CHAPTER VI

Interior Finish

=58. Lathing; Grounds.=--Lathing is usually considered a part

of the plasterer's work but the carpenter is expected to prepare the

grounds and place the necessary furrings. The success of the plasterer

depends in no small degree upon the way the carpenter does this work.

If corners are not firmly constructed, cracks will be sure to appear in

the plastering.

In lathing, joints must be broken upon different studding every dozen

lath, and joints are not to be allowed about a door or window opening

where their presence would weaken the wall; such as short lath nailed

at one end only. Neither are lath to be placed at right angles to the

usual run of lath on the wall because uneven shrinkage would cause the

plaster to crack.

That the plasterer may make walls true and of uniform thickness about

door and window openings and along the floor, grounds are placed as in

Fig. 118. Such grounds are of stock if 13/16" × 1" or 2" nailed firmly

to the studding. Grounds for base should be placed so that the wall may

be lathed and plastered entirely to the floor that cold and vermin may

be kept out.

[Illustration: Fig. 118. Plaster Grounds]

[Illustration: Fig. 119. Detail of Partition Wall]

For grounds on external corners in a room, metallic corners especially

manufactured for this purpose are recommended.

The beginner will be surprised at the numberless places requiring

attention in preparing for the plasterer. He should visualize every

corner and angle as he thinks the plasterer or lather must have it.

=59. Interior Walls.=--Fig. 119 illustrates the construction of

a corner of an interior wall which is to be recommended highly for

strength. All door studding are to be doubled for strength, also window

openings of unusual size.

Interior door jambs are not usually placed until after plastering has

been done. Thresholds are no longer used with interior openings where

both rooms are to be heated.

Joists doubled to support partitions should be spread sufficiently to

allow furnace pipes to enter, and still provide bearing for partition

studs.

Badly crooked studs in a partition wall may be straightened by sawing

a kerf on the hollow side, almost thru, and wedging with a shingle

point. A cleat nailed to the side of the stud after wedging will give

the original strength. Straight studs should be selected for use about

openings.

In setting studs for interior door jambs where studs are to be doubled

on the inside, add to the width of door enough to make the outer edges

of the casings center on studs, and double inside these, as in figuring

openings between studs for outside door jambs. Make allowance for the

extra thickness of stud on each side. For height of opening, where no

threshold is to be used, add 2½" to the height of the door. Remember

that enough more must be cut from vertical studs to allow for thickness

of header.

=60. Stair Building; Porch Steps.=--Stair building is an art

in itself and as such belongs to millwork rather than to carpentry.

However, the carpenter must know the principles of simple stair lay-out

and construction for he is called upon to construct porch steps,

basement and often attic stairs. In smaller communities he may also

have to build the main stair. Fig. 120 illustrates three common types

of stair.

In planning a stair, the first requisite is to know its rise and run,

Fig. 121. The rise in this case is the vertical distance measured from

the top of the first floor to the top of the second floor. The run is

the horizontal span of the stair.

[Illustration: Fig. 120-a-b Types of Stairs Fig. 120-c]

[Illustration: Fig. 121. Rise and Run of Stair]

A good average stair for a cottage will have a rise per step of 7

inches and a run of tread of 10 inches. Variations will have to be made

in both rise and tread to meet conditions, but the student may take

these dimensions as starting dimensions unless otherwise directed.

Steps should not be either too steep, due to excessive rise per foot,

or "slow" due to extreme width of step. An old rule for determining the

relation of rise to tread is: "Twice the rise plus the tread should

equal 24"."

Proceed as follows: (1) Lay off on a story pole the total rise of the

stair by placing the pole upright in the well hole. (2) Set a pair of

dividers to 1" and step off this distance so marked. If there is a

remainder, increase or diminish the divider's space and again step off

the space. Continue this until a setting is obtained which gives no

remainder. The number of risers will be found by counting the spaces,

and the rise per step by measuring one of these spaces. (3) If the run

of the stair is not of exact specification (some variation is usually

possible) the run per step or tread may be determined by the rule just

given. If a definite total run is specified the tread must be figured.

(4) Since there is always one more riser than tread, the run per step

is obtained by dividing the total run in inches by the number of risers

less one. The numbers thus obtained for rise and run per step are the

ones to be used on the framing square in laying out the stringers.

[Illustration: Fig. 122. Laying out String]

[Illustration: Fig. 123. Pitch Board.]

[Illustration: Fig. 124. Economical Center Stringer]

(5) Joint one edge of each stringer straight and square and place the

framing square as in Fig. 122 and scribe along both blade and tongue.

