CHAPTER II

TYPES AND METHODS OF CONSTRUCTION

Five types of construction have been employed in building the road:

(1) the typical subway near the surface with flat roof and "I" beams

for the roof and sides, supported between tracks with steel bulb-angle

columns used on about 10.6 miles or 52.2 per cent. of the road; (2)

flat roof typical subway of reënforced concrete construction supported

between the tracks by steel bulb-angle columns, used for a short

distance on Lenox Avenue and on the Brooklyn portion of the Brooklyn

Extension, also on the Battery Park loop; (3) concrete lined tunnel

used on about 4.6 miles or 23 per cent. of the road, of which 4.2 per

cent. was concrete lined open cut work, and the remainder was rock

tunnel work; (4) elevated road on steel viaduct used on about 5 miles

or 24.6 per cent. of the road; (5) cast-iron tubes used under the

Harlem and East Rivers.

[Sidenote: _Typical

Subway_]

The general character of the flat roof "I" beam construction is shown

in photograph on page 28 and drawing on this page. The bottom

is of concrete. The side walls have "I" beam columns five feet apart,

between which are vertical concrete arches, the steel acting as a

support for the masonry and allowing the thickness of the walls to be

materially reduced from that necessary were nothing but concrete used.

The tops of the wall columns are connected by roof beams which are

supported by rows of steel columns between the tracks, built on

concrete and cut stone bases forming part of the floor system.

Concrete arches between the roof beams complete the top of the subway.

Such a structure is not impervious, and hence, there has been laid

behind the side walls, under the floor and over the roof a course of

two to eight thicknesses of felt, each washed with hot asphalt as

laid. In addition to this precaution against dampness, in three

sections of the subway (viz.: on Elm Street between Pearl and Grand

Streets, and on the approaches to the Harlem River tunnel, and on the

Battery Park Loop) the felt waterproofing has been made more effective

by one or two courses of hard-burned brick laid in hot asphalt, after

the manner sometimes employed in constructing the linings of

reservoirs of waterworks.

[Illustration: TYPICAL SECTION OF FOUR TRACK SUBWAY]

[Illustration: FOUR-TRACK SUBWAY--SHOWING CROSS-OVER SOUTH OF 18TH

STREET STATION]

In front of the waterproofing, immediately behind the steel columns,

are the systems of terra-cotta ducts in which the electric cables are

placed. The cables can be reached by means of manholes every 200 to

450 feet, which open into the subway and also into the street. The

number of these ducts ranges from 128 down to 32, and they are

connected with the main power station at 58th and 59th Streets and the

Hudson River by a 128-duct subway under the former street.

[Sidenote: _Reinforced

Concrete

Construction_]

The reinforced concrete construction substitutes for the steel roof

beams, steel rods, approximating 1-1/4 inches square, laid in varying

distances according to the different roof loads, from six to ten

inches apart. Rods 1-1/8 inches in diameter tie the side walls,

passing through angle columns in the walls and the bulb-angle columns

in the center. Layers of concrete are laid over the roof rods to a

thickness of from eighteen to thirty inches, and carried two inches

below the rods, imbedding them. For the sides similar square rods and

concrete are used and angle columns five feet apart. The concrete of

the side walls is from fifteen to eighteen inches thick. This type is

shown by photographs on page 41. The rods used are of both square

and twisted form.

[Illustration: LAYING SHEET WATERPROOFING IN BOTTOM]

[Illustration: SPECIAL BRICK AND ASPHALT WATERPROOFING]

[Sidenote: _Methods of

Construction

Typical

Subway_]

The construction of the typical subway has been carried on by a great

variety of methods, partly adopted on account of the conditions under

which the work had to be prosecuted and partly due to the personal

views of the different sub-contractors. The work was all done by open

excavation, the so-called "cut and cover" system, but the conditions

varied widely along different parts of the line, and different means

were adopted to overcome local difficulties. The distance of the rock

surface below the street level had a marked influence on the manner in

which the excavation of the open trenches could be made. In some

places this rock rose nearly to the pavement, as between 14th and 18th

Streets. At other places the subway is located in water-bearing loam

and sand, as in the stretch between Pearl and Grand Streets, where it

was necessary to employ a special design for the bottom, which is

illustrated by drawing on page 42.

This part of the route includes the former site of the ancient Collect

Pond, familiar in the early history of New York, and the excavation

was through made ground, the pond having been filled in for building

purposes after it was abandoned for supplying water to the city. The

excavations through Canal Street, adjacent, were also through made

ground, that street having been at one time, as its name implies, a

canal.

From the City Hall to 9th Street was sand, presenting no particular

difficulties except through the territory just described.

At Union Square rock was encountered on the west side of Fourth Avenue

from the surface down. On the east side of the street, however, at the

surface was sand, which extended 15 feet down to a sloping rock

surface. The tendency of the sand to a slide off into the rock

excavation required great care. The work was done, however, without

interference with the street traffic, which is particularly heavy at

that point.

