CHAPTER I

E-text prepared by Ronald Holder, Diane Monico, and the Project Gutenberg

Online Distributed Proofreading Team (https://www.pgdp.net/)

Note: Project Gutenberg also has an HTML version of this

file which includes the numerous original illustrations.

See 17569-h.htm or 17569-h.zip:

(https://www.gutenberg.org/dirs/1/7/5/6/17569/17569-h/17569-h.htm)

or

(https://www.gutenberg.org/dirs/1/7/5/6/17569/17569-h.zip)

Interborough Rapid Transit

THE NEW YORK SUBWAY

Its Construction and Equipment

[Illustration: OPERATING ROOM OF POWER HOUSE]

[Illustration: (I.R.T. symbol)]

New York

Interborough Rapid Transit Company

ANNO. DOMI. MCMIV

Copyright, 1904, by

Interborough Rapid Transit Co.

New York

Planned and Executed by The

McGraw Publishing Co.

[Illustration: (McGraw Publishing Company New York logo)]

TABLE OF CONTENTS

Page No.

INTRODUCTION, 13

CHAPTER I. THE ROUTE OF THE ROAD--PASSENGER STATIONS

AND TRACKS, 23

CHAPTER II. TYPES AND METHODS OF CONSTRUCTION, 37

CHAPTER III. POWER HOUSE BUILDING, 67

CHAPTER IV. POWER PLANT FROM COAL PILE TO SHAFTS OF

ENGINES AND TURBINES, 77

CHAPTER V. SYSTEM OF ELECTRICAL SUPPLY, 91

CHAPTER VI. ELECTRICAL EQUIPMENT OF CARS, 117

CHAPTER VII. LIGHTING SYSTEM FOR PASSENGER STATIONS

AND TUNNEL, 121

CHAPTER VIII. ROLLING STOCK--CARS, TRUCKS, ETC., 125

CHAPTER IX. SIGNAL SYSTEM, 135

CHAPTER X. SUBWAY DRAINAGE, 145

CHAPTER XI. REPAIR AND INSPECTION SHED, 147

CHAPTER XII. SUB-CONTRACTORS, 151

INTERBOROUGH RAPID TRANSIT COMPANY

_Directors_

August Belmont

E. P. Bryan

Andrew Freedman

James Jourdan

Gardiner M. Lane

John B. McDonald

Walter G. Oakman

John Peirce

Morton F. Plant

William A. Read

Alfred Skitt

Cornelius Vanderbilt

George W. Young

_Executive Committee_

August Belmont

Andrew Freedman

James Jourdan

Walter G. Oakman

William A. Read

Cornelius Vanderbilt

_Officers_

August Belmont, President

E. P. Bryan, Vice-president

H. M. Fisher, Secretary

D. W. McWilliams, Treasurer

E. F. J. Gaynor, Auditor

Frank Hedley, General Superintendent

S. L. F. Deyo, Chief Engineer

George W. Wickersham, General Counsel

Chas. A. Gardiner, General Attorney

DeLancey Nicoll, Associate Counsel

Alfred A. Gardner, Associate Counsel

_Engineering Staff_

S. L. F. Deyo, Chief Engineer.

_Electrical Equipment_

L. B. Stillwell, Electrical Director.

H. N. Latey, Principal Assistant.

Frederick R. Slater, Assistant Engineer in charge of Third Rail

Construction.

Albert F. Parks, Assistant Engineer in charge of Lighting.

George G. Raymond, Assistant Engineer in charge of Conduits and Cables.

William B. Flynn, Assistant Engineer in charge of Draughting Room.

_Mechanical and Architectural_

J. Van Vleck, Mechanical and Construction Engineer.

William C. Phelps, Assistant Construction Engineer.

William N. Stevens, Ass't Mechanical Engineer.

Paul C. Hunter, Architectural Assistant.

Geo. E. Thomas, Supervising Engineer in Field.

_Cars and Signal System_

George Gibbs, Consulting Engineer.

Watson T. Thompson, Master Mechanic.

J. N. Waldron, Signal Engineer.

RAPID TRANSIT SUBWAY CONSTRUCTION COMPANY

_Directors_

August Belmont

E. P. Bryan

Andrew Freedman

James Jourdan

Gardiner M. Lane

Walther Luttgen

John B. McDonald

Walter G. Oakman

John Peirce

Morton F. Plant

William A. Read

Cornelius Vanderbilt

George W. Young

_Executive Committee_

August Belmont

Andrew Freedman

James Jourdan

Walter G. Oakman

William A. Read

Cornelius Vanderbilt

_Officers_

August Belmont, president

Walter G. Oakman, vice-president

John B. McDonald, contractor

H. M. Fisher, secretary

John F. Buck, treasurer

E. F. J. Gaynor, auditor

S. L. F. Deyo, chief engineer

George W. Wickersham, general counsel

Alfred A. Gardner, attorney

_Engineering Staff_

S. L. F. Deyo, Chief Engineer.

H. T. Douglas, Principal Assistant Engineer.

A. Edward Olmsted, Division Engineer, Manhattan-Bronx Lines.

Henry B. Reed, Division Engineer, Brooklyn Extension.

Theodore Paschke, Resident Engineer, First Division, City Hall to 33d

Street, also Brooklyn Extension, City Hall to Bowling Green; and

Robert S. Fowler, Assistant.

Ernest C. Moore, Resident Engineer, Second Division, 33d Street to

104th Street; and Stanley Raymond, Assistant.

William C. Merryman, Resident Engineer, Third Division, Underground

Work, 104th Street to Fort George West Side and Westchester Avenue

East Side; and William B. Leonard, W. A. Morton, and William E.

Morris, Jr., Assistants.

Allan A. Robbins and Justin Burns, Resident Engineers, Fourth

Division, Viaducts; and George I. Oakley, Assistant.

Frank D. Leffingwell, Resident Engineer, East River Tunnel Division,

Brooklyn Extension; and C. D. Drew, Assistant.

Percy Litchfield, Resident Engineer, Fifth Division, Brooklyn

Extension, Borough Hall to Prospect Park; and Edward R. Eichner,

Assistant.

M. C. Hamilton, Engineer, Maintenance of Way; and Robert E. Brandeis,

Assistant.

