CHAPTER X.

TUNNELS THROUGH HARD ROCK (Continued).

EXCAVATION BY DRIFTS: THE SIMPLON AND MURRAY HILL TUNNELS.

[Illustration: FIG. 55.--Diagram Showing Sequence of Excavations in

Drift Method of Tunneling Rock.]

=General Description.=--The method of tunneling through hard rock by

drifts is preferred by European engineers. All the great Alpine tunnels,

from the Mont Cenis tunnel to the Simplon, are examples of tunneling by

drifts. In this method the sequence of excavation is shown

diagrammatically by Fig. 55. The work begins by excavating a drift close

to the floor of the proposed tunnel (as shown in the center of the

figure) and far in advance of the excavation of any other part. The

section marked 2 is next removed and still later the portions marked 3.

Then with the removal of the parts marked 4 the whole section of the

tunnel will be open.

The drift is usually strutted by means of side posts carrying a

cap-piece placed at intervals, and having a ceiling of longitudinal

planks resting on the successive caps. In hard rock the roof of the

section does not, as a rule, require regular strutting, occasional

supports being placed at intervals to prevent the fall of isolated

fragments: When the rock is disintegrated or full of seams, a regular

strutting may be necessary, and this may be either longitudinal or

polygonal in type. When longitudinal strutting is employed, a sill is

laid across the roof of the drift, and upon this are set up two struts

converging toward the top and supporting a cap-piece close to the roof.

On this cap-piece are placed the first longitudinal crown bars carrying

transverse poling-boards. Additional props standing on the sill and

radiating outward are inserted as parts No. 3 are excavated. These

radial props carry longitudinal bars which in turn support transverse

poling-boards. When polygonal strutting is used, it may take the form of

three or five segment arches of heavy timbers.

In hard rock tunnels, as a rule, there is no danger of caving in because

of heavy pressures, and the whole section is left open for some time

before it is lined. The lining may be of concrete masonry, but in many

long tunnels, excavated through hard rock, the side walls are lined with

rubble masonry and the arch with brick, and, in some instances, even the

arch has been lined with rubble masonry. With skilful laborers at hand

the rubble masonry lining has proved most efficient and economical,

because the rock is utilized as it is excavated without any further

operation. Concrete, however, is more extensively employed for lining

tunnels than any other material.

Tunnels excavated by drifts enable simple means of hauling to be

employed, and this is one of the reasons why the method finds so much

favor with European engineers. The tracks are laid along the floor of

the drift, and carry all the spoil from parts Nos. 2, 3, and 4, as well

as from the front of the drift itself. As fast as the full section is

completed, this single track in the drift is replaced by two tracks

running close to the sides of the tunnel, or by a broad-gauge track with

a third rail.

THE SIMPLON TUNNEL.[8]

Before entering upon a description of the constructive details of this,

the longest railway tunnel in the world, it may be well to give a

general idea of the undertaking. Many schemes for the connection of

Italy and Switzerland by a railway near the Simplon Road Pass have been

devised, including one involving no great length of underground work,

the line mounting by steep gradients and sharp curves. The present

scheme, put forward in 1881 by the Jura-Simplon Ry. Co., consists

broadly of piercing the Alps between Brigue, the present railway

terminus in the Rhone Valley, and Iselle, in the gorge of the Diveria,

on the Italian side, from which village the railway will descend to the

existing southern terminus at Domo d’Ossola, a distance of about 11

miles.

[8] Abstract from a paper read before the Institution of Civil

Engineers by Charles B. Fox, Jan. 26, 1900.

In conjunction with this scheme a second tunnel is proposed, to pierce

the Bernese Alps under the Lötschen Pass from Mittholz to a point near

Turtman in the Rhone Valley; and thus, instead of the long détour by

Lausanne and the Lake of Geneva, there will be an almost direct line

from Berne to Milan _via_ Thun, Brigue, and Domo d’Ossola.

Starting from Brigue, the new line, running gently up the valley for

1¹⁄₄ miles, will, on account of the proximity of the Rhone, which has

already been slightly diverted, enter the tunnels on a curve to the

right of 1050 ft. radius. At a distance of 153 yards from the entrance,

the straight portion of the tunnel commences, and extends for 12 miles.

The line then curves to the left with a radius of 1311 ft. before

emerging on the left bank of the Diveria. Commencing at the northern

entrance, a gradient of 1 in 500 (the minimum for efficient drainage)

rises for a length of 5¹⁄₂ miles to a level length of 550 yards in the

center, and then a gradient of 1 in 143 descends to the Italian side. On

the way to Domo d’Ossola one helical tunnel will be necessary, as has

been carried out on the St. Gothard. There will be eventually two

parallel tunnels having their centers 56 ft. apart, each carrying one

line of way; but at the present time only one heading, that known as No.

1, is being excavated to full size, No. 2 being left, masonry lined

where necessary, for future developments. By means of cross headings

every 220 yds. the problems of transport and ventilation are greatly

facilitated, as will be seen later. As both entrances are on curves, a

small “gallery of direction” is necessary, to allow corrections of

alinement to be made direct from the two observatories on the axis of

the tunnel.

The outside installations are as nearly in duplicate as circumstances

will allow, and consist of the necessary offices, workshops,

engine-sheds, power-houses, smithies, and the numerous buildings

entailed by an important engineering scheme. Great care is taken that

the miners and men working in the tunnel shall not suffer from the

sudden change from the warm headings to the cold Alpine air outside; and

for this purpose a large building is in course of erection, where they

will be able to take off their damp working clothes, have a hot and cold

douche, put on a warm dry suit, and obtain refreshments at a moderate

cost before returning to their homes. Instead of each man having a

locker in which to stow his clothes, a perfect forest of cords hangs

down from the wooden ceiling, 25 ft. above floor-level, each cord

passing over its own pulleys and down the wall to a numbered

belaying-pin. Each cord supports three hooks and a soap-dish, which,

when loaded with their owner’s property, are hauled up to the ceiling

out of the way. There are 2000 of these cords, spaced 1 ft. 6 ins.

apart, one to each man. The engineers and foremen are more privileged,

being provided with dressing-rooms and baths, partitioned off from the

two main halls. An extensive clothes washing and drying plant has been

laid down, and also a large restaurant and canteen. At Iselle, a

magazine holding 2200 lbs. of dynamite is surrounded and divided into

two separate parts by earth-banks, 16 ft. high. The two wooden houses,

in which the explosive is stored, are warmed by hot-water pipes to a

temperature between 61° F. and 77° F., and are watched by a military

patrol; but at Brigue a dynamite manufactory, started by an enterprising

company at the time of the commencement of the works, supplies this

commodity at frequent intervals, thereby avoiding the necessity of

storing in such large quantities. This dynamite factory has been

largely increased, and supplies dynamite to nearly all the mining and

tunneling enterprises in Switzerland.