[Illustration: DUCTS IN SIDE WALLS--EIGHT ONLY OF THE SIXTEEN LAYERS

ARE SHOWN]

[Illustration: REINFORCED CONCRETE CONSTRUCTION]

[Illustration: ROOF SHOWING CONCRETE-STEEL CONSTRUCTION--LENOX AVENUE

AND 140TH-141ST STREETS]

[Illustration: SECTION OF SUBWAY AT PEARL STREET

This construction was made necessary by encountering a layer of Peat

resting on Clay]

[Illustration: SURFACE RAILWAY TRACKS SUPPORTED OVER EXCAVATION ON

UPPER BROADWAY]

[Illustration: SUBDIVISION OF 36" AND 30" GAS MAINS OVER ROOF OF

SUBWAY--66TH STREET AND BROADWAY]

The natural difficulties of the route were increased by the network of

sewers, water and gas mains, steam pipes, pneumatic tubes, electric

conduits and their accessories, which filled the streets; and by the

surface railways and their conduits. In some places the columns of the

elevated railway had to be shored up temporarily, and in other places

the subway passes close to the foundations of lofty buildings, where

the construction needed to insure the safety of both subway and

buildings was quite intricate. As the subway is close to the surface

along a considerable part of its route, its construction involved the

reconstruction of all the underground pipes and ducts in many places,

as well as the removal of projecting vaults and buildings, and, in

some cases, the underpinning of their walls. A description in detail

of the methods of construction followed all along the line would make

an interesting book of itself. Space will only permit, however, an

account of how some of the more serious difficulties were overcome.

On Fourth Avenue, north of Union Square to 33d Street, there were two

electric conduit railway tracks in the center of the roadway and a

horse car track near each curb part of the distance. The two electric

car tracks were used for traffic which could not be interrupted,

although the horse car tracks could be removed without inconvenience.

These conditions rendered it impracticable to disturb the center of

the roadway, while permitting excavation near the curb. Well-timbered

shafts about 8 x 10 feet, in plan, were sunk along one curb line and

tunnels driven from them toward the other side of the street, stopping

about 3-1/2 feet beyond its center line. A bed of concrete was laid on

the bottom of each tunnel, and, when it had set, a heavy vertical

trestle was built on it. In this way trestles were built half across

the street, strong enough to carry all the street cars and traffic on

that half of the roadway. Cableways to handle the dirt were erected

near the curb line, spanning a number of these trestles, and then the

earth between them was excavated from the curb to within a few feet of

the nearest electric car track. The horse car tracks were removed.

Between the electric tracks a trench was dug until its bottom was

level with the tops of the trestles, about three feet below the

surface as a rule. A pair of heavy steel beams was then laid in this

trench on the trestles. Between these beams and the curb line a second

pair of beams were placed. In this way the equivalent of a bridge was

put up, the trestles acting as piers and the beams as girders. The

central portion of the roadway was then undermined and supported by

timbering suspended from the steel beams. The various gas and water

pipes were hung from timbers at the surface of the ground. About four

sections, or 150 feet, of the subway were built at a time in this

manner. When the work was completed along one side of the street it

was repeated in the same manner on the other side. This method of

construction was subsequently modified so as to permit work on both

sides of the street simultaneously. The manner in which the central

part of the roadway was supported remained the same and all of the

traffic was diverted to this strip.

[Illustration: SUPPORT OF ELEVATED RAILWAY STATION AT 42D STREET AND

SIXTH AVENUE]

Between 14th and 17th Streets, because of the proximity of the rock to

the surface, it was necessary to move the tracks of the electric

surface railway from the center of the street some twenty feet to the

east curb, without interrupting traffic, which was very heavy at all

times, the line being one of the main arteries of the Metropolitan

system. Four 12 x 12-inch timbers were laid upon the surface. Standard

cast-iron yokes were placed upon the timbers at the usual distance

apart. Upon this structure the regular track and slot rails were

placed. The space between the rails was floored over. Wooden boxes

were temporarily laid for the electric cables. The usual hand holes

and other accessories were built and the road operated on this timber

roadbed. The removal of the tracks was made necessary because the rock

beneath them and the concrete around the yokes was so closely united

as to be practically monolithic, precluding the use of explosives.

Attempts to remove the rock from under the track demonstrated that it

could not be done without destroying the yokes of the surface railway.

[Illustration: SUPPORTING ELEVATED RAILROAD BY EXTENSION GIRDER--64TH

STREET AND BROADWAY]

The method of undermining the tracks on Broadway from 60th to 104th

Streets was entirely different, for the conditions were not the same.

