CHAPTER IX.

TUNNELS THROUGH HARD ROCK; GENERAL DISCUSSION; REPRESENTATIVE MECHANICAL

INSTALLATIONS FOR TUNNEL WORK.

The present high development of labor-saving machinery for excavating

rock makes this material one of the safest and easiest to tunnel of any

with which the engineer ordinarily has to deal. To operate this

machinery requires, however, the development of a large amount of power,

its transmission to considerable distances, and, finally, its economical

application to the excavating tools. The standard rock excavating

machine is the power drill, which requires either air or hydraulic

pressure for its operation according to the special type employed. Under

present conditions, therefore, the engineer is limited either to air or

water under compression for the transmission of his power. Steam-power

may be employed directly to operate percussion rock drills; but owing to

the heat and humidity which it generates in the confined space where the

drills work, and because of other reasons, it is seldom employed

directly. Electric transmission, which offers so many advantages to the

tunnel builder, in most respects is largely excluded from use by the

failure which has so far followed all attempts to apply it to the

operation of rock drills. As matters stand, therefore, the tunnel

engineer is practically limited to steam and falling water for the

generation of power, and to compressed air and hydraulic pressure for

its transmission.

Whether the engineer should adopt water-power or steam to generate the

power required for his excavating machinery depends upon their relative

availability, cost, and suitability to the conditions of work in each

particular case. Where fuel is plentiful and cheap, and where

water-power is not available at a comparatively reasonable cost,

steam-power will nearly always prove the more economical; where,

however, the reverse conditions exist, which is usually the case in a

mountainous country far from the coal regions, and inadequately supplied

with transportation facilities, but rich in mountain torrents,

water-power will generally be the more economical. In a succeeding

chapter the power generating and transmission plants for a number of

rock tunnels are described, and here only a general consideration of the

subject will be presented.

=Steam-Power Plant.=--A steam-power plant for tunnel work should be much

the same as a similar plant elsewhere, except that in designing it the

temporary character of its work must be taken into consideration. This

circumstance of its temporary employment prompts the omission of all

construction except that necessary to the economical working of the

plant during the period when its operation is required. The power-house,

the foundations for the machinery, and the general construction and

arrangement, should be the least expensive which will satisfy the

requirements of economical and safe operation for the time required. It

will often be found more economical as a whole to operate the machinery

with some loss of economy during the short time that it is in use than

to go to much greater expense to secure better economy from the

machinery by design and construction, which will be of no further use

after the tunnel is completed. The longer the plant is to be required,

the nearer the construction may economically approach that of a

permanent plant. As regards the machinery itself, whose further

usefulness is not limited by the duration of any single piece of work,

true economy always dictates the purchase of the best quality. Speaking

in a general way, a steam-power plant for tunnel work comprises a boiler

plant, a plant of air compressors with their receivers, and an electric

light dynamo. When hydraulic transmission of power is employed, the air

compressors are replaced by high-pressure pumps; and when electric

hauling is employed, one or more dynamos may be required to generate

electricity for power purposes, as well as for lighting. In addition to

the power generating machines proper, there must be the necessary piping

and wiring for transmitting this power, and, of course, the equipment of

drills and other machines for doing the actual excavating, hauling, etc.

=Reservoirs.=--When water-power is employed, a reservoir has to be

formed by damming some near-by mountain stream at a point as high as

practicable above the tunnel. The provision of a reservoir, instead of

drawing the water directly from the stream, serves two important

purposes. It insures a continuous supply and constant head of water in

case of drought, and also permits the water to deposit its sediment

before it is delivered to the turbines. The construction of these

reservoirs may be of a temporary character, or they may be made

permanent structures, and utilized after construction is completed to

supply power for ventilation and other necessary purposes. In the first

case they are usually destroyed after construction is finished. In

either case, it is almost unnecessary to say, they should be built amply

safe and strong according to good engineering practice in such works,

for the duration of time which they are expected to exist.

=Canals and Pipe Lines.=--For conveying the water from the reservoirs to

the turbines, canals or pipe lines are employed. The latter form of

conduit is generally preferable, it being both less expensive and more

easily constructed than the former. It is advisable also to have

duplicate lines of pipe to reduce the possibility of delay by accident

or while necessary repairs are being made to one of the pipes. The pipe

lines terminate in a penstock leading into the turbine chamber, and

provided with the necessary valves for controlling the admission of

water to the turbines.

