Goble Creek Bridge

A ninety-foot reinforced concrete bridge was built over Goble Creek on

the Columbia River Highway about one-half mile east of Goble. This

bridge has a pile foundation which was put in by the Warren Construction

Company on a cost plus basis for $1,583.32. The superstructure was built

by Lindstrom and Fiegeson on a unit price basis. The cost of the

structure complete was $5,907.14.

The engineering work in connection with this work was handled by H. C.

Compton, resident engineer, on the Goble Section, and the inspection of

the placement of steel and pouring of concrete was in charge of L. M.

Huggins.

Third biennial report of the Oregon State Highway Commission · 第 130 / 292 题