CHAPTER XI.

TUNNELS THROUGH HARD ROCK (Continued).--EXCAVATION BY HEADINGS.

EUROPEAN AND AMERICAN METHODS.

The more common method of tunneling through hard rock is to begin the

work by a heading, instead of by a drift. This heading may be of small

dimensions, and the remainder of the section may also be removed in

successive small parts, or it may be the full width of the section, and

the enlargement of the section be made in one other cut.

[Illustration: FIG. 61.--Diagram Showing Sequence of Excavation in

Heading Method of Tunneling Rock.]

=General Discussion.=--When the tunnel is excavated by means of several

cuts, which is the method usually employed in Europe, the sequence of

work is as indicated by Fig. 61. Work is begun by driving the center top

heading No. 1, whose floor is at the level of the bottom of the roof

arch, and which is usually excavated by the circular cut method. This

heading is widened by removing parts Nos. 2 and 3 until the top part of

the section is removed, then the roof arch is built with its feet

resting on the unexcavated rock below. The lower portion of the section

or bench is removed by first sinking the trench No. 4, after which part

No. 5 is taken out, and then parts Nos. 6 and 7, and the side walls

built. Part No. 8 for the culvert is finally opened. The heading is, as

a rule, driven far in advance, but the excavation of each of the other

parts follows the preceding one at a distance behind of about 300 ft.

The strutting, when any is required, is usually the typical radial

strutting of the Belgian method of tunneling. The masonry lining is

constructed practically the same as in tunnels excavated by a drift. The

hauling is done on a single track laid in the heading No. 1, which

separates into double tracks where the full top section has been

excavated by the removal of parts No. 2. These two tracks are again

combined and form a single track along the top of part No. 5, which has

been left wider than part No. 4 for this particular purpose. When part

No. 3 is excavated a standard-gauge track is laid on its floor; and as

the full section of the tunnel is completed by taking out parts Nos. 4

and 5, this single track is replaced by two standard-gauge tracks, into

which it switches. Spoil is transferred from the narrow-gauge tracks on

the upper level, to the standard-gauge tracks on the tunnel floor, by

means of chutes, and building material is transferred in the opposite

direction by means of hoisting apparatus.

When the excavation is made by a single wide heading, and a single other

cut for removing the bench, which is the method preferred by American

engineers, it is called the Heading and Bench method. The work begins by

removing a top heading the full width of the section; this heading is

usually made 7 ft. or 8 ft. high, and is excavated by the center cut

method. The method of strutting usually employed is to erect successive

three- or five-segment timber arches, whose feet rest on the top of the

bench; when the bench is removed, posts are inserted under the feet of

each arch. These arches are covered with a lagging of plank. In America

it has often been the practice to let this strutting serve as a

temporary lining, and to replace it only after some time, often after

years, with a permanent lining of masonry. In a succeeding chapter, some

of the methods adopted in relining timber-lined arches with masonry are

described. The hauling is done by either narrow or broad gauge tracks

laid on the floor of the completed section below. A device called a

bench carriage is often employed to enable the cars running on the

heading tracks to dump their loads into the cars below, without

interfering with the work on the bench front. This device consists of a

wide platform carried on trucks, running on rails at the sides of the

tunnel floor, so that it is level with the floor of the heading. The

front of this platform carries a hinged leaf which may be raised and

lowered, and which forms a sort of gang-plank reaching to the floor of

the heading. By running the heading cars out on to this traveling

platform, they can be dumped into the cars below entirely clear of the

work in progress on the bench front.

For the purpose of illustrating the two methods of driving tunnels by a

heading, which have been briefly described, the St. Gothard and the Fort

George tunnels have been selected. The St. Gothard tunnel is selected,

as being one of the longest tunnels in the world, and because it was

excavated by a number of small parts; and the Fort George tunnel, as

being a double-track tunnel, driven by a heading, and bench, and having

a concrete lining.

ST. GOTHARD TUNNEL.

The St. Gothard tunnel penetrates the Alps between Italy and France, and

is 9¹⁄₄ miles long. It was constructed in 1872-82.