=Turbines.=--There are numerous forms of turbines on the market, but

they may all be classed either as impulse turbines or as reaction

turbines. Impulse turbines are those in which the whole available energy

of the water is converted into kinetic energy before the water acts on

the moving part of the turbine. Reaction turbines are those in which

only a part of the available energy of the water is converted into

kinetic energy before the water acts on the moving vanes. Impulse

turbines give efficient results with any head and quantity of water, but

they give better results when the quantity of water varies and the head

remains constant. Reaction turbines, on the contrary, give better

results when the quantity of water remains constant and the head varies.

These observations indicate in a general way the form of turbine which

will best meet the particular conditions in each case. The number of

turbines required, and their dimensions, will be determined in each case

by the number of horse-power required and the quantity of water

available. The power of the turbines is transmitted to the air

compressors or pumps by shafting and gearing.

=Air Compressors.=--An air compressor is a machine--usually driven by

steam, although any other power may be used--by which air is compressed

into a receiver from which it may be piped for use. For a detailed

description of the various forms of air compressors the reader should

consult the catalogues of the several makers and the various text-books

relating to air compression and compressed air. Air compressors, like

other machines, suffer a loss of power by friction. The greatest loss of

power, however, results from the heat of compression. When air is

compressed, it is heated, and its relative volume is increased.

Therefore, a cubic foot of hot air in the compressor cylinder, at say,

60 lbs. pressure, does not make a cubic foot of air at 60 lbs. pressure

after cooling in the receiver. In other words, assuming pressure to be

constant, a loss of volume results due to the extraction of the heat of

compression after the air leaves the compressor cylinder. To reduce the

amount of this loss, air compressors are designed with means to extract

the heat from the air before it leaves the compressor cylinder. Air

compressors may first be divided into two classes, according to the

means employed for cooling the air, as follows: (1) Wet compressors, and

(2) dry compressors. A wet compressor is one which introduces water

directly into the cylinder during compression, and a dry compressor is

one which admits no water to the air during compression. Wet compressors

may be subdivided into two classes: (1) Those which inject water in the

form of spray into the cylinder during compression, and (2) those which

use a water piston for forcing the air into confinement.

The following brief discussion of these various types of compressors is

based on the concise practical discussion of Mr. W. L. Saunders, M. Am.

Soc. C. E., in “Compressed Air Production.” The highest isothermal

results are obtained by the injection of water into the cylinders, since

it is plain that the injection of cold water, in the shape of a finely

divided spray, directly into the air during compression will lower the

temperature to a greater degree than simply to surround the cylinder and

parts by water jackets which is the means of cooling adopted with dry

compressors. A serious obstacle to water injection, and that which

condemns this type of compressor, is the influence of the injected water

upon the air cylinder and parts. Even when pure water is used, the

cylinders wear to such an extent as to produce leakage and to require

reboring. The limitation to the speed of a compressor is also an

important objection. The chief claim for the water piston compressor is

that its piston is also its cooling device, and that the heat of

compression is absorbed by the water. Water is so poor a conductor of

heat, however, that without the addition of sprays it is safe to say

that this compressor has scarcely any cooling advantages at all so far

as the cooling of the air during compression is concerned. The water

piston compressor operates at slow speed and is expensive. Its only

advantage is that it has no dead spaces. In the dry compressor a

sacrifice is made in the efficiency of the cooling device to obtain low

first cost, economy in space, light weight, higher speed, greater

durability, and greater general availability.

Air compressors are also distinguished as double acting and simple

acting. They are simple acting when the cylinder is arranged to take in

air at one stroke and force it out at the next, and they are double

acting when they take in and force out air at each stroke. In form

compressors may be simple or duplex. They are simple when they have but

one cylinder, and duplex when they have two cylinders. A straight line

or direct acting compressor is one in which the steam and air cylinders

are set tandem. An indirect acting compressor is one in which the power

is applied indirectly to the piston rod of the air cylinder through the

medium of a crank. Mr. W. L. Saunders writes in regard to direct and

indirect compression as follows:--

“The experience of American manufacturers, which has been more

extensive than that of others, has proved the value of direct

compression as distinguished from indirect. By direct compression is

meant the application of power to resistance through a single straight

rod. The steam and air cylinders are placed tandem. Such machines

naturally show a low friction loss because of the direct application

of power to resistance. This friction loss has been recorded as low as

5%, while the best practice is about 10% with the type which conveys

the power through the angle of a crank shaft to a cylinder connected

to the shaft through an additional rod.”