=Geological Conditions.=--Before the Simplon tunnel was authorized,

expert evidence was taken as to the feasibility of the project. The

forecasts of the three engineers chosen, in reference to the rock to be

encountered and its probable temperature, have, as far as the galleries

have gone (an aggregate distance of nearly 2¹⁄₂ miles), generally been

found correct. At the north end, a dark argillaceous schist veined with

quartz was met with, and from time to time beds of gypsum and dolomite

have been traversed, the dip of the strata being on the whole favorable

to progress, though timbering is resorted to at dangerous places. Water

was plentiful at the commencement; in fact, one inrush has not been

stopped, and is still flowing down the heading. The total quantity of

water flowing from the tunnel mouth is 16 gallons per second, of which 2

gallons per second are accounted for by the drilling machines. At

Iselle, however, a very hard antigorio gneiss obtains, and is likely to

extend for 4 miles. Very dry and very compact, it requires no timbering,

and represents no great difficulty to the powerful Brandt rock-drills,

which work under a head of 3280 ft. of water.

The temperature of the rock depends not only on the depth from the

surface, but largely upon the general form of that surface combined with

the conductivity of the rock. Taking these points into consideration

with the experience gained from the construction of the St. Gothard

tunnel, 95° F. was estimated as the probable maximum temperature, owing

to the height of Monte Leone (11,660 ft.), which lies almost directly

over the tunnel axis.

=Survey.=--After having determined upon the general position of the

tunnels, taking into consideration the necessary gradients, the

temperature of the rock, and a large bed of troublesome gypsum on the

north side, two fixed points on the proposed center line were taken,

one at each entrance of tunnel No. 1, and the bearings of these two

points, with reference to a triangulation survey made in 1876, were

calculated sufficiently accurately to determine, for the time being, the

direction of the tunnel. In 1898, a new triangulation survey was made,

taking in eleven summits, Monte Leone holding the central position. This

survey was tied into that of the Wasenhorn and Faulhorn, made by the

Swiss Government, and the accuracy was such that the probable error in

the meeting of the two headings is only 6 cms. or 2¹⁄₂ ins.

On the top of each summit is placed a signal, consisting of a small

pillar of masonry founded on rock, and capped with a sharp pointed cone

of zinc, 1 ft. 6 ins. high. An observatory was built at each end of the

tunnel in such a position that three of the summits could be seen, a

condition very difficult to fulfill on the south side owing to the depth

of the gorge, the mountains on either side being over 7000 ft. high.

Having taken the angles to and from each visible signal, and therefrom

having calculated the direction of the tunnel, it was necessary to fix,

with extreme accuracy, sighting-points on the axis of the tunnel, in

order to avoid sighting on to the surrounding peaks for each subsequent

correction of the alinement of the galleries. To do this, a theodolite

24 ins. long and 2³⁄₈ ins. in diameter, with a magnifying power of 40

times, was set up in the observatory, and about 100 readings were taken

of the angles between the surrounding signals and the required

sighting-points. In this manner the error likely to occur was diminished

to less than 1′. Thus at the north end two points were found about 550

yds. before and behind the observatory, while on the south side, owing

to the narrowness of the gorge, the points could only be placed at 82

yds. and 126 yds. in front. One of these sighting-points consists of a

fine scratch ruled on a piece of glass fixed in an iron frame, behind

which is placed an acetylene lamp,--corrections of alinement are always

done by night,--the whole being rigidly fixed into a niche cut in the

rock and protected from climatic and other disturbing agencies by an

iron plate.

=Method of Checking Alinement.=--The direction of heading No. 1 is

checked by experts from the Government Survey Department at Lausanne

about three times a year, and for this purpose a transit instrument is

set up in the observatory. A number of three-legged iron tables are

placed at intervals of 1 mile or 2 miles along the axis of tunnel No. 1,

and upon each of these is placed a horizontal plane, movable by means of

an adjusting screw, in a direction at right angles to the axis, along a

graduated scale. On this plane are small sockets, into which the legs of

an acetylene lamp and screen, or of the transit instrument, can be

quickly and accurately placed. The screen has a vertical slit, 3 ins. in

height, and variable between ¹³⁄₁₆ in. and ³⁄₁₆ in. in breadth,

according to the state of the atmosphere, and at a distance shows a fine

thread of light. The instrument, having first been sighted on to the

illuminated scratch of the sighting-point, is directed up the tunnel,

where a thread of light is shown from the first table. With the aid of a

telephone this light is adjusted so that its image is exactly coincident

with the cross hairs, and the reading on the graduated scale is noted.

This is done four or five times, the average of these readings being

taken as correct, and the plane is clamped to that average. The

instrument is then taken to the first table and is placed quickly and

accurately over the point just found (by means of the sockets), and the

lamp is carried to the observatory. After first sighting back, a second

point is given on the second table, and so on. These points are marked

either temporarily in the roof of the heading by a short piece of cord

hanging down, or permanently by a brass point held by a small steel

cylinder, 8 ins. long and 3 ins. in diameter, embedded in concrete in

the rock floor, and protected by a circular casting, also sunk in cement

concrete, holding an iron cover resembling that of a small manhole. From

time to time the alinement is checked from these points by the

engineers, and after each blast the general direction is given by the

hand from the temporary points. To check the results of the

triangulation survey, astronomical observations have been taken

simultaneously at each end. With regard to the levels, those given on

the excellent Government surveys have been taken as correct, but they

have also been checked over the pass.