(6) Scribe the line _A_ parallel to the 9" run, at a distance from

it equal to the rise diminished by the thickness of the proposed tread.

(7) Continue to lay the square as in (5) until the required number of

steps have been laid out. A pitch board might have been constructed and

made use of instead of the framing square in laying out the stringers.

This is nothing more than a piece of stock which serves as a template

by which to lay out the rise and run of each step, Fig. 123. A cleat

or fence nailed to one edge after the three edges have been planed to

dimensions permits easy and accurate placing of the same.

(8) There remains the sawing out. On open stringers this is done

by sawing square across the board or plank. Where the exposed ends

of risers would make a bad appearance, the cuts in the stringers

for risers are made mitering and the ends of the risers are mitered

correspondingly. In either case the end of the riser will be flush with

the exposed side of the stringer or string.

Fig. 124 illustrates an economical way of constructing a center

stringer, a 2" × 4" having nailed to its top edge the waste cut from

the side or wall stringers.

[Illustration: Fig. 125. Stringer for Attic Stair]

=61. Risers and Treads.=--Upon the common stair, such as attic and

porch, etc., treads and risers are placed as in Fig. 120, being nailed

to place, risers first and then treads.

On porch steps and open stringers, the treads should overhang at their

ends an amount equal to that given the front. The cove, if one be used,

should be carried around and "returned" under the end of the tread.

On enclosed or semi-enclosed stringers, a combination of stringer

and wall board is commonly used. Fig. 125 illustrates a type of

construction often used upon attic stairs. In this the side stringers

are framed of 1" stock and then nailed to the wall board of similar

thickness. Such construction is not suited for first floor stair work

where the effects of shrinkage would show to greater disadvantage.

[Illustration: Fig. 126. Main Stair Detail]

Fig. 126 illustrates the manner of framing a modern stair suitable

for a first floor where the best type of construction is demanded. As

a rule, such stair work will be done at a mill and the stair brought

to the building knock-down. The carpenter will have framed the rough

stringers which are to support the ceiling below the stair, and placed

them so that they may be used as a temporary stair for the workmen. If

the stairway is an open one or semi-open, the plastering under these

stringers will have been placed, the stair being put together on the

floor and then raised to its place. If the well-hole is such that the

stair must be assembled while the strings or wall boards are in place,

the lath and plaster must be left off the rough stringers until after

the stair has been assembled and the wedges glued and driven in place

as shown in the illustration. Rough stringers must be placed far enough

from the sides of the well-hole so that the wall board may settle in

place and that the wedges may be easily placed, usually about 4" or 5"

from the wall will be sufficient.

=62. Porches.=--Fig. 127 illustrates the manner of framing the

floor of a porch. Such framework should be given a pitch downward away

from the house of about 1" in 10' that the water may be drained.

[Illustration: Fig. 127. Detail of Porch Framing]

Fig. 128 illustrates the manner of placing water table and flooring,

etc. Water table is first placed, the corners being mitered and the

whole furred out from the frame about a quarter of an inch to allow any

dampness to escape. Porch floors should have their joints painted with

lead just before being laid.

[Illustration: Fig. 128. Detail of Porch Finish]

Posts and balusters are usually placed after the porch roof has been

placed, the upper frame being temporarily supported by studs.

In Fig. 127 is also shown the manner of framing the bearing joists,

ceiling joists and rafters for a hip roof. The various cuts are

obtained in the same manner as are similar cuts on the main roof. Porch

roofs are seldom given as much pitch as the main roof. They do not need

as much and must, usually, be kept below the window sill line of the

second story.

Fig. 128 also illustrates a common type of trim for porch cornice.

Where supporting plates are long, a flitch plate girder is formed of

them by the insertion between them of a stiff plate of structural steel

of suitable length and width.

=63. Interior Finish.=--A part of the carpenter's duty is the

placing of all interior finish, such as base boards, door jambs, etc.

Formerly the carpenter made, or "got out" his trim by hand but today he

finds it much pleasanter and cheaper to buy the machine-made product of

the mill. Even door and window frames are usually purchased from the

mill, either assembled or knock-down.