=Receivers.=--Compressed air is stored in receivers which are simply

iron tanks capable of withstanding a high internal pressure. The purpose

of these tanks is to provide a reservoir of compressed air, and also to

allow the air to deposit its moisture. From the receivers the air is

conveyed to the workings through iron pipes, which decrease gradually in

diameter from the receivers to the front.

=Rock Drills.=--The various forms of rock drills used in tunneling have

been described in Chapter III., and need not be considered in detail

here except to say that American engineers usually employ percussion

drills, while European engineers also use rotary drills extensively. A

comparison between these two types of drills was made in excavating the

Aarlberg tunnel in Austria, where the Brandt hydraulic rotary drill was

used at one end, and the Ferroux percussion drill was used at the other

end. The rock was a mica-schist. The average monthly progress was 412

ft., with a maximum of 646 ft., with the rotary drills, and an average

of 454 ft. with the percussion drill.

=Excavation.=--Since considerable time is required to get the power

plant established, the excavation of rock tunnels is often begun by

hand, but hand work is usually continued for no longer a period than is

necessary to get the power plant in operation. Generally speaking, the

greatest difficulty is encountered in excavating the advanced drift or

heading. Based on the mode of blasting employed, there are two methods

of driving the advanced gallery, known as the circular cut and the

center cut methods. In the first method a set of holes is first drilled

near the center of the front in such a manner that they inclose a cone

of rock; the holes, starting at the perimeter of the base of the cone,

converge toward a junction at its apex. Seldom more than four to six

holes are comprised in this first set. Around these first holes are

driven a ring of holes which inclose a cylinder of rock, and if

necessary succeeding rings of holes are driven outside of the first

ring. These holes are blasted in the order in which they are driven, the

first set taking out a cone of rock, the second set enlarging this cone

to a cylinder, and the other sets enlarging this cylinder to the

required dimensions of the heading. The number of holes, however, varies

with the quality of rock and they are seldom driven deeper than 4 or 5

ft. This method of excavating the heading, which is commonly followed by

European engineers, is illustrated in Figs. 50 to 52. In these figures

are indicated the number of holes in each round and the sequence of

rounds for the soft, medium and hard rock, as used in the Turchino

tunnel of the Genova Ovada Asti line of the Mediterranean Railway of

Italy. The heading was about 9 ft. square, and five sets of holes were

used in blasting, the depths being 3.91, 4.26 and 4.6 ft. for soft,

medium and hard rock, respectively, and the amount of dynamite consumed

was 2.38, 3.91 and 5.1 pounds per cubic yard for the three classes of

rock.

[Illustration: ~in Soft Rock~

~in Medium Rock~

~in Hard Rock~

FIGS. 50 to 52.--Arrangement of Drill Holes in the Heading of Turchino

Tunnel.]

[Illustration: FIGS. 53 and 54.--Arrangement of Drill Holes in the

Heading of the Fort George Tunnel.]

In the center-cut method, which is the one commonly employed in America,

the holes are arranged in vertical rows, and are driven from 8 to 10 ft.

deep. Fig. 53 shows the arrangement of the holes, and the method of

blasting them, as used in the excavation of the heading for the Fort

George tunnel of the New York rapid transit. The two center rows of

holes converge toward each other so as to take out a wedge of rock;

others are bored straight, or parallel, with the vertical plane of the

tunnel. Those bored around the perimeter are driven either outward or

upward, according as they are located, close to the sides or roof of the

tunnel. In this case, the holes of the center cut were driven 9 ft.

deep, while all the other holes were bored to a depth of 8 ft.

The width of the advanced gallery or heading depends upon the quality of

the rock. In hard rock American engineers give it the full width of the

tunnel section; but this cannot be done in loose or fissured rock, which

has to be supported, the headings here being usually made about 8 × 8

ft. The wider heading is always preferable, where it is possible, since

more room is available for removing the rock, and deeper holes can be

bored and blasted.

