=74. Methods of Estimating.=--Building costs may be divided into

two main divisions, cost of material and cost of labor. There is but

one so-called safe way to figure or estimate the cost of any particular

piece of carpentry work. This consists in "taking off" the material

quantities in detail and to this adding the labor cost of placing the

same. This is the method in common use by contractors in making a final

estimate. Where a rough or working estimate is required, such as an

architect's estimate of the probable cost of a building planned by him,

two methods may be used. One consists in figuring the cubical contents

in feet and multiplying a predetermined, or unit price per cubic

foot for that type of house. Ordinarily, the main frame is figured,

counting from the basement floor to the top of the attic walls that

are, or may be finished--outside measurements. Porches and open spaces

are not figured. A second method consists in estimating the number of

squares (100 sq. ft.) of side wall, of partitions, of floors, etc.,

and multiplying a predetermined price per square for a similar type of

building. This latter method is more accurate than the cubic-foot unit

method.

=75. Table for Estimating by Cubic-Foot Unit.=--The following

table of unit prices will give a rough working estimate for various

types of building differentiated after the custom of insurance

adjusters. The prices are for 1915 and to be of any value must be

compared with known costs of similar structures in the community in

which they are to be used. Any evident variations in unit costs so

discovered should be noted and corrections made.

CUBIC-FOOT UNIT ESTIMATE

COUNTRY PROPERTY PER CUBIC FOOT

Frame dwelling, small box house, no cornice 5c

Frame dwelling, shingle roof, small cornice, no sash

weights, plain 6¼- 7½c

Brick dwelling, same class 8¼-10c

Frame dwelling, shingle roof, good cornice, sash weights,

blinds (good house) 8¼-10c

Brick dwelling, same class 11¼-12½c

Frame barn, shingle roof, not painted, plain finish 2¼- 3¼c

Frame barn, shingle roof, painted, good foundation 3 - 4¼c

Frame store, shingle roof, painted, plain finish 6¼- 8¼c

Brick store, shingle roof, painted, good cornice,

well finished 8¼-11¼c

Frame church or school house, ordinary 6¼- 8¼c

Brick church or school house, ordinary 10 -12½c

If slate or metal roof, add %c per cubic foot.

CITY PROPERTY

Frame dwelling, shingle roof, pine floors and finish, no

bath or furnace, plain finish (good house) ?½- 8¼c

Brick dwelling, same class 10 -11¼c

Frame dwelling, shingle roof, hardwood floors in hall and

parlor, bath, furnace, fair plumbing 10 -11¼c

Brick dwelling same class 10 -12½c

Frame dwelling, shingle roof, hardwood in first floor,

good plumbing, furnace, artistic design, some interior

ornamentation, well painted 12½-15c

Brick dwelling, good plumbing, bath, furnace, pine finish,

well painted 13¼-18c

=76. Grading Rules.=--There is no uniformity as to grades of

lumber. Fifteen or more associations have rules for inspection. and

classification of lumber and these rules vary with the association and

from year to year in the same association. The following rules taken

from a catalogue of a middle west lumber concern will be found helpful:

Yellow Pine Dimension, Studding, Joists and Timbers

_No. 1 Common._--The best grade and the one recommended for use on

first class jobs.

_No. 2 Common._--Dimension up to 20 feet long only can be obtained

in this grade. Timbers are not manufactured in No. 2. This stock will

show defects not found in No. 1 grade, and some pieces are not entirely

straight. It is a sound, serviceable grade, but not recommended for

first class work.

Yellow Pine Boards, Sheathing, Shiplap, and Fencing

_No. 1 Common._--This grade is not clear, but is strictly sound

and uniform in thickness and width. It is used on the best classes of

work, for barn boards, and wherever exposed to wear and weather.

_No. 2 Common._--This grade is sound but contains more sound knots

than No. 1 and is somewhat coarser. It is mostly used on first class

jobs for sub or rough floors, and for sheathing under siding. It can be

used for outside work, but is not recommended for this purpose except

upon cheap buildings. No. 8 Common. A fairly good lower grade which

will work up nicely but with some waste due to cutting out defects.

Runs uneven in quality. Makes a fair subfloor or sheathing.

Yellow Pine Flooring, Ceiling, Partition, and Drop Siding

_Clear Grade._--The best grade manufactured. Practically free from

defects and the grade used upon first class jobs. Is strong, sound, and

will lay without waste due to cutting out of imperfections. Should be

used when a natural finish is desired. No. 1 Common. This grade will

contain small, sound knots, sap stains, pitch or pitch pockets. It

is sound and durable, and a good grade for ordinary work or wherever

covered with paint.

_No. 2 Common._ Coarser than No. 1 grade; will lay up with little

waste. Is sound, and flooring of this grade is often used for sheathing

or sub flooring where a warm, tight job is desired. Can also be used on

cheap painted jobs.

Fir Boards, Timbers, Drop Siding, Ceiling and Flooring

_Select No. 1 Barn Boards._--This grade is especially selected and

is better than No. 1.

_No. 1 Timbers._--Good sound straight stock, to be used for sills

and posts subjected to moisture.

_Clear Ceiling._--Free from defects. Good for cornice work and

porch ceilings.

_Edge Grain Flooring, Clear Grade._--Especially suited to porch

floors as it wears well and resists effects of moisture.

_Clear Drop Siding._--Contains no sap, shakes or other defects.

Shingles, Lap Siding, Y. P. and Cypress Finish, White Pine

Boards

_5 to 2 Clears._--The heaviest grade five shingles laid one on top

of the other will measure 2" at the butts.

_6 to 2 Extra Star A Star._--A lighter grade, but clear and 16",

as are the 5 to 2" grade.

_Bevel or Lap Siding._--Carried in stock in red cedar, redwood,

cypress, and white pine. "Clear" is free from all defects.

_Cypress "C" Grade._--Has small sound knots and other slight

defects such as can be covered with paint. All siding is bundled 10

pieces to the bunch in random lengths. Not furnished in specified

lengths.

_Yellow Pine and Cypress Finish._--This stock in "clear" grade is

practically free from defects. The yellow pine is suitable for interior

finish. Cypress is suitable for inside finish or for cornice work on

first class jobs. "C" cypress finish contains some knots and other

slight defects. Is suitable for outside finish on ordinary jobs.

_White Pine Boards._ As a rule, carried in stock only in No. 1

grade. Nothing but sound, red-knotted boards should be included. No

shakes. Excellent for exposure to weather.

=77. Estimating Lumber Quantities.=--Lumber is measured in terms

of the board foot as a unit, 12" by 12" by 1" or its equivalent,

indicated by the abbreviation B. M. (board measure).

_Example:_

Determine the B. M. in a girder 6" by 8" by 16'.

_Solution:_

Rule--Thickness in inches times width in inches, divided by 12" times

the length in feet gives a number equal to the number of board feet.

(6" × 8") / 12 × 16' = 64' B.M.

Stock less than 1" thick is figured as 1" thick. In commercial practice

lumbermen make use of tables in determining quantities. Appendix III.

In estimating quantities, suitable allowance must be made for waste.

This waste is incurred (1) thru loss when boards or planks are cut to

required lengths. Standard lengths are 10', 12', 14', etc., and these

will not always cut to advantage. (2) Waste is incurred in machining

the stock, as dressing, edging, tonguing and grooving. Necessary

allowances will be indicated herein.

_Heavy Timbers._ Girders, posts, etc., are determined by count.

_Joists._ To determine the number of joists required for a room

or a building, count the actual number required beginning at a wall

(¾ times number of feet in length or width of room when set 16" on

centers), and to this add one joist to be placed against the second

wall.

Cataloged or listed sizes are for lumber fresh from the saw.

Shrinkage due to seasoning and surfacing one side and one edge so

that the stock may have uniform thickness and width will give actual

sizes as follows: 2" × 4" when sized on one side and one edge,

will give 1⅝" x 3⅝"; 2" × 6", _S_-1-_S_ and 1_E_,

1⅝" × 5⅝"; 2" × 8", _S_-1-_S_ and 1_E_ gives 1⅝" ×

7½"; 2" × 10", _S_-1-_S_ and 1_E_ gives 1⅝" x 9½";

2" x 12", _S_-1-_S_ and 1_E_ gives 1⅝ x 11½. When

_S_-2-_S_ and 2_E_ or sized on 4 sides, stock will

measure ⅛" less than indicated above.

_Studs for Walls and Partitions._--Count one for each lineal

foot of wall or partition, where specified 16" on centers. The extra

studs are to be used in doubling corners, at doors and windows, and in

gables. Barns and sheds will not require these extra studs.

_Bridging._--Allow 25 lineal feet of 2" by 4" for each square of

flooring.

_Rafters._--On a plain roof, count actual number and add one, as

in counting for joists.

_Sheathing._--Calculate the exact surface to be covered, deduct

openings; then, for unmatched sheathing or barn boards or fencing, as

it is also called, add 1/12 for 12" boards, 1/16 for 10" boards and ⅛

where 8" boards are used. Four inch and 6" are seldom laid solid, being

used mainly for roof sheathing for shingle roofs, and laid 2" apart.

These additions are due to the fact that thru seasoning and dressing,

a 12" board becomes 11½", a 10" becomes 9⅝", an 8" becomes 7¾", a 6"

becomes 5¾" and a 4" becomes 3¾". The additions specified allow for

waste in cutting.

_Shiplap._ Calculate the exact surface to be covered, deduct

openings; then add for floors 17%, for sidewalls 20%, for roofs 25%.

Sheathing laid with 2" spaces should have proportionate deductions

made, that is, on 1" × 6", figure as if laid solid, then deduct ¼; for

1" × 4" deduct ⅓. Sheathing when matched, such as is used sometimes

for sub-floors and side walls and roof sheathing under slate roofs

and better known as flooring, will be estimated by figuring the exact

surface to be covered, deducting the openings, then adding for 6"

stock, which is the kind most always used, 15% for floors, 17% for

sidewalls, and 20% for roofs.