The street is a wide one with a 22-foot parkway in the center, an

electric conduit railway on either side, and outside each track a wide

roadway. The subway excavation extended about 10 feet outside each

track, leaving between it and the curb ample room for vehicles. The

construction problem, therefore, was to care for the car tracks with a

minimum interference with the excavation. This was accomplished by

temporary bridges for each track, each bridge consisting of a pair of

timber trusses about 55 feet long, braced together overhead high

enough to let a car pass below the bracing. These trusses were set up

on crib-work supports at each end, and the track hung from the lower

chords. (See photograph on page 42.) The excavation then proceeded

until the trench was finished and posts could be put into place

between its bottom and the track. When the track was securely

supported in this way, the trusses were lifted on flat cars and moved

ahead 50 feet.

At 66th Street station the subway roof was about 2 feet from the

electric railway yokes and structures of the street surface line. In

order to build at this point it was necessary to remove two large gas

mains, one 30 inches and the other 36 inches in diameter, and

substitute for them, in troughs built between the roof beams of the

subway, five smaller gas mains, each 24 inches in diameter. This was

done without interrupting the use of the mains.

[Illustration: MOVING BRICK AND CONCRETE RETAINING WALL TO MAKE ROOM

FOR THIRD TRACK--BROADWAY AND 134TH STREET]

At the station on 42d Street, between Park and Madison Avenues, where

there are five subway tracks, and along 42d Street to Broadway, a

special method of construction was employed which was not followed

elsewhere. The excavation here was about 35 feet deep and extended 10

to 15 feet into rock. A trench 30 feet wide was first sunk on the

south side of the street and the subway built in it for a width of two

tracks. Then, at intervals of 50 feet, tunnels were driven toward the

north side of the street. Their tops were about 4 feet above the roof

of the subway and their bottoms were on the roof. When they had been

driven just beyond the line of the fourth track, their ends were

connected by a tunnel parallel with the axis of the subway. The rock

in the bottom of all these tunnels was then excavated to its final

depth. In the small tunnel parallel with the subway axis, a bed of

concrete was placed and the third row of steel columns was erected

ready to carry the steel and concrete roof. When this work was

completed, the earth between the traverse tunnels was excavated, the

material above being supported on poling boards and struts. The roof

of the subway was then extended sidewise over the rock below from the

second to the third row of columns, and it was not until the roof was

finished that the rock beneath was excavated. In this way the subway

was finished for a width of four tracks. For the fifth track the earth

was removed by tunneling to the limits of the subway, and then the

rock below was blasted out.

[Illustration: MOVING WEST SIDE WALL TO WIDEN SUBWAY FOR THIRD

TRACK--135TH STREET AND BROADWAY]

[Illustration: SUBWAY THROUGH NEW "TIMES" BUILDING, SHOWING

INDEPENDENT CONSTRUCTION--THE WORKMEN STAND ON FLOOR GIRDERS OF

SUBWAY]

[Illustration: COLUMNS OF HOTEL BELMONT, PASSING THROUGH SUBWAY AT 42D

STREET AND PARK AVENUE]

In a number of places it was necessary to underpin the columns of the

elevated railways, and a variety of methods were adopted for the work.

A typical example of the difficulties involved was afforded at the

Manhattan Railway Elevated Station at Sixth Avenue and 42d Street. The

stairways of this station were directly over the open excavation for

the subway in the latter thoroughfare and were used by a large number

of people. The work was done in the same manner at each of the four

corners. Two narrow pits about 40 feet apart, were first sunk and

their bottoms covered with concrete at the elevation of the floor of

the subway. A trestle was built in each pit, and on these were placed

a pair of 3-foot plate girders, one on each side of the elevated

column, which was midway between the trestles. The column was then

riveted to the girders and was thus held independent of its original

foundations. Other pits were then sunk under the stairway and trestles

built in them to support it. When this work was completed it was

possible to carry out the remaining excavation without interfering

with the elevated railway traffic.

At 64th Street and Broadway, also, the whole elevated railway had to

be supported during construction. A temporary wooden bent was used to

carry the elevated structure. The elevated columns were removed until

the subway structure was completed at that point. (See photograph on

page 45.)

[Illustration: SMALL WATER MAINS BETWEEN STREET SURFACE AND SUBWAY

ROOF, SUBSTITUTED FOR ONE LARGE MAIN--125TH STREET AND LENOX AVE.]

[Illustration: SPECIAL CONSTRUCTION OF 6-1/2-FOOT SEWER, UNDER CHATHAM

SQUARE]

A feature of the construction which attracted considerable public

attention while it was in progress, was the underpinning of a part of

the Columbus Monument near the southwest entrance to Central Park.

This handsome memorial column has a stone shaft rising about 75 feet

above the street level and weighs about 700 tons. The rubble masonry

foundation is 45 feet square and rests on a 2-foot course of concrete.