The important rôle played by the power plant and other mechanical

installations in constructing tunnels through rock has already been

mentioned. In some methods of soft-ground tunneling, and particularly in

soft-ground subaqueous tunneling, it is also often necessary to employ a

mechanical installation but slightly inferior in size and cost to those

used in tunneling rock. It is proposed to describe very briefly here a

few typical individual plants of this character, which will in some

respects give a better idea of this phase of tunnel work than the more

general descriptions.

=Rock Tunnels.=--The tunnels selected to illustrate the mechanical

installations employed in tunneling through rock are: The Mont Cenis,

Hoosac Tunnel, the Cascade Tunnel, the Niagara Falls Power Tunnel, the

Palisades Tunnel, the Croton Aqueduct Tunnel, the Strickler Tunnel in

America, and the Graveholz Tunnel and the Sonnstein Tunnel in Europe. In

addition there will be found in another chapter of this book a

description of the mechanical installations at the St. Gothard,

Pennsylvania and other tunnels.

_Mont Cenis Power Plant._--The mechanical installation consisted of the

Sommeilier air compressors built near the portals. The Sommeilier

compressors, Mr. W. L. Saunders says, were operated as a ram, utilizing

a natural head of water to force air at 80 lbs. pressure into a

receiver. The column of water contained in the long pipe on the side of

the hill was started and stopped automatically by valves controlled by

engines. The weight and momentum of the water forced a volume of air

with such a shock against the discharge valve that it was opened, and

the air was discharged into the tank; the valve was then closed, the

water checked; a portion of it was allowed to discharge, and the space

was filled with air, which was in turn forced into the tank. Only 73% of

the power of the water was available, 27% being lost by the friction of

the water in the pipes, valves, bends, etc. Of the 73% of net work, 49.4

was consumed in the perforators, and 23.6 in a dummy engine for working

the valves of the compressors and for special ventilation.

The compressed air was conveyed from each end through a cast-iron pipe

7⁵⁄₈ in. in diameter, up to the front of the excavation. The joints of

the pipes were made with turned faces, grooved to receive a ring of

oakum which was tightly screwed and compressed into the joint. To

ascertain the amount of leakage of the pipes, they and the tanks were

filled with air compressed to 6 atmospheres, and the machines stopped;

after 12 hours the pressure was reduced to 5.7 atmospheres, or to 95% of

the original pressure.

Sommeilier’s percussion drilling machines were used in the excavation of

this tunnel. They were provided with 8 or 10 drills acting at the same

time, and mounted on carriages running on tracks. These were withdrawn

to a safe place during the blasting, and advanced again after the broken

rock was removed from the front and the new tracks laid.

Machine shops were built at both ends of the tunnel for building and

repairing the drilling machines, bits, tools, etc. A gas factory was

built at each end for lighting purpose.

_Hoosac Tunnel._--The Hoosac tunnel on the Fitchburg R.R. in

Massachusetts is 25,000 ft. long, and the longest tunnel in America. The

material through which the tunnel was driven was chiefly hard granitic

gneiss, conglomerate, and mica-schist rock. The excavation was conducted

from the entrances and one shaft, the wide heading and single-bench

method being employed, with the center-cut system of blasting which was

here used for the first time. The tunnel was begun in 1854, and

continued by hand until 1866, when the mechanical plant was installed.

Most of the particular machines employed have now become obsolete, but

as they were the first machines used for rock tunneling in America they

deserve mention. The drills used were Burleigh percussion drills,

operated by compressed air. Six of these drills were mounted on a single

carriage, and two carriages were used at each front. The air to operate

these drills was supplied by air compressors operated by water-power at

the portals and steam-power at the shaft. The air compressors consisted

of four horizontal single-acting air cylinders with poppet valves and

water injection. The compressors were designed by Mr. Thomas Deane, the

chief engineer of the tunnel.

_Palisades Tunnel._--The Palisades tunnel was constructed to carry a

double track railway line through the ridge of rocks bordering the west

bank of the Hudson River and known as the Palisades. It was located

about opposite 116th St. in New York City. The material penetrated was a

hard trap rock very full of seams in places, which caused large

fragments to fall from the roof. The excavation was made by a single

wide heading and bench, employing the center-cut method of blasting with

eight center holes and 16 side holes for the 7 × 18 ft. heading.