If shiplap or matched sheathing is laid diagonally add 5% for waste due

to lack of ability to reverse cut.

_Siding._--For bevel siding, calculate the exact surface, deduct

openings; then add for 6" siding when laid 4½" to the weather, 33%; for

the 4" siding add 50%.

_Drop Siding._--Drop siding, ceiling and wainscoting are figured

just like matched flooring, which is described below.

_Flooring._--For square edge, calculate the exact surface to be

covered, add for 6" flooring 11% for waste in matching, etc.; for 4"

flooring add 20%. It is becoming common practice to specify flooring by

actual face measurement after being machined. The following figures are

for actual surface measurements.

For matched flooring, calculate the exact surface to be covered, then

add 20% for 5¼" flooring, for 3¼" flooring add 25%, for 2¼" add 33%,

for 1½ add 40%.

Flooring less than 1" thick, like all other lumber, is estimated as 1"

thick.

_Shingles._--A bunch of shingles contains the equivalent of 250

shingles of 4" average width. With an exposure of 4½" to the weather

a 4" average shingle will cover 18 square inches, making 800 shingles

to the square. Waste in doubling the first course and in laying will

necessitate an addition of 8% on a plain roof and 12% on hips or on

gabled walls. Cost estimates are based upon the M. or 1000.

SHINGLES PER SQUARE

Plain roof, 4 " exposure, 990; roof cut up, 1010

Plain roof, 4½" exposure, 880; roof cut up, 900

Plain roof, 5 " exposure, 790; roof cut up, 810

_Lath._ Lath for interior plaster work are usually ⅜" by 1⅜" by

4', put up in bundles of 50 each and are sold by the 1000. 1000 lath

will cover 70 yards of surface and will require 8 lbs. of 3d fine

lath nails. Lathing is usually considered a part of the plasterer's

contract. There is no uniformity of practice as to the deduction for

openings.

_Building Papers._ The cheapest is "rosin sized," and is not

waterproof. This is used mainly under floors and upon side walls under

bevel siding. It is sold by the pound in rolls each 36" wide containing

500 square feet.

Dry felt is used where better protection from cold is desired. In the

cheaper grades, the material is made of wood fiber and rosin. In the

better grades wool is used. Tar felt, used where moisture is to be

resisted, is dry felt saturated with tar. These materials are sold by

the pound: 12, 15, and 20 lbs. to the 100 square feet, in rolls of

various widths. A catalog should be consulted for weights and covering

capacity.

=78. Estimating Millwork Quantities.=--The number of doors and

windows will be determined by an actual count.

Mouldings, casings, baseboard when moulded, window stools, etc., are

sold by the 100 feet lineal measure, random lengths. Extra charge is

made for specified lengths where the quantities are determined by scale

measurements of the plan and elevations. Window frames of stock sizes,

door frames, inside jambs, stair parts, buffets, etc., will be found

priced in millmen's catalogs, and assist greatly in determining prices

for ordinary work. This text cannot give space to list such data, which

is so readily obtained from commercial catalogs.

=79. Example of Form for Bill of Materials.=--

BILL

=========================================================================

Ticket | | | | | | Price

or |No. of|No. of|Size |Length|Description|--------++----------------

Catalog| Feet |Pieces| | | | Rate || Extensions

Number | | | | | | ||

-------+------+------+-----+------+-----------+----+---++---+----++------

| 270 | 30 |2 × 4| 14 |Y. P., SIS | | || | ||

| | | | | and IE | 22 | || 5 | 94 ||

| | 2 | M | |5-2" red | | || | ||

| | | | | cedar | | || | ||

| | | | | shingles | 3 | 55|| 7 | 10 ||

| 300 | 1 × 6| | |# 2 Y. P.--| | || | ||

| | | | | flooring | 20 | || 6 | 00 || 19 40

-------+------+------+-----+------+-----------+----+---++---+----++------

=80. Estimating Labor Costs.=[A]--In estimating labor costs

the following data is to be made use of. The estimator will have to

determine the hours per day and the scale of wages per hour paid in his

locality, and make whatever changes in the data is necessary. He should

also compare the quantity of work done by men he may observe with that

given herewith. The time data herewith is based upon the work of one

mechanic who has mastered his trade fairly well. With an efficient

foreman and a selected group of workmen these time allowances can be

reduced in many instances as much as one-half. Experience alone will

determine the possibilities of such reductions with safety.

[Footnote A: For a more complete treatise of labor costs, the student

is referred to Gillette's Handbook of Cost Data, Section X, the source,

in the main, of the basis of this data.]

COST OF PLACING FRAME AND COVERING

By One Man

HRS. PER 1000 B.M. FT.

Sills and plates 6" × 8", no gains or mortises 20

Sills and plates 6" × 8", gains no mortises 40

Sills and plates 6" × 8", gains and mortises 60

Joists and box sills 20

Studding 2" × 4" 32

Studding 2" × 6" 23

Rafters 2" × 4", plain gable roof 40

Rafters 2" × 4", hip roof add 5% to 30% for each hip or valley.

Rafters 2" × 6", plain gable roof 27

Rafters 2" × 6", hip roof add 5% to 30% for each hip or valley.

Sheathing, square edged, horizontal, walls 16

Sheathing, square edged, diagonal, walls 19

Sheathing, 6" matched, walls 24

Sheathing, 6" matched, walls diagonal 32

Sheathing for floors, sub-floors, square edged 10

Sheathing for floors, sub-floors, square edged diagonal 12

Roof Sheathing, plain gable roof 13

Roof Sheathing, hip roof 20

COST OF PLACING FRAME AND COVERING (Continued)

HRS. PER 1000 LIN. FT.

Cornices 400 to 800

Water table, 3 member 220

Corner boards 73

Belt 195

HRS. PER M.

Shingling, plain roof, new work 3½

Shingling, hips and valleys, add 5% for each hip or valley.

Shingling, old work, add 20% for labor in removing old shingles.

Shingling side walls, plain 5½

Shingling side walls, fancy 8

HRS. PER 1000 B.M. FT.

Siding, bevel, 6" 35

Siding, bevel, 4" 42

Siding, shiplap 27

Siding, drop, when window and door casings and corner boards are

placed over siding 120

Siding, drop, when jointed between casings and corner boards 32

Surfaced barn boards 11½

Ceiling, store 53

Wainscoting, cut, put up, finished with cap and ¼ round, in a

dwelling 46

COST OF PLACING FLOORS

By One Man

HRS. PER 1000 B.M. FT.

Floors, pine 35

Floors, yellow pine, 3¼" face, laid on sheathing, including paper

between, smoothing rough joints, business block 40

Floors, yellow pine, 3¾" face, laid direct on joist, no smoothing 26⅔

Floors, yellow pine, 3¼" face, smoothed and sanded 45

Floors, maple, 2¼" face, laid not smoothed 40

Floors, maple, 2¼" face, laid and smoothed 80

Floors, maple, 1½" face, laid and well smoothed 107

Floors, oak, fine floor, glued, smoothed, scraped, sand papered 320

COST OF BRIDGING AND FURRING

HRS. PER 1000 LIN. FT.

Bridging 65

Placing plaster grounds 20

COST OF PLACING BASEBOARDS

b HRS. PER 100 LIN. FT.

Baseboard, three member, hardwood, average number miters 10

Baseboard, two member, scribed to floor 16

Baseboard, plain, ¼ round at floor 8

Moulding, bed, flat, 3" 2½

COST OF PLACING DOORS, WINDOWS, BLINDS

HRS. ON EACH

Window, to put together when K. D. (knock-down) 1½

Window, making frame 3

Window, setting frame ¾

Window, setting frame in brickwork 1

Window, fitting and hanging sash per pair 1

Window, hanging blinds per pair, before frames are set ¾

Window, hanging blinds per pair, after frames are set 2

Window, casing inside 2

Window, ordinary pine in frame building, including setting of frame 5

Window, same but hardwood 6½

Window, ordinary pine in brick building, including setting of frame 6½

Window, same but hardwood 9

Window, attic and cellar 1¾

Door, making frame 2½

Door, making frame with transom 3½

Door, common hardwood, set jambs, case, hang and finish, including

transom 10

Door, common 1⅜" pine complete 4½

Door, common 1¾" pine complete 5½

Door, casing opening one side ¾

Door, casing opening both sides 1½

Door, fitting, hanging and trimming 1½

Door, fitting, hanging and trimming outside door, pine 2½

Door, fitting, hanging and trimming outside door, oak 4

Sliding doors, pine, (framing not included) to finish complete

with lining, jambs, casing and hardware, per pair 32

Sliding doors, same, but hardwood 48

Sliding doors for barn 12' × 18' 24

Transom, fixed 1

Transom, hung 1½

ESTIMATING

COST OF STAIR WORK

HRS. ON EACH

Box stair, cellar or attic 25

One flight plain stair, 7-room house, hand rail, balusters 40

One flight fine stair, 9-room house, handrail, paneled 100

PORCHES IN GENERAL

Hours per lineal foot 5

Balustrade hours per 1000 lineal feet 500

Lattice for porches, hours per 1000 square feet 16 to 200

LATH

Lath, hours per 1000 7

MISCELLANEOUS LABOR ITEMS

Paneling, pine, hours per 100 sq. ft. 50

Paneling, hardwood, hours per 100 sq. ft. 83

Drawers, dovetailed, hours, each 2½

Drawers, 15" × 18", including racks and fittings 2

Shelves, in storeroom, dadoed into compartments 18" square, hours

per 100 sq. ft. 62½

Shelves, pantry, no dado, hours per 100 sq. ft. shelf 37½

Closet hooks on strip of wood, 12" apart, hours per 100 lineal feet 15

Sideboard, oak, 8' × 8', hours 100

=81. Estimating Quantities of Nails.=--The following table will

enable one to estimate the quantity of nails required for the various

kinds of common carpentry. The table of length and number of nails

to the pound, Appendix III, may be made use of in determining nail

estimates for other kinds of work not here specified.