=Details of Tunnels.=--In cross-section, tunnel No. 1 is 13 ft. 7 ins.

wide at formation level, increasing to 16 ft. 5 ins., with a total

height of 18 ft. above rail-level, and a cross-sectional area of about

250 sq. ft. This large section will allow of small repairs being

executed in the roof without interruption of the traffic, and will also

allow of strengthening the walls by additional masonry on the inside.

The thickness of the lining, never wholly absent, and the material of

which it is composed, depend upon the pressure to be resisted, and only

in the worst case is an invert resorted to. The side drain, to which the

rock floor is made to slope, will be composed of half-pipes of 7 to 1

cement concrete. The roof is constructed of radial stones.

Tunnel No. 2, being left as a heading, is driven on that side nearest to

No. 1, to minimize the length of the cross-headings, and measures 10 ft.

2 ins. wide by 6 ft. 7 ins. high. Masonry is used only where necessary,

and in that case is so built as to form part of the lining of the tunnel

when eventually completed. Concrete is put in to form a foundation for

the side wall, and a water channel. The cross-headings, connecting the

two parallel headings, occur every 220 yds., and are placed at an angle

of 56° to the axis of the tunnel, to avoid sharp curves in the

contractors’ railway lines. They will eventually be used as much as

possible for refuges, chambers for storing the tools and equipment of

the platelayers, and signal-cabins. The refuges, 6 ft. 7 ins. wide by 6

ft. 7 ins. high and 3 ft. 3 ins. deep, occur every 110 yards, every

tenth being enlarged to 9 ft. 10 ins. wide by 9 ft. 10 ins. deep and 10

ft. 2 ins. high, still larger chambers being constructed at greater

intervals.

=Method of Excavation.=--The work at each end of the tunnel is carried

on quite independently, consequently, though similar in principle, the

methods vary in detail, apart from the fact that different geological

strata require different treatment. Broadly speaking, the two parallel

headings, each 59 sq. ft. in section, are first driven by means of

drilling-machines and the use of dynamite, this work being carried on

day and night, seven days in the week; No. 1 heading is then enlarged to

full size by hand-drilling and dynamite. On the Italian side, where the

rock is hard and compact, breakups are made at intervals of 50 yds., and

a top gallery is driven in both directions, but, for ventilation

reasons, is never allowed to get more than 4 yds. ahead of the break-up,

which is gradually lengthened and widened to the required section. No

timbering is required, except to facilitate the excavation and the

construction of the side walls. Steel centers are employed for the arch;

they entail fewer supports, give more room, and are capable of being

used over again more frequently without damage. They consist of two

I-beams bent to a template and riveted together at the crown, resting at

either side on scaffolding at intervals of 6 ft.; longitudinals 12 ft.

by 4 ins. by 4 ins. support the roof. Hand rock-drilling is carried out

in the ordinary way, one man holding the tool and a second striking;

measurements of excavation are taken every 2 or 3 yds., a plumb-line is

suspended from the center of the roof, and at every half-meter (20 ins.)

of height horizontal measurements are taken to each side.

At the Brigue end a softer rock is encountered, necessitating at times

heavy timbering in the heading, and especially in the final excavation

to full size, Fig. 56. The bottom heading, 6 ft. 6 in. high, is driven

in the center, and the heading is then widened to the full extent and

timbered; the concrete forming the water channel and the foundation for

one side wall is put in; the side walls are built to a height of 6 ft. 6

ins., and the tunnel is fully excavated to a further height of 6 ft. 6

ins. from the first staging. The side walls are then continued up for

the second 6 ft. 6 ins., and from the second floor a third height of 6

ft. 6 ins. is excavated and timbered. Finally the crown is cleared out,

heavy wooden centers are put in, the arch is turned and all timbers are

withdrawn except the top poling-boards, supporting the loose rock.

[Illustration: FIG. 56.--Sketches Showing Sequence of Work in Excavating

and Lining the Simplon Tunnel.

1

2

3

4

5

6

7

8]

The masonry for the side walls is obtained either from the tunnel itself

or from a neighboring quarry, and varies in character according to the

pressure; but the face of the arch is always of cut or artificial

stones, the latter being 7 to 1 cement concrete. Where the alinement

heading, or the “gallery of direction,” joins the curving portion of

tunnel No. 1, the section is very much greater, and necessitates special

timbering.

=Transport (Italian Side).=--A small line of railway, 2 ft. 7¹⁄₂ ins.

gauge, with 40-lb. rails, enters all three portals; but since the

construction of a wooden bridge over the Diveria, the route through the

“gallery of direction,” across heading No. 2, to tunnel No. 1, is used

exclusively; this railway leads to the face in both headings, and, where

convenient, from one heading to the other by the cross-galleries.

Different types of wagons are in use; but in general they are

four-wheeled, non-tipping box wagons, supplied with brakes and holding 2

cu. yds. of débris. A special type of locomotive is used, designed to

pass round curves of 50 ft. radius, and supplied with a specially large

boiler to avoid firing in the tunnel.

[Illustration: FIG. 57.--General Details of the Brandt Rotary Drills

Employed at the Simplon Tunnel.]

=Method of Working.=--The drilling-machines employed are of the Brandt

type, Fig. 57, and are mounted in the following manner: A small

four-wheeled carriage supports at its center a beam, the shorter arm of

which carries the boring mechanism and the longer a counterpoise; near

its center is the distributor. In the short arm is a clamp holding the

rack-bar or butting column, which is a wrought-iron cylinder with a

plunger constituting a ram, and is jammed by hydraulic pressure between

the walls of the heading, thus forming a rigid support for the

boring-machine, and an efficient abutment against the reaction of the

drill. This rack-bar can be rotated on its clamp in a plane parallel to

the axis of the beam. Three or four separate boring-machines can be

mounted on the rack-bar, and can be adjusted in any reasonable position.