Ingersoll-Sergeant 2¹⁄₂ in. drills were used, four in each heading and

six on each bench, and 30 ft. per 10 hours was considered good work for

one drill.

The power-plant was situated at the west portal of the tunnel, and the

power was transmitted by electricity and compressed air to the middle

shaft and east portal workings. The plant consisted of eight 100 H. P.

boilers, furnishing steam to four Rand duplex 18 × 22 in. air

compressors, and an engine running a 30 arc light dynamo. The compressed

air was carried over the ridge by pipes, varying from 10 ins. to 5 ins.

in diameter, to the shaft and to the east portal, and was used for

operating the hoisting engines as well as the drills at these workings.

Inside the tunnel, specially designed derrick cars were employed to

handle large stones, they being also operated by compressed air. This

car ran on a center track, while the mucking cars ran on side tracks,

and it was employed to lift the bodies of the cars from the trucks,

place them close to the front, being worked where large stone could be

rolled into them, and return them to the trucks for removal. In addition

to handling the car bodies the derrick was used to lift heavy stones.

The hauling was done first by horse-power, and later by dummy

locomotives.

_Croton Aqueduct Tunnel._--In the construction of the Croton Aqueduct

for the water supply of New York City, a tunnel 31 miles long was built,

running from the Croton Dam to the Gate House at 135th St. in New York

City. The section of the tunnel varies in form, but is generally either

a circular or a horseshoe section. In all cases the section was designed

to have a capacity for the flow of water equal to a cylinder 14 ft. in

diameter. To drive the tunnel, 40 shafts were employed. The material

penetrated was of almost every character, from quicksand to granitic

rock, but the bulk of the work was in rock of some character. The

excavation in rock was conducted by the wide heading and bench method,

employing the center-cut method of blasting. Four air drills, mounted on

two double-arm columns were employed in the heading. The drills for the

bench work were mounted on tripods. Steam-power was used exclusively for

operating the compressors, hoisting engines, ventilating fans and pumps;

but the size and kind of boilers used, as well as the kind and capacity

of the machines which they operated, varied greatly, since a separate

power-plant was employed for each shaft with a few exceptions. A

description of the plant at one of the shafts will give an indication of

the size and character of those at the other shafts, and for this

purpose the plant at shaft 10 has been selected.

At shaft 10 steam was provided by two Ingersoll boilers of 80 H. P.

each, and by a small upright boiler of 8 H. P. There were two 18 × 30

in. Ingersoll air compressors pumping into two 42 in. × 10 ft. and two

42 in. × 12 ft. Ingersoll receivers. In the excavation there were twelve

3¹⁄₂ in. and six 3¹⁄₈ in. Ingersoll drills, four drills mounted on two

double arm columns being used on each heading, and the remainder mounted

on tripods being used on the bench. Two Dickson cages operated by one

12 × 12 in. Dickson reversible double hoisting engine provided

transportation for material and supplies up and down the shaft. A

Thomson-Houston ten-light dynamo operated by a Lidgerwood engine

provided light. Drainage was effected by means of two No. 9 and one No.

6 Cameron pumps. At this particular shaft the air exhausted from the

drills gave ample ventilation, especially when after each blast the

smoke was cleared away by a jet of compressed air. In other workings,

however, where this means of ventilation was not sufficient, Baker

blowers were generally employed.

_Strickler Tunnel._--The Strickler tunnel for the water supply of

Colorado Springs, Col., is 6441 ft. long with a section of 4 ft. × 7 ft.