QUANTITIES OF NAILS

MATERIALS POUNDS SIZE KIND

Joists and sills per 1000 B.M. ft. 25 20d common.

Studding per 1000 B.M. ft. 15 10d common.

Rafters per 1000 B.M. ft. 15 10d common.

Sheathing, drop

siding, shiplap per 1000 B.M. ft. 20 8d common.

Cornice per 1000 lin. ft. 18 8d common.

Shingling per 1000 4 4d common.

Bevel siding per 1000 B.M. ft. 18 6d common.

Ceiling, wainscoting per 1000 B.M. ft. 20 6d common.

Floors, pine per 1000 B.M. ft. 30 8d common.

Floors, hardwood per 1000 B.M. ft. 30 6d common.

Baseboard per 1000 B.M. ft. 12 8d finish.

Window trim, one side ¾ 8d finish.

Door trim, one side ¾ 8d finish.

Lath per 1000 8 3d common, fine.

Lattice for porches per 1000 sq. ft. 20 3d common.

Balustrade per 1000 lin. ft. 18 6d casing.

=82. Example of Form for Carpentry Costs.=--The following form,

used by a practical carpenter, and published in the Correspondence

Department of _The American Carpenter and Builder_, should suggest

means whereby the data just given may be made more readily available

for estimating purposes.

It must be remembered in interpreting all such data that costs will

vary greatly with conditions. A carpenter, for illustration, who gives

his time and attention to general carpentry cannot lay shingles with

the speed a specialist in shingling can. Again, a carpenter cannot make

window and door frames by hand with the same speed that these can be

made by machinery in a mill. The prices given herewith are for work

done by a general carpentry mechanic. The estimator should test out

these figures to see how they compare with actual working conditions in

his community. The following table is made for "country" conditions,

the men working at 30c per hour, 9 hours a day.

MATERIALS IN PLACE AT 30c PER HOUR

===========================================================================

| Ft. per | Hrs. per | Cost of Labor | Nails

Various Materials | 9-hrs. | 1000 +-------+---------+----+----

| 2 Men | ft. | M Ft.| L or Sq.|Lbs.|Size

------------------------+----------+-----------+-------+---------+----+----

Joists and sills | 900 | 20 | $6.00 | | 25 | 20d

Studding placed | 600 | 30 | 9.00 | | 15 | 10d

Rafters | 450 | 40 | 12.00 | | 15 | 10d

Sheathing vertical | 750 | 24 | 7.20 | | 20 | 8d

Sheathing, diagonal | 562 | 32 | 9.60 | | 20 | 8d

Bevel siding | 514 | 35 | 10.50 | | 18 | 6d

Cornices | 45 | 400 | | .12 -L | 18 | 8d

Shingling new roofs | 4000 | 4½ | 1.35 | | 4 | 4d

Lathing for plaster | 2572 | 7 | 2.10 | | 8 | 3d

Lattice for porches | 1125 | 16 | 4.80 | | 20 | 3d

Balustrade for porches | 36 | 500 | | .15 -L | 18 | 6d

Base boards 8" pine | 216 | 83 | 24.90 | .02½ -L | 12 | 8d

Baseboards, 8" hardwood | 108 | 166 | 49.80 | .05 -L | |

Floors laid, pine | 514 | 35 | 10.50 | | 30 | 8d

Floors laid, hardwood. | 100 | 180 | 54.00 | .05½ -L | 30 | 6d

Floors cleaned, hardwood| 100 | 180 | 54.00 | .05½ -L | |

Wainscoting, pine | 54 | | | .10 -L | 20 | 6d

Paneling, pine | 36 | | | .15 -Sq| |

Paneling, hardwood | 22 | | | .25 -Sq| |

Porches and verandas | | | |1.50 -L | 18 | 8d

------------------------+----------+-----------+-------+---------+----+----

M = 1000 Ft. L = Lineal Sq = Square Feet.

Shingles are for new roofs; where hips and valleys are required add 5%

additional for each one; where old shingles and nails must be removed,

add again (20% to total) for this work.

The above rate is based on figures of 30c per hour. For other rates the

following will apply in addition: At 35c per hour add 17%; at 40c add

34%; at 45c add 51%; and at 50c per hour add

_Example:_

(_A_) Take 1,000 feet of hardwood floor to be cleaned at 50c per

hour = $54.00 + $36.72 = $90.72

Looking again we find it would take 180 hours at 50c per hour = $90.00

(_B_) Take 1,000 feet of joists to be placed at 50c per hour =

$6.00 + 14.08 = $10.08.

Looking for the hours we find it would take 20 at 50c, or $10.00.

=83. Total Building Costs by Percentages.=--Having carefully

estimated the costs of one or two of the large items in a building,

such as lumber or millwork or labor, the total cost of a building may

be approximated with a fair degree of accuracy by a general contractor

by means of the following table of percentages. Foundations or any

other parts of a building which may be unusual should be excluded

and figured separately in detail. In any event, before a building

is finally completed the contractor will have to settle with each

sub-contractor upon the basis of detailed cost estimates. Where time

is available, the contractor as a rule secures bids from the various

sub-contractors, such as the plumber, the lather, the mason, etc.,

combining these and adding his commission of 10% for oversight, and an

additional 10% for incidentals or contingencies.

COSTS BY PERCENTAGES

Frame Brick

Items Building Dwelling

Excavation, brick and cut stone 16% 36%

Plastering and materials, including lathing 8 6

Millwork including glass and glazing 21 20

Lumber 19 12

Carpentry labor 18 10

Hardware 3½ 3

Tinwork and galvanized iron 2½ 4½

Plumbing and gas fitting and materials 7 3

Painting and materials 5 5½

Heating (not included)

--------------

Total 100% 100%

_Example:_

A lumber bill for a given frame house is found to "figure" $500,

determine the approximate cost of the various sub-contracts, and

for the house as a whole.

_Solution:_

$500 = 19% of the total cost.

Total cost = $2632 (exclusive of heating).

Excavation, brick and cement work = 16% of $2632 = $421.12

Plastering = 8% of $2632 = 210.56

Millwork and glazing = 21% of $2632 = 552.72

Carpentry labor = 18% of $2632 = 473.76

Hardware = 3½% of $2632 = 92.12

Tinwork = 2½% of $2632 = 65.80

Plumbing = 7% of $2632 = 184.24

Painting = 5% of $2632 = 131.60

Lumber = 500.00

--------

$2631.92

To this must be added heating, electric wiring, electric and gas

fixtures, window shades, cement walks, sewerage, grading, decoration of

walls, architect's fee and contractor's commission.

For furnace heat, add 6 to 7% ; for steam, add 8 to 10% ; for hot

water, add 10 to 12% additional.

For electric wiring, add 1¼%. For fixtures, electric and gas, add 2 to

3%.

To this total add 10% for incidentals and contingencies; add 10% for

contractor's charge. Above this amount add 6% for architect's fee, to

get the cost to the owner.

Such a method of estimating should not be mistaken for anything but

fairly safe approximation where normal conditions exist.

APPENDIX I

[Illustration: Fig. 152.]

Natural Trigonometric Functions. Consider the angle _DAE_, Fig.

152. From any point on the line AD drop a line perpendicular to the

side _AE_ forming the right triangle ABC. Let _a_ represent

the value or length of the side _BC_; let _b_ represent the

value of the side _AC_; let _c_ represent the value of the

side _AB_. The ratio of the side _a_ to the side _c_

is called the sine of the angle _A_. More concisely stated,

_a/c_ = sin _A_. The sine of an angle is the ratio of its

opposite side to its hypotenuse, or opposite side over hypotenuse =

sine of angle _A_ = sin _A_. In a similar manner:

_b_ adjacent side

--- = --------------- = cosine of angle _A_ = cos _A_.

_c_ hypotenuse

_a_ opposite side

--- = --------------- = tangent of angle _A_ = tan _A_.

_b_ adjacent side

_b_ adjacent side

--- = ---------------- = cotangent of angle _A_ = cot _A_.

_a_ opposite side

_c_ hypotenuse

--- = ---------------- = secant of angle _A_ = sec _A_.

_b_ adjacent side

_c_ hypotenuse

--- = --------------- = cosecant of angle _A_ = csc _A_.

_a_ opposite side

These ratios are known as natural functions of the angle because their

values change with every change in the value of the angle.

The lengthening of the sides of the angle should not be mistaken for

a change in the value of the angle. Draw to scale very carefully any

angle and drop lines from any two points, as at _B_ and _B′_,

Fig. 152, which shall be perpendicular to the base line. Measure the

sides of the triangles so formed and express their ratios as functions

of the angle _A_. Comparing like functions of large and small

triangle it will be seen that once an angle is known in degrees, its

sine, cosine, etc., are determined irrespective of the length of sides.

And, vice versa, if we know the functional values or ratios of certain

sides of the right triangle formed about an angle, we have determined

the value of the angle in degrees. The Table of Natural Trigonometric

Functions, Appendix II, is nothing more than a compilation of these

various ratios carefully figured out and placed in the form of a table

to assist in the easy solution of problems having to do with the

finding of certain parts of a triangle when other parts are given.

With a protractor, measure the angle A of the triangle whose sides were

just measured, and compare the ratios of the sides or the functional

values with those given in the Table, Appendix III, for the same angle.

The larger the scale of the drawing, the greater the accuracy. By

making use of the hundredths scale of the framing square together with

a finely pointed pair of dividers, variation in values should not be

great.

=Solutions of Right Triangles.=--By the solution of right

triangles is meant the finding of unknown sides or angles when values

of other sides and angles are known.

_Example 1._--Given _A_ = 30 degrees, _c_ = 24;

Find _B, a, b_.

_Solution_--_B_ = 90-30 = 60 degrees. (The sum of the angles

of a triangle equals 180 degrees. _C_ = 90 degrees.)

(1) _a_/_c_ = sin _A_; whence, _a_ = _c_ sin _A_.

(_a_ = _c_ times sine _A_.)