=Material Penetrated.=--The St. Gothard tunnel was excavated through

rock, consisting chiefly of gneiss, mica-schist, serpentine, and

hornblende, the strata having an inclination of from 45° to 90°. At many

points the rock was fissured, and disintegrated easily, and water was

encountered in large quantities, causing much trouble.

=Excavation.=--The sequence of excavation is shown by Fig. 14, p. 36.

First the top center heading, No. 1, whose dimensions varied from 8.25 ×

8.6 ft. to 8.5 × 9 ft., according to the quality of the rock, was driven

never less than 1000 ft. and sometimes over 3000 ft. in advance of parts

No. 2. The excavation of parts No. 2 opened up the full top section, and

parts Nos. 3, 4, 5, 6, and 7, were removed in the order numbered.

=Strutting.=--Where regular strutting was required, the construction

shown in Fig. 62 was adopted.

=Masonry.=--The St. Gothard tunnel is lined throughout with masonry.

After the upper portion of the section was fully excavated, the roof

arch was built with its feet resting upon short planks on the top of the

bench. Plank centers were used in constructing the arch. For the arch

brick masonry was employed, but the side walls were built of rubble

masonry. Shelter niches, about 3 ft. deep, were built into the side

walls at intervals, and about every 3,000 ft. storage niches about 10

ft. deep, and closed with a door, were constructed. The culvert was of

brick masonry.

=Mechanical Installation.=--Water-power was used exclusively in driving

the St. Gothard tunnel. At the north end, the Reuss, and at the south

end, the Tessin and the Tremola, rivers or torrents were dammed, and

their waters conducted to turbine plants at the opposite ends of the

tunnel. The power thus furnished by the Reuss was about 1,500 H.P., and

the power furnished by the combined supply of the Tessin and Tremola was

1,220 H.P. The turbine plant at both ends at first consisted of four

horizontal impulse turbines, but later, two more turbines were added at

the south end. Each of the two sets of four turbines first installed

drove five groups of three compressors each, and the two supplementary

turbines drove two groups of four compressors each. The compressors were

of the Colladon type with water injection, and four groups of three

compressors each were capable of furnishing 1,000 cu. yds. of air

compressed to between seven and eight atmospheres every hour, or about

100 H.P. per hour, delivered to the drills at the front. This air when

exhausted provided about 8,000 cu. yds. of fresh air per hour for

ventilation.

The compressors at each entrance discharged into a group of four

cylindrical receivers of wrought-iron each 5.3 ft. in diameter by 29.5

ft. long, and having a capacity of 593 cu. ft. The cylinders were placed

horizontally, the first one receiving the air at one end and discharging

it at the other end into the next cylinder, and so on. By this

arrangement the air was drained of its moisture, and the discharge from

the end receiver into the tunnel delivery pipes was not affected by the

pulsations of the compressors. The delivery pipe decreased from 8 in. in

diameter at the receiver to 4 ins. in diameter, and finally to 2¹⁄₂ ins.

in diameter, at the front.

The drills employed were of various patterns. The first one employed was

the Dubois & François “perforator,” in which the drill-bit was fed

forward by hand. This was replaced by Ferroux drills having an automatic

feed. Jules McKean’s “perforator” was employed at the north end of the

tunnel. All of these drills were of the percussion type, and were

mounted on carriages running on tracks. Their comparative efficiency was

officially tested in drilling granitic gneiss with an operating air

pressure of 5.5 atmospheres with the following results:

NAME OF DRILL. PENETRATION

INS. PER MIN.

Ferroux 1.6

McKean 1.4

Dubois & François 1.04

Soummelier 0.85

The heading was excavated by the circular cut method, the holes being

driven as follows: Near the center of the heading three holes were first

drilled, converging so as to inclose a pyramid with a triangular base.