The boring-machine performs the double function of continually pressing

the drill into the rock by means of a hollow ram (_I_) and of imparting

to the drill and ram a uniform rotary motion. This rotary motion is

given by a twin cylinder single-acting hydraulic motor (_E_), the two

pistons, of 2⁷⁄₈ ins. stroke, acting reciprocally as valves. The cranks

are fixed at an angle of 90° to each other on the shaft, which carries a

worm, gearing with a worm-wheel (_Q_) mounted upon the shell (_R_) of

the hollow ram (_I_), and this shell in turn engages the ram by a long

feather, leaving it free to slide axially to or from the face of the

rock. The average speed of the motor is 150 revolutions to 200

revolutions per minute, the maximum speed being 300 revolutions per

minute. The loss of power between the worm and worm-wheel is only 15% at

the most; the worm being of hardened steel and the wheel of gun-metal,

the two surfaces in contact acquire a high degree of polish, resulting

in little wearing or heating. Taking into consideration all other

sources of loss, 70% of the total power is utilized. The pressure on the

drill is exerted by a cylinder and hollow ram (_I_), which revolves

about the differential piston (_S_), which is fixed to the envelope

holding the shell (_R_). This envelope is rigidly connected to the

bed-plate of the motor, and, by means of the vertical hinge and pin

(_T_), is held by the clamp (_V_) embracing the rack-bar. When water is

admitted to the space in front of the differential piston the ram

carrying the drilling-tool is thrust forward, and when admitted to the

annular space behind the piston, the ram recedes, withdrawing the tool

from the blast-hole. The drill proper is a hollow tube of tough steel

2³⁄₄ ins. in external diameter, armed with three or four sharp and

hardened teeth, and makes from five to ten revolutions per minute,

according to the nature of the rock. When the ram has reached the end of

its stroke of 2 ft. 2¹⁄₂ ins., the tool is quickly withdrawn from the

hole and unscrewed from the ram; an extension rod is then screwed into

the tool and into the ram, and the boring is continued, additional

lengths being added as the tool grinds forward; each change of tool or

rod takes about 15 secs. to 25 secs. to perform. The extension rods are

forged steel tubes, fitted with four-threaded screws, and having the

same external diameter as the drill. They are made in standard lengths

of 2 ft. 8 ins., 1 ft. 10 ins., and 11³⁄₄ ins. The total weight of the

drilling-machine is 264 lbs., and that of the rack-bar when full of

water is 308 lbs. The exhaust water from the two motor cylinders escapes

through a tube in the center of the ram and along the bore of the

extension rods and drill, thereby scouring away the débris and keeping

the drill cool; any superfluous water finds an exit through a hose below

the motors and thence away down the heading. The distributor, already

mentioned, supplies each boring-machine and the rack-bar with hydraulic

pressure from the mains, with which connection is effected by means of

flexible or articulated pipe connections, allowing freedom in all

directions. The area of the piston for advancing the tool is 15¹⁄₂ sq.

ins., which, under a pressure of 1470 lbs. per sq. in., gives a pressure

of over 10 tons on the tool, while for withdrawing the tool 2¹⁄₂ tons is

available. In the rock found at Iselle, namely, antigorio gneiss, a hole

2³⁄₄ ins. in diameter and 3 ft. 3 ins. in length is drilled, normally,

in 12 mins. to 25 mins.; a daily rate of advance of 18 ft. to 19 ft. 6

ins. is made in a heading having a minimum cross-section of 59 sq. ft.;

the time taken to drill ten to twelve holes, 4 ft. 7 ins. deep, is 2¹⁄₂

hrs.

When the débris resulting from one operation has been sufficiently

cleared away, a steel flooring, which is provided near the face to

enable shoveling to be more easily done, and to give an even floor for

the wheels of the drilling-carriage, is laid bare at the head of the

line of rails, and the drilling-machines are brought up on their

carriage by eight or ten men. When advanced sufficiently close to the

face, the rack-bar is slewed round across the gallery and is wedged up

against the rock sides; connection is made between the distributor and

the hydraulic main, by means of the flexible pipe, and pressure is

supplied by a small copper tube to the rack-bar ram, thereby rigidly

holding the machine. Next, connections are made between the three

drilling-machines and the distributor, and in 20 mins. from the time the

machine was brought up all three drills are hard at work, water pouring

from the holes.

The noise of the motors and grinding-tools is sufficient to drown all

but shouts; and where the extension rods do not fit tightly, small jets

of water play in all directions, necessitating the wearing of tarpaulins

by the men directing the tools. Lighting is done wholly by small

oil-lamps, provided with a hook to facilitate fixing in any crack in the

rock; electricity will probably be used to light that portion of the

tunnel which is completed.

Two men are allotted to each drill, one to drive the motor, the other to

direct and replenish the tool, one foreman and two men in reserve

completing the gang. A small hammer is freely used to loosen the screw

joints of the extension rods and drill. A hole is usually commenced by a

two-edged flat-pointed tool, until a sufficient depth is reached to

prevent the circular tool from wandering over the face of the rock, but

in many instances the hole is commenced with a circular tool. The

exhaust water during this period flows away by the hose underneath the

motor. In the antigorio gneiss, ten to twelve holes are drilled for each

attack, three to four in the center to a depth of 3 ft. 3 ins., the

remainder, disposed round the outside of the face, having a depth of 4

ft. 7 ins. The average time taken to complete the holes is 1³⁄₄ hr. to

2¹⁄₂ hrs. Instead of pulverizing the rock, as do the diamond drills, it

is found that the rock is crushed, and that headway is gained somewhat

in the manner of a circular saw through wood. The core of rock inside

the tool breaks up into small pieces, and can be taken out if necessary

when the drill requires lengthening.