(2) _b_/_c_ = cos _A_; whence _b_ = _c_ cos _A_.

From the Tables, Appendix II, sin of _A_, or 30 degrees, = .5.

Substituting numerical values in (1), _a_ = 12.

Again, from Tables, cos _A_, or 30 degrees, = .866. Substituting

numerical values in (2), _b_ = 20.784.

Arith. check _c²_ = _a²_ + _b²_; 24² = 12² + 20.78²; 576 = 144 + 431.8;

576 = 576.

Graphic check.=--The graphic check which, it will be seen, might

have been made use of as a graphic solution, consists in setting one

square upon another with the angle of direction and the length of

one side determined by the data given. That is, in this problem the

protractor is set at 30 degrees and a length of 24 units is taken on

the inclined square. The lengths of a and b are then carefully measured

by taking a reading of the full inches and reading, the remaining

fraction to hundredths by means of a sharp pair of dividers and the

hundredths scale of the square.

Very many carpenters make use of graphic solutions such as this in

determining rafter lengths. A little consideration, however, will show

that it is a rather risky method of procedure unless the scale is large

and the work scaled small. Graphs serve as easy checks against grave

errors upon all kinds of work.

_Example 2._--Given _A_ and _a_. To find _B_, _c_, and _b_.

_Solution_--_B_ = 90 degrees _A_.

_a_/_c_ = sin _A_; _c_ = _a_/sin _A_

_b_/_c_ = cos _A_; _b_ = _c_ cos _A_.

Substitute the numerical values and check as in _Example 1_.

_Example 3._--Given _A_ and _b_. To find _B_, _a_, and _c_.

_Solution_--_B_ = 90 degrees _A_.

_a_/_c_ = sin _A_; _a_ = _c_ × sin _A_.

_b_/_c_ = cos _A_; _c_ = _b_ / cos _A_

Substitute the numerical values and check as in Example i.

_Example 4._--Given _a_ and _c_. To find _A_, _B_, and _b_.

_Solution_--sin _A_ = _a_ / _c_ (That is, look in the tables, Appendix II, for the angle

which has a sine equal to the result obtained by dividing the numerical

value of the side _a_ by the value of the side _c_.)

_B_ = 90 degrees _A_.

_b_/_c_ = cos _A_; _b_ = _c_ cos _A_.

Substitute numerical values and check as in Example i.

_Example 5._--Given _a_ and _b_. To find _A_, _B_. and _c_.

_Solution_--tan _A_ = _a_ / _b_

_B_ = 90 degrees _A_.

_a_/_c_ = sin _A_; _c_ = _a_ / sin _A_

Substitute numerical values and check as in Example 1.

APPENDIX II

Directions. An examination of the table of natural functions will

indicate in the column at the left, angles of degrees to and including

45 degrees, reading down. The column to the extreme right will be found

to contain degrees from 45-90 inclusive, reading up.

This compact arrangement of table is made possible thru the fact that

sines and cosines, tangents and cotangents are reciprocals one of the

other. That is, as the sine (column 2, reading down) increases in

value, the cosine of the complementary angle (columns 6 and 2, reading

up) decreases.

_Example 1._--Find the value of the sine of 40 degrees.

_Solution_--Columns 1 and 2, reading down, sin 40 degrees = .6428.

_Example 2._--Find the value of sin 50 degrees.

_Solution_--Columns 6 and 5, reading up, sin 50 degrees = .7660.

_Example 3._--Find the value of cos 40 degrees.

_Solution_--Columns 1 and 5, reading down, cos 40 degrees = .7660

which is as might have been expected. Since 40 degrees is the

complement of 50 degrees, the cos 40 degrees should be the same in

value as the sin 50 degrees.

_Example 4._--Find the value of cos 87 degrees.

_Solution_--Columns 6 and 2 reading up, cos 87 degrees = .0523

_Example 5._--Tangent and cotangent values. Proceed as with sines

using columns 1 and 3, reading down, for tangent values between 0-45

degrees inclusive, columns 6 and 4, reading up, for values between

45-90 degrees.

For cotangent values between 0-45 degrees use columns 1 and 4 reading

down, and columns 6 and 3 reading up for cotangent values between

45-90 degrees inclusive.

TABLE OF NATURAL SINES, TANGENTS, COSINES, AND COTANGENTS

============================================================

Degrees | Sine | Tangent | Cotangent| Cosine |

----------+---------+---------+----------+----------+-------

0 | 0 | 0 | ∞ | 1 | 90

1 | .0175 | .0175 | 57.2900 | .9998 | 89

2 | .0349 | .0349 | 28.6363 | .9994 | 88

3 | .0523 | .0524 | 19.0811 | .9986 | 87

4 | .0698 | .0699 | 14.3007 | .9976 | 86

----------+---------+---------+----------+----------+-------

5 | .0872 | .0875 | 11.4301 | .9962 | 85

----------+---------+---------+----------+----------+-------

6 | .1045 | .1051 | 9.5144 | .9945 | 84

7 | .1219 | .1228 | 8.1443 | .9925 | 83

8 | .1392 | .1405 | 7.1154 | .9903 | 82

9 | .1564 | .1584 | 6.3138 | .9877 | 81

----------+---------+---------+----------+----------+-------

10 | .1736 | .1763 | 5.6713 | .9848 | 80

----------+---------+---------+----------+----------+-------

11 | .1908 | .1944 | 5.1446 | .9816 | 79

12 | .2079 | .2126 | 4.7046 | .9781 | 78

13 | .2250 | .2309 | 4.3315 | .9744 | 77

14 | .2419 | .2493 | 4.0108 | .9703 | 76

----------+---------+---------+----------+----------+-------

15 | .2588 | .2679 | 3.7321 | .9659 | 75

----------+---------+---------+----------+----------+-------

16 | .2756 | .2867 | 3.4874 | .9613 | 74

17 | .2924 | .3057 | 3.2709 | .9563 | 73

18 | .3090 | .3249 | 3.0777 | .9511 | 72

19 | .3256 | .3443 | 2.9042 | .9455 | 71

----------+---------+---------+----------+----------+-------

20 | .3420 | .3640 | 2.7475 | .9397 | 70

----------+---------+---------+----------+----------+-------

21 | .3584 | .3839 | 2.6051 | .9336 | 69

22 | .3746 | .4040 | 2.4751 | .9272 | 68

23 | .3907 | .4245 | 2.3559 | .9205 | 67

24 | .4067 | .4452 | 2.2460 | .9135 | 66

----------+---------+---------+----------+----------+-------

25 | .4226 | .4663 | 2.1445 | .9063 | 65

----------+---------+---------+----------+----------+-------

26 | .4384 | .4877 | 2.0503 | .8988 | 64

27 | .4540 | .5095 | 1.9626 | .8910 | 63

28 | .4695 | .5317 | 1.8807 | .8829 | 62

29 | .4848 | .5543 | 1.8040 | .8746 | 61

----------+---------+---------+----------+----------+-------

30 | .5000 | .5774 | 1.7321 | .8660 | 60

----------+---------+---------+----------+----------+-------

31 | .5150 | .6009 | 1.6643 | .8572 | 59

32 | .5299 | .6249 | 1.6003 | .8480 | 58

33 | .5446 | .6494 | 1.5399 | .8387 | 57

34 | .5592 | .6745 | 1.4826 | .8290 | 56

----------+---------+---------+----------+----------+-------

35 | .5736 | .7002 | 1.4281 | .8192 | 55

----------+---------+---------+----------+----------+-------

36 | .5878 | .7265 | 1.3764 | .8090 | 54

37 | .6018 | .7536 | 1.3270 | .7986 | 53

38 | .6157 | .7813 | 1.2799 | .7880 | 52

39 | .6293 | .8098 | 1.2349 | .7771 | 51

----------+---------+---------+----------+----------+-------

40 | .6428 | .8391 | 1.1918 | .7660 | 50

----------+---------+---------+----------+----------+-------

41 | .6561 | .8693 | 1.1504 | .7547 | 49

42 | .6691 | .9004 | 1.1106 | .7431 | 48

43 | .6820 | .9325 | 1.0724 | .7314 | 47

44 | .6947 | .9657 | 1.0355 | .7193 | 46

----------+---------+---------+----------+----------+-------

45 | .7071 | 1.0000 | 1.0000 | .7071 | 45

----------+---------+---------+----------+----------+-------

| Cosine |Cotangent| Tangent | Sine |Degrees

----------+---------+---------+----------+----------+-------

TO FIND THE VALUE OF AN ANGLE, THE VALUE OF A FUNCTION BEING KNOWN

_Example 6._--sin = .5150, find the angle.

_Solution_--Looking in columns 2 and 5 (sine values from

0-90 degrees) Ans. 31 degrees (Columns 2 and 1).

_Example 7._--cot = 1.3764, find the angle.

_Solution_--Looking in columns 3 and 4, Ans. = 36 degrees.

=Interpolation.=--Frequently one must find a functional value for

fractional degrees, or degrees and minutes. Also, it becomes necessary

to find the value of an angle with greater accuracy than even degrees,

as given in the table herewith. This process of finding more accurate

values is known as interpolation.

TO FIND THE VALUE OF A FUNCTION WHEN THE ANGLE IS IN FRACTIONAL DEGREES

_Example 8._--Find the value of tan 50 degrees 20 min.

_Solution._--tan 50 degrees = 1.1918

tan 51 degrees = 1.2349

difference for an interval of 1 degree = .0431

20 min. = 20/60 = 1/3 of 1 degree; ⅓ of .0431 = .0144

tan 50 degrees 20 min. = 1.1918 + .0144 = 1.2062.

The value of a fractional degree would be similarly treated for the

sine, these functions increasing as the value of the angle increases.

The cosine and cotangent, however, decrease in value as the angle

increases. For this reason the fractional value of the cosine and

cotangent must be subtracted from, instead of added to, the value of

the function of the next lower number of degrees.

_Example 9._ Find the value of cos 26 deg. 30 min.

