Grading and Macadam--Comstock to Leona

This section is through the south end of Pass Creek Canyon, beginning

approximately a mile and a half south of Comstock and extending to a

point a half mile north of Leona, being 4.6 miles in length. The

contract was a joint contract signed by the County Court and State

Highway Commission and was awarded to Hall & Soleim of Eugene on

September 5, 1917. Work covered by the contract was for grading and

macadamizing, culverts and bridges.

Due to shortage of labor, poor shipments on macadam rock, and financial

difficulties, the contractors were obliged to ask the State Highway

Commission to take over the work. On August 20, 1918, after a conference

with the County Court and the Contractor's Surety Company, this was

done. The work was completed November 30, 1918. The construction details

under the State supervision were handled by a State construction

engineer, representing the Contractors and Surety Company, and the

engineering details by the resident engineer on the work--the latter

rendering regular monthly estimates of work done on the unit contract

prices, of the original contract.

This work complete will cost approximately $80,000.00 of which the

County will pay $74,349.72 and the State $5,650.28.

The construction of this section was in charge of E. B. Bishop, resident

engineer, and F. E. LaPointe, construction superintendent.

Third biennial report of the Oregon State Highway Commission · 第 146 / 292 题