CHAPTER V

EARTH ROADS

Highways constructed without the addition of surfacing material to the

natural soil of the right-of-way are usually called earth roads. But

if the natural soil exhibits peculiar characteristics or is of a

distinct type, the road may be referred to by some distinctive name

indicating that fact. Hence, roads are referred to as clay, gumbo,

sandy or caliche roads as local custom may elect. In each case,

however, the wearing surface consists of the natural soil, which may

have been shaped and smoothed for traffic or may be in its natural

state except for a trackway formed by the vehicles that have used it.

=Variations in Soils.=--The nature of the existing soil will obviously

determine the serviceability and physical characteristics of the road

surface it affords. That is to say that even under the most favorable

conditions some earth roads will be much more serviceable than others,

due to the better stability of the natural soil. Some soils are dense

and somewhat tough when dry and therefore resist to a degree the

tendency of vehicles to grind away the particles and dissipate them in

the form of dust. Such soils retain a reasonably smooth trackway in

dry weather even when subjected to considerable traffic. Other soils

do not possess the inherent tenacity and stability to enable them to

resist the action of wheels and consequently grind away rapidly. Roads

on such soils become very dusty. These are the extremes and between

them are many types of soils or mixtures of soils possessing varying

degrees of stability, and, in consequence, differing rates of wear.

Similarly the various soils exhibit different degrees of stability

when wet.

It is to be expected that soils will differ with the geographical

location, for it is well known that there is a great variation in

soils in the various parts of the world. But wide differences are also

encountered in the soil on roads very near each other and even on

successive stretches of the same road. It is for this reason that

earth roads often exhibit great differences in serviceability even in

a restricted area.

=Variation in Rainfall.=--The stability of a soil and its ability to

support the weight of vehicles varies greatly with the amount of water

in the soil. A certain small amount of moisture in the soil is

beneficial in that practically every soil compacts more readily when

moist than when dry because the moisture aids in binding together the

particles. But most soils also become unstable when the amount of

water present is in excess of that small amount referred to above and

the stability decreases very rapidly as the amount of water in the

soil increases.

The serviceability of an earth road will change continually as the

moisture content of the soil changes and consequently the general

utility of the earth road system in any locality is dependent to a

considerable extent upon the amount and seasonal distribution of

precipitation. The methods of maintaining earth roads appropriate to

any locality must of necessity be adapted to the climatic conditions,

and the amount of work required to give the highest possible degree of

serviceability will be exceedingly variable from season to season and

from place to place. In regions of great humidity, earth roads may be

expected to have a low average of serviceability, while in arid

regions they may possess sufficient durability for a considerable

volume of traffic. The design adopted for earth roads and the methods

of maintenance followed should therefore be carefully evolved to meet

the soil and climate conditions where the roads are located. These

will differ greatly throughout a state or even a county.

=Cross Sections.=--The general principles of road design were set

forth in Chapter IV. In Fig. 11 are shown typical cross sections for

earth roads adapted to various conditions as indicated. It is not

apparent that one form of ditch is particularly preferable to the

other and since some engineers prefer the V section and others the

trapezoidal section both are shown. It would appear that the V shaped

ditch is somewhat the easier to construct with the blade grader while

the trapezoidal is readily excavated with the slip or fresno scraper.

The ditch capacity required and consequently the dimensions will

depend upon the drainage requirements, as was pointed out in Chapter

III.

[Illustration: Fig. 11. Cross Section for Earth Roads]

EARTH ROADS IN REGIONS OF CONSIDERABLE RAINFALL

In the zones where the annual precipitation exceeds 30 inches

distributed over several months, earth roads will be unserviceable for

a considerable period each year unless they are constructed so as to

minimize the effect of water. This is done by providing for the best

possible drainage and by adopting a method of maintenance that will

restore the surface to a smooth condition as quickly as possible after

a period of rainy weather or after the "frost comes out" in the

spring.

Before the construction of the desired cross section is undertaken,

all of the grade reduction should be completed, except for minor cuts

which can be handled with the elevating grader in the manner that will

be described presently.

Where any considerable change in grade is to be effected, the earth

can be moved in several ways and of these the most economical cannot

be readily determined. Ordinarily a contractor or a county will use

the equipment that happens to be at hand even though some other might

be more advantageous.

