CHAPTER XVIII

Logistics

The conquest of Leyte was taking longer than had been anticipated. The

decision of the Japanese to make Leyte the decisive battleground

of the Philippines had forced the Americans to commit not only the

reserve 32d and 77th Infantry Divisions but also the 112th Cavalry

Regimental Combat Team, the 11th Airborne Division, and elements of

the 38th Infantry Division. The inability of the Americans to establish

considerable land-based air forces on Leyte, as well as the unexpected

Japanese reinforcement program, had retarded the campaign. Not only

was the timetable of future operations in the Pacific upset, but a

strong possibility existed that it would not be feasible to establish

a major logistical and air base on the island--the primary purpose

of the operation.

The construction program on Leyte was hampered by conflicting

priorities and, as had been foreseen, very poor terrain, bad weather

conditions, and a shortage of service personnel.

Construction

Retelling the disagreements and describing the conflicts that arose

over the everchanging needs of the Army, Navy, and Air Forces would

be involved, tedious, and unprofitable. But the progress of the

construction program must be recounted, since it had direct bearing

not only on the Leyte Campaign but also on the Mindoro and Luzon

operations.

Airfields

The importance of the development of the airfields cannot be

overemphasized. The inability of the Sixth Army to meet its

construction dates on the airstrips, because of poor soil conditions

and heavy rains, prevented the U. S. forces from stopping the flow

of Japanese reinforcements and made it impossible for the Allied

Air Forces to give sufficient land-based air support to the ground

troops. It also forced a postponement of the Mindoro operation. It

is well, therefore, to summarize just what had been accomplished in

airfield construction.

Work on the Tacloban airstrip had been handicapped at first by the

heavy concentration of troops, supplies, and equipment in the area

during the early stages of the operation. Thereafter, work was further

hampered by the insufficient supply of coral for surfacing the runway

and by the very heavy traffic concentrated on the haul road because of

the necessity for unloading cargo over White Beach. By 25 December,

1 runway, 50 dispersal areas, 536,000 square feet of alert apron,

1 diagonal taxiway, 1 parallel dispersal taxiway, and 8,943 feet of

additional dispersal taxiways had been constructed.

The Dulag airfield was located on the flat flood plain of the Marabang

River. The difficulties encountered were numerous: time lost because

of excessive rains that amounted to thirty-five inches in forty days;

air alerts; very poor drainage, which required the construction of

a system of drag-line trenches to the river; and very poor access

roads. The access roads required an excessive expenditure of time,

labor, and material in order to maintain traffic to the airfield. One

runway, 2 alert areas with gravel surface and 2 with mat surface,

1 matted transport parking area, 133 dispersal areas, and 24,200 feet

of dispersal taxiways were constructed by 25 December.

In the latter part of November all construction work was stopped on the

three airfields in the Burauen area, but not before considerable time

and effort had been expended in futile attempts to make the airfields

usable. [1029] Since these airfields could not be made serviceable,

General Krueger received permission from General MacArthur to construct

an airfield in the Tanauan area, and moved his headquarters from

Tanauan to Tologosa on 28 November in order that construction might

be started. The new site had a good sandy surface, its drainage

was satisfactory, and it proved to be an excellent location for an

airfield. By 16 December the field became operational, and by the

25th there had been completed 1 runway with mat surfacing, 1 overrun,

90,000 square feet of warm-up area, 120,000 square feet of alert apron,

1 parallel taxiway, and 26 large dispersal areas. [1030]

Roads

The rehabilitation of roads presented problems as vexatious as those

in airfield construction. In southern Leyte Valley, the road that

ran from Dulag through Burauen to Dagami soon became impassable

for about two miles on each side of Burauen. This section of the

road was completely rebuilt by dumping approximately three feet of

gravel over it. The remainder of the road was kept open most of the

time by permitting only one-way traffic. The other roads were just as

bad. After heavy rains the road in the Army Service Command area was

frequently under at least two feet of water. The streets in Tacloban

disintegrated so rapidly that much engineer effort was required to

keep them open. Such maintenance was necessary to assure continued

operation of the many supply and administrative facilities located

in the city. [1031] The roads on the west coast were, if possible,

even worse. Upkeep of the roads in general required a "profligate

expenditure of engineer troops." It was found that a battalion could

accomplish no more in a month than a platoon could have carried out

in a week under good weather conditions. The roads required a rock or

gravel foundation one to three feet thick, whereas a road-metal surface

of three to four inches on an earth base was normally adequate. Since

priority was given to work on the principal roads and airfields, the

construction of access roads, as well as hardstands for hospitals,

depots, and other needed installations was greatly delayed. In this

connection General Krueger stated: "This, in turn, greatly affected the

supply situation, including construction materials, by lack of access

to the depots, lack of storage space into which to discharge ships,

and lack of facilities and spare parts to permit repair and servicing

of engineer heavy equipment as well as other critical transportation

and combat vehicles." [1032]