D. L. Turner, Assistant Engineer in charge of Stations.

A. Samuel Berquist, Assistant Engineer in charge of Steel Erection.

William J. Boucher, Assistant Engineer in charge of Draughting Rooms.

[Illustration: (INTERBOROUGH RAPID TRANSIT)]

INTRODUCTION

The completion of the rapid transit railroad in the boroughs of

Manhattan and The Bronx, which is popularly known as the "Subway," has

demonstrated that underground railroads can be built beneath the

congested streets of the city, and has made possible in the near

future a comprehensive system of subsurface transportation extending

throughout the wide territory of Greater New York.

In March, 1900, when the Mayor with appropriate ceremonies broke

ground at the Borough Hall, in Manhattan, for the new road, there were

many well-informed people, including prominent financiers and

experienced engineers, who freely prophesied failure for the

enterprise, although the contract had been taken by a most capable

contractor, and one of the best known banking houses in America had

committed itself to finance the undertaking.

In looking at the finished road as a completed work, one is apt to

wonder why it ever seemed impossible and to forget the difficulties

which confronted the builders at the start.

The railway was to be owned by the city, and built and operated under

legislation unique in the history of municipal governments,

complicated, and minute in provisions for the occupation of the city

streets, payment of moneys by the city, and city supervision over

construction and operation. Questions as to the interpretation of

these provisions might have to be passed upon by the courts, with

delays, how serious none could foretell, especially in New York where

the crowded calendars retard speedy decisions. The experience of the

elevated railroad corporations in building their lines had shown the

uncertainty of depending upon legal precedents. It was not, at that

time, supposed that the abutting property owners would have any legal

ground for complaint against the elevated structures, but the courts

found new laws for new conditions and spelled out new property rights

of light, air, and access, which were made the basis for a volume of

litigation unprecedented in the courts of any country.

An underground railroad was a new condition. None could say that the

abutting property owners might not find rights substantial enough, at

least, to entitle them to their day in court, a day which, in this

State, might stretch into many months, or even several years. Owing to

the magnitude of the work, delay might easily result in failure. An

eminent judge of the New York Supreme Court had emphasized the

uncertainties of the situation in the following language: "Just what

are the rights of the owners of property abutting upon a street or

avenue, the fee in and to the soil underneath the surface of which has

been acquired by the city of New York, so far as the same is not

required for the ordinary city uses of gas or water pipes, or others

of a like character, has never been finally determined. We have now

the example of the elevated railroad, constructed and operated in the

city of New York under legislative and municipal authority for nearly

twenty years, which has been compelled to pay many millions of dollars

to abutting property owners for the easement in the public streets

appropriated by the construction and maintenance of the road, and

still the amount that the road will have to pay is not ascertained.

What liabilities will be imposed upon the city under this contract;

what injury the construction and operation of this road will cause to

abutting property, and what easements and rights will have to be

acquired before the road can be legally constructed and operated, it

is impossible now to ascertain."

It is true, that the city undertook "to secure to the contractor the

right to construct and operate, free from all rights, claims, or other

interference, whether by injunction, suit for damages, or otherwise on

the part of any abutting owner or other person." But another eminent

judge of the same court had characterized this as "a condition

absolutely impossible of fulfillment," and had said: "How is the city

to prevent interference with the work by injunction? That question

lies with the courts; and not with the courts of this State alone, for

there are cases without doubt in which the courts of the United States

would have jurisdiction to act, and when such jurisdiction exists they

have not hitherto shown much reluctance in acting.... That legal

proceedings will be undertaken which will, to some extent at least,

interfere with the progress of this work seems to be inevitable...."

Another difficulty was that the Constitution of the State of New York

limited the debt-incurring power of the city. The capacity of the city

to undertake the work had been much discussed in the courts, and the

Supreme Court of the State had disposed of that phase of the situation

by suggesting that it did not make much difference to the municipality

whether or not the debt limit permitted a contract for the work,

because if the limit should be exceeded, "no liability could possibly

be imposed upon the city," a view which might comfort the timid

taxpayers but could hardly be expected to give confidence to the

capitalists who might undertake the execution of the contract.

Various corporations, organized during the thirty odd years of

unsuccessful attempts by the city to secure underground rapid transit,

claimed that their franchises gave them vested rights in the streets

to the exclusion of the new enterprise, and they were prepared to

assert their rights in the courts. (The Underground Railroad Company

of the City of New York sought to enjoin the building of the road and

carried their contest to the Supreme Court of the United States which

did not finally decide the questions raised until March, 1904, when

the subway was practically complete.)

Rival transportation companies stood ready to obstruct the work and

encourage whomever might find objection to the building of the road.

New York has biennial elections. The road could not be completed in

two years, and the attitude of one administration might not be the

attitude of its successors.

The engineering difficulties were well-nigh appalling. Towering

buildings along the streets had to be considered, and the streets

themselves were already occupied with a complicated network of

subsurface structures, such as sewers, water and gas mains, electric

cable conduits, electric surface railway conduits, telegraph and

power conduits, and many vaults extending out under the streets,

occupied by the abutting property owners. On the surface were street

railway lines carrying a very heavy traffic night and day, and all the

thoroughfares in the lower part of the city were congested with

vehicular traffic.

Finally, the city was unwilling to take any risk, and demanded

millions of dollars of security to insure the completion of the road

according to the contract, the terms of which were most exacting down

to the smallest detail.

The builders of the road did not underestimate the magnitude of the

task before them. They retained the most experienced experts for every

part of the work and, perfecting an organization in an incredibly

short time, proceeded to surmount and sweep aside difficulties. The

result is one of which every citizen of New York may feel proud. Upon

the completion of the road the city will own the best constructed and

best equipped intraurban rapid transit railroad in the world. The

efforts of the builders have not been limited by the strict terms of

the contract. They have striven, not to equal the best devices, but to

improve upon the best devices used in modern electrical railroading,

to secure for the traveling public safety, comfort, and speedy

transportation.

The road is off the surface and escapes the delays incident to

congested city streets, but near the surface and accessible, light,

dry, clean, and well ventilated. The stations and approaches are

commodious, and the stations themselves furnish conveniences to

passengers heretofore not heard of on intraurban lines. There is a

separate express service, with its own tracks, and the stations are so

arranged that passengers may pass from local trains to express trains,

and vice versa, without delay and without payment of additional fare.

