Let us see what can be done by both these working night

and day for 250 days in the year; thus making ample

allowance for repairs and stoppages.

The dredges employed at the barrage, of 20 horse power,

and raising sand from a depth of seven metres, filled

thirty-three lighters in the day and twenty-eight in the

night, in all 61 _per diem_, giving a total of 610 to 700

_met. cub._; but these machines were almost continually

stopped for want of a sufficient number of lighters.

These same dredges, on the Seine, removed as much as 500

_met. cub._ in the day, and an equal quantity at night,

excavating, it is true, at a depth of only 2 _met._ 50.

The price paid per cubic metre was 0 _fr._ 75, including

carrying away and discharging. At the barrage, on account

of the low price of labour, the cubic metre has not cost

0 _fr._ 50.

For deepening the roadstead of Toulon, dredges of

twenty-five horse power were employed, which raised the

mud from a depth of 9 _met._ 50 below low water.

These dredges worked 270 days in the year, and each

raised 194,755 _met. cub._ The cubic metre of soil

extracted was fixed provisionally for the account at 1

_fr._ 20, including the transport and discharge, which

was at an average distance of several miles in the open

sea.

At the port of Valencia, dredges of thirty-five horse

power were employed, raising 750 _met. cub._ _per diem_,

from a depth of 5 to 7 _metres_. A steamer of seventy

horse power towed the lighters to a distance of fifteen

miles, and the cubic _metre_ thus raised and transported

only cost 0 _fr._ 75.

From these data it may be assumed, that the dredges of

twenty horse power will raise 500 _met. cub._ of earth

_per diem_ from a depth of 4 _met._, and we may fix the

price of extraction, including transport, at 0 _fr._, 75;

that the dredges of thirty-five horse power will raise

750 _met. cub._ at 1 _fr._ By causing the dredges to work

day and night, and assuming, as we have said, an average

of 250 working days in the year, a dredge of twenty horse

power will excavate _per ann._ 250,000

and a dredge of thirty-five horse power 375,000

-------

_met. cub._ 625,000

The total quantity of excavation to be performed by

dredges being 57,205,342 _met. cub._, if the work is

to be done in five years, it will be necessary to have

nineteen pairs of dredges; and, if it be observed that

for the greater part of the Isthmus, the excavation may

be done by hand to the depth of a foot at least below

the level of the Mediterranean, since the bottom of the

Bitter Lakes remains dry at a depth which reaches 8

_met._, 58, it will be found that nineteen pairs will be

amply sufficient.

Supposing half the work to be done by each kind of

dredge respectively, the cost is found to be 50,054,674

CANAL OF COMMUNICATION.—The quantity of earth-work to be

performed for the canal of communication and irrigation

is calculated from the sections at 10,320,884 _met. cub._

from the receipt of water to Lake Timsah. For this work

men will easily be found, at the rate of 3 _piast._ (0

_fr._ .75) including all expenses, and each workman will

do easily 2 _met._ _per diem_, which reduces the price of

the cubic _metre_ to 0 _fr_. 37½.

The cost of excavating the canal will therefore be 3,870,331

For the small canal of irrigation, leading from the last

channel to Suez, the quantity of earth-work is 2,218,500

_met. cub._ For this it will be necessary to pay the men

0 _fr._ 90 _per diem_, and they will easily do 2 _met._

25 _cub._, which will be 0 _fr._ 40 per _met. cub._

The cost of this part will therefore be 887,400

Add 10 _per cent._ for tools 6,529,667

Contingencies 173,654

----------------

Total for the first part _fr._ 72,000,000

ARTICLE II.

WORKS OF ART.

To give a concise but accurate notion of the expense of the works of art,

we shall fix the prime cost of the materials, compared with the prices

paid in the execution of the works of the barrage, and then it will be

easy to determine the outlay necessary for the present works, as compared

with that of the former.

ROUGH STONE.—The rough stone used in the barrage comes

from the quarries of Toura, situated 30 _kil._ from

the place where it is used. It costs 22 _paras_ the

_quintal_, or 4 _fr._, 20, the _cubic metre_, delivered

on the spot. That which will be used in the works of the

Maritime Canal will come from the quarries of Ataka, on

the shores of the bay of Suez, at a distance of 20 _kil._

from Suez. This being a calcareous stone, like that of

Toura, if it is brought to the boats by a railroad and

towed by steamers, there is sure to be a saving in the

extraction and transport. We have however, taken the

price at 5 _fr._ to cover all difficulties in forming

establishments, the higher rate of labour, and the cost

of the railroad. This is the price paid for the blocks

employed at the port of Cherbourg.

