CHAPTER V

Exterior Covering and Finish

=49. Sheathing or Sheeting.=--After the frame work of a building

is erected and the openings made in the frame for windows and doors,

the sheeting is to be placed. Sheeting is placed either horizontally

across the studs or diagonally, sometimes both ways, depending upon

the specifications of the architect. The diagonal is somewhat stronger

but is more expensive. The horizontal is satisfactory upon ordinary

frame dwellings, especially where the building is braced at the corners

by studs cut in diagonally, or by sheeting placed diagonally at the

corners as in Fig. 90. Such sheeting should be matched and well nailed

with two 8d nails to each stud. Building paper should be placed upon

the sheeting to further protect the interior from cold.

[Illustration: Fig. 90. Sheathing]

Roof sheeting for shingle roofs may best be of unmatched boards spaced

about 2" apart. For slate, matched stock should be used and this

covered with a tar or asphalt paper.

[Illustration: Fig. 91. Setting T-bevel for Roof Boards]

In making the face cut on roof boards for hips or valleys the framing

tool or the T-bevel may be made use of, being set to the complement of

the angle used in making the side or cheek cut on jack rafters. The

complement angle in this case equals 90 less the angle of the side cut

of jack. Or, if the framing square is to be used, the same numbers

used in making the side cut of the jack will be used in laying out the

face cut of roof boards, with the scribing being done along the tongue

instead of along the blade as in the case of the side cut.

A second T-bevel may be set as in Fig. 91, the beam being placed across

the edge of the jack and at right angles to it, with the blade adjusted

to the cheek or sawed surface of the jack which is to fit against hip

or valley rafter. A framing tool might be used.

Carpenters more frequently, however, get the angles for sawing roof

boards by laying the board to be cut out over the hip or valley rafter,

then sawing along the side the rafter as in Fig. 92.

In warm climates, weather boarding is often applied directly to the

studs, no sheeting being used; the frame being strongly braced at the

corners.

=50. Scaffolding.=--Cornice is placed after sheeting. To do this

advantageously it is necessary to erect scaffolding or staging. Fig.

93 illustrates a common type. Stock 2" × 4" is used for the uprights,

and 1" × 6" for the horizontal members and braces or stays. Planks

are placed upon these horizontals as shown. Fig. 94 illustrates a

substitute for staging, a scaffold bracket upon which planks are laid.

[Illustration: Fig. 92. Sawing Roof Boards]

[Illustration: Fig. 93. Scaffolding]

[Illustration: Fig. 94. Scaffold Bracket]

=51. Cornice.=--Cornices are generally classified as open or

skeleton, and box, Figs. 95 and 96. Each of these types will be found

constructed in almost endless variety of forms. The illustrations shown

will serve the purposes of this text. The student should familiarize

himself with the various common forms, details of which may be got from

any good, modern book on building details.

[Illustration: Fig. 95. Skeleton Cornice]

[Illustration: Fig. 96. Box Cornice]

In making the various cuts on cornice work, a miter-box must be

available for mouldings. The old type of wood miter box, with the

various necessary cuts laid out in its sides is satisfactory. Some

experimenting will be necessary upon the part of the beginner to

determine the manner of placing the moulding in the box to give the

correct cut.

The cuts for the plancher, which rests in the planes of a hipped roof

and which must be membered around a corner are determined in a manner

similar to that described for roof boards, Sec. 49, from the cuts of

the jack rafter cheeks.

[Illustration: Fig. 97a. Skeleton Cornice]

[Illustration: Fig. 97-b. Box Cornice.]

Fig. 97 illustrates the manner of "framing in" the lookouts on' gables

where a skeleton cornice is used. Also there is illustrated the manner

of placing lookouts in gables for a box cornice. Unless the cornice is

quite wide, these blocks are merely fastened to the underside of the

roof boards at intervals of 3 or 4 feet. The depth of these blocks will

depend upon the manner of framing the tail ends of the rafters.

Metallic gutters made to assume the form of the crown mould, no wood

crown mould being used, will be found in common use upon ordinary

house construction. A fall of ½ inch to every 10 feet is usually given

gutters.

=52. Raked Mouldings.=--In all cases where a moulding resting in

one plane, as crown or bed moulding at the eaves, is to be membered

with moulding swung up out of that plane, as up a gable, one of two

things must be done to make the surfaces of the mouldings match or

member properly at the joint: (1) The moulding at the eave may have

its top edge tipped forward until its top edge lies in the same plane

as the top edge of the corresponding gable moulding; (2) a moulding

with a new face may be worked which will member with the eaves moulding

when their reverse surfaces are fitted to the fascia or, in case of bed

moulding, to the frieze.