The subway passes under its east side within 3 feet of its center,

thus cutting out about three-tenths of the original support. At this

place the footing was on dry sand of considerable depth, but on the

other side of the monument rock rose within 3 feet of the surface. The

steep slope of the rock surface toward the subway necessitated

particular care in underpinning the footings. The work was done by

first driving a tunnel 6 feet wide and 7 feet high under the monument

just outside the wall line of the subway. The tunnel was given a

2-foot bottom of concrete as a support for a row of wood posts a foot

square, which were put in every 5 feet to carry the footing above.

When these posts were securely wedged in place the tunnel was filled

with rubble masonry. This wall was strong enough to carry the weight

of the portion of the monument over the subway, but the monument had

to be supported to prevent its breaking off when undermined. To

support it thus a small tunnel was driven through the rubble masonry

foundation just below the street level and a pair of plate girders run

through it. A trestle bent was then built under each end of the

girders in the finished excavation for the subway. The girders were

wedged up against the top of the tunnel in the masonry and the

excavation was carried out under the monument without any injury to

that structure.

[Illustration: THREE PIPES SUBSTITUTED FOR LARGE BRICK SEWER AT 110TH

STREET AND LENOX AVENUE]

[Illustration: SEWER SIPHON AT 149TH STREET AND RAILROAD AVENUE]

[Illustration: CONCRETE SEWER BACK OF ELECTRIC DUCT MANHOLE--BROADWAY

AND 58TH STREET]

At 134th Street and Broadway a two-track structure of the steel beam

type about 200 feet long was completed. Approaching it from the south,

leading from Manhattan Valley Viaduct, was an open cut with retaining

walls 300 feet long and from 3 to 13 feet in height. After all this

work was finished (and it happened to be the first finished on the

subway), it was decided to widen the road to three tracks, and a

unique piece of work was successfully accomplished. The retaining

walls were moved bodily on slides, by means of jacks, to a line 6-1/4

feet on each side, widening the roadbed 12-1/2 feet, without a break

in either wall. The method of widening the steel-beam typical subway

portion was equally novel. The west wall was moved bodily by jacks

the necessary distance to bring it in line with the new position of

the west retaining wall. The remainder of the structure was then moved

bodily, also by jacks, 6-1/4 feet to the east. The new roof of the

usual type was then added over 12-1/2 feet of additional opening. (See

photographs on pages 46 and 47.)

[Illustration: CONCRETE SEWER BACK OF SIDE WALL, BROADWAY AND 56TH

STREET]

[Illustration: LARGE GAS AND WATER PIPES, RELAID BEHIND EACH SIDE WALL

ON ELM STREET]

Provision had to be made, not only for buildings along the route that

towered far above the street surface, but also for some which

burrowed far below the subway. Photograph on page 47 shows an

interesting example at 42d Street and Broadway, where the pressroom of

the new building of the "New York Times" is beneath the subway, the

first floor is above it, and the first basement is alongside of it.

Incidentally it should be noted that the steel structure of the

building and the subway are independent, the columns of the building

passing through the subway station.

[Illustration: DIFFICULT PIPE WORK--BROADWAY AND 70TH STREET]

At 42d Street and Park Avenue the road passes under the Hotel Belmont,

which necessitated the use of extra heavy steel girders and

foundations for the support of the hotel and reinforced subway

station. (See photograph on page 48.)

Along the east side of Park Row the ascending line of the "loop" was

built through the pressroom of the "New York Times" (the older

downtown building), and as the excavation was considerably below the

bottom of the foundation of the building, great care was necessary to

avoid any settlement. Instead of wood sheathing, steel channels were

driven and thoroughly braced, and construction proceeded without

disturbance of the building, which is very tall.

At 125th Street and Lenox Avenue one of the most complicated network

of subsurface structures was encountered. Street surface electric

lines with their conduits intersect. On the south side of 125th Street

were a 48-inch water main and a 6-inch water main, a 12-inch and two

10-inch gas pipes and a bank of electric light and power ducts. On the

north side were a 20-inch water main, one 6-inch, one 10-inch, and one

12-inch gas pipe and two banks of electric ducts. The headroom between

the subway roof and the surface of the street was 4.75 feet. It was

necessary to relocate the yokes of the street railway tracks on Lenox

Avenue so as to bring them directly over the tunnel roof-beams.

Between the lower flanges of the roof-beams, for four bents, were laid

heavy steel plates well stiffened, and in these troughs were laid four

20-inch pipes, which carried the water of the 48-inch main. (See

photograph on page 49.) Special castings were necessary to make

the connections at each end. The smaller pipes and ducts were

rearranged and carried over the roof or laid in troughs composed of

3-inch I-beams laid on the lower flanges of the roof-beams. In

addition to all the transverse pipes, there were numerous pipes and

duct lines to be relaid and rebuilt parallel to the subway and around

the station. The change was accomplished without stopping or delaying

the street cars. The water mains were shut off for only a few hours.