=64. Setting Door Jambs.=--If the studs about interior door

openings have been carefully selected for straightness and properly set

or plumbed, the setting of the door jamb should be an easy matter, If

this work has not been properly done, considerable ingenuity will be

required oftentimes to get the frame set so that its edges are out of

wind and the frame plumb. If a jamb should not be set plumb and out of

wind, the operation of making a door fit its stops properly is a most

trying one and the result usually unsatisfactory. Too much emphasis

cannot be placed upon the necessity for proper placing of studs and

jambs. (1) Saw off the head lugs just enough to allow the frame to be

placed in the opening. (2) Cut a spacing stick of a length sufficient

to reach from the floor to the under surface of the head jamb when

that member is in its proper place. (3) Place the head jamb at one of

its ends upon this stick and tack the jamb to the stud lightly. (4)

Level the head jamb and lightly tack the second jamb, inserting wedging

blocks or shingle points between the jamb and stud. A spread stick cut

to hold the jambs apart properly at the base is desirable. (5) Lay a

piece of finish floor against the face of each jamb and scribe along

the top of this to indicate where the jambs must be cut off to fit the

finish floor when it is placed. It is taken for granted that the finish

floor is to be laid last. If a finish floor is not to be used, or if it

is to be placed before the wall trim, the head jamb will be leveled

but not located as to height, the dividers being used to scribe the

feet, being set so that the proper amount will be cut off to allow the

jamb to rest at the right height when cut to the scribed lines. (6)

Remove the jamb and saw to the scribed lines. (7) Replace the frame and

tack it at one side after plumbing it both on its face side and face

edge. See that the jamb is at the right height by inserting the blocks

of flooring used in scribing to length. (8) Tack the second side-jamb

close to the head. (9) Sight across the edges of these jambs and adjust

the loose jamb until the frame is out of wind. Plumb its face, blocking

the back. Shingles placed point to point provide easy blocking where

the space is not too large. A straight-edge placed against the face

of a jamb will indicate whether it has been sprung in the blocking or

wedging between jamb and stud.

[Illustration: Fig. 129. Setting Dividers at Meeting Rails]

[Illustration: Fig. 130. Scribing Bottom of Lower Sash]

=65. Fitting Window Sash.=--Sash are often fitted before the

house is plastered and before the sash are glazed. (1) Joint the top

and sides of the top sash, chamfering the arrises very slightly by a

stroke or two with the plane. (2) Cut and fit the meeting rails about

the parting stops remembering to leave a little "play," that successive

coats of paint on the stops may not cause binding, 1/16" on each side

is not too much. (3) Joint the edges of the lower sash. (4) Since the

bottom rail has not been beveled, only the lugs sawed off, the meeting

rails will appear with reference to one another as in Fig. 129. Set a

pair of dividers to a distance equal to that between the tops of the

meeting rails. This can be done by placing the dividers between the

meeting rails. (5) Scribe the bottom rail as indicated in Fig. 130.

If the sash has been glazed so that the outer face of the bottom rail

is not accessible from the inside, the scribing is to be done on the

inside of the bottom rail and a T-bevel set to the slope of the sill

and this used to transfer the angle to the edges of the sash. Before

scribing the bottom rail, see that the meeting rails are apart a

uniform distance across the sash. (6) Saw and then plane to the scribed

line.

Where sash weights are to be used, they are easiest placed before

lathing. The proper tying of a sash cord so that it shall not work

loose with time is a matter for careful instruction by the teacher. No

good carpenter will have his sash cords coming untied. The cord can be

cut the estimated length after the weight has been attached, and a knot

or loop tied in the free end so that the cord shall not slip thru the

pulley.

In case weights are not placed before the lath and plaster, it will

be necessary to make use of a "duck" to draw the end of the sash cord

up thru the removed pocket cover of the jamb. This "duck" is usually

a piece of lead beaten about one end of a piece of stout short cord.

This lead weight is lowered thru the pulley by means of a longer cord,

the end of the sash cord is then fastened to the longer cord, after

removing the duck, and then drawn up and thru the pulley.

To determine the length of sash cord, draw the sash weight to the top

of the jamb and, setting a sash upon the sill, mark and cut the cord

about four or five inches below the opening in the edge of the sash in

which the knotted end of the cord is to rest.