On 21 December General Krueger estimated that after the elimination

of certain projects on which informal agreements had been reached,

the extent of completion by 5 January of the other projects would be

as follows: main supply roads, 50 percent; access roads, 20 percent;

Air Forces installations (exclusive of air depot and assembly plants),

44 percent; hospitals, 40 percent; base supply and services, 25

percent; oil and aviation gasoline storage (exclusive of naval oil

storage which had not been started), 50 percent; Navy installations, 20

percent; and headquarters construction, 40 percent. [1033] The gloomy

prognostications of Sixth Army engineers had proven all too true.

Supplies

Inland Movement of Supplies

As the roads on Leyte became more and more unserviceable, greater

reliance was placed on the use of naval vessels to transport supplies

and personnel to various parts of the island. The Transportation

Section, Sixth Army, maintained a small-boat pool that was used

extensively to transport light cargo and personnel between Tacloban,

San Ricardo, Palo, Tanauan, Tolosa, Dulag, and Catmon Hill. [1034]

LCM's were widely employed on the northern and eastern coasts of the

island and LSM's operated on the west coast. [1035] (Table 2)

Table 2--Shipping Tonnage Discharged in Leyte-Samar Area, 28 October-25

December 1944

------------------------------------------------------------------

| Tonnage |Average Daily| Lighterage on Hand

Period | Discharge|Rate of |--------------------------

| |Discharge |LCT's|LCM's|DUKW's| Barges

--------------+----------+-------------+-----+-----+------+-------

Total | 571,350 | | | | |

|----------+-------------+-----+-----+------+-------

28 Oct-3 Nov | 33,901 | 4,843 | 11 | 54 | 107 | 18

4 Nov-10 Nov | 32,421 | 4,632 | 35 | 63 | 315 | 33

11 Nov-17 Nov | 141,238 | 20,177 | 26 | 69 | 219 | 33

18 Nov-24 Nov | 110,494 | 15,785 | 18 | 59 | 253 | 39

25 Nov-1 Dec | 47,744 | 6,821 | 28 | 71 | 289 | 38

2 Dec-8 Dec | 56,786 | 8,112 | 24 | 53 | 297 | 43

9 Dec-15 Dec | 53,387 | 7,627 | 21 | 53 | 294 | 42

16 Dec-22 Dec | 68,677 | 9,811 | 39 | 68 | 300 | 49

23 Dec-25 Dec | 26,702 | 8,900 | 39 | 69 | 287 | 49

------------------------------------------------------------------

Source: G-4 Report, Sixth Army Operations Report Leyte, p. 218.

The troops that were fighting in the mountains were frequently supplied

by airdrops by the 11th Air Cargo Resupply Squadron from supplies that

were available in the Leyte area. From about the middle of November

until the latter part of December, 1,167,818 pounds of supplies

were either dropped or delivered by air. (Table 3) Two hundred and

eighty-two plane loads of supplies were dropped, a total of 2,776

parachutes being used. Because of the nature of the terrain and the

proximity of the Japanese, the proportion of airdropped supplies

that could be recovered varied from 65 to 90 percent. Approximately

60 percent of the parachutes were recovered and returned to the 11th

Air Cargo Resupply Squadron. [1036]

Supplying the West Coast

The landing of the 77th Division on the west coast of Leyte brought

into sharper focus the difficult job of giving adequate logistical

support to the tactical units. The Sixth Army supply lines were

tenuous. There was a shortage of shipping, and furnishing supplies

to the troops fighting in the mountains was especially difficult.

In planning for the amphibious movement of the 77th Division,

the resupply shipping set up for the division was as follows: on 9

December, two days after the division's landing at Deposito, 12 LSM's

and 4 LCI's would bring in supplies; on 11 December, 12 LSM's and 5

LCI's would bring in additional supplies; and on 13 December 12 LSM's

and 4 LCI's would carry further supplies to the division. Thereafter, 3

LSM's would be assigned the task of supplying the 77th Division. [1037]