The lowest holes, inclined downwards, are full of water; consequently

two detonators and two fuses are inserted, but apart from this, water

has little effect on the charge. The fuses of the central holes are

brought together and cut off shorter than those of the outer holes, in

order that they may explode first to increase the effect of the outer

charges. All portable objects, such as drills, pipe connections, tools,

etc., have meanwhile been carried back; the steel flooring is covered

over with a layer of débris to prevent injury from falling rock, and to

the end of the hydraulic main is screwed a brass plug pierced by five

holes; and immediately the explosions occur a valve is opened in the

tunnel, and five jets of water play upon the rock, laying the dust and

clearing the air. The necessity for this was shown on one occasion when

this nozzle was broken by the explosion and the water had to be turned

off immediately to avoid useless waste; on reaching the face, the

atmosphere was found to be so highly charged with dust and smoke that it

was impossible to distinguish the stones at the feet, although a lamp

had been placed on the ground; and despite the fact that the air tube

was in full blast, the men experienced great difficulty in breathing. A

truck is now brought up, and four men clear a passage in front, through

the heap of débris, two with picks and two with shovels, while on either

side and behind are as many men as space will permit. The stone is

thrown either to the sides of the heading or into the wagon, shoveling

being greatly aided by the steel flooring, which, before the explosion,

had been laid over the rails for nearly 10 yds. down the tunnel to

receive the falling rock. These steel plates are taken up when cleared,

and the wagon is pushed forward until the drilling-machine can be

brought up again, leaving the remaining débris at the sides to be

handled at leisure during the next attack. The roof and side walls are,

of course, carefully examined with the pick, to discover and detach any

loose or hanging rock. The times taken for each portion of the attack in

this particular antigorio gneiss are as follows: Bringing up and

adjustment of drills, 20 mins.; drilling, between 1³⁄₄ hr. and 2¹⁄₂

hrs.; charging and firing, 15 mins.; clearing away débris, 2 hrs.; or

for one whole attack, between 4¹⁄₂ hrs. and 5¹⁄₂ hrs., resulting in an

advance of 3 ft. 9 in., or a daily advance of nearly 18 ft.

From this it appears that the time spent in clearing away the débris

equals that taken up in drilling, and it is in this clearing that a

saving of time is likely to be effected rather than in the process of

drilling. Many schemes have been tried, such as a mechanical plow for

making a passage; at Brigue, “marinage,” or clearing by means of

powerful high-pressure water-jets, directed down the tunnel, was tried,

but the idea is not yet sufficiently developed.

Another series of experiments has been tried at Brigue with regard to

the utilization of liquid air as an explosive agent instead of dynamite;

and for this purpose a plant has been laid down, consisting of one

ammonia-compressor, two air-compressors, and two refrigerators,

furnishing ¹⁄₁₀ gallon of liquid air per hour at an expenditure of 17 H.

P. The system used is that of Professor Linde, who himself directs the

experiments. The great difficulty experienced is that of shortening the

interval of time that must elapse between the manufacture of the

cartridge and its explosion. The liquid oxygen, with which the

cartridge, containing kieselguhr (silicious earth) and paraffin, is

saturated, evaporates very readily, losing power every moment; hence the

effect of each cartridge cannot be guaranteed, and though it is an

exceedingly powerful explosive when used immediately after manufacture,

no practical result has yet been obtained.

=Power Station.=--Water is abundant at either end, and therefore

hydraulic power is the motive force employed. On the Italian side, a dam

5 ft. high has been thrown across the Diveria at a point near the Swiss

frontier, about 3 miles above the site of the installations. A portion

of the water thus held back enters, through regulating doors and

gratings, a masonry channel leading to two parallel settling tanks, each

111 ft. by 16 ft., whence, after dropping all its sand and solid matter,

the now pure water passes into the water-house, and, after flowing over

a dam, through a grating and past the admission doors, enters a metallic

conduit of 3-ft. pipes. Each of the settling tanks and the approach

canal are provided with doors at the lower end leading direct to the

river, through which all the sand and solid matter deposited can be

scoured naturally by allowing the river-water to rush freely through.

For this purpose the floor of the basins is on an average gradient of 1

in 30. For a similar reason the river-bed just outside the entrance to

the approach canal is lined with wooden planks, from which the stones

collecting behind the dam can be scoured by allowing an iron flap,

hinged at the bottom, to change its position from the vertical to the

horizontal in a gap left purposely in the dam, so causing a rushing

torrent to sweep it clean.

The chief levels are:

Level of water at dam 794.00 meters above sea level.

„ in water-house 793.70 „ „ „ „

„ at turbines 618.50 „ „ „ „

giving a total fall of 175.20 ms. or 570 ft., and a pressure of 17.52

atmospheres.

The quantity of water capable of being taken from the Diveria in winter,

when the rivers which are dependent upon the mountain snows for their

supply are at their lowest, is calculated to be 352 gallons per second.

Thus, taking the fall to be diminished by friction, etc., to 440 ft.,

and the useful effect at 70%, there is obtained 2000 H. P. on the

turbine shaft.

The metallic conduit varies in material according to the pressure; thus

cast-iron pipes 3 ft. in diameter and ¹³⁄₁₆ in. thick are used up to a

pressure of 2 atmospheres, from which point they are of wrought-iron.

The cast-iron portion has of late caused a good deal of trouble, owing

to settlement of the piers causing occasional bursts, consequently a

masonry pier has been placed under each joint of this portion. The

following table gives the thicknesses and diameters, varying with the

pressure:

+---------+-------------+-------------+------+

| WATER | THICKNESS. | DIAMETER. |WEIGHT|

|PRESSURE.| | | PER |

| | | | YARD.|

+---------+-------+-----+-----+-------+------+

| Head | Milli-|Inch.|Feet.|Inches.| Lbs. |

| in Feet.|meters.| | | | |

+---------+-------+-----+-----+-------+------+

| 246 | 6 | ¹⁄₄ | 3 | 0 | 326 |

| 311 | 7 | ... | 3 | 0 | 383 |

| 360 | 8 | ... | 3 | 0 | 431 |

| 393 | 9 | ... | 3 | 0 | 483 |

| 426 | 10 | ... | 3 | 0 | 556 |

| 476 | 12 | ... | 3 | 0 | 651 |

| 590 | 16 | ⁵⁄₈ | 3 | 3¹⁄₃ | 977 |

+---------+-------+-----+-----+-------+------+

This pipe is supported every 30 ft. on small masonry piers, on the top

of which is placed a block of wood hollowed out to receive the pipe,

thus allowing any movement due to the contraction and expansion of the

conduit. However, to prevent this movement becoming excessive, the pipe

is passed at intervals of 300 yds. to 500 yds. through a cubical block

of masonry of 13 ft. side, strengthened by longitudinal tie-bars. Five

bands of angle-bar riveted round the pipe, with their flanges embedded

in the masonry, constitute a rigid fixed point. Straw mats are thrown

over the pipe where it is exposed to the sun. The temperature of the

conduit is not, however, found to vary greatly, since the pipe is kept

full of water. To supply the rock-drills with water at a maximum

pressure of 100 atmospheres, or 1470 lbs. per sq. in., a plant of four

pairs of high-pressure pumps has been laid down, and a still larger

addition is in course of erection. At present, two Pelton turbines of

250 H.P. each, running at 170 revolutions per minute, drive the pumps,

by means of toothed gearing, at 63 revolutions per minute. These pumps

are of very simple but strong construction, single suction and double

delivery, entailing one suction and one delivery-valve, both heavy and

both of small lift. The larger portion of the plunger has exactly double

the cross-sectional area of the smaller portion, so that in the forward

stroke half of the water taken in at the last admission is pumped into

the high-pressure mains, and at the same time a fresh supply of water is

sucked in. During the backward stroke half of this new supply is pumped

into the mains, and the remainder enters the second chamber, to be

pumped during the next forward stroke. Thus the work done in the two

strokes is practically the same. The pumps are in pairs, and are set at

an angle of 90°, to insure uniform pressure and uniform delivery in the

mains. Their size varies; but at Iselle there are three pairs, with a

stroke of 2 ft. 2¹⁄₂ ins., and the plungers of 2¹¹⁄₁₆ in. and 1⁷⁄₈ ins.

(approximately) in diameter, supplying 1.32 gallons per second.

To avoid injury to the valves, the water to be pumped is taken from a

stream up the mountain side, and is passed through filter screens. The

high-pressure water, after passing an accumulator, enters the tunnel in

solid drawn wrought-iron tubes, 3¹⁄₈ ins. in internal diameter, ³⁄₁₆ in.

thick, and in lengths of 26 ft. The diameter of these mains varies with

their length, so as to avoid loss of pressure. With the 1250 yds. of

tunnel now driven 10 atmospheres are lost.

At Brigue the installations are, as far as possible, identical. The

Rhone water, however, before reaching the water-house, is carried from

the filter basins, a distance of 2 miles, in an armored canal built upon

the Hennebique system,[9] the walls and supporting beams, of cement

concrete, being strengthened by internal tie-bars of steel. The concrete

struts, resembling balks of timber at a distance, are occasionally 35

ft. high and 1 ft. 7¹⁄₂ ins. square. The metallic conduit is 5 ft. in

diameter, with a minimum flow of 176 cu. ft. per second and a total fall

of 185 ft. In case water-power should be unavailable, three

semi-portable steam engines, two of 80 H.P. and one of 60 H.P., are

always kept in readiness at each end of the tunnel, and are geared by

belts to the turbine shaft.

[9] Network of steel rods embedded in concrete.

=Ventilation.=--In tunneling, one of the most important problems to be

solved is that of ventilation, and it is for this reason that the

Simplon tunnel consists of two parallel headings with cross cuts at

intervals of 220 yds. At Brigue, a shaft 164 ft. deep was sunk through

the overlying rock until the “gallery of direction” was encountered. Up

this chimney the foul air is drawn by wood fires, the fresh air--a

volume of 19,000,000 cu. ft. per day, or 13,200 cu. ft. per

minute--entering by heading No. 2, penetrating up to the last cross

gallery, and returning by tunnel No. 1. The entrances of No. 1 and the

“gallery of direction,” besides those of all the intermediate cross

galleries, are closed by doors. By this arrangement, however, fresh air

does not reach the working faces; therefore a pipe, 8 ins. in diameter,

is led from the fresh air in No. 2 to within 15 yds. of the face of each

heading, and up this pipe a draft of air is induced by means of a jet of

water, the volume to each face being 800 cu. ft. per minute. One single

jet of water from the high-pressure mains, with a diameter of ¹⁄₁₆ in.,

is capable of supplying over 1000 cu. ft. of air per minute at the end

of 160 yds. of pipe, and during the attack the men at the drills are in

a constant breeze with the thermometer standing at 70° F. At Iselle, air

is blown into the entrance of heading No. 2 at the rate of 14,100 cu.

ft. per minute by two fans driven from the turbine shaft. This air

travels from the fans along a pipe 18 ins. in diameter, till a point 15

yds. up the tunnel is reached, where beyond a door the pipe narrows to

form a nozzle 10 ins. in diameter. This door is kept open to allow the

outside air to be induced up the tunnel, as the headings are at present

only 2500 yds. long, giving a resistance of not quite sufficient power

to cause the air to return. The fresh air then travels up No. 2,

crossing over the top of the “gallery of direction,” from which it is

shut off by doors, to the last cross gallery, returning by No. 1, and

finally leaving either by the “gallery of direction” or by No. 1. A

system of cooling the air and driving it on by means of a large number

of water-jets will be installed in No. 2 where that heading crosses over

the “gallery of direction,” but at present there is no need for it.

The average temperature at the face is 73° F. during the drilling

operation, 76° F. after firing the charges, and a maximum of 80° F.,

lately attaining to 86° F. on the south side, with 80° F. and 85° F.

before and after firing. The temperature of the rock is taken at every

110 yds. in holes 5 ft. deep, and shows a gradual increase according to

the depth of over-laying rock, to the conductivity of the rock, and to

the form of the mountain surface. The maximum hitherto reached on the

north side is 68° F., while on the south side, although a smaller

distance has been traversed, it attains to 79° F., due to the more rapid

increase in depth. Moreover, the temperature of the rock is observed at

the permanent stations, 550 yds. from the entrances, in its relation to

that of the tunnel and outside air, and though on the north side that of

the rock varies almost as quickly as that of the tunnel air, on the

south it is influenced very much less.