Special precautions have been taken and devices adopted to prevent a

failure of the electric power and the consequent delays of traffic. An

electro pneumatic block signal system has been devised, which excels

any system heretofore used and is unique in its mechanism. The third

rail for conveying the electric current is covered, so as to prevent

injury to passengers and employees from contact. Special emergency and

fire alarm signal systems are installed throughout the length of the

road. At a few stations, where the road is not near the surface,

improved escalators and elevators are provided. The cars have been

designed to prevent danger from fire, and improved types of motors

have been adopted, capable of supplying great speed combined with

complete control. Strength, utility, and convenience have not alone

been considered, but all parts of the railroad structures and

equipment, stations, power house, and electrical sub-stations have

been designed and constructed with a view to the beauty of their

appearance, as well as to their efficiency.

The completion of the subway marks the solution of a problem which for

over thirty years baffled the people of New York City, in spite of the

best efforts of many of its foremost citizens. An extended account of

Rapid Transit Legislation would be out of place here, but a brief

glance at the history of the Act under the authority of which the

subway has been built is necessary to a clear understanding of the

work which has been accomplished. From 1850 to 1865 the street surface

horse railways were sufficient for the requirements of the traveling

public. As the city grew rapidly, the congestion spreading northward,

to and beyond the Harlem River, the service of surface roads became

entirely inadequate. As early as 1868, forty-two well known business

men of the city became, by special legislative Act, incorporators of

the New York City Central Underground Railway Company, to build a line

from the City Hall to the Harlem River. The names of the incorporators

evidenced the seriousness of the attempt, but nothing came of it. In

1872, also by special Act, Cornelius Vanderbilt and others were

incorporated as The New York City Rapid Transit Company, to build an

underground road from the City Hall to connect with the New York &

Harlem Road at 59th Street, with a branch to the tracks of the New

York Central Road. The enterprise was soon abandoned. Numerous

companies were incorporated in the succeeding years under the general

railroad laws, to build underground roads, but without results; among

them the Central Tunnel Railway Company in 1881, The New York & New

Jersey Tunnel Railway Company in 1883, The Terminal Underground

Railway Company in 1886, The Underground Railroad Company of the City

of New York (a consolidation of the last two companies) in 1896, and

The Rapid Transit Underground Railroad Company in 1897.

All attempts to build a road under the early special charter and later

under the general laws having failed, the city secured in 1891 the

passage of the Rapid Transit Act under which, as amended, the subway

has been built. As originally passed it did not provide for municipal

ownership. It provided that a board of five rapid transit railroad

commissioners might adopt routes and general plans for a railroad,

obtain the consents of the local authorities and abutting property

owners, or in lieu of the consents of the property owners the approval

of the Supreme Court; and then, having adopted detail plans for the

construction and operation, might sell at public sale the right to

build and operate the road to a corporation, whose powers and duties

were defined in the Act, for such period of time and on such terms as

they could. The Commissioners prepared plans and obtained the consents

of the local authorities. The property owners refused their consent;

the Supreme Court gave its approval in lieu thereof, but upon inviting

bids the Board of Rapid Transit Railroad Commissioners found no

responsible bidder.

The late Hon. Abram S. Hewitt, as early as 1884, when legislation for

underground roads was under discussion, had urged municipal ownership.

Speaking in 1901, he said of his efforts in 1884:

"It was evident to me that underground rapid transit could

not be secured by the investment of private capital, but in

some way or other its construction was dependent upon the

use of the credit of the City of New York. It was also

apparent to me that if such credit were used, the property

must belong to the city. Inasmuch as it would not be safe

for the city to undertake the construction itself, the

intervention of a contracting company appeared

indispensable. To secure the city against loss, this company

must necessarily be required to give a sufficient bond for

the completion of the work and be willing to enter into a

contract for its continued operation under a rental which

would pay the interest upon the bonds issued by the city for

the construction, and provide a sinking fund sufficient for

the payment of the bonds at or before maturity. It also

seemed to be indispensable that the leasing company should

invest in the rolling stock and in the real estate required

for its power houses and other buildings an amount of money

sufficiently large to indemnify the city against loss in

case the lessees should fail in their undertaking to build

and operate the railroad."

Mr. Hewitt became Mayor of the city in 1887, and his views were

presented in the form of a Bill to the Legislature in the following

year. The measure found practically no support. Six years later, after

the Rapid Transit Commissioners had failed under the Act of 1891, as

originally drawn, to obtain bidders for the franchise, the New York

Chamber of Commerce undertook to solve the problem by reverting to Mr.

Hewitt's idea of municipal ownership. Whether or not municipal

ownership would meet the approval of the citizens of New York could

not be determined; therefore, as a preliminary step, it was decided to

submit the question to a popular vote. An amendment to the Act of 1891

was drawn (Chapter 752 of the Laws of 1894) which provided that the

qualified electors of the city were to decide at an annual election,

by ballot, whether the rapid transit railway or railways should be

constructed by the city and at the public's expense, and be operated

under lease from the city, or should be constructed by a private

corporation under a franchise to be sold in the manner attempted

unsuccessfully, under the Act of 1891, as originally passed. At the

fall election of 1894, the electors of the city, by a very large vote,

declared against the sale of a franchise to a private corporation and

in favor of ownership by the city. Several other amendments, the

necessity for which developed as plans for the railway were worked

out, were made up to and including the session of the Legislature of

1900, but the general scheme for rapid transit may be said to have

become fixed when the electors declared in favor of municipal

ownership. The main provisions of the legislation which stood upon the

statute books as the Rapid Transit Act, when the contract was finally

executed, February 21, 1900, may be briefly summarized as follows:

(_a_) The Act was general in terms, applying to all cities in the

State having a population of over one million; it was special in

effect because New York was the only city having such a population. It

did not limit the Rapid Transit Commissioners to the building of a

single road, but authorized the laying out of successive roads or

extensions.

(_b_) A Board was created consisting of the Mayor, Comptroller, or

other chief financial officer of the city; the president of the

Chamber of Commerce of the State of New York, by virtue of his office,

and five members named in the Act: William Steinway, Seth Low, John

Claflin, Alexander E. Orr, and John H. Starin, men distinguished for

their business experience, high integrity, and civic pride. Vacancies

in the Board were to be filled by the Board itself, a guaranty of a

continued uniform policy.