Around these center holes from 9 to 13 others were driven parallel to

the tunnel axis. The center holes were blasted first, and then the

surrounding holes. From 3 to 5 hours were required to drill the two sets

of holes, and from three to four hours were required to remove the

blasted rock. The number of holes drilled in removing each of the

various parts was as follows:

Part No. 1 6 to 9

Part No. 2 6 to 10

Part No. 3 2

Part No. 4 6 to 9

Part No. 5 3

Part No. 6 6 to 9

Part No. 7 1

--------

Total for full section 36 to 40

=Hauling.=--Two different systems were employed for hauling the spoil

and construction material in the St. Gothard tunnel. To remove the spoil

from parts Nos. 1 and 2 a narrow-gauge track was laid on the floor of

the heading, and the cars were hauled by horses, the grade being

descending from the fronts. These narrow-gauge cars were dumped into

larger broad-gauge cars running on the track laid on the floor of the

completed section and hauled by compressed air locomotives (Fig. 63). To

raise the incoming structural material from the broad-gauge cars to the

narrow-gauge cars running on the level above, hoisting devices were

employed.

[Illustration: FIG. 62.--Method of Strutting Roof, St. Gothard Tunnel.]

[Illustration: FIG. 63.--Sketch Showing Arrangement of Car Tracks, St.

Gothard Tunnel.]

FORT GEORGE TUNNEL.[10]

From a point north of 157th Street and Broadway almost to Dyckman

Street, that is, a distance of nearly two miles, the New York Subway

passes under an elevation known as Fort Washington Heights, which almost

bounds Manhattan Island at its upper end near the Harlem Ship Canal.

Under this elevation the rapid transit railroad was constructed in

tunnel. The tunnel was driven from two intermediate shafts over 110 ft.

deep, located one at 169th Street and the other at 181st Street and

Broadway. Both shafts were sunk at one side of the center line of the

tunnel. After these shafts had been utilized for working purposes during

the construction of the tunnel, they were equipped with electric

elevators to carry passengers from the streets to the deep station.

[10] Condensed from a paper by Stephen W. Hopkins in _Harvard

Engineering Journal_, April, ’08.

=Material.=--The material encountered in the excavation of the Fort

George tunnel was the usual mica schist met everywhere on Manhattan

Island. It was full of seams with strata running in every direction to

such an extent that at many points the roof of the tunnel had to be

supported by timbers; at other parts along the line the rock was so

disintegrated that it was considered a very loose and treacherous soil.

Two serious accidents, each accompanied by loss of life, occurred during

the construction of this tunnel. Both of them were caused by the sudden

fall of a large ledge of rock which, after the tunnel had been excavated

to the full section, remained hanging on the roof, deprived of any

support and held in place by the little cohesion of the material packing

the seams.

=Excavation.=--The tunnel was excavated by the heading method in only

two cuts, viz., the heading and bench as indicated in the Fig. 65. The

heading, almost as wide as the upper portion of the tunnel section, was

excavated in the manner explained on page 91. After the heading was

removed, the enlargement of the entire upper section of the tunnel was

accomplished by driving three inclined holes at each side of the

heading. They were driven at different depths and inclinations, as shown

in the figure and were called trimming holes. At the same time the bench

was removed by means of five holes--three vertical and two inclined. The

line of subgrade was reached by means of five grading holes driven

almost horizontal with a slight inclination downward. The air drills for

the heading were mounted on columns, all the others on tripods. The

blasting was done in the following order: the grading holes were blasted

in the first round, the bench and trimming in the second, the center cut

of the heading in the third, the sides in the fourth and the dry holes

in the last. Thus each advance of 7 ft. of the whole tunnel section was

made by means of forty holes fired in five rounds which consumed 277

lbs. of dynamite with an average additional quantity of 76 lbs., making

a total of 353 lbs. With the exception of the center cut, where 60%

dynamite was used, all the other holes were discharged with 40%

dynamite.

[Illustration: ~Cross Section.~

~Longitudinal Section.~

FIG. 64.--Arrangement of Drill Holes in the Fort George Tunnel.

FIG. 65.--Longitudinal Section of the Heading and Bench Excavation at

the Fort George Tunnel.]