At the port of Valencia (in Spain), the extraction of

large blocks, the transport to the quay and loading, only

cost 4 _fr._ 25.

HEWN STONE.—The hewn stone for the barrage, came from

the quarries of Toura and Massara, at an average distance

of 33 _kil._ from the place where used. These stones were

first transported a distance of 6 _kil._ to the banks of

the Nile, by means of bullock carts, then transferred

to sailing barges, and carried by water to the distance

above-mentioned.

The price per _cubic metre_ was 24 _piast._ (6 _fr._) for

extraction, and 18 _piast._ (4 _fr._ 50) for carriage; in

all 10 _fr._ 50.

For the works of the Maritime Canal, stone will be used

coming from quarries now in work on the banks, at the

level of high water for the whole extent of the Gulf of

Suez, and also from quarries on the shore of the Red Sea,

at a distance of about 10 _kil._ from Suez, which furnish

a shelly calcareous stone, soft when extracted, but

hardening by exposure to the air, and also in sea water.

This stone has been successfully employed in building the

Grand Hotel of Suez, and has cost 33 _piast._ (8 _fr._

25.) the _cubic metre_, hewn and delivered at the quay.

We have adopted this price, increased by 60 _per cent._

in order to cover the distance, and to arrive more easily

at the comparison which we wish to establish.

BRICKS.—The bricks used in the barrage were made by

steam machines, and cost, on account of extraordinary

circumstances, 26 _fr._ per thousand. Those which will

be made by hand or by means of bullock machines in the

_Wady Tomilat_, will not cost half so much; for they can

be made in the whole of that valley at the rate of 6 to 7

_fr._ per thousand, on account of the great quantity of

combustibles found in that locality.

We have however assumed, that on account of the expense

of transport, from Pelusium to Suez, the bricks will come

to the same price, as at the barrage, which is evidently

an excess.

LIME.—The lime cost at the barrage, 8 _fr._ 70 the _cubic

metre_, delivered on the spot. That which is made at Suez

comes to 7 _fr_. 75 delivered. This lime is made in the

valley of Guébé, with the combustibles found there in

abundance, and which only cost the labour of cutting and

transport.

POZZOLANO.—As the lime used in the barrage was fat lime,

it was necessary to make artificial Pozzolano, which

came to 45 _piast._ (11 _fr._ 25) the _cubic metre_.

This Pozzolano could not be used for sea work, for we

are convinced by experience that it is affected by the

magnesia which is found in sea-water. It can, therefore,

only serve for the works of the canal of communication,

and, like the bricks, it will cost less than at the

barrage.

For the sea masonry, we have happily discovered solid

masses in the harbour of Suez, anciently formed at the

time of the Caliphs, or more probably at that of the

Ptolemies. These masses of masonry are so compact, that

when fragments are detached, the stone breaks more easily

than the mortar, which is simply composed of sand and

hydraulic lime.

This lime very probably comes from the mountains of

Ataka, which contain several beds of calcareous marl;

and there is no doubt that, by making researches, the

beds that supplied the hydraulic lime may be discovered.

Samples have been sent to M. Leplay, chief engineer and

professor at the School of Mines, for analyzation, and

more will be sent until good beds shall be found.

On this supposition, it is more than likely that the

masonry of the Maritime Canal will be less expensive than

that of the barrage, since it will be enough to have

hydraulic lime to mix with the sand, which is found at

all points of the Canal.

TIMBER.—The timber will come from Anatolia and Caramania.

Oak and fir planks will be procured from Trieste. These

materials will not cost more than at the barrage; for,

though the distance of inland transport is greater,

the expense of trans-shipment will be avoided by the

construction of a new lock, which will unite the

Mahmoudieh Canal, and consequently the Nile, with the sea.

IRON.—It will be the same with regard to wrought and cast

iron, which will be procured from England and Russia.

Now, the barrage of the Nile is 1006 _metres_ in length, with four locks,

of which two are double, of 12 _metres_ opening, and two others of 15

_metres_. It is established upon a general platform at 7 _metres_ below

the low water, is 46 _metres_ wide, and four _metres_ average thickness,

with two lines of jaunting piles, and 1600 _metres_ of quay walls, and

only cost 18,000,000 _francs_, including the purchase of steam machines,

to the number of twenty-two, the construction of all works and all the

charges of administration, which were considerable.