(_c_) The Board was to prepare general routes and plans and submit the

question of municipal ownership to the electors of the city.

(_d_) The city was authorized, in the event that the electors decided

for city ownership, to issue bonds not to exceed $50,000,000 for the

construction of the road or roads and $5,000,000 additional, if

necessary, for acquiring property rights for the route. The interest

on the bonds was not to exceed 3-1/2 per cent.

(_e_) The Commissioners were given the broad power to enter into a

contract (in the case of more than one road, successive contracts) on

behalf of the city for the construction of the road with the person,

firm, or corporation which in the opinion of the Board should be best

qualified to carry out the contract, and to determine the amount of

the bond to be given by the contractor to secure its performance. The

essential features of the contract were, however, prescribed by the

Act. The contractor in and by the contract for building the road was

to agree to fully equip it at his own expense, and the equipment was

to include all power houses. He was also to operate the road, as

lessee of the city, for a term not to exceed fifty years, upon terms

to be included in the contract for construction, which might include

provision for renewals of the lease upon such terms as the Board

should from time to time determine. The rental was to be at least

equal to the amount of interest on the bonds which the city might

issue for construction and one per cent. additional. The one per cent.

additional might, in the discretion of the Board, be made contingent

in part for the first ten years of the lease upon the earnings of the

road. The rental was to be applied by the city to the interest on the

bonds and the balance was to be paid into the city's general sinking

fund for payment of the city's debt or into a sinking fund for the

redemption at maturity of the bonds issued for the construction of the

rapid transit road, or roads. In addition to the security which might

be required by the Board of the contractor for construction and

operation, the Act provided that the city should have a first lien

upon the equipment of the road to be furnished by the contractor, and

at the termination of the lease the city had the privilege of

purchasing such equipment from the contractor.

(_f_) The city was to furnish the right of way to the contractor free

from all claims of abutting property owners. The road was to be the

absolute property of the city and to be deemed a part of the public

streets and highways. The equipment of the road was to be exempt from

taxation.

(_g_) The Board was authorized to include in the contract for

construction provisions in detail for the supervision of the city,

through the Board, over the operation of the road under the lease.

One of the most attractive--and, in fact, indispensable features of

the scheme--was that the work of construction, instead of being

subject to the conflicting control of various departments of the City

Government, with their frequent changes in personnel, was under the

exclusive supervision and control of the Rapid Transit Board, a

conservative and continuous body composed of the two principal

officers of the City Government, and five merchants of the very

highest standing in the community.

Provided capitalists could be found to undertake such an extensive

work under the exacting provisions, the scheme was an admirable one

from the taxpayers' point of view. The road would cost the city

practically nothing and the obligation of the contractor to equip and

operate being combined with the agreement to construct furnished a

safeguard against waste of the public funds and insured the prompt

completion of the road. The interest of the contractor in the

successful operation, after construction, furnished a strong incentive

to see that as the construction progressed the details were consistent

with successful operation and to suggest and consent to such

modifications of the contract plans as might appear necessary from an

operating point of view, from time to time. The rental being based

upon the cost encouraged low bids, and the lien of the city upon the

equipment secured the city against all risk, once the road was in

operation.

Immediately after the vote of the electors upon the question of

municipal ownership, the Rapid Transit Commissioners adopted routes

and plans which they had been studying and perfecting since the

failure to find bidders for the franchise under the original Act of

1891. The local authorities approved them, and again the property

owners refused their consent, making an application to the Supreme

Court necessary. The Court refused its approval upon the ground that

the city, owing to a provision of the constitution of the State

limiting the city's power to incur debt, would be unable to raise the

necessary money. This decision appeared to nullify all the efforts of

the public spirited citizens composing the Board of Rapid Transit

Commissioners and to practically prohibit further attempts on their

part. They persevered, however, and in January, 1897, adopted new

general routes and plans. The consolidation of a large territory into

the Greater New York, and increased land values, warranted the hope

that the city's debt limit would no longer be an objection, especially

as the new route changed the line so as to reduce the estimated cost.

The demands for rapid transit had become more and more imperative as

the years went by, and it was fair to assume that neither the courts

nor the municipal authorities would be overzealous to find a narrow

construction of the laws. Incidentally, the constitutionality of the

rapid transit legislation, in its fundamental features, had been

upheld in the Supreme Court in a decision which was affirmed by the

highest court of the State a few weeks after the Board had adopted its

new plans. The local authorities gave their consent to the new route;

the property owners, as on the two previous occasions, refused their

consent; the Supreme Court gave its approval in lieu thereof; and the

Board was prepared to undertake the preliminaries for letting a

contract. These successive steps and the preparation of the terms of

the contract all took time; but, finally, on November 15, 1899, a form

of contract was adopted and an invitation issued by the Board to

contractors to bid for the construction and operation of the railroad.

There were two bidders, one of whom was John B. McDonald, whose terms

submitted under the invitation were accepted on January 15, 1900; and,

for the first time, it seemed as if a beginning might be made in the

actual construction of the rapid transit road. The letter of

invitation to contractors required that every proposal should be

accompanied by a certified check upon a National or State Bank,

payable to the order of the Comptroller, for $150,000, and that within

ten days after acceptance, or within such further period as might be

prescribed by the Board, the contract should be duly executed and

delivered. The amount to be paid by the city for the construction was

$35,000,000 and an additional sum not to exceed $2,750,000 for

terminals, station sites, and other purposes. The construction was to

be completed in four years and a half, and the term of the lease from

the city to the contractor was fixed at fifty years, with a renewal,

at the option of the contractor, for twenty-five years at a rental to

be agreed upon by the city, not less than the average rental for the

then preceding ten years. The rental for the fifty-year term was fixed

at an amount equal to the annual interest upon the bonds issued by the

city for construction and 1 per cent. additional, such 1 per cent.

during the first ten years to be contingent in part upon the earnings

of the road. To secure the performance of the contract by Mr. McDonald

the city required him to deposit $1,000,000 in cash as security for

construction, to furnish a bond with surety for $5,000,000 as security

for construction and equipment, and to furnish another bond of

$1,000,000 as continuing security for the performance of the contract.