_Solution_--cos 26 deg. = .8988

cos 27 deg. = .8910

difference for interval of 1 deg. = .0078

30 min. = ½ of 1 deg.; ½ of .0078 = .0039

cos. 26 deg. 30 min. = .8988 - .0039 = .8949.

TO FIND THE VALUE OF AN ANGLE WHEN THE FUNCTIONAL VALUE CANNOT BE FOUND

IN EXACT FORM IN THE TABLE

_Example 10._--Find the angle whose tan is .5

_Solution_--From the table, .4877 = tan 26 deg.

.5095 = tan 27 deg.

difference for interval of 1 deg. = .0218

.5000 = tan angle X.

.4877 = tan 26 deg.

difference for interval between tan angle X and tan 26 deg. = .0123

123/218 of 1 deg. or 60 min. = 34 min.

Therefore, angle whose tangent = .5 = 26 deg. 34'.

Rule: (1) Search the body of the table for the functional values next

above and next below that given. (2) Find the difference between these

functional values. This difference is for an interval of 1 degree or

60 minutes. (3) Find the difference between the given functional value

and that of the lower angle of the two used above. (4) Express this

last difference as the numerator of a fraction whose denominator is

the first difference found, or the difference for the interval of 1

degree. This gives the fractional part of 1 degree or 60 minutes which

the second difference is. (5) Express this difference in minutes and

add if the function be a sine or tangent, and substract if a cosine

or cotangent to the number of degrees representing the angle whose

function was the lower of the two functions found given in the table.

APPENDIX III

USEFUL TABLES

FRACTIONAL EQUIVALENTS FOR DECIMAL VALUES

================================================================

.0156 | 1/64 || .2656 | 17/64 || .5156 | 33/64 || .7656 | 49/64

.0312 | 1/32 || .5312 | 9/32 || .2812 | 17/32 || .7812 | 25/32

.0468 | 3/64 || .2968 | 19/64 || .5468 | 35/64 || .7968 | 51/64

.0625 | 1/64 || .3125 | 5/16 || .5625 | 9/16 || .8125 | 13/16

.0781 | 5/64 || .3281 | 21/64 || .5781 | 37/64 || .8281 | 53/64

.0937 | 3/32 || .3437 | 11/32 || .5937 | 19/32 || .8437 | 27/32

.1093 | 7/64 || .3593 | 23/64 || .6093 | 39/64 || .8593 | 55/64

.125 | 1/8 || .375 | 3/8 || .625 | 5/8 || .875 | 7/8

.1406 | 9/64 || .3906 | 25/64 || .6406 | 41/64 || .8906 | 57/64

.1562 | 5/32 || .4062 | 13/32 || .6562 | 21/32 || .9062 | 29/32

.1718 | 11/64 || .4218 | 27/64 || .6718 | 43/64 || .9218 | 59/64

.1875 | 3/16 || .4375 | 7/16 || .6875 | 11/16 || .9375 | 15/16

.2031 | 13/64 || .4531 | 29/64 || .7031 | 45/64 || .9531 | 61/64

.2187 | 7/32 || .4687 | 15/32 || .7187 | 23/32 || .9687 | 31/32

.2343 | 15/64 || .4843 | 31/64 || .7343 | 47/64 || .9843 | 63/64

.250 | 1/4 || .500 | 1/2 || .750 | 3/4 || 1.000 | 1

================================================================

Where rafter lengths are determined by multiplying unit lengths by

the run, the answer will almost invariably result in a decimal. Such

decimal values may be readily translated into fractional forms by means

of the accompanying table.

Example: A roof of ⅓ pitch has a common rafter run of 14';

find the length of common rafter.

Answer: 14 × 14.42" = 201.88" or 16.82'. By the table, .82 = 53/64.

A carpenter, however, would not care for such accuracy; the

nearest 1/16" or even ⅛" would be sufficient.

WOOD AND MACHINE SCREW SIZES

The difference between consecutive sizes is .01316".

===================================================================

No. of | Size of || No. of | Size of || No. of | Size of

Screw | Number in || Screw | Number in || Screw | Number in

Gage | Decimals || Gage | Decimals || Gage | Decimals

--------+------------++--------+------------++--------+------------

000 | .03152 || 16 | .26840 || 34 | .50528

00 | .04486 || 17 | .28156 || 35 | .51844

0 | .05784 || 18 | .29472 || 36 | .53160

1 | .07100 || 19 | .30788 || 37 | .54476

2 | .08416 || 20 | .32104 || 38 | .55792

3 | .09732 || 21 | .33420 || 39 | .57108

4 | .11048 || 22 | .34736 || 40 | .58424

5 | .12364 || 23 | .36052 || 41 | .59740

6 | .13680 || 24 | .37368 || 42 | .61056

7 | .14996 || 25 | .38864 || 43 | .62372

8 | .16312 || 26 | .40000 || 44 | .63688

9 | .17628 || 27 | .41316 || 45 | .65004

10 | .18944 || 28 | .42632 || 46 | .66320

11 | .20260 || 29 | .43948 || 47 | .67636

12 | .21576 || 30 | .45264 || 48 | .68952

13 | .22892 || 31 | .46580 || 49 | .70268

14 | .24208 || 32 | .47896 || 50 | .71584

15 | .25524 || 33 | .49212 || |

--------+------------++--------+------------++--------+------------

Frequently the carpenter wishes to know the diameter of hole necessary

to receive the shank of a screw of a certain gage. Should a screw gage

be accessible, he may readily determine this. Should no gage be at

hand, he may determine the size of hole by consulting the accompanying

table of Wood and Machine Screw Sizes.

Example: What size bit must be selected to bore a hole for a

No. 10 screw. By the table, a No. 10 screw is .18944" in diameter.

By the table of Fractional Equivalents for Decimal Values it will

be seen that a 3/16" bit must be used. The test for gage of screw is

always made over the shank just below the head.

LENGTH AND NUMBER OF WIRE NAILS TO THE POUND

================================================================

Size |LENGTH|COMMON|CASING|FINISH|CLINCH|FENCE | FINE | GAL.

| INS. | | | | | | | SHINGLE

-----+------+------+------+------+------+------+------+---------

¾ | ¾ | | | | | | |

⅞ | ⅞ | | | | | | |

2d | 1 | 900 | | | | | 1440 |

3d | 1¼ | 615 | | | | | 810 | 568

4d | 1½ | 322 | 473 | 584 | | | 250 |

5d | 1¾ | 254 | | | | | |

6d | 2 | 200 | 180 | 300 | 157 | 114 | |

7d | 2¼ | 154 | | | | | |

8d | 2½ | 106 | 112 | 190 | 99 | 74 | |

9d | 2¾ | 85 | | | | | |

10d | 3 | 74 | 90 | 134 | 69 | 42 | |

12d | 3¼ | 57 | | | | | |

16d | 3½ | 46 | .| | | | |

20d | 4 | 29 | | | | | |

30d | 4½ | 23 | | | | | |

40d | 5 | 17 | | | | | |

50d | 5½ | 14 | | | | | |

60d | 6 | 11 | | | | | |

-----+------+------+------+------+------+------+------+------

Nails are sold in quantity by the keg, 100 lbs. of nails, exclusive

of the keg. Twenty, 30, 40, 50 and 60d are "base." Other sizes have

certain fixed additions per keg to this base price. For example, the

price list adopted by manufacturers in 1896 allows an addition per keg

of $.70 for 2d common, $.45 for 3d common, etc.

Wire nails are also bought and sold by weight, the size of wire

according to the standard wire gage and the length in inches being

taken into consideration in specifying the size and in fixing the price

per pound.

Common wire nails are thick and have large flat heads. They are used

in rough work where strength is desired. Finishing nails are used for

fine work such as inside woodwork and cabinet work. Casing nails are

somewhat thicker and stronger than finishing nails; they have smaller

heads.

WIRE BRADS

====================================================================

Size, inches | ½ | ½ | ⅝ | ¾ | ¾ | ¾ | ⅞ | ⅞ | 1

Wire Gage, nos | 20 | 18 | 19 | 19 | 18 | 16 | 18 | 17 | 18

Approx no brads to lb. |7500|7200|4267|3556|2758|2600|2364|1781|2069

-----------------------+----+----+----+----+----+----+----+----+----

Size, inches | 1 | 1 | 1¼ | 1¼ | 1½ | 1½ | 1½ | 1¾ | 1¾

Wire Gage, nos | 17 | 16 | 17 | 16 | 16 | 15 | 14 | 15 | 14

Approx no brads to lb. |1558|1143|1246| 913| 761| 584| 500| 500| 406

-----------------------+----+----+----+----+----+----+----+----+----

Size, inches | 2 | 2 | 2½ | 2½ | 3 | 3 | 3 | |

Wire Gage, nos | 14 | 13 | 13 | 12 | 14 | 12 | 11 | |

Approx no brads to lb. | 350| 268| 214| 164| 150| 137| 105| |

-----------------------+----+----+----+----+----+----+----+----+----

BOARD MEASURE TABLE

==================================================================================

|

Size | Length, in Feet, of Joist, Scantling and Timber

in +----+----+----+----+----+----+----+----+----+----+----+----+----+----+-----

Inches| 12 | 14 | 16 | 18 | 20 | 22 | 24 | 26 | 28 | 30 | 32 | 34 | 36 | 38 | 40

-------+----+----+----+----+----+----+----+----+----+----+----+----+----+----+-----