If this amount is divided by the total length of 1006, 17,900 francs

will be obtained for the cost of a running _metre_, including all the

accessories of locks, quays, machines, and charges of administration.

BARRAGE LOCKS.—Adopting this figure, which is too high

by a good third for the Maritime Canal, the two barrage

locks and the oblique barrage, being altogether 300

metres in length, would cost _fr._ 5,370,000

We say that this figure is much too high; 1st. Because

the barrage was made to support a pressure of 4 to 5

_metres_ of water, while those of the Maritime Canal

will never have to sustain more than 2,50 _met._ at the

_maximum_ height of the water; 2nd. Because the waters

of the Nile, rising to 7,50 _met._ above the low water

line, it was necessary to elevate the masonry, piles, and

arches, to make at the same time a bridge of passage, and

to increase the weight of the masonry; 3rd. and lastly,

Because it was necessary to defend the banks of the Nile

by 1600 metres of quay walls, both at the approaches of

the barrage and at the head of the three canals, which is

not necessary here.

Notwithstanding these reasons, we have adopted the above

figure, in order to obtain a result, rather in excess

than below the reality, and thus to give every confidence

in our valuations.

JETTIES AT PELUSIUM AND SUEZ.—For the jetties, both at

Pelusium and Suez, we have said that we should adopt

the mode of construction by loose stones, as has been

done in the greatest known works, and in the majority

of the ports in the Mediterranean, such as Cannes,

Bandol, Barcelona, Valencia, Cadiz, Genoa, &c. &c.,

always reducing the width of the causeway according to

the necessity of the case. Thus, the jetty which is

to windward in the prevailing winds, has a width of 8

_metres_ at the summit for its causeway, which is at 1

_met._, 50, above low water.

There is, moreover, a parapet 4 _met._ thick and 3

_met._, 50, high. On the other hand, the jetty to the

leeward has a causeway only 6 _metres_ wide, and the

parapet 3 _met._ thick and 2 _met._, 50, high.

In order to enable the ships to approach the windward

jetty, and to be towed its whole length, masonry in

hydraulic mortar has been disposed on the interior slope

of the jetty from a depth of 3 _met._ below low water,

as shown on the section drawn on the map. This is only

in imitation of what is seen in the harbour of Bastia,

as well as in those of Cannes and Bandol, and the other

details have been taken from those adopted in the

construction of the last-mentioned.

Assuming that the jetty east of Suez will be 4000 _met._

long, there will be 970,000 _met. cub._ of rough stones,

which at 5 _fr._ the _metre_ on board the vessels,

amounts to _fr._ 4,750,000

Taking the transport and sinking at 2 _fr._,

which is a great deal, we have 1,940,000

---------

Total _fr._ 6,690,000

---------

Say in round numbers 7,000,000

For the western jetty, the same amount 7,000,000

For the jetty west of Pelusium, if we assume that the

transport will be for a distance of 150 _kil._ at 0 _fr._

03 _per ton_, _per kil._ which will be about 0 _fr._ 06

_per cubic metre_, we shall have 9 _fr._ for the cost of

transport, to which add 1 _fr._ for sinking; with the

cost of extraction it will be 15 _fr._ per _cubic metre_.

The quantity being 1,000,000 _met. cub._ we get an amount

of 15,000,000

and as much for the western jetty 15,000,000

MOLE OF PELUSIUM.—The defensive mole being 500 _met._ in

length, its contents will be 250,000 _met. cub._, and the

cost of its construction 3,750,000

RETAINING BASIN.—The semicircular dyke forming the

retaining basin will have a developement of 6200 _met._

and the contents will be 890,000 _met. cub._ its cost

will therefore be 13,500,000

The shingling on the banks of the canal for a length of

100 _kil._ is estimated at 1,500,000

QUAY WALLS OF PORT TIMSAH.—The quay walls to be constructed

in the harbour of Lake Timsah, for a length of 1500

_met._ are estimated at 1200 _fr._ the running _metre_

(though we have constructed some entirely of hewn stone,

which only cost 850 _fr._); the cost of this item will

therefore be 1,800,000

In order to ascertain in a general manner whether the

figures which we exhibit are in conformity with the data

resulting from experience, we have examined the costs of

analogous works, that we might compare them with those

which we have determined.