It penetrates the ridge connecting Pike’s Peak and the Big Horn

Mountains, at an elevation of 11,540 ft. above sea level. The material

penetrated is a coarse porphyritic granite and morainal débris, the

portion through the latter material being lined. The mechanical

installation consisted of a water-power electric plant operating air

compressors. The water from Buxton Creek having a fall of 2400 ft. was

utilized to operate a 36 in. 220 H. P. Pelton water-wheel, which

operated a 150 K. W. three-phase generator. From this generator a 3500

volt current was transmitted to the east portal of the tunnel, where a

step-down transformer reduced it to a 220 volt current to the motor. The

transmission line consisted of three No. 5 wires carried on cross-arm

poles and provided with lightning arresters at intervals. The plant at

the east portal of the tunnel consisted of a 75 H. P. electric motor,

driving a 75 H. P. air compressor, and of small motors to drive a

Sturtevant blower for ventilation, to run the blacksmith shop, and to

light the tunnel, shop, and yards. From the compressor air was piped

into the tunnel at the east end, and also over the mountain to the west

portal workings. Two drills were used at each end, and the air was also

used for operating derricks and other machinery. For removing the spoil

a trolley carrier system was employed. A longitudinal timber was

fastened to the tunnel roof, directly in the apex of the roof arch. This

timber carried by means of hangers a steel bar trolley rail on which the

carriages ran. Outside of the portal this rail formed a loop, so that

the carriage could pass around the loop and be taken back to the working

face. Each carriage carried a steel span of 1¹⁄₂ cu. ft. capacity, so

suspended that by means of a tripping device it was automatically dumped

when the proper point on the loop was reached.

_Niagara Falls Power Tunnel._--The tail-race tunnel built to carry away

the water discharged from the turbines of the Niagara Falls Power Co.,

has a horse-shoe section 19 × 21 ft. and a length of 6700 ft. It was

driven through rock from three shafts by the center-cut method of

blasting. In sinking shaft No. 0 very little water was encountered, but

at shafts Nos. 1 and 2 an inflow of 800 gallons and 600 gallons per

minute, respectively, was encountered. The principal plant was located

at shaft No. 2, and consisted of eight 100 H.P. boilers, three 18 × 30

in. Rand duplex air compressors, a Thomson-Houston electric-light plant,

and a sawmill with a capacity of 20,000 ft. B. M. per day. The shafts

were fitted with Otis automatic hoisting engines, with double cages at

shafts Nos. 1 and 2, and a single cage at shaft No. 0. The drills used

were 25 Rand drills and three Ingersoll-Sergeant drills. The pumping

plant at shaft No. 2 consisted of four No. 7 and one No. 9 Cameron

pumps, and that at shaft No. 2 consisted of two No. 7 and two No. 9

Cameron pumps and three Snow pumps. An auxiliary boiler plant consisting

of two 60 H. P. boilers was located at shaft No. 1, and another,

consisting of one 75 H. P. boiler, was located at shaft No. 0.

_Cascade Tunnel._--The Cascade tunnel was built in 1886-88 to carry the

double tracks of the Northern Pacific Ry. through the Cascade Mountains

in Washington. It is 9850 ft. long with a cross-section 16¹⁄₂ ft. wide

and 22 ft. high, and is lined with masonry. The material penetrated was

a basaltic rock, with a dip of the strata of about 5°. The rock was

excavated by a wide heading and one bench, using the center-cut system

of blasting. A strutting consisting of five-segment timber arches

carried on side posts, spaced from 2 ft. to 4 ft. apart, and having a

roof lagging of 4 × 6 in. timbers packed above with cord-wood. The

mechanical plant of the tunnel is of particular interest, because of the

fact that all the machinery and supplies had to be hauled from 82 to 87

miles by teams, over a road cut through the forests covering the

mountain slopes. This work required from Feb. 22 to July 15, 1886, to

perform. In many places the grades were so steep that the wagons had to

be hauled by block and tackle. The plant consisted of five engines, two

water-wheels, five air compressors, eight 70 H. P. steam-boilers, four

large exhaust fans, two complete electric arc-lighting plants, two fully

equipped machine-shop outfits, 36 air drills, two locomotives, 60 dump

cars, and two sawmill outfits, with the necessary accessories for these

various machines. This plant was divided about equally between the two

ends of the tunnel. The cost of the plant and of the work of getting it

into position was $125,000.

_Graveholz Tunnel._--The Graveholz tunnel on the Bergen Railway in

Norway is notable as being the longest tunnel in northern Europe, and

also as being built for a single-track narrow-gauge railway. This tunnel

is 17,400 feet long, and is located at an elevation of 2900 feet above

sea-level. Only about 3% of the length of the tunnel is lined. The

mechanical installation consists of a turbine plant operating the

various machines. There are two turbines of 100 H. P. and 120 H. P.

taking water from a reservoir on the mountain slope, and furnishing 220

H. P., which is distributed about as follows: Boring-machines, 60 H. P.;

ventilation, 30 to 40 H. P.; electric locomotives, 15 H. P.; machine

shop, 15 H. P.; electric-lighting dynamo, 25 H. P.; electric drills, the

surplus, or some 40 H. P. The boring-machines and electric drills will

be operated by the smaller 100 H. P. turbine.