[Illustration: Fig. 131. Using Block to Locate Door Stop Position on

Jamb]

=66. Placing Door, Window, and other Trim.=--In Fig. 110-a is

shown one of the many styles of casing in common use. Base blocks and

casing stock are prepared at the mill and the carpenter has but to

cut these to the proper lengths and fit and attach them. (1) The base

block is first placed, tho some workmen prefer to fit the base first,

cutting it to a length such as will allow the proper placing of the

block after the base is nailed in position. Where the finish floor is

laid last, this block will be scribed at its bottom by means of a piece

of flooring, otherwise the dividers would be used. (2) After the blocks

are placed the casings are cut to length and nailed. (3) The head

member is next made up and placed. It is customary for all door and

window heads, where built up, to be constructed at one time. It should

be noted that door casings are not placed flush with the face of the

jamb. They should be kept back about 5/16". This is to allow the easy

placing of hinges and also for appearance' sake. In all casing work the

expedient of sawing under at the back should be supplemented by the use

of the block plane, where necessary, that tight joints may result.

Window stool stock, like that of casings, is prepared at a mill and

needs only to be cut to length and have the ends "returned" to match

the face edge. (1) Lower the sash, then fit the stool to this allowing

enough "play" that subsequent paint or varnish may not cause the stool

to bind the lower rail of the sash. (2) Place and nail the apron. (3)

Cut and place the side casings. Note that side casings are placed

flush with the face of the jambs. The crack so formed is concealed when

the stop bead is placed. (4) Place the head.

[Illustration: Fig. 132. Door Parts]

Base boards and base mould may now be placed. Blocks of a thickness of

the finish floor placed along the wall at frequent intervals will serve

to locate the position of the base above the rough floor, when the

finish floor is to be laid afterward. Internal corners of base mould

and picture mould, when of irregular face, should be coped. External

corners should have mitered joints. Shoe mould will be placed after the

finish floor is laid.

Stop beads may next be placed in the windows and in such doors as are

not rabbeted. Head stops are placed first and the side stops then coped

to these. A block of a width equal to the thickness of the door will

be an aid in placing stops easily, Fig. 131. Window stops should be so

placed that the lower sash may move freely as it is raised.

=67. Hanging Doors.=--In the fitting of large doors, such as in

dwellings, allowance must be made for subsequent coats of varnish or

paint, usually a scant 1/16" is allowed at top and each side of a door.

The bottom of a door is often not touched, except to saw away the lugs

of the stiles, until after the door is hung. The door is hinged, then

closed and the bottom scribed to the floor so as to allow the door to

swing over rugs or carpet freely. Where a threshold is to be used, the

door is scribed to fit the thickness of the proposed threshold. ⅛"

should be allowed at the bottom of the door for play. If a door has a

stile with a bow in its face, it should be turned so that the bow is

next the stop of the lock side.

[Illustration: Fig. 133. Measuring Opening]

=68. Fitting a Door.=--The names of the parts of a door and

their relative positions are indicated in Fig. 132. (1) Mark with a

try-square and saw off the lugs, the parts of the stiles which project

beyond the rails. (2) Plane an edge of the door until it fits the side

of the frame against which it is to be hung. If the frame is straight,

this edge may be planed straight. It is not wise to take for granted

the squareness or straightness of a frame. A test or series of tests

may first be made with square and straight-edge. A mechanic, however,

usually planes an edge until it fits the frame, testing by holding the

door against the frame as near to its position as its size will allow.

(3) Measure the width of the frame at its top and bottom, Fig. 133,

and transfer these dimensions to the top and bottom of the door, Fig.

134. When approaching the line, in planing, place the door against

the frame often enough to see where the allowances must be made for

irregularities in the frame. (4) Plane the top edge of the door until

it fits the frame properly when the first planed edge is in position.

(5) The length of the door will be determined by scribing it to the

floor after being hinged.

The edge of the door which is to swing free is usually planed slightly

lower at the back arris than at the front. An examination of the

movement of an ordinary house door will show the reason for this.

[Illustration: Fig. 134. Laying off Width]

=69. Hinging a Door.=--The hinges most commonly used in carpentry

are the kind known as butts. Where the door stands in a vertical

position, hinges in which the two parts are joined by a loose pin are

generally used. By removing the pins the door may be removed without

taking the screws out of the hinge. Such hinges are more easily applied

than those with the fixed pin. (1) Place the door in position; keep

it tight against the top and the hinge side of the frame. (2) Measure

from top and bottom of the door to locate the position for the top of

the higher hinge and the bottom of the lower hinge. Usually, the lower

hinge is placed somewhat farther from the bottom than the higher hinge

is from the top. (3) With the knife or chisel mark on both door and

frame at the points just located, Fig. 135. (4) Take out the door,

place the hinge as in Fig. 136, and mark along the ends with a knife.

In a similar manner mark the frame. Make certain that the openings on

door and on frame are laid off so as to correspond before proceeding

further, (5) Set the gage for the depth the hinge is to be sunk Fig.

