading, and an inclined plane is built connecting it with the

tracks on the next level below. In place of these inclined planes, and

also in place of those between the floor of the tunnel and the level

above, some form of hoisting device is sometimes employed to lift the

cars from one level to the other. There are some advantages to this

method in point of economy, but the hoisting-machines are not easily

worked in the darkness, and accidents are likely to occur.

[Illustration: FIG. 73.--Diagram Showing Sequence of Excavation in

Modified Belgian Method.]

In the advanced top heading and in the upper part of the section

narrow-gauge tracks are necessarily employed, and these may be continued

along the floor of the finished section, or the permanent broad-gauge

railway tracks may be laid as fast as the full section is completed. In

the former case the permanent tracks are not laid until the entire

tunnel is practically completed; and in the latter case, unless a third

rail is laid, the loads have to be transshipped from the broad- to the

narrow-gauge tracks or _vice versa_. It is the more general practice to

use a third rail rather than to transship every load.

=Modifications.=--Considering the extent to which the Belgian method of

tunneling has been employed, it is not surprising that many

modifications of the standard mode of procedure have been developed. The

modification which differs most from the standard form is, perhaps, that

adopted in excavating the Roosebeck tunnel in Germany. This method

preserves the principal characteristic of the Belgian method, which is

the construction of the upper part of the section first; but instead of

building the side walls from the bottom upward, they are built in small

sections from the top downward. The excavation begins by driving the

center top heading No. 1, Fig. 73, whose floor is at the level of the

springing lines of the roof arch, and then the two side parts No. 2 are

excavated, opening up the entire upper portion of the section in which

the roof arch is built, as in the regular Belgian method. The next step

is to excavate part No. 3, shoring up the arch at frequent intervals.

Between these sets of shoring the side walls are built, resting on

planks on the floor of part No. 3, and then the sets of shores are

removed and replaced by masonry. Next part No. 4 is excavated, shored,

and filled with masonry as was part No. 3. In exactly the same way parts

5, 6, 7, and 8 are constructed in the order numbered. To prevent the

distortion of the arch during the side-wall construction it is braced by

horizontal struts, as indicated above in Fig. 71.

=Advantages.=--The advantages of the Belgian method of tunneling may be

summarized as follows: (1) The excavation progresses simultaneously at

several points without the different gangs of excavators interfering

with each other, thus securing rapidity and efficiency of work; (2) the

excavation is done by driving a number of drifts or parts of small

section, which are immediately strutted, thus causing the minimum

disturbance of the surrounding material; (3) the roof of the tunnel,

which is the part of the lining exposed to the greatest pressures, is

built first.

[Illustration: FIG. 74.--Sketch Showing Failure of Roof Arch by Opening

at Crown.]

=Disadvantages.=--The disadvantages of the Belgian method of tunneling

may be summarized as follows: (1) The roof arch which rests at first on

compressible soil is liable to sink; (2) before the invert is built

there is danger of the arch and side walls being distorted or sliding

under the lateral pressures; (3) the masonry of the side walls has to be

underpinned to the arch masonry.

=Accidents and Repairs.=--One of the most frequent accidents in the

Belgian method of tunneling is the sinking of the roof arch owing to

its unstable foundation on the unexcavated soil of the lower portion of

the section. The amount of settlement may vary from a few inches in firm

soil to over 2 ft. in loose soils. To counteract the effect of this

settlement it is the general practice to build the arch some inches

higher than its normal position. When the settlement is great enough to

infringe seriously upon the tunnel section, repairs have to be made; and

the only way of accomplishing them is to demolish the arch and rebuild

it from the side walls. It is usually considered best not to demolish

the arch until the invert has been placed, so that no further

disturbance is likely to occur once the lining is completed anew.

The rotation of the arch about its keystone, or the opening of the arch

at the crown, by the squeezing inward of the haunches by the lateral

pressures, is another characteristic accident. Fig. 74 shows the nature

of the distortion produced; the segments of the arch move toward each

other by revolving on the intradosal edges of the keystone, which are

broken away and crushed together with the operation, while the

extradosal edges are opened. It is to prevent this occurrence that the

horizontal struts shown in Fig. 71 are employed. The manner of repairing

this accident differs, depending upon the extent of the injury. When the

intradosal edges of the keystone are but slightly crushed, the repairing

is done as directed by Fig. 75. When the keystone is completely crushed,

however, the indications are that the material of the keystone, usually

brick, is not strong enough to resist the pressures coming upon it, and

it is advisable to substitute a stronger material in the repairs, and a

stone keystone is constructed as shown by Fig. 75. The middle stone of

this keystone extends through the depth of the arch ring, and the two

side stones only half-way through, their purpose being merely to resist

the crushing forces which are greatest at the intrados. Sometimes, when

the pressures are unsymmetrical, the arch ring breaks at the haunches as

well as the crown, as shown by Fig. 75, which also indicates the mode of

repairing. This consists in demolishing the original arch, and

rebuilding it with stone voussoirs inserted in place of the brick in

which the rupture occurred.

[Illustration: FIG. 75.--Sketches Showing Methods of Repairing Roof Arch

Failures.]

Tunneling: A Practical Treatise. · 第 12 / 18 章