Engineering $ 2,029.80
Construction--
Clearing and Grubbing $2,400.00
Common Excavation, 11,688 cu. yds. at 45c. 5,259.60
Intermediate Excavation, 6,085 cu. yds. at 60c. 3,651.00
Solid Rock Excavation, 1,016 cu. yds. at $1.15 1,168.40
Overhaul per 100 ft., 7,220 cu. yds. at 3c. 216.60
12-inch Plain Concrete Pipe, 134 lin. ft. at
$1.00 134.00
24-inch Reinforced Concrete pipe, 160 lin. ft.
at $2.50 400.00
6-inch Porous Drain Tile, 591 lin. ft. at 20c. 118.20
Class A Concrete, 120.46 c. y. at $24.00 2,891.04
Class B Concrete, 11.62 c. y. at $16.00 185.92
Metal Reinforcement, 7,625 lbs. at 8c. 609.84
Repairing Timber Bridge 26.34
Laying 315.5 lin. ft. of Drain Tile and
Backfilling 56.00
Total paid to Contractor 17,116.94
----------
Total Cost $19,146.74
Paid by County 17,119.44
Paid by State $2,027.30
----------
Total $19,146.74