A few statistics may be of interest with regard to the progress of the

last three months (taken from the trimestrial report of January, 1900).

At Brigue, where there are three drilling-machines in No. 1 and two in

the parallel heading, the total length excavated was 995 yds. or 6409

cu. yds. in 89 working days, the average cross-sectional area being 57

sq. ft. This required 507 attacks and 3066 holes, which had a total

depth of 26,600 ft. and 14,700 re-sharpenings of the drilling-tool, with

44,000 lbs. of dynamite.

The average time occupied in drilling was 2 hrs. 45 mins., while

charging, firing, and clearing away the débris took 6 hrs., 35 mins. At

Brigue 648 men and 29 horses were employed at one time in the tunnel. At

Iselle the numbers were 496 men and 16 horses, working in shifts of 8

hrs. Outside the tunnel, in the shops, forges, etc., the men work 8 hrs.

to 11 hrs. per day, the total being 541 men at Brigue and 346 men at

Iselle. On the Italian side, where the rock is very much harder, there

were three drilling-machines in each heading; the total length

excavated, with a cross-sectional area of 62 sq. ft., was 960 yds. or

6700 cu. yds. in 91 working days. This required 61,293 re-sharpened

tools, 758 attacks, 7940 holes with a total depth of 33,000 ft., and

56,000 lbs. of dynamite. The average time spent in drilling was 2 hrs.

55 mins., and in charging and clearing 2 hrs. 36 mins. Thus, in the hard

gneiss, to excavate 1 cu. yd. of rock required 8¹⁄₂ lbs. of dynamite,

and each tool pierced 6¹⁄₂ ins. of rock before it required

re-sharpening.

THE MURRAY HILL TUNNEL.

The drift method of excavating tunnels was followed in Section IV of the

New York Subway, under Park Avenue between 33rd and 41st Streets. At

this point the four tracks of the subway pass under a rocky elevation,

known as Murray Hill, in two double track parallel tunnels, 43 ft.

apart, center to center. Here already existed a double track tunnel

which was built many years ago by the New York Central and Hudson River

R.R., and is now used by the Madison Avenue surface cars. The two subway

tunnels were driven close below the existing tunnel and also very near

the foundations of expensive residences along Park Avenue, particularly

on Murray Hill, one of the best residential sections of the city.

=Material Penetrated.=--The material penetrated by the excavation

consisted chiefly of a surface outcrop of the mica-schist rock which

underlies Manhattan Island. The rock was for the most part in compact

strata, dipping at about 45° from East to West, but at intervals an

unstable stratum was encountered which when free slid on the underlying

stratum. Troubles from such slides were experienced during the

construction of the tunnel.

=Cross-Section.=--The cross-section selected for the tunnels had

vertical side walls and a three-centered roof arch with the flattest

curve at the crown. The interior dimensions were 25 ft. wide and 16 ft.

high. The selected cross-section was not the best suited for a tunnel to

be driven through rock, where the sharpest curve should be at the top,

but in this case the flattened curve was chosen because of local

conditions; chiefly, the presence of the existing tunnel and the

consequent necessity of leaving a certain thickness of rock between it

and the new tunnel, without depressing very much the grade of the

subway.

[Illustration: FIG. 58.--Sequence of Excavation in the Murray Hill

Tunnel.]

=Excavation.=--The two parallel tunnels were driven exclusively from the

ends reached by shafts; thus the tunnels were attacked at four parts. It

was in these tunnels that a comparative test was made of the different

methods of driving tunnels through rock. The contractor applied the

heading and drift method at the southern ends of the tunnels, the

eastern tunnel being driven by means of a drift while in the western

tunnel the usual heading method was followed. This latter method is

illustrated in the chapter following and the eastern tunnel at 33rd

Street, excavated by means of a drift, is here considered.

Fig. 58 shows the sequence of cuts adopted for this tunnel. It was begun

by a bottom drift, about 10 ft. high, 8 ft. wide and 7 ft. deep, which

was located at one side of the axis of the tunnel, as indicated in the

figure. This drift was immediately widened by removing the portions

marked 2. About 50 ft. in the rear the part marked 3 was taken away,

thus clearing the entire lower portion of the tunnel. Section 4, about

50 ft. to the rear of section 3, was then broken down and removed.

The methods of drilling and blasting were as follows: In taking out the

original drift, a wedge-shaped center cut was made and then enlarged to

the full size of the drift by drilling parallel holes. The succeeding

sections, 2 and 3, were removed by driving parallel holes, while the top

section, 4, was taken away by a center cut and parallel holes. The

drills were mounted on columns, two drills to a column, and the holes

were usually drilled about 7 ft. deep, starting with a diameter of 2³⁄₄

in. and ending with a diameter of 1³⁄₄ in. They were blasted with 40%

dynamite in light charges, only a few holes being fired at a time,

usually not more than three or four.

[Illustration: FIG. 59.--Traveling Platform for the Excavation of the

Upper Side of the Murray Hill Tunnel.]

To remove section 4, a traveling platform 10¹⁄₂ ft. long and 25 ft. wide

was used. This platform, as shown in Fig. 59, consisted of two

longitudinal beams mounted on four double flanged wheels which were

running on tracks laid 23 ft. apart. Resting on top of these beams were

four 12 in. × 12 in. uprights braced in every direction against the

framework of the platform. This frame was built of 12 in. × 12 in. beams

laid longitudinally, the transverse beams being 12 in. × 14 ins. The

platform proper was made of 3 in. planks, and was set 9 ft. above the

tunnel floor. The columns supporting the drills for the excavation of

the upper section 4, were set up above the platform which was then

reinforced by other vertical props, as indicated by the dotted lines in

the figure. These props, however, were placed so as to leave a clearance

beneath the platform for the cars to carry away the débris from the

front. During the blasting the platform was moved back so that the

blasted rock fell to the floor of the tunnel, whence it was loaded into

boxes on the cars.