The city in addition to this security had, under the provisions of the

Rapid Transit Act, a first lien on the equipment, and it should be

mentioned that at the expiration of the lease and renewals (if any)

the equipment is to be turned over to the city, pending an agreement

or arbitration upon the question of the price to be paid for it by the

city. The contract (which covered about 200 printed pages) was minute

in detail as to the work to be done, and sweeping powers of

supervision were given the city through the Chief Engineer of the

Board, who by the contract was made arbiter of all questions that

might arise as to the interpretation of the plans and specifications.

The city had been fortunate in securing for the preparation of plans

the services of Mr. William Barclay Parsons, one of the foremost

engineers of the country. For years as Chief Engineer of the Board he

had studied and developed the various plans and it was he who was to

superintend on behalf of the city the completion of the work.

During the thirty-two years of rapid transit discussion between 1868,

when the New York City Central Underground Company was incorporated,

up to 1900, when the invitations for bids were issued by the city,

every scheme for rapid transit had failed because responsible

capitalists could not be found willing to undertake the task of

building a road. Each year had increased the difficulties attending

such an enterprise and the scheme finally evolved had put all of the

risk upon the capitalists who might attempt to finance the work, and

left none upon the city. Without detracting from the credit due the

public-spirited citizens who had evolved the plan of municipal

ownership, it may be safely asserted that the success of the

undertaking depended almost entirely upon the financial backing of the

contractor. When the bid was accepted by the city no arrangements had

been made for the capital necessary to carry out the contract. After

its acceptance, Mr. McDonald not only found little encouragement in

his efforts to secure the capital, but discovered that the surety

companies were unwilling to furnish the security required of him,

except on terms impossible for him to fulfill.

The crucial point in the whole problem of rapid transit with which the

citizens of New York had struggled for so many years had been reached,

and failure seemed inevitable. The requirements of the Rapid Transit

Act were rigid and forbade any solution of the problem which committed

the city to share in the risks of the undertaking. Engineers might

make routes and plans, lawyers might draw legislative acts, the city

might prepare contracts, the question was and always had been, Can

anybody build the road who will agree to do it and hold the city safe

from loss?

It was obvious when the surety companies declined the issue that the

whole rapid transit problem was thrown open, or rather that it always

had been open. The final analysis had not been made. After all, the

attitude of the surety companies was only a reflection of the general

feeling of practical business and railroad men towards the whole

venture. To the companies the proposition had come as a concrete

business proffer and they had rejected it.

At this critical point, Mr. McDonald sought the assistance of Mr.

August Belmont. It was left to Mr. Belmont to make the final analysis,

and avert the failure which impended. There was no time for indecision

or delay. Whatever was to be done must be done immediately. The

necessary capital must be procured, the required security must be

given, and an organization for building and operating the road must be

anticipated. Mr. Belmont looking through and beyond the intricacies of

the Rapid Transit Act, and the complications of the contract, saw that

he who undertook to surmount the difficulties presented by the

attitude of the surety companies must solve the whole problem. It was

not the ordinary question of financing a railroad contract. He saw

that the responsibility for the entire rapid transit undertaking must

be centered, and that a compact and effective organization must be

planned which could deal with every phase of the situation.

Mr. Belmont without delay took the matter up directly with the Board

of Rapid Transit Railroad Commissioners, and presented a plan for the

incorporation of a company to procure the security required for the

performance of the contract, to furnish the capital necessary to carry

on the work, and to assume supervision over the whole undertaking.

Application was to be made to the Supreme Court to modify the

requirements with respect to the sureties by striking out a provision

requiring the justification of the sureties in double the amount of

liabilities assumed by each and reducing the minimum amount permitted

to be taken by each surety from $500,000 to $250,000. The new

corporation was to execute as surety a bond for $4,000,000, the

additional amount of $1,000,000 to be furnished by other sureties. A

beneficial interest in the bonds required from the sub-contractors was

to be assigned to the city and, finally, the additional amount of

$1,000,000, in cash or securities, was to be deposited with the city

as further security for the performance of the contract. The plan was

approved by the Board of Rapid Transit Railroad Commissioners, and

pursuant to the plan, the Rapid Transit Subway Construction Company

was organized. The Supreme Court granted the application to modify the

requirements as to the justification of sureties and the contract was

executed February 21, 1900.

As president and active executive head of the Rapid Transit Subway

Construction Company, Mr. Belmont perfected its organization,

collected the staff of engineers under whose direction the work of

building the road was to be done, supervised the letting of

sub-contracts, and completed the financial arrangements for carrying

on the work.

The equipment of the road included, under the terms of the contract,

the rolling stock, all machinery and mechanisms for generating

electricity for motive power, lighting, and signaling, and also the

power house, sub-stations, and the real estate upon which they were to

be erected. The magnitude of the task of providing the equipment was

not generally appreciated until Mr. Belmont took the rapid transit

problem in hand. He foresaw from the beginning the importance of that

branch of the work, and early in 1900, immediately after the signing

of the contract, turned his attention to selecting the best engineers

and operating experts, and planned the organization of an operating

company. As early as May, 1900, he secured the services of Mr. E. P.

Bryan, who came to New York from St. Louis, resigning as

vice-president and general manager of the Terminal Railroad

Association, and began a study of the construction work and plans for

equipment, to the end that the problems of operation might be

anticipated as the building and equipment of the road progressed. Upon

the incorporation of the operating company, Mr. Bryan became

vice-president.

In the spring of 1902, the Interborough Rapid Transit Company, the

operating railroad corporation was formed by the interests represented

by Mr. Belmont, he becoming president and active executive head of

this company also, and soon thereafter Mr. McDonald assigned to it the

lease or operating part of his contract with the city, that company

thereby becoming directly responsible to the city for the equipment

and operation of the road, Mr. McDonald remaining as contractor for

its construction. In the summer of the same year, the Board of Rapid

Transit Railroad Commissioners having adopted a route and plans for an

extension of the subway under the East River to the Borough of

Brooklyn, the Rapid Transit Subway Construction Company entered into a

contract with the city, similar in form to Mr. McDonald's contract, to

build, equip, and operate the extension. Mr. McDonald, as contractor

of the Rapid Transit Subway Construction Company, assumed the general

supervision of the work of constructing the Brooklyn extension; and

the construction work of both the original subway and the extension

has been carried on under his direction. The work of construction has

been greatly facilitated by the broad minded and liberal policy of the

Rapid Transit Board and its Chief Engineer and Counsel, and by the

coöperation of all the other departments of the City Government, and

also by the generous attitude of the Metropolitan Street Railway

Company and its lessee, the New York City Railroad Company, in

extending privileges which have been of great assistance in the

prosecution of the work. In January, 1903, the Interborough Rapid

Transit Company acquired the elevated railway system by lease for 999

years from the Manhattan Railway Company, thus assuring harmonious

operation of the elevated roads and the subway system, including the

Brooklyn extension.

