DETAILED EXPENDITURE STATEMENT--GRADING COMSTOCK TO LANE COUNTY LINE

Engineering $ 2,029.80

Construction--

Clearing and Grubbing $2,400.00

Common Excavation, 11,688 cu. yds. at 45c. 5,259.60

Intermediate Excavation, 6,085 cu. yds. at 60c. 3,651.00

Solid Rock Excavation, 1,016 cu. yds. at $1.15 1,168.40

Overhaul per 100 ft., 7,220 cu. yds. at 3c. 216.60

12-inch Plain Concrete Pipe, 134 lin. ft. at

$1.00 134.00

24-inch Reinforced Concrete pipe, 160 lin. ft.

at $2.50 400.00

6-inch Porous Drain Tile, 591 lin. ft. at 20c. 118.20

Class A Concrete, 120.46 c. y. at $24.00 2,891.04

Class B Concrete, 11.62 c. y. at $16.00 185.92

Metal Reinforcement, 7,625 lbs. at 8c. 609.84

Repairing Timber Bridge 26.34

Laying 315.5 lin. ft. of Drain Tile and

Backfilling 56.00

Total paid to Contractor 17,116.94

----------

Total Cost $19,146.74

Paid by County 17,119.44

Paid by State $2,027.30

----------

Total $19,146.74

Third biennial report of the Oregon State Highway Commission · 第 144 / 292 题