On August 6, 1918, a contract was awarded to S. S. Schell for
macadamizing the above newly graded section in Pass Creek Canyon, by the
State Highway Commission, same to be a standard three course broken
stone, water bound surface. This work was carried through in a very able
manner on the part of the Contractor and completed November 16, 1918.
This surfacing makes an all year road, of one of the worst pieces of
road in the State. The entire cost of this work was paid by the State.
DETAILED EXPENDITURE STATEMENT--MACADAMIZING--COMSTOCK TO LANE COUNTY
LINE
Engineering $ 302.09
Advertisements for bids 66.90
Construction--
Broken Stone Macadam, 4,354 cu. yds. at
$3.35 $14,585.90
Earth Filler, 150 cu. yds. at 75c. 112.50
Removing Slides 117.70
----------
Total Paid to Contractor 14,816.10
----------
Total Cost $15,185.09