The incorporators of the Interborough Rapid Transit Company were

William H. Baldwin, Jr., Charles T. Barney, August Belmont, E. P.

Bryan, Andrew Freedman, James Jourdan, Gardiner M. Lane, John B.

McDonald, DeLancey Nicoll, Walter G. Oakman, John Peirce, Wm. A. Read,

Cornelius Vanderbilt, George W. Wickersham, and George W. Young.

The incorporators of the Rapid Transit Subway Construction Company

were Charles T. Barney, August Belmont, John B. McDonald, Walter G.

Oakman, and William A. Read.

[Illustration: (wings)]

[Illustration: EXTERIOR VIEW OF POWER HOUSE]

CHAPTER I

THE ROUTE OF THE ROAD--PASSENGER STATIONS AND TRACKS

The selection of route for the Subway was governed largely by the

amount which the city was authorized by the Rapid Transit Act to

spend. The main object of the road was to carry to and from their

homes in the upper portions of Manhattan Island the great army of

workers who spend the business day in the offices, shops, and

warehouses of the lower portions, and it was therefore obvious that

the general direction of the routes must be north and south, and that

the line must extend as nearly as possible from one end of the island

to the other.

The routes proposed by the Rapid Transit Board in 1895, after

municipal ownership had been approved by the voters at the fall

election of 1894, contemplated the occupation of Broadway below 34th

Street to the Battery, and extended only to 185th Street on the west

side and 146th Street on the east side of the city. As has been told

in the introductory chapter, this plan was rejected by the Supreme

Court because of the probable cost of going under Broadway. It was

also intimated by the Court, in rejecting the routes, that the road

should extend further north.

It had been clear from the beginning that no routes could be laid out

to which abutting property owners would consent, and that the consent

of the Court as an alternative would be necessary to any routes

chosen. To conform as nearly as possible to the views of the Court,

the Commission proposed, in 1897, the so called "Elm Street route,"

the plan finally adopted, which reached from the territory near the

General Post-office, the City Hall, and Brooklyn Bridge Terminal to

Kingsbridge and the station of the New York & Putnam Railroad on the

upper west side, and to Bronx Park on the upper east side of the city,

touching the Grand Central Depot at 42d Street.

Subsequently, by the adoption of the Brooklyn Extension, the line was

extended down Broadway to the southern extremity of Manhattan Island,

thence under the East River to Brooklyn.

The routes in detail are as follows:

[Sidenote:

_Manhattan-Bronx

Route_]

Beginning near the intersection of Broadway and Park Row, one of the

routes of the railroad extends under Park Row, Center Street, New Elm

Street, Elm Street, Lafayette Place, Fourth Avenue (beginning at Astor

Place), Park Avenue, 42d Street, and Broadway to 125th Street, where

it passes over Broadway by viaduct to 133d Street, thence under

Broadway again to and under Eleventh Avenue to Fort George, where it

comes to the surface again at Dyckman Street and continues by viaduct

over Naegle Avenue, Amsterdam Avenue, and Broadway to Bailey Avenue,

at the Kingsbridge station of the New York & Putnam Railroad, crossing

the Harlem Ship Canal on a double-deck drawbridge. The length of this

route is 13.50 miles, of which about 2 miles are on viaduct.

Another route begins at Broadway near 103d Street and extends under

104th Street and the upper part of Central Park to and under Lenox

Avenue to 142d Street, thence curving to the east to and under the

Harlem River at about 145th Street, thence from the river to and

under East 149th Street to a point near Third Avenue, thence by

viaduct beginning at Brook Avenue over Westchester Avenue, the

Southern Boulevard and the Boston Road to Bronx Park. The length of

this route is about 6.97 miles, of which about 3 miles are on viaduct.

[Illustration: MAP SHOWING THE LINES OF THE INTERBOROUGH RAPID TRANSIT

CO. 1904]

At the City Hall there is a loop under the Park. From 142d Street

there is a spur north under Lenox Avenue to 148th Street. There is a

spur at Westchester and Third Avenues connecting by viaduct the

Manhattan Elevated Railway Division of Interborough Rapid Transit

Company with the viaduct of the subway at or near St. Ann's Avenue.

[Sidenote: _Brooklyn Route_]

The route of the Brooklyn Extension connects near Broadway and Park

Row with the Manhattan Bronx Route and extends under Broadway, Bowling

Green, State Street, Battery Park, Whitehall Street, and South Street

to and under the East River to Brooklyn at the foot of Joralemon

Street, thence under Joralemon Street, Fulton Street, and Flatbush

Avenue to Atlantic Avenue, connecting with the Brooklyn tunnel of the

Long Island Railroad at that point. There is a loop under Battery Park

beginning at Bridge Street. The length of this route is about 3 miles.

The routes in Manhattan and The Bronx may therefore be said to roughly

resemble the letter Y with the base at the southern extremity of

Manhattan Island, the fork at 103d Street and Broadway, the terminus

of the westerly or Fort George branch of the fork just beyond Spuyten

Duyvil Creek, the terminus of the easterly or Bronx Park branch at

Bronx Park.

[Sidenote: _Location

of Stations_]

The stations beginning at the base of the Y and following the route up

to the fork are located at the following points:

South Ferry, Bowling Green and Battery Place, Rector Street and

Broadway, Fulton Street and Broadway, City Hall, Manhattan; Brooklyn

Bridge Entrance, Manhattan; Worth and Elm Streets, Canal and Elm

Streets, Spring and Elm Streets, Bleecker and Elm Streets, Astor Place

and Fourth Avenue, 14th Street and Fourth Avenue, 18th Street and

Fourth Avenue, 23d Street and Fourth Avenue, 28th Street and Fourth

Avenue, 33d Street and Fourth Avenue, 42d Street and Madison Avenue

(Grand Central Station), 42d Street and Broadway, 50th Street and

Broadway, 60th Street and Broadway (Columbus Circle), 66th Street and

Broadway, 72d Street and Broadway, 79th Street and Broadway, 86th

Street and Broadway, 91st Street and Broadway, 96th Street and

Broadway.

