By ANDREW BELL Resident Engineer

The natural navigation of the Ottawa River from the head of the Island

of Montreal to Ottawa City--a distance of nearly a hundred miles--is

interrupted between the villages of Carillon and Grenville which are

thirteen miles apart by three rapids, known as the Carillon, Chûte à

Blondeau, and Longue Sault Rapids, which are in that order from east to

west. The Carillon Rapid is two miles long and has, or had, a fall of 10

feet the Chûte à Blondeau a quarter of a mile with a fall of 4 feet and

the Longue Sault six miles and a fall of 46 feet. Between the Carillon

and Chûte à Blondeau there is or was a slack water reach of three and a

half miles, and between the latter and the foot of the Longue Sault a

similar reach of one and a quarter miles.

Small canals limited in capacity to the smaller locks on them which were

only 109 feet long 19 feet wide, and 5 to 6 feet of water on the sills,

were built by the Imperial Government as a military work around each of

the rapids. They were begun in 1819 and completed about 1832. They were

transferred to the Canadian Government in 1856. They are built on the

north shore of the river, and each canal is about the length of the

rapid it surmounts.

[Illustration: THE GREAT DAM ACROSS THE OTTAWA RIVER, AT CARILLON.]

The Grenville Canal (around the Longue Sault) with seven locks, and the

Chûte à Blondeau with one lock, are fed directly from Ottawa. But with

the Carillon that method was not followed as the nature of the banks

there would have in doing so, entailed an immense amount of rock

excavation--a serious matter in those days. The difficulty was overcome

by locking up at the upper or western end 13 feet and down 23 at lower

end, supplying the summit by a 'feeder from a small stream called the

North River, which empties into the Ottawa three or four miles below

Carillon, but is close to the main river opposite the canal.

In 1870-71 the Government of Canada determined to enlarge these canals

to admit of the passage of boats requiring locks 200 feet long, 45 feet

wide, and not less than 9 feet of water on the sills at the lowest

water. In the case of the Grenville Canal this was and is being done by

widening and deepening the old channel and building new locks along

side of the old ones. But to do that with the Carillon was found to be

inexpedient. The rapidly increasing traffic required more water than the

North River could supply in any case, and the clearing up of the country

to the north had materially reduced its waters in summer and fall, when

most needed. To deepen the old canal so as to enable it to take its

supply from the Ottawa would have caused the excavation of at least

1,250,000 cubic yards of rock, besides necessitating the enlargement of

the Chûte à Blondeau also.

It was therefore decided to adopt a modification of the plan proposed

by Mr. T.C. Clarke, of the present firm of Clarke Reeves & Co, several

years before when he made the preliminary surveys for the then proposed

"Ottawa Ship Canal," namely to build a dam across the river in the

Carillon Rapid but of a sufficient height to drown out the Chûte à

Blondeau, and also to give the required depth of water there.

During the summer and fall of 1872 the writer made the necessary surveys

of the river with that end in view. By gauging the river carefully in

high and low water, and making use of the records which had been kept by

the lock masters for twenty years back, it was found that the flow of

the river was in extreme low water 26,000 cubic feet per second, and

in highest water 190,000 cubic feet per second, in average years about

30,000 and 150,000 cubic feet respectively. The average flow in each

year would be nearly a mean between those quantities, namely, about

90,000 cubic feet per second. It was decided to locate the dam where it

is now built, namely, about the center of Carillon Rapid, and a mile

above the village of that name and to make it of a height sufficient to

raise the reach between the head of Carillon and Chûte à Blondeau about

six feet, and that above the latter two feet in ordinary water. At the

site chosen the river is 1,800 feet wide, the bed is solid limestone,

and more level or flat than is generally found in such places--the banks

high enough and also composed of limestone. It was also determined to

build a slide for the passage of timber near the south shore (see map),

and to locate the new canal on the north side.

Contracts for the whole works were given out in the spring of 1873, but

as the water remained high all the summer of that year very little could

be done in it at the dam. In 1874 a large portion of the foundation,

especially in the shallow water, was put in. 1875 and 1876 proved

unfavorable and not much could be done, when the works were stopped.

They were resumed in 1879, and the dam as also the slide successfully

completed, with the exception of graveling of the dam in the fall of

1881. The water was lower that summer than it had been for thirty five

years before. The canal was completed and opened for navigation the

following spring.

Scientific American Supplement, No. 384, May 12, 1883 · 第 11 / 40 题