=Strutting.=--When the rock was seamy and full of fissures, running in

every direction, it was necessary to support the roof of the excavation.

This was done in the following manner: After part 4 was removed the

timbers supporting the roof of the excavation were set up. In this case,

the polygonal strutting was used. This consisted of heavy timber frames

placed transversely to the axis of the tunnel and supporting the planks

or poling-boards which ran longitudinally against the roof of the

excavation. The seven-segment arch frame was used in the Murray Hill

tunnel. At the bottom of part 4 were placed longitudinally 12 × 16 in.

beams and upon them rested the inclined segments which, with a

horizontal one, formed the arch frame as shown in Fig. 60. When the

pressures were too heavy the crown segment was reinforced by a 6 × 12

in. beam, kept in place by two 12 × 12 in. inclined props which rested

on the templates. As the tunnel was lined with concrete, the timbering

was left in place and it was built outside the line of the extrados of

the concrete lining. Timbering was only used for a short distance but it

necessitated a larger amount of rock excavation when it was required.

[Illustration: FIG. 60.--Timbering Used in the Murray Hill Tunnel.]

=Hauling.=--Great efficiency was shown in the method of hauling away the

excavated materials. Three narrow-gauge parallel tracks were laid on the

floor of the tunnel and extended to the faces of the advance drifts.

Small flat cars were run on these tracks. They carried steel boxes, 5

ft. square and 15 ins. deep, fitted with three lifting rings and chains.

When filled, the cars were run to the bottom of the shaft, the boxes

were hoisted by a stiff-legged derrick placed at the shaft head, and the

débris was dumped into storage bins of 300 cu. yds. capacity. These bins

were elevated 8 ft. above the street so that the wagons could be driven

under it to take loads of spoil by means of chutes. The broken rock was

loaded into the boxes by hand.

=Concrete Lining.=--The tunnel was lined with concrete which was

manufactured by a quite elaborate plant. A stone crushing plant,

consisting of bins for raw and crushed stone, was erected at the shaft

head and a mixing plant was suspended from the shaft. On the platform of

the shaft head were two bins side by side, one for crushed stone, the

other for sand; both of which communicated, by means of trap doors, with

a hopper chute. The materials from the hopper were delivered into a

measuring box where cement was laid on top of the other ingredients by

hand. They were then conveyed through a canvas chute into a cubical

mixer operated by an engine. The mixer discharged its contents into

skips set on cars at the bottom of the shaft and the concrete was hauled

inside the tunnel ready for use.

The construction of the lining was accomplished by means of traveling

platforms. The footing courses were laid first. Because these projected

inward about 18 ins. from the faces of the finished sidewalks it was

possible to lay a track rail on their top inner edges on each side of

the tunnel. These track rails carried the traveling platforms. There

were three of these platforms; the forward one was used for building the

side walls; the center one, for carrying a derrick; the last one, for

building the roof arch. The side wall platform was mounted on six

wheels. On each side there was mounted an adjustable lagging which was

curved to conform to the inside profile of the side wall. In operation

this platform was run to the point where the side walls were to be

constructed and the lagging was adjusted to position and fastened. Skips

of concrete were then hoisted on its top, their contents were shoveled

into the space between the lagging and the wall of the excavation and

were there rammed into place until the finished concrete had reached the

top of the lagging. When the concrete had set, the wedges holding the

lagging in place were loosened and the platform was moved ahead and

adjusted for building a new section of wall. The derrick platform was

23¹⁄₂ ft. wide and 18 ft. long. Transversely, it had three bays, two of

which were floored over and one was left without flooring to allow

passage for the concrete skips to and from the cars, on the tunnel floor

beneath. At the center of the floored area was mounted a derrick to

handle the skips. In operation, the derrick platform came between the

side wall platform ahead and the roof platform behind. The construction

of the roof platform was practically the same as the side wall platform

with the addition of roof arch centers at each bent on which lagging

could be placed. The mode of procedure was to erect the form for a small

space between the side walls already built and the haunches of the

center, to shovel concrete from the skips and to run it into place. Then

the roof lagging, a part at a time, was placed upward from the haunches

and the concrete was filled and rammed behind it. The lining was built

from the haunches upward until the two sides approached within a

distance of about 5 ft. from each other at the crown. This 5 ft. crown

strip or key was built by working from the rear toward the front end of

the platform.

=Plant.=--The plant used by the contractors for Section IV. of the

subway comprised a central power plant located about 4000 ft. from the

work. This was on 42nd Street near the East River and furnished power

for the work on both Sections IV. and V. The buildings consisted of an

engine room 63 × 30 ft. and a boiler room, 42 × 28 ft. In the former

room was located one Rand-Corliss air compressor, 22 × 40 × 48 ins.,

having a capacity of 5000 cu. ft. of free air per minute; in the latter

room there were two 200 H.P. water tube boilers. There were also the

necessary equipment of feed water pump, air condenser pump, etc. The

compressors discharged into a 20 × 5¹⁄₂ ft. receiver of riveted steel

through a 7 in. pipe. The air from the receiver was carried by a 10 in.

pipe 3.277 ft. to the corner of Park Avenue and 41st Street, and was

thence run south along Park Avenue in an 8 in. pipe, from which 3 in.

branches led to the four headings of the work.

=Ventilation.=--The ventilation of the tunnel caused very little

trouble. In cool weather the natural draft of the shafts and the air

discharged from the drills served to keep the atmosphere wholesome. In

warm weather, artificial means were necessary to clear the workings of

foul air, particularly after blasting. They comprised at each end a 4

ft. American exhaust fan drawing air from a 12 in. riveted galvanized

iron pipe, which extended to the working faces.

=Illumination.=--The tunnel was lighted by electric lamps which extended

even to the working face. During the blasting, however, all the lamps

and wires within 100 ft. from the front were removed and gasoline

torches were used; they were also employed before the electric lamps and

wires could be replaced, to light the tunnel during the operation of

clearing the débris.