2 × 4| 8| 9| 11| 12| 13| 15| 16| 17| 19| 20| 21| 23| 24| 25| 27

2 × 6| 12| 14| 16| 18| 20| 22| 24| 26| 28| 30| 32| 34| 36| 38| 40

2 × 8| 16| 19| 21| 24| 27| 29| 32| 35| 37| 40| 43| 45| 48| 51| 53

2 × 10| 20| 23| 27| 30| 33| 37| 40| 43| 47| 50| 53| 57| 60| 63| 67

2 × 12| 24| 28| 32| 36| 40| 44| 48| 52| 56| 60| 64| 68| 72| 76| 80

2 × 14| 28| 33| 37| 42| 47| 51| 56| 61| 65| 70| 75| 79| 84| 89| 93

3 × 6| 18| 21| 24| 27| 30| 33| 36| 39| 42| 45| 48| 51| 54| 57| 60

3 × 8| 24| 28| 32| 36| 40| 44| 48| 52| 56| 60| 64| 68| 72| 76| 80

3 × 10| 30| 35| 40| 45| 50| 55| 60| 65| 70| 75| 80| 85| 90| 95| 100

3 × 12| 36| 42| 48| 54| 60| 66| 72| 78| 84| 90| 96| 102| 108| 114| 120

3 × 14| 42| 49| 56| 63| 70| 77| 84| 91| 98| 105| 112| 119| 126| 133| 140

4 × 4| 16| 19| 21| 24| 27| 29| 32| 35| 37| 40| 43| 45| 48| 51| 53

4 × 6| 24| 28| 32| 36| 40| 44| 48| 52| 56| 60| 64| 68| 72| 76| 80

6 × 6| 36| 42| 48| 54| 60| 66| 72| 78| 84| 90| 96| 102| 108| 114| 120

6 × 8| 48| 56| 64| 72| 80| 88| 96| 104| 112| 120| 128| 136| 144| 152| 160

8 × 8| 64| 75| 85| 96| 107| 117| 128| 139| 149| 160| 171| 181| 192| 203| 213

8 × 10| 80| 93| 107| 120| 133| 147| 160| 173| 187| 200| 213| 227| 240| 253| 267

10 × 10| 100| 117| 133| 150| 167| 183| 200| 217| 233| 250| 267| 283| 300| 317| 333

10 × 12| 120| 140| 160| 180| 200| 220| 240| 260| 280| 300| 320| 340| 360| 380| 400

12 × 12| 144| 168| 192| 216| 240| 264| 288| 312| 336| 360| 384| 408| 432| 456| 480

12 × 14| 163| 196| 224| 252| 280| 308| 336| 364| 392| 420| 448| 476| 504| 532| 560

14 × 14| 196| 229| 261| 294| 327| 359| 392| 425| 457| 490| 523| 555| 588| 621| 653

-------+----+----+----+----+----+----+----+----+----+----+----+----+----+----+-----

STRENGTH OF MATERIALS

YELLOW PINE POSTS

Load in Tons

Length

in ft. Size in inches

4 × 4 5 × 5 6 × 6 7 × 7 8 × 8 9 × 9

8 4 5 6 7 8 9

10 3 4 5 6 7 8

12 2 3 4 5 6 7

14 1 2 3 4 5 6

16 1 2 3 4 5

18 1 2 3 4

HARD PINE BEAMS AND GIRDERS

Load in Tons

Length

in ft. Size in inches

2 × 6 3 × 6 4 × 6 6 × 6 8 × 8

6 1 1½ 2 3 5½

8 ¾ 1 1½ 2½ 5

10 ¾ 1¼ 2 4½

12 ½ 1 1½ 3

14 ½ 1 2½

16 ½ 2

18 1

STEEL I BEAMS

Load in Tons

Length Size in inches

in ft.

6 8 12

10 7 14 18

12 6 12 16

14 5 10 14

16 4 8 12

18 2 6 10

20 4 8

22 2 6

24 4

BRICK PIERS

Load in Tons

Height Size in inches

in ft.

6 × 6 6 × 8 8 × 8 8 × 12 12 × 12 12 × 16 16 × 16

6 2 3 4 5 6 7 9

8 1½ 2½ 3½ 4¾ 5½ 6 8

10 1 2 3 5 5½ 6 7

STRESSES FOR STRUCTURAL TIMBERS

WORKING UNIT STRESSES USED IN DRY LOCATIONS

Bending Compression

Stress in Horizontal Parallel to Perpen-

extreme shear grain "Short dicular

Species of fibre stress Columns" to grain

Timber Lbs. sq.in. Lbs. sq.in. Lbs. sq.in. Lbs. sq.in.

*Fir, Douglas

Dense grade 1,600 100 1,200 350

Sound grade 1,300 85 900 300

Hemlock, eastern 1,000 70 700 300

Hemlock, western 1,300 75 900 300

Oak 1,400 125 900 400

Pine, eastern white 900 80 700 250

Pine, Norway 1,100 85 800 300

*Pine, southern yellow

Dense grade 1,600 125 1,209 350

Sound grade 1,300 85 900 300

Spruce 900 70 600 200

Tamarack 1,200 95 900 350

* NOTE: The safe working stresses given in this table are for

timbers with defects limited according to the sections on defects

in the rules of the Southern Pine Association for Select Structural

Material. "Dense" southern yellow pine and "dense" Douglas fir

should also conform to the other requirements of this rule. "Sound"

southern yellow pine and "sound" Douglas fir require no additional

qualifications, whereas the other species should, in addition to

being graded for defects, have all pieces of exceptionally low

density for the species excluded.

This table gives working unit stresses for structural timbers

used in dry locations, and is compiled in the main from material

furnished by the Forest Products Laboratory, Madison, Wis.

TABLE OF BRICK WALL CONTENTS IN NUMBER OF BRICKS

Seven Bricks to Each Sq. Ft. of Wall Surface

No. of

sq ft. Thickness

of wall

4" 8" 12" 16" 20" 24"

1 7 15 23 30 38 45

2 15 30 45 60 75 90

3 23 45 68 90 113 135

4 30 60 90 120 150 180

5 38 75 113 150 188 225

6 45 90 135 180 225 270

7 53 105 158 210 263 315

8 60 120 180 240 300 360

9 68 135 203 270 338 405

10 75 150 225 300 375 450

20 150 300 450 600 750 900

30 225 450 675 900 1,125 1,350

40 300 600 900 1,200 1,500 1,800

50 375 750 1,125 1,500 1,875 2,250

60 450 900 1,350 1,800 2,250 2,700

70 525 1,050 1,575 2,100 2,625 3,150

80 600 1,200 1,800 2,400 3,000 3,600

90 675 1,350 2,025 2,700 3,375 4,050

100 750 1,500 2,250 3,000 3,750 4,500

_Example_--Determine the number of bricks in a wall 12" × 18' × 60'.

_Solution_--The wall contains a surface area of 1,080 sq. ft. By

the table 100 sq. ft. contains 2,250 bricks, then 1,000 sq. ft. will

contain 22,500 bricks. 80 sq. ft. will contain, by the table, 1,800

bricks, making a total of 24,300 bricks.

APPENDIX IV

(Short Cuts to Roof Framing)

Griffith's Framing Tables For the Square and Octagonal Roof

=Directions for Using Table for the Steel Square.=--Fig. 70-a.

Example.--Given a square hipped roof, that is, a roof with

square corners, having a span of 25 ft. and a pitch of ½.

1. _To Lay Out Miter Cut of Plate._--Take 12" on tongue of framing

square and 12" on blade; scribe along blade. (Cf. small table, Fig.

70-a.)

2. _Length of Ridge._--Length of long plate diminished by length

of short plate, increased by thickness of ridge piece plus diagonal

thickness of hip.

3. _To Lay Out Common Rafter._--

a. Plumb cut. (Cf. column 5, beginning at left, Fig. 70-a.) Take

12" on tongue of square and 12" on blade (column 2), scribe

along blade.

b. Length of common rafter. (Cf. column 11) 12½ (run of common

rafter) x 16.97" (length of common rafter per foot of run) = 17'

8.12" = 17' 8⅛ (.12" = ⅛", columns 3 and 4).

c. Seat cut. (Cf. column 8) Take 12" on tongue and 12" on blade;

scribe along tongue.

d. Tail for common rafter.

(1) Length determined as was that of common rafter, the horizontal

projection or length of look- out becoming multiplier. 173

(2) End cut use same numbers as for plumb cut but invert position of

square.

e. Reduction for ridge. Measure straight back from plumb cut a

distance equal to 3/ the thickness of ridge piece.

4. _To Lay Out Hip or Valley Rafter.-_-

a. Plumb cut. (Cf. column 6) Take 17" on the tongue and 12" on the

blade; scribe along the blade.

b. Side cut. (Cf. column 16) Take 17" on the tongue and 20.78" or

20-13/16" (columns 3 and 4) on the blade; scribe along the blade.

This also gives the miter cut at the end of the tail of the hip for

fascia, and also the miter cut at the bird's mouth joint of

valley rafter, where it must be cut out to fit the angle of the

plate.

c. Length of hip or valley rafter. (Cf. column 12) 12½ (run of

common rafter) x 20.78" (length of hip or valley rafter per foot

of run of common rafter) = 21' 7.75" = 21' 7¾" (.75 = ¾, columns

3 and 4.)

d. Seat cut. (Cf. column 9) Take 17" on tongue and 12" on the

blade, scribe along the tongue.

e. Tail for hip or valley rafter.

(1) Length determined as was that of hip or valley rafter, the

horizontal projection of tail or length of the lookout of common

rafter becoming the multiplier.

(2) End cut use same numbers as for plumb cut of hip or valley but

invert square.

f. Reduction for ridge. Measure straight back from plumb cut ½

diagonal thickness of ridge.

g. Backing of hip. (Cf. column 21) Take 12" (rise of common rafter)

on the tongue and 20-13/16" on the blade scribe along the tongue

for angle of backing.

h. Drop of hip when no backing is given. (Cf. column 23) Reduce at

seat cut 9/16", measured at right angles to seat cut.

5. _To Lay Out Jacks._--

a. Plumb cut. Same as that for the common rafter!

b. Side cut. (Cf. column 14) Take 12" on the tongue and 16.97" or

17" on blade (.97" = 1", columns 3 and 4), scribe on the blade.

Scribing along the tongue will give the face cut of roof boards, also

of plancher.

c. Length. Jacks set 24" centers, beginning with shortest jack =2'

10" (column 19). Second shortest jack = length of shortest

increased 2' 10", etc.