=Elevating Grader.=--Where the topography is such as to permit its

use, the elevating grader is employed in grade reduction to load the

earth into dump wagons in which it is hauled to the fill or waste

bank. The elevating grader consists essentially of a heavy shear plow

or disc plow which loosens the earth and deposits it on a moving

canvas apron. The apron carries the material up an incline and

deposits it into a wagon which is driven along under the end of the

apron. When the wagon is loaded, the grader is stopped while the

loaded wagon is hauled out and an empty one drawn into position. The

motive power for the elevating grader is either a tractor or five or

six teams of mules. For many kinds of work, particularly where

frequent turning is necessary or where the ground is yielding, mules

are preferable to a tractor. The apron is operated by gearing from the

rear wheels of the grader. Generally four mules are hitched to a

pusher in the rear of the grader and six or eight in the lead. This

method of grade reduction is particularly advantageous when the

material must be hauled a distance of 500 yards or more, because wagon

hauling in such cases is the most economical method to employ. A

tractor may be used to draw the elevating grader and one having a

commercial rating of 30 to 45 horsepower is required.

=Maney Grader.=--If the haul is long and the nature of the cut will

not permit the use of the elevating grader because of excessive grades

or lack of room for turning, a grader of the Maney type may be used.

This consists of a scoop of about one cubic yard capacity, suspended

from a four-wheel wagon gear. When loading, the scoop is let down and

filled in the same manner as a two-wheeled scraper or "wheeler." The

pull required to fill a Maney grader is so great that a tractor is

ordinarily employed in place of a "snap" team. The tractor is hitched

at the end of the tongue, without interfering with the team drawing

the grader. One team readily handles the grader after it is loaded.

For this service a tractor having a commercial rationing of 25 to 30

horsepower is required.

=Wheel Scraper.=--For moving earth for distances between 150 and 500

yards, the wheel scraper of a capacity of about 1-1/2 yards is quite

generally employed. The soil must be loosened with a plow before it

can conveniently be loaded into the wheeler and a heavy plow is

ordinarily employed for that purpose. Two furrows with the plow will

loosen a strip of earth about as wide as the scoop of the scraper and

if more is loosened it will be packed down by the scrapers wheeling in

place to load. A helper or "snap" team is employed to assist in

loading, after which the wheel scraper is handled by one team.

=Slip Scraper.=--The slip scraper differs from the wheel scraper in

that the scoop is not suspended from wheels but is dragged along the

ground. It is drawn by one team and the capacity is two to five cubic

feet, but the material spills out to some extent as the scraper is

dragged along and the method is not suitable for long hauls, 100 feet

being about the economical limit.

=Fresno Scraper.=--The Fresno scraper is one form of slip scraper

requiring four horses or mules for efficient work. It differs

somewhat from the ordinary slip scraper in shape and is of larger

capacity, but is a drag type of scraper much favored in the western

states.

SHAPING TO PROPER CROSS SECTION

If a road has been graded so that the profile is satisfactory or if

the existing profile of the location is satisfactory, and the surface

is to be shaped to a prescribed cross section, either the elevating

grader or the blade grader may be employed.

=Elevating Grader Work.=--If the elevating grader is used in shaping

the earth road, the apron will be lowered and the material will be

excavated at the sides of the road and deposited on the middle

portion. If slight changes in grade are desired, wagons will accompany

the grader and catch under the apron at the high places and haul the

material to the low places. After the earth has been deposited it must

be worked over to secure the correct cross section and be made

passable for vehicles. This requires that clods be broken, weeds and

grass that are mixed with the earth be removed by harrowing and

forking and that the surface be carefully smoothed with a blade

grader. This latter operation will have to be repeated several times

before a satisfactory surface is secured. But this miscellaneous work

is highly important and under no circumstances ought to be neglected.

Nothing so detracts from an otherwise creditable piece of work as

failure to provide a smooth surface for the use of vehicles. It is

especially uncomfortable for the users of a highway if sods and weeds

in quantity are left in the road after it has been graded. The humus

that will be left in the soil as the vegetable matter decays increases

the porosity of the road surface making it more absorbent than soil

without humus. This increases the susceptibility to softening from

storm water or ground water.

The tractor can advantageously be used to draw the elevating grader on

this class of work, but will be greatly handicapped if there are wet

sections along the road, through which the tractor must be driven. In

many cases its use is prohibited by such conditions and for all-round

service of this character, mules are preferred for motive power.

[Illustration: Fig. 12.--Tractor-grader Outfit]

=Use of Blade Grader.=--Heavy blade graders designed to be drawn by a

tractor are suitable for shaping the earth road. Some of these have

blades 12 feet long and excellent control for regulating the depth of

cutting. Often two such graders are operated tandem. These machines

have a device which permits the operator to steer the grader

independently of the tractor. Thus the grader can be steered off to

the side to cut out the ditches, while the tractor continues to travel

on the firm part of the road. Earth moved with the blade grader is

usually fairly free from large lumps and can readily be smoothed to a

satisfactory surface for the use of traffic. The sods and weeds will

be drawn into the road along with the earth just as they are when the

elevating grader is employed. Precaution must therefore be taken to

eliminate them before the vegetable matter decays, and to smooth the

surface for the use of traffic.