The dyke of Cherbourg, which is 3800 _met._ long, has

cost 68,000,000, after all the vicissitudes it has

undergone from the beginning of the century. It comes

therefore to about 17,900 _fr._ per running _metre_.

Its depth is 18 _met._, 80 below high water, while the

average depth of those projected is only 4 _met._ Now if

we assume, as is evidently correct, that the bulk, and

consequently the cost of each, are as the square of its

height, we find that as the dyke of Cherbourg cost 17,900

_fr._ the running _metre_, those of Suez should cost

twenty-two times less, that is 815 _fr._ yet they come to

1790 _fr._ the running _metre_.

The jetties of the harbour of Joliette at Marseilles,

allowance made for all expenses, come to 5500 _fr._ the

running _metre_. Their foundations are 11 _met._, 50

below low water. Those of Pelusium ought, therefore, to

cost nine times less, that is 615 _fr._

The mole of the harbour of Valencia, which is 560 _met._

long, and the foundation 8 _metres_, 50, deep, was

awarded for a sum of 3,000,000 _fr._: according to this

price the defensive mole of Pelusium should cost less

than that sum, while we have estimated it at 3,750,000

_fr._

The mole of the harbour of Cannes, which is only 150

_met._ long, has been estimated at 1,300,000 _fr._, which

is 8666 _fr._ per running metre, but it goes to depths

of water that reach 10 _met._: its cost is therefore,

at least six times more considerable than that of the

jetties of Suez; yet our estimate is more than the fifth

of that figure.

We may therefore say that our estimates are in excess

as regards the works of Suez, and very much more so for

those of Pelusium, since, in proportion, our figures

exceed even those of works executed under the most

unfavourable conditions.

CANAL OF COMMUNICATION.—For the canal of communication,

we have first to erect pumps of 500 horse power in

the aggregate, in order to provide amply for all the

incidents of navigation, irrigation, losses by filtration

and evaporation; as, for irrigation and navigation we

only require 800,000 _metres cub. per diem_, while pumps

of 500 horse power will supply 1,296,000.

STEAM PUMPS.—The steam pumps that have been erected in

Egypt, have come to 2,200 _fr._ per horse power, fixed

and mounted complete; for this item, therefore, there

will be an expenditure of 1,100,000

BARRAGE LOCKS.—There will be six barrage locks with

draw-bridges; the locks will be 12 _met._ wide and 54

_met._ long between the gates. The cost of each barrage

lock complete will be 300,000 _fr._ and for the six 1,800,000

CULTIVATION OF LANDS.—For bringing the lands into

cultivation we must reckon 200 _fr. per feddan_, or 500

_fr. per hectare_. It is true that land may be bought in

the country, all prepared with agricultural buildings,

magazines, cattle, plant, &c. &c., at the rate of 250

_fr._ the _feddan_ (625 _fr._ the _hectare_), but the

agricultural system established on these lands is very

defective.

The expenditure for 40,000 _feddans_, or 16,000

_hectares_, will be 8,000,000

FIXING THE SANDS.—For fixing the sands we have seen that

the cost would be 66 _fr._, 80, the _hectare_. It appears

to us advantageous to carry out this operation on a large

scale; we have therefore adopted the figure of 24,000

_hectares_ (60,000 _feddans_). The expenditure for this

item will be 1,603,200

CONDUIT PIPES.—For the conduit pipes, of which there

will be a total length of 80,000 _metres_, we adopt

those on the Charmeroi principle, although there are now

earthenware pipes very suitable for water courses, and

which do not cost half what the Charmeroi pipes do. These

latter, 0 _met._, 10, in diameter, which is the size

adopted, are laid complete, including the trenches, 1

_met._, 40 deep, at 6 _fr._, 30 _per metre_. On account

of the carriage, we put the _metre_ at 8 _fr._, which

makes an amount of 640,000

LIGHT HOUSES AND BEACONS.—We assume that there will be

two lighthouses, one at the Damietta point, and the other

on the Red Sea, at Raz Mohammed. There will be besides,

two beacons at the head of the jetties at Pelusium and

at Suez. The lighthouses with their lenticular apparatus

will cost, the two 150,000 _fr._

and the two beacons 20,000 _fr._

in all 170,000

There will be houses for the officers, barracks for the

workmen, stables for the animals, magazines for the

provisions, materials, &c. &c., for which we set down an

approximate amount of 1,000,000

-----------------

Total cost of Art. II. for Works of Art _fr._ 84,233,200

Total cost of Art. I. Earth-works 72,000,000

-----------------

Total cost _fr._ 156,233,200

We assume that it will require full six years to

accomplish the works, and that the expenses of

administration will amount to two and a half _per cent._

on the total cost; therefore for this item will be

required a sum of 3,905,830

A farther sum for contingent works, unforeseen 2,410,970

-----------------

Grand total of the cost _fr._ 162,550,000

DISTRIBUTION OF THE WORK.—Let us now see how this sum

is to be expended, and in what manner the works may be

distributed, in order to their completion in the space of

six years.