Beginning with longest jack = length of common rafter diminished by

2' 10", etc.

d. Tail for jack. Same as for common rafter.

6. _Note._--

All rafter lengths are measured down the middle of the top edges

theoretically. On the square cornered roof, measurements of hip

or valley rafters may be made from the long point without further

reduction in length providing a 2" thick ridge is used. Jacks

need no further reduction in length on a square cornered building

provided the hips or valleys are of the same thickness as the jacks

and the measurements are made from the long points of the jacks.

Otherwise suitable reductions must be made for rafter and ridge

thicknesses.

=Directions for Using Table for Protractor.=--Fig. 70-b.

Example.--Given to frame an octagonal silo with a span of 21'

and a roof pitch of 11" to the foot.

1. _To Lay Out Miter Cut of Plate._--(Cf. small table Fig. 70-b.)

Eight sided polygon, plate miter = 67½ degrees. Set a T-bevel by means

of a protractor[B] to this angle.

[Footnote B: Starrett's "Framing Tool" is strongly recommended for

framing in degrees, Cf. Figs. 81 and 82.]

2. _To Find Length of a Side for Plate._--(Cf. small table, Fig.

70-b.) 21' (2 x run) x .414 (cotangent of octagon) = 8.69' = 8%' (.69 =

%, columns 3 and 4.)

3. _To Lay Out Common Rafter._--

a. Plumb cut.--(Cf. column 5) = 47 deg. 30 min. Set

T-bevel by means of protractor to same.

b. Length.--(Cf. column 11). Take 10½ (run) × 16.28"

(length of common rafter per foot of run) = 14' 2.94" =

14' 3". (.94 = 1, columns 3 and 4.)

c. Seat cut.--(Cf. column 8) 42 deg. 30 min. Set T-bevel

by means of protractor.

d. Tail.--

(1) Length Determined as is length of common

rafter (Cf. column 11), horizontal projection of

tail or length of lookout becoming the multiplier.

(2) End cut. Use same number of degrees as for

plumb cut.

4. _To Lay Out Hip or Valley Rafter._--

a. Plumb cut.--(Cf. column 7) = 49 deg. 50 min.

b. Side cut.--(Cf. column 17) = 17 deg. 40 min. This

also gives miter cut at end of hip tail for fascia, and

also the miter cut of the bird's mouth joint of valley

rafter, where it must be cut out to fit the angle of

the plate.

c. Length of hip or valley rafter.--(Cf. column 13) 10½

(run of common rafter) × 17.03" (length of octagon

hip or valley per foot of run of common rafter) = 14'

10.82" = 14' 10⅞" (.82 = ⅞, columns 3 and 4).

d. Seat cut.--(Cf. column 10) = 40 deg. 10 min. Use

protractor and T-bevel.

e. Tail for hip or valley rafter.--

(1) Length. Determined as for hip or valley, horizontal

projection of tail or length of lookout of

common rafter becoming multiplier.

(2) End cut. Use same number of degrees as for

plumb cut of hip or valley.

f. Backing of hip.--(Cf. column 22) = 74 deg. 50 min.

g. Drop of hip when no backing is used.--(Cf. column 24)

= 5/16".

5. To Lay Out Jacks.--

a. Plumb cut.--Same as for common rafter.

b. Side cut.--(Cf. column 15) = 17 deg.

c. Length.--(Cf. column 20) = 12/5 that for square roof

of same pitch. When set 16" centers = 12/5 × 21¾" =

52¼", common difference. Proceed accordingly.

d. Tail for jack.--Same as for common rafter.

APPENDIX V

MISCELLANEOUS ESTIMATING

Excavations. Excavations are estimated in terms of the cubic yard, 27

cubic feet. The price per yard will vary according to the nature of the

soil.

Where ground is not level, the plot should be divided into squares,

each square being figured as to its cubical contents and the various

amounts combined.

ANALYSIS OF COST FACTORS PER CUBIC YARD

Spading or picking labor, ¾ hour at ...............

Throwing out labor, ¾ hour at .....................

Wheeling 50 feet, ⅜ hour at .......................

--------

Cost per yard $

=Concrete.=--Concrete is estimated in terms of the cubic yard. The

price will vary somewhat according to the mixture and the amount of

form work required. Mixtures are designated as "rich"--1 part cement,

2 parts sand, 4 parts crushed rock, by volume; "medium"--1:2½:5;

"ordinary"--1:3:6, and "lean,"--1:4:8. The rich mixture is used for

cellar floors on high grade work. Cisterns and tanks make use of a

special mixture of 1:2:3, the stone or gravel being passed thru a %"

screen. Cement topping for cellar floors is a mortar composed of 1 part

cement and 2 parts sharp sand. Sometimes a 1:1 mixture is used. Cellar

floors and sidewalks are often priced by the foot surface measure,

standard specifications for depth and construction being understood.

TABLE FOR ESTIMATING QUANTITIES FOR CONCRETE

(Proportion of materials in one cubic foot of concrete.)

MIXTURE

Rich (1:2:4) Medium (1:2½:5) Ordinary (1:3:6)

Cement 0.058 bbl. 0.048 bbl. 0.041 bbl.

Sand 0.0163 cu. yd. 0.0170 cu. yd. 0.0174 cu. yd.

Stone or gravel: 0.0326 cu. yd. 0.0341 cu. yd. 0.0348 cu. yd.

_Example_ Estimate quantities of various materials needed for a

wall 10" × 7' × 48', using a 1:2½:5 mixture.

_Solution_--(10 × 7 × 48) / 12 = 280 cu. ft.

Cement = 280 × 0.048 bbl. = 13.44 bbl.

Sand = 280 × 0. 017 cu. yd. = 4.76 cu. yd.

Stone = 280 × 0.0341 cu. yd. = 9.548 cu. yd.

Knowing the cost of cement per bbl. and of sand and stone per cu. yd.,

the cost of materials for the wall may be easily determined.

TABLE FOR ESTIMATING QUANTITIES FOR CEMENT MORTAR

(Proportion of materials in one cubic foot of cement mortar)

MIXTURE

1:1½ 1:2 1:2½

Cement 0.1481 bbl. 0.1239 bbl. 0.1052 bbl.

Sand 0.0311 cu. yd. 0.0344 cu. yd. 0.0370 cu. yd.

_Example_ Estimate quantities of material for 1:2 cement mortar

for topping of cellar floor 1" × 24' × 40'.

_Solution_--(24 × 40) = 80 cu. ft.

Cement = 80 × 0.1239 bbl. = 9.912 bbl.

Sand = 80 × 0.0344 cu. yd. = 2. 752 cu. yd.

ANALYSIS OF LABOR COST FACTORS PER CUBIC YARD

1 mason, 2 hours @ .......................

2 laborers, 2 hours each @ ...............

-------

Total $

Where forms are required add

1 carpenter, 2¼ hours @ ...................

Cellar floor construction costs approximately the same as wall work

having forms. The expense of form work in ordinary basement wall

construction is offset by labor and additional cement cost of topping

of cellar floor.

=Brickwork.=--The unit of measurement in brickwork is the 1000

bricks, ordinarily.

To determine the number of bricks in a wall, multiply each square foot

of surface by 7 (sometimes 7½ is used) which is the average number of

bricks per foot of wall when 4" thick. Add 5% for breakage. Deduct

for openings over 2' square. For walls thicker than 4", make suitable

allowance.

A mason can lay 800 to 1000 common and 300 to 400 face bricks in a day.

Bricks may be laid in lime mortar or in cement mortar.

ANALYSIS OF COST FACTORS PER 1000 BRICKS, LIME MORTAR 1:3

Brick, 1000 @ ............................

Lime, 3 bu. @ ............................

Sand, ½ cu. yd. @ ........................

Mason, 10 hrs. @ .........................

Tender, 10 hrs. @ ........................

-------

Total $

ANALYSIS OF COST FACTORS PER 1000 BRICKS, CEMENT MORTAR 1:3

Brick, 1000 @ ............................

Portland cement, 1¼ bbl. @................

Sand ½ cu. yd. @ .........................

Mason, 10 hrs. @ .........................

Tender, 10 hrs. @ ........................

-------

Total $

=Chimneys.=--One foot of chimney height will contain five courses

of ordinary bricks.

CHIMNEYS

No. Size of Size of No. Bricks

Flues Flue Chimney per Ft.

1 8" × 8" 16" × 16" 30

2 8" × 8" 16" × 28" 50

3 8" × 8" 16" × 40" 70

1 12" × 12" 20" × 20" 40

=Slate Roof.=--Exposure of each slate will equal the length of

a slate diminished by 3" (the usual amount of lap) divided by 2,

multiplied by the width of the slate.

To determine the number of slates required, divide the area to be

covered by the exposure of each slate as determined just above.

_Example_--Determine the number of 6" × 12" slates required to

cover a surface 16' × 20'.

_Solution_--( (12" - 3") / 2) × 6" = 27 sq. in.

(16 × 20 × 144") / 27" = 1707 slates.

TABLE OF SLATES PER SQUARE OF 100 FEET

Size Length of Expos. No. Req. Nails Req.

6" × 12" 4½" 533 3.8 lbs.

7" × 14" 5½" 377 2.66

8" × 16" 6½" 277 2

9" × 18" 7½" 214 1.5

ANALYSIS OF COST FACTORS PER SQUARE. (100 SQ. FT.)

Slate, @ .............................

Slater, 8 hrs., @ ....................

Roofing Paper, @ .....................

Placing paper, 20 min ................

Nails, 2 lbs. (8" × 16" slate) @ .....

--------

Total $

Metal work extra.

=Plastering.=--Plastering is estimated by the square yard. In

estimating the number of square yards, deduct ½ the area of openings.

The extra labor involved in working around grounds is thus allowed for.