[Illustration: 34TH STREET AND PARK AVENUE, LOOKING SOUTH]

The stations of the Fort George or westerly branch are located at the

following points:

One Hundred and Third Street and Broadway, 110th Street and Broadway

(Cathedral Parkway), 116th Street and Broadway (Columbia University),

Manhattan Street (near 128th Street) and Broadway, 137th Street and

Broadway, 145th Street and Broadway, 157th Street and Broadway, the

intersection of 168th Street, St. Nicholas Avenue and Broadway, 181st

Street and Eleventh Avenue, Dyckman Street and Naegle Avenue (beyond

Fort George), 207th Street and Amsterdam Avenue, 215th Street and

Amsterdam Avenue, Muscoota Street and Broadway, Bailey Avenue, at

Kingsbridge near the New York & Putnam Railroad station.

The stations on the Bronx Park or easterly branch are located at the

following points:

One Hundred and Tenth Street and Lenox Avenue, 116th Street and Lenox

Avenue, 125th Street and Lenox Avenue, 135th Street and Lenox Avenue,

145th Street and Lenox Avenue (spur), Mott Avenue and 149th Street,

the intersection of 149th Street, Melrose and Third Avenues, Jackson

and Westchester Avenues, Prospect and Westchester Avenues, Westchester

Avenue near Southern Boulevard (Fox Street), Freeman Street and the

Southern Boulevard, intersection of 174th Street, Southern Boulevard

and Boston Road, 177th Street and Boston Road (near Bronx Park).

[Illustration: PROFILE OF RAPID TRANSIT RAILROAD MANHATTAN AND

BRONX LINES.]

The stations in the Borough of Brooklyn on the Brooklyn Extension are

located as follows:

Joralemon Street near Court (Brooklyn Borough Hall), intersection of

Fulton, Bridge, and Hoyt Streets; Flatbush Avenue near Nevins Street,

Atlantic Avenue and Flatbush Avenue (Brooklyn terminal of the Long

Island Railroad).

From the Borough Hall, Manhattan, to the 96th Street station, the line

is four-track. On the Fort George branch (including 103d Street

station) there are three tracks to 145th Street and then two tracks to

Dyckman Street, then three tracks again to the terminus at Bailey

Avenue. On the Bronx Park branch there are two tracks to Brook Avenue

and from that point to Bronx Park there are three tracks. On the Lenox

Avenue spur to 148th Street there are two tracks, on the City Hall

loop one track, on the Battery Park loop two tracks. The Brooklyn

Extension is a two-track line.

There is a storage yard under Broadway between 137th Street and 145th

Street on the Fort George branch, another on the surface at the end of

the Lenox Avenue spur, Lenox Avenue and 148th Street, and a third on

an elevated structure at the Boston Road and 178th Street. There is a

repair shop and inspection shed on the surface adjoining the Lenox

Avenue spur at the Harlem River and 148-150th Streets, and an

inspection shed at the storage yard at Boston Road and 178th Street.

[Sidenote: _Length of

Line._]

The total length of the line from the City Hall to the Kingsbridge

terminal is 13.50 miles, with 47.11 miles of single track and sidings.

The eastern or Bronx Park branch is 6.97 miles long, with 17.50 miles

of single track.

[Illustration: PROFILE OF BROOKLYN EXTENSION.]

[Sidenote: _Grades and

Curves._]

The total length of the Brooklyn Extension is 3.1 miles, with about 8

miles of single track.

The grades and curvature along the main line may be summarized as

follows:

The total curvature is equal in length to 23 per cent. of the straight

line, and the least radius of curvature is 147 feet. The greatest

grade is 3 per cent., and occurs on either side of the tunnel under

the Harlem River. At each station there is a down grade of 2.1 per

cent., to assist in the acceleration of the cars when they start. In

order to make time on roads running trains at frequent intervals, it

is necessary to bring the trains to their full speed very soon after

starting. The electrical equipment of the Rapid Transit Railroad will

enable this to be done in a better manner than is possible with steam

locomotives, while these short acceleration grades at each station, on

both up and down tracks, will be of material assistance in making the

starts smooth.

Photograph on page 26 shows an interesting feature at a local

station, where, in order to obtain the quick acceleration in grade for

local trains, and at the same time maintain a level grade for the

express service, the tracks are constructed at a different level. This

occurs at many local stations.

On the Brooklyn Extension the maximum grade is 3.1 per cent.

descending from the ends to the center of the East River tunnel. The

minimum radius of curve is 1,200 feet.

[Illustration: STANDARD STEEL CONSTRUCTION IN TUNNEL--THIRD RAIL

PROTECTION NOT SHOWN]

[Illustration: PLAN OF BROOKLYN BRIDGE STATION AND CITY HALL LOOP]

[Sidenote: _Track_]

The track is of the usual standard construction with broken stone

ballast, timber cross ties, and 100-pound rails of the American

Society of Civil Engineers' section. The cross ties are selected hard

pine. All ties are fitted with tie plates. All curves are supplied

with steel inside guard rails. The frogs and switches are of the best

design and quality to be had, and a special design has been used on

all curves. At the Battery loop, at Westchester Avenue, at 96th

Street, and at City Hall loop, where it has been necessary for the

regular passenger tracks to cross, grade crossings have been avoided;

one track or set of tracks passing under the other at the intersecting

points. (See plan on this page.)

The contract for the building of the road contains the following

somewhat unusual provision: "The railway and its equipment as

contemplated by the contract constitute a great public work. All parts

of the structure where exposed to public sight shall therefore be

designed, constructed, and maintained with a view to the beauty of

their appearance, as well as to their efficiency."

It may be said with exact truthfulness that the builders have spared

no effort or expense to live up to the spirit of this provision, and

that all parts of the road and equipment display dignified and

consistent artistic effects of the highest order. These are noticeable

in the power house and the electrical sub-stations and particularly in

the passenger stations. It might readily have been supposed that the

limited space and comparative uniformity of the underground stations

would afford but little opportunity for architectural and decorative

effects. The result has shown the fallacy of such a supposition.

[Illustration: PLAN OF 28TH ST. & 4TH AVENUE STATION.]