137 and gage both door and frame. (6) Set another gage for width of

openings, Fig. 138, and gage both door and frame, keeping the head of

the gage against the front of the door. (7) Chisel out these gains on

door and frame, Fig. 139. (8) If loose-pin butts are used, separate the

parts and fasten them in place. Use a spiral drill to make openings

for the screws. To insure the hinges' pulling tight against the side

of the gain make the holes just a little nearer the back side of the

screw hole of the hinge Put the door in place and insert the pins. It

is a good mechanic who can make a door hang properly the first time it

is put up. It is better, therefore, to insert but one or two screws in

each part of a hinge until the door has been tried. (9) If the door

hangs away from the frame on the hinge side, take it off; take off

hinge on door or frame, or both if the crack is large; chisel the gain

deeper at its front. By chiseling at the front only and feathering

the cut toward the back, the gain needs to be cut but about one-half

as deep as if the whole hinge were sunk. If the door should fail to

shut because the hinge edge strikes the frame to soon, the screws of

the offending hinge must be loosened and a piece of heavy paper or

cardboard inserted along the entire edge of the gain. Fasten the screws

and cut off the surplus paper with a knife. If plain butt hinges are

used the operations are similar to those just described except that the

whole hinge must be fastened to the door and the door held in place

while fastening the hinges to the frame.

[Illustration: Fig. 135. Locating Hinge Position]

[Illustration: Fig. 136. Knifing Hinge Location]

=70. Fitting Locks.=--Two types of lock are in common use upon

dwelling doors, the rim and the mortise lock. The rim lock, Fig.

140, is used upon cheap construction and is attached to the outer

surface of the door. The mortise lock is used upon the better class

of work; the box is housed into a mortise and the selvage into a gain

cut into the edge of the door stile. Door locks are made so that the

bolts may be reversed to fit either right or left hand doors. This is

accomplished by removing a screw in the side of the box and carefully

lifting the bolt, replacing it in reversed position. A right hand door

is one which swings to the right when pushed open.

[Illustration: Fig. 137. Setting Gage for Depth of Gain]

[Illustration: Fig. 138. Setting gage for Width of Gain]

To attach a rim lock: (1) Place the lock against the side of the door

and mark thru the key hole and knob spindle hole with a sharp awl or

divider point. (2) Remove the lock and bore appropriate sized holes.

(3) Fasten the lock and place the escutcheons, knob spindle and knobs.

(4) Locate and attach the strike or latch plate.

[Illustration: Fig. 139. Gain Ready for Hinge]

To place a mortise lock, Fig. 141: (1) In a manner similar to that used

in placing the rim lock, locate the knob spindle and key holes. A more

accurate result is obtained if the knob spindle hole is located by four

points, one at each corner of the square, Fig. 142. In placing the

lock, keep the selvage back from the edge of the door a scant 1/16" so

that the selvage may be sunk below the edge of the door by that amount

when mortised in.

[Illustration: Fig. 140. Rim Lock]

[Illustration: Fig. 141. Mortise Lock]

This will permit the door to be trimmed without the removal of the

lock in case the door should swell after being fitted and locked. (2)

Bore the holes for knob spindle and key. (3) Locate a center line on

the edge of the stile and bore for the mortise which shall receive the

box of the lock. (4) Place the box and then mark about the protruding

selvage using a sharp knife, Fig. 143. (5) Remove the lock and "gain

in" the selvage, Fig. 144. (6) Fasten the lock by means of the screws

thru the selvage and attach the escutcheons, knob spindle and knobs.

(7) Close the door and mark the vertical position of the latch upon the

jamb. (8) Open the door and place the latch or strike plate, locating

its vertical position by means of the knife marks just made upon the

jamb, and its horizontal position by a measurement taken from the latch

to the face of the door; transfer to the jamb by rule or gage. (9)

Scribe about the plate and then gain it into the jamb. On a door with a

rabbeted jamb instead of an adjustable stop, the essential measurement

will be from the back arris of the stile to the front of the latch.

(10) Attach the plate, then chisel out the openings for latch and bolt.

Equally common is the practice of taking step (3) first, with steps (1)

and (2) taken after step (5).

=71. Laying and Scraping Floors.=--Quarter-sawed stock makes

the best wearing floor. However, oak wears well in either plain or

quarter-sawed forms. All hard wood finish floors are milled with

tongues and grooves on edges and ends. Holes for nailing are usually

drilled at the mill also.