[Illustration: SPECIAL RIVETED RECTANGULAR WATER PIPE, OVER ROOF OF

SUBWAY AT 126TH STREET AND LENOX AVENUE]

As has been said, the typical subway near the surface was used for

about one-half of the road. Since the sewers were at such a depth as

to interfere with the construction of the subway, it meant that the

sewers along that half had to be reconstructed. This indicates but

very partially the magnitude of the sewer work, however, because

nearly as many main sewers had to be reconstructed off the route of

the subway as on the route; 7.21 miles of main sewers along the route

were reconstructed and 5.13 miles of main sewers off the route. The

reason why so many main sewers on streets away from the subway had to

be rebuilt, was that, from 42d Street, south, there is a natural

ridge, and before the construction of the subway sewers drained to the

East River and to the North River from the ridge. The route of the

subway was so near to the dividing line that the only way to care for

the sewers was, in many instances, to build entirely new outfall

sewers.

[Illustration: THREE-TRACK CONCRETE ARCH--117TH STREET AND BROADWAY]

A notable example of sewer diversion was at Canal Street, where the

flow of the sewer was carried into the East River instead of into the

Hudson River, permitting the sewer to be bulkheaded on the west side

and continued in use. On the east side a new main sewer was

constructed to empty into the East River. The new east-side sewer was

built off the route of the subway for over a mile. An interesting

feature in the construction was the work at Chatham Square, where a

6-1/2-foot circular brick conduit was built. The conjunction at this

point of numerous electric surface car lines, elevated railroad

pillars, and enormous vehicular street traffic, made it imperative

that the surface of the street should not be disturbed, and the sewer

was built by tunneling. This tunneling was through very fine running

sand and the section to be excavated was small. To meet these

conditions a novel method of construction was used. Interlocked

poling boards were employed to support the roof and were driven by

lever jacks, somewhat as a shield is driven in the shield system of

tunneling. The forward ends of the poling boards were supported by a

cantilever beam. The sides and front of the excavation were supported

by lagging boards laid flat against and over strips of canvas, which

were rolled down as the excavation progressed. The sewer was completed

and lined in lengths of from 1 foot to 4-1/2 feet, and at the maximum

rate of work about 12 feet of sewer were finished per week.

[Illustration: CONSTRUCTION OF FORT GEORGE TUNNEL]

At 110th Street and Lenox Avenue a 6-1/2-foot circular brick sewer

intersected the line of the subway at a level which necessitated its

removal or subdivision. The latter expedient was adopted, and three

42-inch cast-iron pipes were passed under the subway. (See photograph

on page 50.) At 149th Street and Railroad Avenue a sewer had to be

lowered below tide level in order to cross under the subway. To do

this two permanent inverted siphons were built of 48-inch cast-iron

pipe. Two were built in order that one might be used, while the other

could be shut off for cleaning, and they have proved very

satisfactory. This was the only instance where siphons were used. In

this connection it is worthy of note that the general changes referred

to gave to the city much better sewers as substitutes for the old

ones.

A number of interesting methods of providing for subsurface structures

are shown in photographs pages 51 to 54. From the General

Post-office at Park Row to 28th Street, just below the surface, there

is a system of pneumatic mail tubes for postal delivery. Of course,

absolutely no change in alignment could be permitted while these tubes

were in use carrying mail. It was necessary, therefore, to support

them very carefully. The slightest deviation in alignment would have

stopped the service.

[Illustration: TWO COLUMN BENT VIADUCT]

[Illustration: TRAVELER FOR ERECTING FORMS, CENTRAL PARK TUNNEL--(IN

THIS TUNNEL DUCTS ARE BUILT IN THE SIDEWALLS)]

[Sidenote: _Concrete-lined

Tunnel_]

Between 33d Street and 42d Street under Park Avenue, between 116th

Street and 120th Street under Broadway, between 157th Street and Fort

George under Broadway and Eleventh Avenue (the second longest

double-track rock tunnel in the United States, the Hoosac tunnel being

the only one of greater length), and between 104th Street and Broadway

under Central Park to Lenox Avenue, the road is in rock tunnel lined

with concrete. From 116th Street to 120th Street the tunnel is 37-1/2

feet wide, one of the widest concrete arches in the world. On the

section from Broadway and 103d Street to Lenox Avenue and 110th Street

under Central Park, a two-track subway was driven through micaceous

rock by taking out top headings and then two full-width benches. The

work was done from two shafts and one portal. All drilling for the

headings was done by an eight-hour night shift, using percussion

drills. The blasting was done early in the morning and the day gang

removed the spoil, which was hauled to the shafts and the portal in

cars drawn by mules. A large part of the rock was crushed for

concrete. The concrete floor was the first part of the lining to be

put in place. Rails were laid on it for a traveler having moulds

attached to its sides, against which the walls were built. A similar

traveler followed with the centering for the arch roof, a length of

about 50 feet being completed at one operation.