Table 3--Airdrops by 11th Air Cargo Resupply Squadron, 11 November-25

December 1944

--------------+--------------------------+-----------+-----------

Branch | Supplies |Weight in | Percent

| | Pounds | of Total

--------------+--------------------------+-----------+-----------

Total | | 1,167,818 | 100.0

| +-----------+-----------

Quartermaster | Rations | 445,916 | 38.3

| Miscellaneous | 357,061 | 30.4

Ordnance | Ammunition | 337,761 | 28.9

Medical | Supply and Equipment | 21,308 | 1.8

Signal | Supply and Equipment | 4,546 | 0.4

Chemical | Chemical Warfare Supplies| 1,226 | 0.2

--------------+--------------------------+-----------+-----------

Units Supplied | Weight | Percent

| | of Total

-----------------------------------------+-----------+-----------

Total | 1,167,818 | 100.0

+-----------+-----------

11th Airborne Division | 388,570 | 33.3

1st Cavalry Division | 301,058 | 25.8

32d Infantry Division | 167,859 | 14.3

24th Infantry Division | 126,004 | 10.7

Guerrillas | 91,054 | 8.7

96th Infantry Division | 52,973 | 4.2

77th Infantry Division | 14,800 | 1.1

112th Cavalry Regiment | 10,300 | 0.8

7th Infantry Division | 4,200 | 0.3

Others | 11,000 | 0.8

-----------------------------------------+-----------+-----------

Source: Report of Transportation Officer, Sixth Army Operations Report

Leyte, p. 271.

The Japanese had sunk two LSM's near Baybay on 4 December and damaged

several other vessels during the Deposito landing. [1038] Because

of the extreme shortage of shipping that resulted, General Hodge

suggested to General Bruce on 8 December that thirty trucks, which

had been scheduled for delivery on the first two convoys of resupply

shipping, be sent overland along the Abuyog-Baybay mountain road and

used to shuttle supplies of the division between the two towns. These

supplies could be sent forward to the 77th Division when its beachhead

merged with that of the 7th Division. [1039] On the following day

the first resupply for the 77th division left Abuyog in a convoy of

trucks which went over the mountains to Baybay, where LCM's took the

cargo and moved it to the area of the 77th Division. [1040]

At 2100 on 10 December, General Hodge notified General Bruce that

the second echelon of resupply was to arrive at 2359 on the following

day at any beach that General Bruce desired. The supplies consisted

of 40,000 rations, 1,000 gallons of 80-octane gasoline, 500 gallons

of diesel oil, 100 tons of ammunition, and 10 tons of medical

supplies. Certain tactical and service units were also to be sent

forward. The third echelon, which was scheduled to arrive on the west

coast on the night of 14-15 December, was to consist of the remaining

units of the 77th Division and "considerable resupply." [1041]

As the tide of battle swept the 77th Division farther northward, its

line of supply and that of the 7th Division became very thin. About 15

December the supply officer of the XXIV Corps summarized the situation

to the corps chief of staff. Between 19 and 25 December three resupply

echelons, consisting of twenty-four LSM's and five LCI's carrying 3,250

tons of supplies, were to arrive on the west coast. He believed this

amount was insufficient. According to his calculations, the daily

requirements for two divisions in heavy fighting were 500 tons of

supplies. He estimated that the supplies of the 77th Division could

not last beyond 18 December. By 19 December the division would be in

short supply unless 100 truck loads of supplies could be sent over

the mountains before that time. The convoy that was to go forward

on the 19th would carry only two days' supplies and there would be

a three-day interval before the arrival of the next convoy. The XXIV

Corps, therefore, was faced with the problem of moving 200 truck loads

of supplies during those three days merely to keep even. After 25

December, one and a half days' supply would be sent overwater every

three days. Since the supply officer of the XXIV Corps had strong

doubts that the road would stand "a movement involving 300 trucks

every three days" it was believed that the supply situation would

steadily worsen. [1042]

On 15 December General Krueger sent a radio message to Admiral Kinkaid

reviewing the critical supply situation and requesting that sufficient

amphibious shipping be made available immediately to carry supplies

to the forces on the west coast. Admiral Kinkaid acquiesced, and

on 22 December a resupply convoy arrived at Ormoc with "sufficient

supplies and equipment to alleviate the critical situation." [1043]

By 26 December a general level of five to ten days' supply of all

classes had been built up, a level that was maintained throughout

the rest of the operation. The XXIV Corps utilized to the maximum

the available space on the LSM convoys, and units on the west coast

employed all available motor transportation to supplement the tonnage

on the convoys. Finally, the supplies were pooled in dumps at Ipil

and Ormoc and then allotted to the units.

On 25 December General Hodge received a Christmas message from his

supply officer: "Best wishes for Merry Xmas and a New Year filled

with supplies, resupplies, more supplies and no supply worries." [1044]

The serious logistical situation was to affect definitely the progress

of the Sixth Army as it fought its way into Ormoc Valley--the last

important enemy stronghold on the island.