THE DAM

In building such a dam as this the difficulties to be contended against

were unusually great. It was required to make it as near perfectly tight

as possible and be, of course, always submerged. Allowing for water used

by canal and slide and the leakage there should be a depth on the crest

of the dam in low water of 2.50 feet and in high of about 10 feet.

These depths turned out ultimately to be correct. The river reaches

its highest about the middle of May, and its lowest in September. It

generally begins to rise again in November. Nothing could be done except

during the short low water season, and some years nothing at all. Even

at the most favorable time the amount of water to be controlled was

large. Then the depth at the site varied in depth from 2 to 14 feet, and

at one place was as much as 23 feet. The current was at the rate of from

10 to 12 miles an hour. Therefore, failures, losses, etc., could not be

avoided, and a great deal had to be learned as the work progressed. I

am not aware that a dam of the kind was ever built, or attempted to be

built across a river having such a large flow as the Ottawa.

The method of construction was as follows. Temporary structures of

various kinds suited to position, time, etc., were first placed

immediately above the site of the dam to break the current. This was

done in sections and the permanent dam proceeded with under that

protection.

In shallow water timber sills 36 feet long and 12 inches by 12 inches

were bolted to the lock up and down stream, having their tops a uniform

height, namely, 9.30 feet below the top of dam when finished. These

sills were, where the rock was high enough, scribed immediately to it,

but if not, they were 'made up' by other timbers scribed to the rock, as

shown by Figs 4 and 5. They were generally placed in pairs about 6 feet

apart, and each alternate space left open for the passage of water, to

be closed by gates as hereafter described. Each sill was fastened by

five 1½ in. bolts driven into pine plugs forced into holes drilled

from 18 inches to 24 inches into the rock. The temporary rock was then

removed as far as possible, to allow a free flow of the water.

In the channels of which there are three, having an aggregate width of

about 650 feet, cribs 46 feet wide up and down stream were sunk. In the

deepest water, where the rock was uneven, they covered the whole bottom

up to about five feet of the level of the silts, and on top of that

isolated cribs, 46 in. X 6 in. and of the necessary height were placed

seven feet apart, as shown at C Figs 2 and 3. At other places similar

narrow cribs were placed on the rock, as shown at D, Figs 2 and 3. The

tops of all were brought to about the same level as the before mentioned

sills. The rock bottom was cleaned by divers of all bowlders, gravel,

etc. The cribs were built in the usual manner, of 12 in. X 12 in. timber

generally hemlock, and carefully fitted to the rock on which they stand.

They were fastened to the rock by 1½ in. bolts, five on each side of a

crib, driven into pine plugs as mentioned for the sills. The drilling

was done by long runners from their tops. The upstream side of the cribs

were sheeted with 4 in. tamarack plank.

On top of these sills and cribs there was then placed all across river a

platform from 36 to 46 feet wide made up of sawed pine timber 12 in.

X 12 in., each piece being securely bolted to its neighbor and to the

sills and cribs below. It was also at intervals bolted through to the

rock.

On top of the "platform" there was next built a flat dam of the

sectional form shown by Fig 1. It was built of 12 in. X 12 in. sawed

pine timbers securely bolted at the crossings and to the platform, and

sheeted all over with tamarack 10 in. thick and the crest covered with

½ in. boiler plate 3 ft. wide. The whole structure was carefully filled

with stone--field stone, or "hard head" generally being used for the

purpose.

At this stage of the works, namely, in the fall of 1881 the structure

presented somewhat the appearance of a bridge with short spans. The

whole river--fortunately low--flowed through the sluices of which there

were 113 and also through a bulkhead which had been left alongside

of the slide with a water width of 60 ft. These openings had a total

sectional area of 4,400 sq. ft., and barely allowed the river to pass,

although, of course, somewhat assisted by leakage.

[Illustration: Fig. 1. CROSS SECTION IN DEEP WATER.]

It now only remained, to complete the dam, to close the openings. This

was done in a manner that can be readily understood by reference to

the cuts. Gates had been constructed with timber 10 in. thick, bolted

together. They were hung on strong wooden hinges and, before being

closed, laid back on the face of dam as shown at B, Figs. 1, 2, and 3.

They were all closed in a short time on the afternoon of 9th November,

1881. To do this it was simply necessary to turn them over, when the

strong current through the sluices carried them into their places, as

shown at A, Figs. 2 and 3 and by the dotted lines on Fig. 1. The closing

was a delicate as well as dangerous operation, but was as successfully

done as could be expected. No accident happened further than the

displacement of two or three of the gates. The openings thus left

were afterward filled up with timber and brushwood. The large opening

alongside of the slide was filled up by a crib built above and floated

into place.

The design contemplates the filling up with stone and gravel on

up-stream side of dam about the triangular space that would be formed by

the production of the line of face of flat dam till it struck the rock.

Part of that was done from the ice last winter; the balance is being put

in this winter.

Observations last summer showed that the calculations as to the raising

of the surface of the river were correct. When the depth on the crest

was 2.50 feet, the water at the foot of the Longue Sault was found to be

25 in. higher than if no dam existed. The intention was to raise it 24

in.

The timber slide was formed by binding parallel piers about 600 feet

long up and down stream, as shown on the map, and 28 ft. apart, with a

timber bottom, the top of which at upper end is 3 ft. below the crest

of dam. It has the necessary stop logs, with machinery to move them, to

control the water. The approach is formed by detached piers, connected

by guide booms, extending about half a mile up stream. See map.

Alongside of the south side of the slide a large bulkhead was built, 69

ft. wide, with a clear waterway of 60 ft. It was furnished with stop

logs and machinery to handle them. When not further required, it was

filled up by a crib as before mentioned.

The following table shows the materials used in the dam and slide, and

the cost:

______________________________________________________________________

| | | Stone | Exca- | |

| Timber, | Iron, | filling, | vation, | Cost. |

| cu. ft. | lb. | cu. yds. | cu. yds.| |

+---------+---------+----------+---------+----------+

Temporary works | 134,500 | 92,000 | 11,400 | | $79,000 |

| | | | | |

Permanent dam | 265,000 | 439,600 | 24,000 | 6,500 | 151,000 |

| | | | | |

Slide, including | 296,500 | 156,400 | 32,800 | | 102,000 |

apparatus | | | | | |

+---------+---------+----------+---------+----------+

| | | | | |

Total | 696,000 | 687,000 | 68,200 | 6,500 | $332,000 |

-----------------+---------+---------+----------+---------+----------+

The above does not include cost of surveys, engineering, or

superintendence, which amounted to about ten per cent, of the above sum.

[Illustration: DETAILS OF THE OTTAWA RIVER DAM, AT CARILLON.]

The construction of the dam and slide was ably superintended by Horace

Merrill, Esq., late superintendent of the "Ottawa River Improvements,"

who has built nearly all the slides and other works on the Ottawa to

facilitate the passage of its immense timber productions.

The contractors were the well known firm of F.B. McNamee & Co., of

Montreal, and the successful completion of the work was in a large

degree due to the energy displayed by the working member of that

firm--Mr. A.G. Nish, formerly engineer of the Montreal harbor.