THE ST. CLAIR TUNNEL

The final model of the soft-ground series reflects, as did the Hoosac

Tunnel model for hard-rock tunneling, final emergence into the modern

period. Although the St. Clair Tunnel was completed over 70 years ago,

it typifies in its method of construction, the basic procedures of

subaqueous work in the present day. The Thames Tunnel of Brunel, and

Haskin's efforts beneath the Hudson, had clearly shown that by

themselves, both the shield and pneumatic systems of driving through

fluid ground were defective in practice for tunnels of large area.

Note that the earliest successful works by each method had been of

very small area, so that the influence of adverse conditions was

greatly diminished.

The first man to perceive and seize upon the benefits to be gained by

combining the two systems was, most fittingly, Greathead. Although he

had projected the technique earlier, in driving the underground City

and South London Railway in 1886, he brought together for the first

time the three fundamental elements essential for the practical

tunneling of soft, water-bearing ground: compressed-air support of the

work during construction, the movable shield, and cast-iron, permanent

lining. The marriage was a happy one indeed; the limitations of each

system were almost perfectly overcome by the qualities of the others.

The conditions prevailing in 1882 at the Sarnia, Ontario, terminal of

the Grand Trunk Railway, both operational and physical, were almost

precisely the same as those which inspired the undertaking of the

Hudson River Tunnel. The heavy traffic at this vital U.S.--Canada rail

interchange was ferried inconveniently across the wide St. Clair

River, and the bank and river conditions precluded construction of a

bridge. A tunnel was projected by the railway in that year, the time

when Haskin's tribulations were at their height. Perhaps because of

this lack of precedent for a work of such size, nothing was done

immediately. In 1884 the railway organized a tunnel company; in 1886

test borings were made in the riverbed and small exploratory drifts

were started across from both banks by normal methods of mine

timbering. The natural gas, quicksand, and water encountered soon

stopped the work.

[Illustration: Figure 43.--REAR VIEW OF ST. CLAIR SHIELD showing the

erector arm placing a cast-iron lining segment. The three motions of

the arm--axial, radial, and rotational, were manually powered.

(Smithsonian photo 49260-C.)]

It was at this time that the railway's president visited Greathead's

City and South London workings. The obvious answer to the St. Clair

problem lay in the successful conduct of this subway. Joseph Hobson,

chief engineer of the Grand Trunk and of the tunnel project, in

designing a shield, is said to have searched for drawings of the

shields used in the Broadway and Tower Subways of 1868-9, but unable

to locate any, he relied to a limited extent on the small drawings of

those in Drinker's volume. There is no explanation as to why he did

not have drawings of the City and South London shield at that moment

in use, unless one considers the rather unlikely possibility that

Greathead maintained its design in secrecy.

[Illustration: Figure 44.--OPENING OF THE ST. CLAIR TUNNEL, 1891.

(_Photo courtesy of Detroit Library, Burton Historical Collection._)]

The Hobson shield followed Greathead's as closely as any other, in

having a diaphragm with closable doors, but a modification of Beach's

sharpened horizontal shelves was also used. However, these functioned

more as working platforms than supports for the earth. The machine was

21-1/2 feet in diameter, an unprecedented size and almost twice that

of Greathead's current one. It was driven by 24 hydraulic rams.

Throughout the entire preliminary consideration of the project there

was a marked sense of caution that amounted to what seems an almost

total lack of confidence in success. Commencement of the work from

vertical shafts was planned so that if the tunnel itself failed, no

expenditure would have been made for approach work. In April 1888,

the shafts were started near both riverbanks, but before reaching

proper depth the almost fluid clay and silt flowed up faster than it

could be excavated and this plan was abandoned. After this second

inauspicious start, long open approach cuts were made and the work

finally began. The portals were established in the cuts, several

thousand feet back from each bank and there the tunneling itself

began. The portions under the shore were driven without air. When the

banks were reached, brick bulkheads containing air locks were built

across the opening and the section beneath the river, about 3,710 feet

long, driven under air pressure of 10 to 28 pounds above atmosphere.

For most of the way, the clay was firm and there was little air

leakage. It was found that horses could not survive in the compressed

air, and so mules were used under the river.

In the firm clay, excavation was carried on several feet in front of

the shield, as shown in the model (fig. 42). About twelve miners

worked at the face. However, in certain strata the clay encountered

was so fluid that the shield could be simply driven forward by the

rams, causing the muck to flow in at the door openings without

excavation. After each advance, the rams were retracted and a ring of

iron lining segments built up, as in the Tower Subway. Here, for the

first time, an "erector arm" was used for placing the segments, which

weighed about half a ton. In all respects, the work advanced with

wonderful facility and lack of operational difficulty. Considering

the large area, no subaqueous tunnel had ever been driven with such

speed. The average monthly progress for the American and Canadian

headings totaled 455 feet, and at top efficiency 10 rings or a length

of 15.3 feet could be set in a 24-hour day in each heading. The 6,000

feet of tunnel was driven in just a year; the two shields met

vis-a-vis in August of 1890.

The transition was complete. The work had been closely followed by the

technical journals and the reports of its successful accomplishment

thus were brought to the attention of the entire civil engineering

profession. As the first major subaqueous tunnel completed in America

and the first in the world of a size able to accommodate full-scale

rail traffic, the St. Clair Tunnel served to dispel the doubts

surrounding such work, and established the pattern for a mode of

tunneling which has since changed only in matters of detail.

Of the eight models, only this one was built under the positive

guidance of original documents. In the possession of the Canadian

National Railways are drawings not only of all elements of the shield

and lining, but of much of the auxiliary apparatus used in

construction. Such materials rarely survive, and do so in this case

only because of the foresight of the railway which, to avoid paying a

high profit margin to a private contractor as compensation for the

risk and uncertainty involved, carried the contract itself and,

therefore, preserved all original drawing records.

While the engineering of tunnels has been comprehensively treated in

this paper from the historical standpoint, it is well to still reflect

that the advances made in tunneling have not perceptibly removed the

elements of uncertainty but have only provided more positive and

effective means of countering their forces. Still to be faced are the

surprises of hidden streams, geologic faults, shifts of strata,

unstable materials, and areas of extreme pressure and temperature.