=Strutting.=--When the rock was of such a character as to be dangerous

and required permanent timber support, until the masonry lining was in

place, the method employed was as follows: a top heading was first

excavated about 10 ft. deep and from 10 ft. to 12 ft. wide for some

distance, 100 ft. to 500 ft., the dangerous rock being supported by 10 ×

10 in. yellow pine plumb or raking posts and sometimes by timber bents

(“caps and legs”). The next process was to widen the heading to the full

width of 30 ft. for a length of about 20 ft., placing timber supports

under the dangerous rock as the widening-out progressed. The excavation

was deepened a little at the sides to 9.5 ft. below the roof grade

(ordered line of excavation) or about 11 ft. below the roof grade, which

was necessary when segmental timbering was to be used, to allow for

placing a 12 × 12 in. “wall plate” (timber sill) along each side. These

wall plates, generally 20 ft. long, were set to the correct elevation

and were leveled by blocking and wedging. As soon as the wall plates

were set, the work of erecting the segmental timber sets, one set at a

time, was begun by starting from the wall plates and supporting the

timber on scaffolding until keyed in, then it was blocked up to the rock

at each joint and at other necessary points. When two or more sets were

erected, lagging, made of boards 2 ins. thick by 6 to 10 ins. wide, was

placed over the segmental timber “sets” and the space above the timber

dry packed with small stone placed by hand. Sometimes there was enough

room between the timber and the rock to do all the dry packing after the

full number of sets, generally six, had been placed on the two wall

plates. The temporary timber posts and braces were taken out as the

segmental timber sets were erected.

The seven timbers that made up a timber set were of yellow pine each

10 × 10 ins., 5 ft. 2 ins. long at the intrados and 5 ft. 6 ins. at the

extrados. The sets were spaced from 3 ft. to 5 ft. apart, but generally

3.5 ft. and braced to each other at each joint of the segmental timbers

by 6 × 8 in. spreaders which were wedged against the joint splices.

When the timbers were all erected on a set of wall plates (20 ft.) and

the lagging and dry packing were completed the work of taking out the

bench, which had been partly drilled as the timber sets were erected,

was resumed. The face of the bench, which had been left about 4 ft. from

the end of the previous set of wall plates, was brought forward slowly

by placing 10 × 10 in. plumb posts which extended below subgrade under

the wall plates. These posts were generally spaced the same as the

timber sets above and directly under them.

When the face of the bench had been brought to within 3 or 4 ft. of the

forward end of the wall plate, the process of widening out and timbering

another 20 ft. length of heading was begun. In some places the rock,

though needing permanent support, was such that the work of taking out

the bench and widening the heading was carried on simultaneously without

increasing the danger; but the greater portion of the work, when

strutting was required, was done as has been described.

[Illustration: FIG. 66.--Diagram Showing the Arrangement of Drill Holes

in the Heading and Bench of the Gallitsin Tunnel.]

=Hauling.=--The excavated material was loaded at the foot of the bench

in dump cars which were run by mule power to the portal or the shaft

according to location, on 36 in. gauge-service tracks. Inclines at 159th

Street were graded from the portal at 158th Street to the street

surface. The cars were formed at this portal into a train and were taken

up the incline to the dump at 162nd Street and the North River by

construction locomotives. At the 168th Street and 181st Street shafts,

the cars were hoisted to the surface in cages (elevators). In the former

case, they were taken to the dump at 165th Street and the North River by

mules and gravity; in the latter case, to various dumps by teams. At

both shafts, stone crushers were located, therefore a great part of the

material did not have to be hauled to the dumps or even taken to the

surface as a great deal of stone was used in dry packing over the

concrete arch. The material from the portal at Fort George was hauled by

mules directly to the dump near by.

=Lining.=--The entire tunnel was lined with concrete, consisting of a

floor 4 ins. thick and vertical side walls 18 ins. thick and 25 ft.

apart, which carried a semicircular arch 18 ins. thick except in the

timbered portions where the thickness was increased to 21 ins. and to 24

and 27 ins. in some places. The springing line of the arch is 6 ft. 2

ins. above the concrete floor (5 ft. 6 ins. above the base of rail),

hence the maximum clearance above the base of rail is 18 ft. The side

walls and arch were built solid of rock to a height of 8 ft. above

springing line and the space above that point between the concrete and

the rock was packed by hand with small stones. The concrete of the arch

was laid on timber centers erected for that purpose.