=Costs.=--The cost of shaping an earth road in the manner described

above will vary through rather wide limits because the nature and

amount of work to be done varies so greatly. Some roads can be graded

satisfactorily for $300.00 per mile, while others will cost $700.00.

But $425.00 per mile may be taken as an average for blade or elevating

grader work plus a moderate amount of grade reduction in the way of

removing slight knolls. For the amount of grade reduction necessary in

rolling country, followed by grader shaping, $1000.00 to $1800.00 per

mile will be required. The method is not adapted to rolling country

where the roads are undulating and require some grade reduction on

every hill. For hilly roads one of the methods described for grade

reduction will be required and the cost will obviously depend upon the

amount of earth moved. Averages of cost figures mean nothing in such

cases as the cost may reach $10,000.00 per mile, or may be as low as

$2000.00 per mile.

=Maintenance.=--Regardless of the care with which an earth road has

been graded, it will be yielding and will readily absorb water for a

long time after the completion of the work. The condition of the

surface will naturally deteriorate rapidly during the first season it

is used unless the road receives the constant maintenance that is a

prerequisite to satisfactory serviceability. The road drag is

generally recommended for this purpose, and if a drag is properly used

it will serve to restore the shape of the surface as fast as it is

destroyed by traffic.

Good results with the drag depend upon choosing the proper time to

drag and upon doing the work in the right way when using the drag. The

best time to drag is as soon after a rain as the road has dried out

enough to pack under traffic. If the work is done while the road is

too wet, the first vehicles traveling the road after it has been

dragged will make ruts and to a considerable extent offset the good

done by the drag. If the road is too dry, the drag will not smooth the

irregularities. A little observation will be required to determine the

proper time for dragging on any particular soil, but usually after a

rain or thaw there is a period lasting a day or two when conditions

are about right.

[Illustration: Fig. 13.--Road Drag]

The drag is used merely to restore the shape of the surface and to do

so a small amount of material is drawn toward the middle of the road.

But there must not be a ridge of loose material left in the middle

after the work is completed. Some patrolmen start at one side of the

road and gradually work across the road on successive trips, finally

finishing up at the side opposite that at which the start was made.

The next dragging should start on the opposite side from the first if

that method is followed.

By shifting his weight on the drag, the operator can adjust the

cutting edge so that very little loose material is moved crosswise of

the road and that is the proper method to pursue. In that case no

ridge will remain at the middle of the road. If a slight one is left

it should be removed by a final trip with the drag.

In addition to the dragging, weeds must be cut along the road about

twice a year, the ditches must be kept cleaned out and culverts open.

All of the maintenance for 10 miles of earth road can be accomplished

by one man giving his entire time to the work, and that is the only

method that has proven adequate to the problem.

EARTH ROADS IN ARID REGIONS

In areas where the rainfall is less than 18 inches per year, and

especially where it is 10 inches or less, an entirely different road

problem exists. The effect of precipitation is of significance

primarily from the standpoint of erosion, and the design of cross

section and ditches and the culvert provisions are entirely different

from those necessary in humid regions.

Frequently the rainfall in semi-arid regions will be seasonal and

provision must be made to care for a large volume of water during the

rainy season, but, in general, road design is adapted to prevention of

erosion rather than to elimination of ground water effects, or the

softening effects of surface water. Generally the rainy period does

not last long enough to warrant expensive construction to eliminate

its general effects. In fact, the saturation of the soil is more

likely to be a benefit than otherwise.

Earth roads are likely to be satisfactory except where the traffic is

sufficient to grind the surface into dust to such an extent that an

excessive dust layer is produced. In such locations the problem is one

of providing a durable surface unaffected by long continued dry

weather.

Grade reduction will have the same importance as in humid areas and

will be carried out in the same way.

Maintenance will consist in repairing the damage from occasional

floods and in removing or preventing accumulations of drifting sand

or dust. Crude petroleum oils have been satisfactory for maintenance

in such locations when used on stable soils.

=Value of Earth Roads.=--The serviceability of the earth road depends

to a large extent upon the care exercised in its maintenance. The only

part of earth road construction that is permanent is the grade

reduction. The cross section that is so carefully shaped at

considerable cost may flatten out in one or two years, especially if

the road goes through unusually wet periods. Traffic will continually

seek a new track during the period when the road is muddy and is as

likely to cross the ditch to the sod near the fence as to use any

other part of the road. Continual and persistent maintenance is

therefore essential to even reasonable serviceability. At best the

earth road will be a poor facility for a considerable period each year

in the regions of year-around rainfall. In most localities, roads of

distinctly minor importance are of necessity only earth roads and for

the comparatively small territory they serve and the small amount of

traffic, they probably serve the purpose. For roads of any importance

in the humid areas of the United States, the earth road cannot carry

satisfactorily the traffic of a prosperous and busy community.