[Illustration: FOUR COLUMN (TOWER) VIADUCT CONSTRUCTION]

[Illustration: MANHATTAN VALLEY VIADUCT, LOOKING NORTH]

[Illustration: ERECTION OF ARCH, MANHATTAN VALLEY VIADUCT]

On the Park Avenue section from 34th Street to 41st Street two

separate double-track tunnels were driven below a double-track

electric railway tunnel, one on each side. The work was done from four

shafts, one at each end of each tunnel. At first, top headings were

employed at the north ends of both tunnels and at the south end of the

west tunnel; at the south end of the east tunnel a bottom heading was

used. Later, a bottom heading was also used at the south end of the

west tunnel. The rock was very irregular and treacherous in character,

and the strata inclined so as to make the danger of slips a serious

one. The two headings of the west tunnel met in February and those of

the east tunnel in March, 1902, and the widening of the tunnels to the

full section was immediately begun. Despite the adoption of every

precaution suggested by experience in such work, some disturbance of

the surface above the east tunnel resulted, and several house fronts

were damaged. The portion of the tunnel affected was bulkheaded at

each end, packed with rubble and grouted with Portland cement mortar

injected under pressure through pipes sunk from the street surface

above. When the interior was firm, the tunnel was redriven, using much

the same methods that are employed for tunnels through earth when the

arch lining is built before the central core, or dumpling of earth, is

removed. The work had to be done very slowly to prevent any further

settlement of the ground, and the completion of the widening of the

other parts of the tunnels also proceeded very slowly, because as soon

as the slip occurred a large amount of timbering was introduced, which

interfered seriously with the operations. After the lining was

completed, Portland cement grout was again injected under pressure,

through holes left in the roof, until further movement of the fill

overhead was absolutely prevented.

[Illustration: COMPLETED ARCH AT MANHATTAN STREET]

As has been said, the tunnel between 157th Street and Fort George is

the second longest two-track tunnel in the United States. It was built

in a remarkably short time, considering the fact that the work was

prosecuted from two portal headings and from two shafts. One shaft was

at 168th Street and the other at 181st Street, the work proceeding

both north and south from each shaft. The method employed for the work

(Photograph on page 56) was similar to that used under Central

Park. The shafts at 168th Street and at 181st Street were located at

those points so that they might be used for the permanent elevator

equipment for the stations at these streets. These stations each have

an arch span of about 50 feet, lined with brick.

[Sidenote: _Steel Viaduct_]

The elevated viaduct construction extends from 125th Street to 133d

Street and from Dyckman Street to Bailey Avenue on the western branch,

and from Brook and Westchester Avenues to Bronx Park on the eastern, a

total distance of about 5 miles. The three-track viaducts are carried

on two column bents where the rail is not more than 29 feet above the

ground level, and on four-column towers for higher structures. In the

latter case, the posts of a tower are 29 feet apart transversely and

20 or 25 feet longitudinally, as a rule, and the towers are from 70 to

90 feet apart on centers. The tops of the towers have X-bracing and

the connecting spans have two panels of intermediate vertical sway

bracing between the three pairs of longitudinal girders. In the low

viaducts, where there are no towers, every fourth panel has zigzag

lateral bracing in the two panels between the pairs of longitudinal

girders.

[Illustration: PROFILE OF HARLEM RIVER TUNNEL AND APPROACHES]

[Illustration: SECTION OF HARLEM RIVER TUNNEL DURING CONSTRUCTION]

[Illustration: ASSEMBLING IRON WORK ON PONTOON--HARLEM RIVER TUNNEL]

The towers have columns consisting as a rule of a 16 x 7/16-inch web

plate and four 6 x 4 x 5/8-inch bulb angles. The horizontal struts in

their cross-bracing are made of four 4 x 3-inch angles, latticed to

form an I-shaped cross-section. The X-bracing consists of single 5 x

3-1/2-inch angles. The tops of the columns have horizontal cap angles

on which are riveted the lower flanges of the transverse girders; the

end angles of the girder and the top of the column are also connected

by a riveted splice plate. The six longitudinal girders are

web-riveted to the transverse girders. The outside longitudinal girder

on each side of the viaduct has the same depth across the tower as in

the connecting span, but the four intermediate lines are not so deep

across the towers. In the single trestle bents the columns are the

same as those just described, but the diagonal bracing is replaced by

plate knee-braces.