The heading and bench method of excavating rock tunnels is not always

followed in the manner just described but is employed with slight

modifications. There is a large variety of modifications but only the

two most commonly used in practical works are given here. The heading

and bench method illustrated in Fig. 66 was used, among others, on the

Gallitsin tunnel along the Pennsylvania R.R. at the summit of the

Alleghenies near Altoona, Pa., and more recently in the tunnels

constructed by the same company under Bergen Hill, N. J., for the

entrance to New York City. The shape of the cross-section of these

tunnels was semicircular arch on vertical side walls. The excavation was

made in three consecutive cuts, viz., the heading marked 1 in the

figure, the top bench 2, and the lower bench 3. A heading 7 ft. high and

10 ft. wide was attached near the crown of the arch and the rock was

removed by means of a center cut and parallel side holes, the number of

holes depending upon the consistency of the rock. The part No. 2 was

excavated by drilling holes at each side to different depths and at

different inclinations in order to reach the line of the profile as well

as the springing line of the proposed tunnel. The central part of the

top bench was excavated by means of holes driven vertically from the

floor of the heading. The bottom bench No. 3, included between the

springing line of the arch and subgrade, was removed by means of five

vertical holes driven from the floor of the top bench. The three

different working parts were kept nearly 10 ft. apart. Blasting was

effected in reversed order to the figures marked in the diagram, viz.,

the bottom bench first and the heading last.

[Illustration: FIG. 67.--Diagram Showing a Modification of the Heading

and Bench Method.]

Still another modification of the heading and bench method, commonly

followed by American engineers, is the one shown in Fig. 67. This

consists in dividing the tunnel section in three parts by horizontal

lines. The resultant parts are first the heading excavated close to the

roof, and as wide as the whole section of the tunnel; second, the top

bench in the middle, and lastly the bottom bench excavated to the depth

of the proposed tunnel floor. The excavation proceeds in the numerical

order, beginning at the heading which was excavated, as usual, by means

of a center cut and side holes to the full width of the proposed tunnel.

First the top bench, then the bottom bench, are removed by means of

vertical holes driven from the floor of the heading and the floor of the

top bench, respectively.

COMPARISON OF METHODS.

The differences between the drift and heading methods of excavating

tunnels through rock, consist chiefly in the excavations, strutting, and

hauling. When the drift method is employed an advanced gallery is opened

along the floor of the tunnel before the upper part of the section is

removed, and when the heading method is employed the upper part of the

section is completely excavated before any part of the section below is

excavated. When the drift method of driving is employed polygonal

strutting is usually used, and longitudinal strutting is employed with

the heading method of driving. In the drift method the hauling is done

by one system of tracks at the same level, while in the heading method

two systems of tracks are employed at different levels.

It is, perhaps, impossible to state without qualification which method

is the better. European engineers who have been connected with both the

Mont Cenis and St. Gothard tunnels, driven by the drift and heading

methods respectively, had the opportunity to practically observe the

advantages and disadvantages of these two methods. Their conclusion was

that the drift method was more convenient for tunnels driven through

hard and compact rock, and that the heading method was better for

tunnels of fissured and disintegrated rocks. To prove this opinion,

experiments were made in one of the tunnels approaching the great St.

Gothard tunnel. On a short tunnel the excavation was made by the drift

method from one portal, while at the other, the heading method was

followed. Although the general rule was fully confirmed still the

conditions at the portals were not identical. More conclusive

experiments were made by Mr. Ira A. Shaler, the contractor for Section

IV., of New York Rapid Transit Railway. He had the opportunity of

driving two parallel tunnels under Murray Hill only 17 ft. apart. The

eastern tunnel was driven by the drift method, the western one by the

heading method. After the work had proceeded for a few months, Mr.

Shaler stated that in his case the drift method was more convenient. He

could spare drilling several holes at each advance, thus obtaining

economy in time, labor and material without considering the advantage of

a simpler transportation of the débris. He promised to publish his

results for the benefit of the profession, but, unfortunately, lost his

life in an accident in the tunnel before the completion of the work.

An advantage that the drift method affords in long tunnels is, that the

water, which is usually found in large quantities under high mountains,

is easily collected in the drift and conveyed to the culvert, while in

the heading method the water from the advance gallery, before being

collected into the culvert built on the floor of the tunnel, must pass

through all the workings. This may be a serious inconvenience when water

is found in large quantities, as, for instance, was the case in the St.

Gothard tunnel, where the stream amounted to 57 gallons per second.

Tunneling: A Practical Treatise. · 第 11 / 18 章