_Sonnstein Tunnel._--The Sonnstein tunnel in Germany is particularly

interesting because of the exclusive use of Brandt rotary drills. The

tunnel was driven through dolomite and hard limestone by means of a

drift and two side galleries. The dimensions of the drift were 7¹⁄₂ ×

7¹⁄₂ ft. The power plant consisted of two steam pressure pumps, one

accumulator, and four drills. The steam-boiler plant, in addition to

operating the pumps, also supplied power for operating a rotary pump for

drainage and a blower for ventilation. The hydraulic pressure required

was 75 atmospheres in the dolomite, and from 85 to 100 atmospheres in

the limestone. The drift was excavated with five 3¹⁄₂ in. holes, one

being placed at the center and driven parallel to the axis of the

tunnel, and four being placed at the corners of a rectangle

corresponding to the sides of the drift, and driven at an angle

diverging from the center hole. The average depths of the holes were 4.3

ft., and the efficiency of the drills was 1 in. per minute. One drill

was employed at each front, and was operated by a machinist and two

helpers, who worked eight-hour shifts, with a blast between shifts at

first, and later twelve-hour shifts, with a blast between shifts. The 24

hours of the two shifts were divided as follows: boring the holes, 10.7

hours; charging the holes, 1.1 hours; removing the spoil, 11.7 hours;

changing shifts, 0.5 hour. The average progress per day for each machine

was 6.7 ft. The total cost of the plant was $17,450.

_St. Clair River Tunnel._--The submarine double-track railway tunnel

under the St. Clair River for the Grand Trunk Ry. is 8500 ft. long, and

was driven through clay by means of a shield, as described in the

succeeding chapter on the shield system of tunneling. The mechanical

plant installed for prosecuting the work was very complete. To furnish

steam to the air compressors, pumps, electric-light engines,

hoisting-engines, etc., a steam-plant was provided on each side of the

river, consisting of three 70 H. P. and four 80 H. P. Scotch portable

boilers. The air-compressor plant at each end consisted of two 20 × 24

in. Ingersoll air compressors. To furnish light to the workings, two 100

candle-power Edison dynamos were installed on the American side, and two

Ball dynamos of the same size were installed on the Canadian side. The

dynamos on both sides were driven by Armington & Sims engines. These

dynamos furnished light to the tunnel workings and to the machine-shops

and power-plant at each end. Root blowers of 10,000 cu. ft. per minute

capacity provided ventilation. The pumping plant consisted of one set of

pumps installed for permanent drainage, and another set installed for

drainage during construction, and also to remain in place as a part of

the permanent plant. The latter set consisted of two 500 gallon

Worthington duplex pumps set first outside of each air lock, closing the

ends of the river portion of the tunnel. For permanent drainage, a

drainage shaft was sunk on the Canadian side of the river, and connected

with a pump at the bottom of the open-cut approach. In this shaft were

placed a vertical, direct-acting, compound-condensing pumping engine

with two 19¹⁄₂ in. high-pressure and two 33³⁄₈ in. low-pressure

cylinders of 24 in. stroke, connected to double-acting pumps with a

capacity of 3000 gallons per minute, and also two duplex pumps of 500

gallons capacity per minute. For permanent drainage on the American

side, four Worthington pumps of 3000 gallons’ capacity were installed in

a pump-house set back into the slope of the open-cut approach. For the

permanent drainage of the tunnel proper two 400 gallon pumps were placed

at the lowest point of the tunnel grade. Spoil coming from the tunnel

proper was hoisted to the top of the open cut by derricks operated by

two 50 H. P. Lidgerwood hoisting-engines. The pressure pumping plant

for supplying water to the hydraulic shield-jacks at each end of the

tunnel consisted of duplex direct-acting engines with 12 in. steam

cylinders and 1 in. water cylinders, supplying water at a pressure of

2000 lbs. per sq. in.

Tunneling: A Practical Treatise. · 第 9 / 18 章