The Manhattan Valley Viaduct on the West Side line, has a total length

of 2,174 feet. Its most important feature is a two-hinged arch of

168-1/2 feet span, which carries platforms shaded by canopies, but no

station buildings. The station is on the ground between the surface

railway tracks. Access to the platforms is obtained by means of

escalators. It has three lattice-girder two-hinge ribs 24-1/2 feet

apart on centers, the center line of each rib being a parabola. Each

half rib supports six spandrel posts carrying the roadway, the posts

being seated directly over vertical web members of the rib. The chords

of the ribs are 6 feet apart and of an H-section, having four 6 x

6-inch angles and six 15-inch flange and web plates for the center rib

and lighter sections for the outside ribs. The arch was erected

without false work.

[Illustration: SHOWING CONCRETE OVER IRON WORK--HARLEM RIVER TUNNEL]

The viaduct spans of either approach to the arch are 46 to 72 feet

long. All transverse girders are 31 feet 4 inches long, and have a 70

x 3/8-inch web plate and four 6 x 4-inch angles. The two outside

longitudinal girders of deck spans are 72 inches deep and the other 36

inches. All are 3/8-inch thick and their four flange angles vary in

size from 5 x 3-1/2 to 6 x 6 inches, and on the longest spans there

are flange plates. At each end of the viaduct there is a through span

with 90-inch web longitudinal girders.

Each track was proportioned for a dead load of 330 pounds per lineal

foot and a live load of 25,000 pounds per axle. The axle spacing in

the truck was 5 feet and the pairs of axles were alternately 27 and 9

feet apart. The traction load was taken at 20 per cent. of the live

load, and a wind pressure of 500 pounds per lineal foot was assumed

over the whole structure.

[Sidenote: _Tubes under

Harlem River_]

One of the most interesting sections of the work is that which

approaches and passes under the Harlem River, carrying the two tracks

of the East Side line. The War Department required a minimum depth of

20 feet in the river at low tide, which fixed the elevation of the

roof of the submerged part of the tunnel. This part of the line, 641

feet long, consists of twin single-track cast-iron cylinders 16 feet

in diameter enveloped in a large mass of concrete and lined with the

same material. The approach on either side is a double-track concrete

arched structure. The total length of the section is 1,500 feet.

The methods of construction employed were novel in subaqueous

tunneling and are partly shown on photographs on pages 62 and 63.

The bed of the Harlem River at the point of tunneling consists of mud,

silt, and sand, much of which was so nearly in a fluid condition that

it was removed by means of a jet. The maximum depth of excavation was

about 50 feet. Instead of employing the usual method of a shield and

compressed air at high pressure, a much speedier device was contrived.

The river crossing has been built in two sections. The west section

was first built, the War Department having forbidden the closing of

more than half the river at one time. A trench was dredged over the

line of the tunnel about 50 feet wide and 39 feet below low water.

This depth was about 10 feet above the sub-grade of the tunnel. Three

rows of piles were next driven on each side of the trench from the

west bank to the middle of the river and on them working platforms

were built, forming two wharves 38 feet apart in the clear. Piles were

then driven over the area to be covered by the subway, 6 feet 4 inches

apart laterally and 8 feet longitudinally. They were cut off about 11

feet above the center line of each tube and capped with timbers 12

inches square. A thoroughly-trussed framework was then floated over

the piles and sunk on them. The trusses were spaced so as to come

between each transverse row of piles and were connected by eight

longitudinal sticks or stringers, two at the top and two at the bottom

on each side. The four at each side were just far enough apart to

allow a special tongue and grooved 12-inch sheet piling to be driven

between them. This sheathing was driven to a depth of 10 to 15 feet

below the bottom of the finished tunnel.

A well-calked roof of three courses of 12-inch timbers, separated by

2-inch plank, was then floated over the piles and sunk. It had three

timber shafts 7 x 17 feet in plan, and when it was in place and

covered with earth it formed the top of a caisson with the sheet

piling on the sides and ends, the latter being driven after the roof

was in place. The excavation below this caisson was made under air

pressure, part of the material being blown out by water jets and the

remainder removed through the airlocks in the shafts. When the

excavation was completed, the piles were temporarily braced and the

concrete and cast-iron lining put in place, the piles being cut off as

the concrete bed was laid up to them.

The second or eastern section of this crossing was carried on by a

modification of the plan just mentioned. Instead of using a temporary

timber roof on the side walls, the permanent iron and concrete upper

half of the tunnels was employed as a roof for the caisson. The trench

was dredged nearly to sub-grade and its sides provided with wharves as

before, running out to the completed half of the work. The permanent

foundation piles were then driven and a timber frame sunk over them to

serve as a guide for the 12-inch sheet piling around the site. Steel

pilot piles with water jets were driven in advance of the wood-sheet

piles, and if they struck any boulders the latter were drilled and

blasted. The steel piles were withdrawn by a six-part tackle and

hoisting engine, and then the wooden piles driven in their place.