The first thing to be done is, evidently, to bring the

fresh water into the Isthmus, in order to supply the

workmen, and to effect the transport of provisions and

materials.

The canal of communication, with its locks, the

irrigating channel, and the water conduit, may be easily

executed in the first year, since these works only

represent 12,539,384 _met. cub._, or, at the _maximum_

6,269,692 days’ work, at the rate of two _cubic metres

per diem_. Taking 300 working days in the year, it will

require 20,898 men. In this part of Egypt from 30 to

40,000 may easily be had if necessary.

In the same year the grand yards will be formed at the

quarries, with all the railways, quays, and landing

places, for the extraction and supply, on a large scale,

of the stone necessary for the moles, jetties, and works

of art.

Contracts will be made with the manufacturers for the

supply of dredges, lighters, towing barges, boats, and

other machines to be employed in the execution of the

works. In this first campaign, the expenditure will be

approximately _fr._ 12,000,000.

In the second year, eight dredges will be mounted in

the harbour of Suez to excavate the channel and the

foundations of the jetties. The operations at the

quarries, the erection of the jetties, and the barrage

lock, may therefore be pushed on with all desirable

activity.

Fresh water will be thrown into Lake Timsah, to set to

work all the other disposable dredges; 30,000 workmen

will perform all the clearance in the extent of the

Bitter Lakes, and for the remainder of the Canal. They

will prepare a trench in the ground to 1 _met._ 50, below

low water, and so form a channel 15 _met._ wide, which

will enable the barges and machines to pass and repass

the whole extent of the Isthmus. All the force will be

applied this year to open a communication between Suez

and Lake Timsah, and consequently between Suez and the

Nile.

The fixing of the downs, and the cultivation of the

lands, will be commenced. The expenditure of this

campaign will be approximately _fr._ 25,000,000.

In the third year the communication of Lake Timsah with

the Mediterranean will be opened, and all the disposable

force will be employed in making the scouring basin and

erecting the jetties. The earth-works will be continued,

the dredging also, the sowings on the downs, and the

agricultural labours. 20,000 workmen will be employed

this year, and the expenditure may be set down at _fr._ 30,000,000.

In the fourth year, the same works as in the preceding,

that is, the earth-works will be continued both by hand

and by the dredges, the jetties, the barrage locks, and

the quay wall in the Lake. Moreover, the defensive mole

will be commenced; the sowings and cultivation extended.

It is estimated that 20,000 workmen will still be

required, and an expenditure of _fr._ 33,000,000

In the fifth and sixth years, the same operations will be

continued, but so many men will no longer be required;

for the dredges will perform the principal part of the

work, and the operations at the quarries can then be

pushed on with all possible activity.

We assume for each of these years an expenditure of

_fr._ 31,000,000; for both _fr._ 62,000,000

Which will make up the amount of the estimate _fr._ 162,000,000

INTEREST TO BE PAID TO THE SHAREHOLDERS.—As it is usual

to pay interest to the shareholders on the amounts

subscribed, in proportion to the paid-up capital, it is

necessary to take an account of the interest so accruing,

and to carry the amount to the cost of execution.

Interest on 12,000,000 _fr._ subscribed the first year

at 5 _per cent._ for six years _fr._ 3,600,000

—25,000,000 2nd yr. 5 _per cent._ 5 yrs. 6,250,000

—30,000,000 3rd ” ” 4 ” 6,000,000

—33,000,000 4th ” ” 3 ” 4,950,000

—31,000,000 5th ” ” 2 ” 3,100,000

—31,000,000 6th ” ” 1 ” 1,550,000

----------------

_fr._ 25,450,000

Total of interest payable to the shareholders, to be

added to the estimated amount of expenditure 162,550,000

-------------

188,000,000

-------------

Let us, however, carry the _maximum_ capital to be

applied in the undertaking to _fr._ 200,000,000