Of the forty-eight stations, thirty-three are underground, eleven are

on the viaduct portions of the road, and three are partly on the

surface and partly underground, and one is partly on the surface and

partly on the viaduct.

[Sidenote: _Space Occupied_]

The underground stations are at the street intersections, and, except

in a few instances, occupy space under the cross streets. The station

plans are necessarily varied to suit the conditions of the different

locations, the most important factor in planning them having been the

amount of available space. The platforms are from 200 to 350 feet in

length, and about 16 feet in width, narrowing at the ends, while the

center space is larger or smaller, according to local conditions. As a

rule the body of the station extends back about 50 feet from the edge

of the platform.

At all local stations (except at 110th Street and Lenox Avenue) the

platforms are outside of the tracks. (Plan and photograph on pages

30 and 31.) At Lenox Avenue and 110th Street there is a single island

platform for uptown and downtown passengers.

[Illustration: 28TH STREET STATION]

[Sidenote: _Island

Platforms_]

At express stations there are two island platforms between the express

and local tracks, one for uptown and one for downtown traffic. In

addition, there are the usual local platforms at Brooklyn Bridge, 14th

Street (photograph on page 34) and 96th Street. At the remaining

express stations, 42d Street and Madison Avenue and 72d Street, there

are no local platforms outside of the tracks, local and through

traffic using the island platforms.

The island platforms at Brooklyn Bridge, 14th Street, and 42d Street

and Madison Avenue are reached by mezzanine footways from the local

platforms, it having been impossible to place entrances in the streets

immediately over the platforms. At 96th Street there is an underground

passage connecting the local and island platforms, and at 72d Street

there are entrances to the island platforms directly from the street

because there is a park area in the middle of the street. Local

passengers can transfer from express trains and express passengers

from local trains without payment of additional fare by stepping

across the island platforms.

At 72d Street, at 103d Street, and at 116th Street and Broadway the

station platforms are below the surface, but the ticket booths and

toilet rooms are on the surface; this arrangement being possible also

because of the park area available in the streets. At Manhattan Street

the platforms are on the viaduct, but the ticket booths and toilet

rooms are on the surface. The viaduct at this point is about 68 feet

above the surface, and escalators are provided. At many of the

stations entrances have been arranged from the adjacent buildings, in

addition to the entrances originally planned from the street.

[Sidenote: Kiosks]

The entrances to the underground stations are enclosed at the street

by kiosks of cast iron and wire glass (photograph on page 33), and

vary in number from two to eight at a station. The stairways are of

concrete, reinforced by twisted steel rods. At 168th Street, at 181st

Street, and at Mott Avenue, where the platforms are from 90 to 100

feet below the surface, elevators are provided.

[Illustration: WEST SIDE OF 23D STREET STATION]

At twenty of the underground stations it has been possible to use

vault lights to such an extent that very little artificial light is

needed. (Photograph on page 35.) Such artificial light as is

required is supplied by incandescent lamps sunk in the ceilings.

Provision has been made for using the track circuit for lighting in

emergency if the regular lighting circuit should temporarily fail.

[Illustration: KIOSKS AT COLUMBUS CIRCLE]

The station floors are of concrete, marked off in squares. At the

junction of the floors and side walls a cement sanitary cove is

placed. The floors drain to catch-basins, and hose bibs are provided

for washing the floors.

[Illustration: BROOKLYN BRIDGE STATION]

Two types of ceiling are used, one flat, which covers the steel and

concrete of the roof, and the other arched between the roof beams and

girders, the lower flanges of which are exposed. Both types have an

air space between ceiling and roof, which, together with the air

space behind the inner side walls, permits air to circulate and

minimizes condensation on the surface of the ceiling and walls.

[Illustration: PLAQUE SHOWING BEAVER AT ASTOR PLACE STATION]

The ceilings are separated into panels by wide ornamental mouldings,

and the panels are decorated with narrower mouldings and rosettes. The

bases of the walls are buff Norman brick. Above this is glass tile or

glazed tile, and above the tile is a faience or terra-cotta cornice.

Ceramic mosaic is used for decorative panels, friezes, pilasters, and

name-tablets. A different decorative treatment is used at each

station, including a distinctive color scheme. At some stations the

number of the intersecting street or initial letter of the street name

is shown on conspicuous plaques, at other stations the number or

letter is in the panel. At some stations artistic emblems have been

used in the scheme of decoration, as at Astor Place, the beaver (see

photograph on this page); at Columbus Circle, the great

navigator's Caravel; at 116th Street, the seal of Columbia University.

The walls above the cornice and the ceilings are finished in white

Keene cement.

[Illustration: EXPRESS STATION AT 14TH STREET, SHOWING ISLAND AND

MEZZANINE PLATFORMS AND STAIRS CONNECTING THEM]

[Illustration: WEST SIDE OF COLUMBUS CIRCLE STATION (60TH

STREET)--ILLUMINATED BY DAYLIGHT COMING THROUGH VAULT LIGHTS]

[Illustration: CARAVEL AND WALL DECORATION]

The ticket booths are of oak with bronze window grills and fittings.

There are toilet rooms in every station, except at the City Hall loop.

Each toilet room has a free closet or closets, and a pay closet which

is furnished with a basin, mirror, soap dish, and towel rack. The

fixtures are porcelain, finished in dull nickel. The soil, vent and

water pipes are run in wall spaces, so as to be accessible. The rooms

are ventilated through the hollow columns of the kiosks, and each is

provided with an electric fan. They are heated by electric heaters.

The woodwork of the rooms is oak; the walls are red slate wainscot and

Keene cement.

Passengers may enter the body of the station without paying fare. The

train platforms are separated from the body of the station by

railings. At the more important stations, separate sets of entrances

are provided for incoming and outgoing passengers, the stairs at the

back of the station being used for entrances and those nearer the

track being used for exits.

[Illustration: CITY HALL STATION]

An example of the care used to obtain artistic effects can be seen at

the City Hall station. The road at this point is through an arched

tunnel. In order to secure consistency in treatment the roof of the

station is continued by a larger arch of special design. (See

photograph on this page.) At 168th Street, and at 181st Street,

and at Mott Avenue stations, where the road is far beneath the

surface, it has been possible to build massive arches over the

stations and tracks, with spans of 50 feet.