Strips of plastering less than 1 foot wide are estimated as a foot

in width. Closet areas are increased by J/ to make allowance for the

extra labor involved in working small surfaces. Special plastering of

cornice, etc., will be charged extra: Lathing is usually a part of the

plasterer's contract, tho done by a different set of workmen. The unit

is either the square yard or the 1000 laths.

ANALYSIS OF COST FACTORS FOR LATHING A SQUARE (100 SQ. FT.)

Lath, 1500 @ .........................

Nails, 10 lbs. 3d fine @ .............

Lather, 8 hrs. @ .....................

--------

Total ............................$

ANALYSIS OF COST FACTORS PER SQUARE FOR 2-COAT LIME PLASTER

Lime, 10 bu. @ .......................

Hair, 6 lbs. @ .......................

Sand, 1 yd. @ ........................

2 plasterers, 12 hrs. each @ .........

1 helper, 12 hrs. @ ..................

--------

Total ............................$

ANALYSIS OF COST FACTORS PER SQUARE FOR 3-COAT LIME PLASTER

Lime, 13 bu. @ .......................

Hair, 8 lbs. @ .......................

Sand, 1½ yds. @ ......................

Plaster of Paris, 1 bbl. @ ...........

2 plasterers, 16 hrs. each @ .........

1 helper, 16 hrs .....................

-------

Total ............................$

=Painting.=--Painting is estimated by the square yard, no

deductions being made for openings such as doors and windows. Railings,

grills, etc., are figured as if solid.

A gallon of paint will cover approximately 250 to 300 sq. ft. of old

work and 350 ft. of new work. A painter should cover 150 sq. ft, 1st.

coat, per hour, and 90 sq. ft., 2nd coat.

Cost factors may be easily determined from the above statements, and

costs easily estimated for ordinary work.

BIBLIOGRAPHY OF REFERENCES

Chicago Millwork Supply Co.: _Price Book and

Specifications for Lumber and Millwork_, Chicago.

Gillette: _Handbook of Cost Data_, Myron C. Clark Co.,

New York.

Gordon-Van Tine Co.: _Price Book and Specifications for

Lumber and Millwork_, Davenport, Iowa.

Griffith: _Essentials of Woodworking_, Manual Arts

Press, Peoria, Ill.

Hodgson: _Modern Carpentry_, Frederick J. Drake Co.,

Chicago.

Hodgson: _Practical Uses of the Steel Square_,

Frederick J. Drake Co-., Chicago.

Kidder: _Architects' and Builders' Pocket Book_, John

Wiley and Sons, New York.

Kidder: _Building, Construction and Superintendence_,

Wm. T. Comstock, New York.

Radford: _Cyclopedia of Building Construction_, Radford

Architectural Co., Chicago.

Radford: _Details of Building Construction_, Radford

Architectural Co., Chicago.

The National Hardwood Lumber Association: _Rules for

Measurement and Inspection of Hardwood Lumber_, McCormick Bldg.,

Chicago.

INDEX

(NUMBERS REFER TO PAGES)

A

American Bond 20

Anchor, Brick Wall 139

Angle Post 118

Apron 109

Architrave 109

Ashlar 20

B

Backing Hip Rafter for Square

Cornered Building 63

Octagon and Other Hips 80

Balloon Frame 27

Base Block 109

Blocks, Placing 128

Mould 109

Mould, Placing 129

Batter Boards 15

Bed Moulding 98

Belt Course 110

Bibliography of Reading References 183

Blind Stop 109, 138

Board Measure Table 169

Bonds, Masonry 20

Brick Walls 20

Contents Table 172

Bridging 32

Building Paper 95, 98

C

Casing 109, 138

Casings, Placing 128

Chalk Line 103

Common Rafter 74

Concrete Mixtures 19

Corner Boards 109

Board, Splicing 102

Posts 38, 39, 109

Cornice 98

Costs, by Percentages 156

Example of Form 154

Counter Flashing 107

Cove 118

Crown Moulding 98

D

Deck 94

Door, Fitting 130

Frame 137

Hanging 129

Hinging 131

Jambs, Setting 125

Parts Named 129

Sill 109

Trim, Placing 127

Drain Tile 24

Drip Cap 109, 138

"Duck" 127

E

End Cut of Common Rafter 55

of Hip and Valley Rafter 62

of Octagonal and Other Hips and Valleys 79

English Bond 20

Estimating 142

Brick Work 180

Estimating Cement Mortar 179

Concrete 178

Cubic-foot Unit 142

Excavations 178

Labor Costs, Carpentry 150

Lathing 182

Lumber Quantities 146

Millwork Quantities 149

Painting 182

Plastering 181, 182

Quantities of Nails 153

Slate Roof 181

Excavations 18

Exterior Wall Coverings 95

F

Fascia 98

Finish Floor 109

Finishing Exterior Walls 108

Flashing 105

Flemish Bond 20

Floors, Laying and Scraping 135

Footings 18

Forms for Concrete 23

Foundations 18

Laying out 13

Foundation Materials 19

Frames, Basement 25

Framing Common Rafter 49

Joists 31

Roof about Chimney 94

Square with Rafter Table 53

Table for Common and Jack Rafters 52

Frieze 98

Full Frame 27

Furring 109

G

Girders 29, 31

Grade Line 16

Grading Rules, Lumber 143

Griffith's Roof Framing Tables 72

Griffith's Tables, Directions for 173

Grounds 115

H

Half-frame 27

Headers 20, 35, 109

Headroom 119

Hip and Valley Rafter End Cut 62

and Valley Rafter Lengths 61

and Valley Rafter Plumb Cut 60

and Valley Rafter Seat Cut 62

and Valley Rafters for Octagon

and other Polygons 74

and Valley Rafter Side Cut 60

Rafter, Unit Lengths 59

I

Interior Finish 115, 125

Walls 117

Interpolation 164

J

Jamb 109, 138

Jack Rafter for Octagonal and

Other Polygonal Roofs 81

for Square Cornered Building 65

K

King-Post 78

L

Lap Siding 111

Lathing 115

Length and Number of Wire Nails

to the Pound 168

Length of Common Rafter 50, 54

of Hip and Valley Rafters 61

of Jacks for Square Cornered Building 66

Length of Octagon and Other Polygonal Jacks 82

of Rafter by Scaling 53

of Side of Polygon 73

Leveling Door Sill 110

Foundation 16

Rod 14

with Straight-edge 17

Lintels 141

Locks, Fitting 132

Lookout 98

Lookouts, Framing 99

M

Main Frame 27

Masonry Construction, Woodwork for 138

Miter Cuts of Plate 69

N

Natural Trigonometric Functions 158

Nosing 118

O

Octagonal and Other Jacks 81

Roofs 73

Octagon Bay, Framing 85

Openings in Framework 42, 94

P

Parting Strip 109, 138

Partition 38

Wall Detail 116

Patterns for Joists and Studding 38

Pier 123

Pitch 46

Pitch Board 120

Placing Joists 32, 41

Plancher 98

Plank Frame 27

Plates 41, 98

Platform, Stair 118

Plumb Cut of Hip and Valley Rafter 60

of Octagonal Hip and Valley Rafters 74

Porches 122

Porch Steps 117

Protractor, Framing with 82

Pulleys 138

Pulley Stile 109, 138

R

Raked Moulding 100

Reduction for King-post 79

for Ridge 57

Ribbon Boards 39

Ridge, Length of 56

Piece 57

Rise 46

Rise of Stair 119

Riser 118, 121

Roof Boards, Cutting of 95, 96, 98

Frame 45

Frame, Any Polygon 69

Framing 45

Framing Terms 46

Rough Floors 42, 109

Rubble Work 20

Run 45

Run of Stair 119

S

Sash Cord 127

Scaffolding 96

Scribing Against Irregular Surface 114

Seat Cut of Common Rafter 55

of Hip and Valley Rafter 62

of Octagonal and Other Hips and Valleys 79

Setting Basement Frames 25

Setting Partitions 41

Studs 40

Window Frames 110

Sheathing or Sheeting 95, 98

Shed Roof Framing 89

Shingling 102

Hips and Valleys 105

Shingle Tins 106

Shoe Mould 109

Placing 129

Side Cut, Hip and Valley Rafters 60

Octagonal and Other Hips and Valleys 75

of Jack Rafter 65

of Octagonal and Other Polygonal Jacks 81

Siding 111

Circular Tower 113

Hook 113

Stick 111

Sills 29, 31, 109, 138

Six-eight-ten Method 15

Sole Piece 109

Solution of Right Triangles 159

Spacing Joists 32

Stair Building 117

Types 118

Stirrups 36

Stock Bill Form 149

Stone Work 20

Stool 109

Stop Bead 109, 138

Story Pole 42

Straightening Studding 117

Strength of Materials 170

Stretchers 20

Stringer 118

T

Table for Hip and Valley Rafters 60

of Common and Jack Rafters 52

Table of Fractional Equivalents

for Decimal Values 166

of Natural Functions 163

of Octagonal Hip and Valley Rafters 75

Tail, Rafter 56

Tangents 69

Threshold 109

Toe Hold 104

Transit 13

Translating Framing Problems from Protractor

to Framing Square and Vice Versa 84

Tread 118, 121

Trimmers 35

U

Uneven Pitch of Roof 90

Useful Tables 166

V

Valley Rafters 65

Rafter Unit Lengths 58

Value of a Function, The Angle Being Given

in Fractional Degrees 164

of Angle, The Value of a Function Being

Known 164

Veneer, Brick 138

W

Wall Board 121

Walls 38

Water Proofing 24

Table 109

Weight Pocket 109, 138

Well Hole 36

Winders, Stair 118

Window Detail, for Brick Wall 140

Frames 137

Sash, Fitting 126

Window Sill 109

Stool 109

Trim, Placing 127

Wire Brads, Table for 169

Wood and Machine Screw, Sizes, Table of 167

Wooden Bricks 26

Wood's Key to the Steel Square 70

Y

Y-level 14

Yoke 109

* * * * *

Transcriber Note

A link to the Index was added to the Contents table.

Carpentry · 第 4 / 4 章