[Illustration: Fig. 142. Locating Knob Spindle Hole]

In laying a finish floor, it is not advisable to lay it with its

lengths extending in the same direction as those of the rough floor.

The shrinkage of the wide boards of the under floor will open unseemly

cracks in the finish floor. Where it is necessary to run lengths for

both floors in the same direction the finish floor should be separated

from the rough floor by thin furring, such as lath, placed 16" apart.

Rough floors laid diagonally overcome this difficulty. Paper is usually

placed between the two floors. Care should be taken in starting a floor

to select straight boards. Where grooves fail to fit tongues of boards

that are laid, a piece of 2" × 4" about 3' or 4' long should be used

as a pounding block that the tongue of the board being laid may not

be battered, the most common cause of trouble in floor laying. Nails

are driven "toeing" thru the board just above the tongue that the heads

may be concealed and also to better draw the board in position. Hammer

marks showing upon the face of a floor indicate carelessness. It is

not necessary that nails should always strike joists, for a good rough

floor will hold such nails with sufficient firmness. Where nails must

be driven into hard maple, a hole must be drilled first. On the great

majority of hard woods the dipping of the point of the nail in soap or

oil will cause it to enter the wood with careful driving, without the

drilling of a hole.

[Illustration: Fig. 143. Locating Selvage Gain]

[Illustration: Fig. 144. Ready for the Lock]

After a hardwood floor has been laid it should be scraped. Scraping

floors is a tedious task at best. Electrically driven machines now

relieve the carpenter of much of this work, the floors being laid and

finished by a specialist in floor work. The shoe mould is placed

last, being nailed to the floor, so that any shrinkage of the joists

will cause the mould to drop with the floor. Base board and shoe mould

should be stained, but not varnished, before the mould is placed.

On account of waste in tonguing and grooving and straightening flooring

stock, an allowance of from ⅕ to ¼ extra is necessary in estimating.

[Illustration: Fig. 145. Detail of Door Frame]

=72. Door and Window Frames.=--Like other carpentry detail, window

and door frames may be constructed in any one of a number of styles.

Fig. 145 illustrates a satisfactory type of door frame for cottage use.

The sill will be given a pitch or fall of 1" in 12" and will have its

ends housed into the jambs. The jambs will be assembled first, being

nailed together. Next, the side casings are fitted at their lower ends,

cut to length and nailed. Frequently they are nailed and then cut to

length. The head casing with its cap is next placed.

Fig. 146 illustrates a common type of cottage window frame. The method

of procedure is not unlike that described for the door frame. The sill

will be grooved on its under side to receive the top edge of the siding

board and given a fall of 1" in 10". Jambs must be grooved to receive

a parting stop as shown. Where weights are to be used each jamb must

have a pocket as detailed. The stock sawed out of the jamb may be made

use of for pocket cover stock by proper manipulation. Pulleys may be

placed before the jambs are assembled, at least the holes for them

should be prepared.

[Illustration: Fig. 146. Detail of Window Frame]

There are a number of "tricks of the trade" in frame making. Their

presentation must be left to the instructor, for the making of frames

belongs to millwork and space can be spared here for general directions

only.

=73. Woodwork in Masonry Structures.=--Wood framing in brick and

other masonry buildings is but slightly different from that wholly in

wood. Fig. 147 illustrates the manner of framing the ends of joists

which rest in solid masonry walls. The ends are shaped as indicated

so that, in case of fire, the floors in falling will not pull over

the walls, but will fall free. Anchors are used to tie the building

together, and these are to be placed near the lower edge of the joists

so that they may split out of the joists easily or allow the floor to

drop free, in case of a falling of the floor and joists.

A popular type of construction is that known as brick veneer, Fig. 148.

It consists of an ordinary framed house with a covering of brick as

shown. These bricks are fastened to the wall by metallic bonds. From

the outside, the building has all of the appearance of solid brick,

while it is claimed that a wall so formed is warmer than one of solid

brick.

[Illustration: Fig. 147-a Fig. 147-b

Joist Framed into Brick Wall]

[Illustration: Fig. 148. Brick Veneer]

Over openings in brick walls, lintels are required to support the arch,

Fig. 150.

Fig. 149 shows the manner of framing a window opening for a brick wall.

Fig. 151 illustrates the manner of attaching a plate to a brick wall.

[Illustration: Fig. 149. Window Detail for Brick Wall]

[Illustration: Fig. 150. Lintels]

[Illustration: Fig. 151. Attaching Plate to Brick Wall]