When the piling was finished, a pontoon 35 feet wide, 106 feet long,

and 12 feet deep was built between the wharves, and upon a separate

platform or deck on it the upper half of the cast-iron shells were

assembled, their ends closed by steel-plate diaphragms and the whole

covered with concrete. The pontoon was then submerged several feet,

parted at its center, and each half drawn out endwise from beneath the

floating top of the tunnel. The latter was then loaded and carefully

sunk into place, the connection with the shore section being made by

a diver, who entered the roof through a special opening. When it was

finally in place, men entered through the shore section and cut away

the wood bottom, thus completing the caisson so that work could

proceed below it as before. Three of these caissons were required to

complete the east end of the crossing.

[Illustration: LOOKING UP BROADWAY FROM TRINITY CHURCH--SHOWING

WORKING PLATFORM AND GAS MAINS TEMPORARILY SUPPORTED OVERHEAD]

The construction of the approaches to the tunnel was carried out

between heavy sheet piling. The excavation was over 40 feet deep in

places and very wet, and the success of the work was largely due to

the care taken in driving the 12-inch sheet piling.

[Sidenote: _Methods of

Construction

Brooklyn

Extension_]

A number of interesting features should be noted in the methods of

construction adopted on the Brooklyn Extension.

The types of construction on the Brooklyn Extension have already been

spoken of. They are (1) typical flat-roof steel beam subway from the

Post-office, Manhattan, to Bowling Green; (2) reinforced concrete

typical subway in Battery Park, Manhattan, and from Clinton Street to

the terminus, in Brooklyn; (3) two single track cast-iron-lined

tubular tunnels from Battery Park, under the East River, and under

Joralemon Street to Clinton Street, Brooklyn.

Under Broadway, Manhattan, the work is through sand, the vehicular

and electric street car traffic, the network of subsurface structures,

and the high buildings making this one of the most difficult portions

of the road to build. The street traffic is so great that it was

decided that during the daytime the surface of the street should be

maintained in a condition suitable for ordinary traffic. This was

accomplished by making openings in the sidewalk near the curb, at two

points, and erecting temporary working platforms over the street 16

feet from the surface. The excavations are made by the ordinary drift

and tunnel method. The excavated material is hoisted from the openings

to the platforms and passed through chutes to wagons. On the street

surface, over and in advance of the excavations, temporary plank decks

are placed and maintained during the drifting and tunneling

operations, and after the permanent subway structure has been erected

up to the time when the street surface is permanently restored. The

roof of the subway is about 5 feet from the surface of the street,

which has made it necessary to care for the gas and water mains. This

has been done by carrying the mains on temporary trestle structures

over the sidewalks. The mains will be restored to their former

position when the subway structure is complete.

From Bowling Green, south along Broadway, State Street and in Battery

Park, where the subway is of reinforced concrete construction, the

"open cut and cover" method is employed, the elevated and surface

railroad structures being temporarily supported by wooden and steel

trusses and finally supported by permanent foundations resting on the

subway roof. From Battery Place, south along the loop work, the

greater portion of the excavation is made below mean high-water level,

and necessitates the use of heavy tongue and grooved sheeting and the

operation of two centrifugal pumps, day and night.

The tubes under the East River, including the approaches, are each

6,544 feet in length. The tunnel consists of two cast-iron tubes

15-1/2 feet diameter inside, the lining being constructed of cast-iron

plates, circular in shape, bolted together and reinforced by grouting

outside of the plates and beton filling on the inside to the depth of

the flanges. The tubes are being constructed under air pressure

through solid rock from the Manhattan side to the middle of the East

River by the ordinary rock tunnel drift method, and on the Brooklyn

side through sand and silt by the use of hydraulic shields. Four

shields have been installed, weighing 51 tons each. They are driven by

hydraulic pressure of about 2,000 tons. The two shields drifting to

the center of the river from Garden Place are in water-bearing sand

and are operated under air pressure. The river tubes are on a 3.1 per

cent. grade and in the center of the river will reach the deepest

point, about 94 feet below mean high-water level.

The typical subway of reinforced concrete from Clinton Street to the

Flatbush Avenue terminus is being constructed by the method commonly

used on the Manhattan-Bronx route. From Borough Hall to the terminus

the route of the subway is directly below an elevated railway

structure, which is temporarily supported by timber bracing, having

its bearing on the street surface and the tunnel timbers. The

permanent support will be masonry piers built upon the roof of the

subway structure. Along this portion of the route are street surface

electric roads, but they are operated by overhead trolley and the

tracks are laid on ordinary ties. It has, therefore, been much less

difficult to care for them during the construction of the subway. Work

is being prosecuted on the Brooklyn Extension day and night, and in

Brooklyn the excavation is made much more rapidly by employing the

street surface trolley roads to remove the excavated material. Spur

tracks have been built and flat cars are used, much of the removal

being done at night.