[Illustration: Fig. 98. Laying out Gable or Raked Moulding]

To member by means of the second method proceed as follows: (1) Make

a full sized drawing of a cross-section of the moulding, Fig. 98. (2)

Draw a number of lines thru the more important reference points of

the moulding at an angle equal to the pitch of the gable. (3) Draw

horizontal lines thru the points of reference and erect a perpendicular

thru these passing thru the back of the mould as _A-B_. (4) Lay

off a line _C-D_, Fig. 98, perpendicular to the oblique lines. (5)

Using the lines _A-B_ and _C-D_ as reference lines, transfer

the distances of the various points on the eaves moulding, measured

horizontally from _A-B_, to pitch lines measured obliquely. A

curve traced thru these points will give the shape of the moulding

required for the gable. Since this moulding would, in all probability,

have to be worked up especially for any particular job, this practice

is not followed except upon large or important work. Cornices are

usually designed so as to avoid such work.

[Illustration: Fig. 99. Miter Box for Raked Gable Moulding Cut at Eaves]

[Illustration: Fig. 100. Miter Box for Plumb Cut of Gable Mouldings]

Figs. 99 and 100 illustrate two miter-boxes constructed for use in

cutting rake mouldings in gables.

In making the miter cuts on mouldings of the eaves, the horizontal

members, no special box is needed. The moulding will be set on the

far side of the box, upside down. The box will have the side cuts

perpendicular to the top edge and the angles across the top edges

will be determined by the miter of the plate, sill, or corner of the

building. On a square cornered building this miter will be one of 45,

12" and 12" being taken on the square. Two cuts of each kind, but

reversed, are made in each box so that the moulding for each side of

each gable may be readily cut. On the octagonal building 5" and 12"

would be used in laying out the miter, with scribing done along the 5"

member of the square.

For the miter cuts of the rake or gable member, special boxes would

best be constructed. For the cut of the gable member where it joins

the eave moulding: (1) Lay off across the top of the miter-box, right

and left, the miter of the plate, sill, or corner of the building. (2)

Down the sides of the box lay off the slanting lines as shown in Fig.

99, at angles determined by the plumb cut of the common rafter. (3) Lay

the moulding in the box as indicated by the cross-section, Fig. 99,

being careful to keep the backs of the mouldings adjusted to the side

and bottom of the box. A good plan is to drive a nail or two in the

bottom of the box against which the moulding may be made to rest, once

the proper position is determined by trial.

For the plumb cut of the gable moulding, (1) lay off lines across

the edges of the box as in Fig. 100, using on the framing square the

numbers which give the plumb cut of the common rafter. Lay off a right

and a left cut as shown. (2) Square these lines down the sides of the

box and saw. (3) The moulding will be placed in the box as shown in the

cross-section view of Fig. 100, especial care being taken to have the

backs of the mouldings adjusted to the back of the box.

Manifestly, one box may contain all these cuts to advantage instead of

having three boxes.

These cuts, Figs. 99 and 100, serve in cutting the miters on ends of

the gable fascia. A little consideration will make clear the remaining

cuts upon ordinary cornice work.

In splicing mouldings, corner boards, etc., a mitered joint is best and

should be made so as to shed water from the joint, Fig. 101.

=53. Shingling.=--The reason for placing cornice before base or

window frames, etc., is to allow the workmen to work inside should

inclement weather overtake building operations at any time. Shingling,

therefore, will follow cornice work.

[Illustration: Fig. 101. Spliced Comer Boards and Moulding]

The amount of shingle to be exposed to the weather will depend in

general upon the pitch of the roof. In no case should this exposure

exceed 5 inches. The shingle most used is 16 inches long, and each

shingle should lap two courses beneath it. The usual amount of lay is

from 4" to 4%", by quarters. When nearing the ridge or comb of a roof

in shingling, the dimensions used on the main body of the roof should

be increased or decreased so as to make the final layer show under the

comb or ridge or saddle boards properly. The worker should begin such

calculations when within about four or five feet of the ridge so that

changes of exposure of the different layers may not be noticeable and

so that the line of shingle butts may be kept parallel with the ridge.

[Illustration: Fig. 102. Beginning Course]

The first layer of shingles should be a double one with joints properly

broken, and with the butts projecting over the crown moulding about 1½"

to 2". Lay the shingles at the gables first, then at intervals of about

ten feet. Stretch a chalk line between these fastening it to the butts

by shingle nails driven into the butts, Fig. 102.

The remaining courses may be laid by means of a straight-edge or by

means of a chalk line. Both practices have ardent advocates. Where

a straight-edge is used, it is usually a piece of lap siding or

clapboard, and is held in place by being lightly tacked.

[Illustration: Fig. 103. Shingling. Toe Hold]

In using the chalk line a man for each end is required. The line is

chalked and snapped for three courses at a time. The mechanic, after

a little practice, is able to keep the butts of the shingles straight

and to sight them so that they shall follow the chalk line mark. On

long courses a third person may be utilized in chalking and in laying

shingles. In chalking, this person holds the line to the roof as

sighted by an end man and the snapping is done on each half of the line.

The chalking of a line so as to conserve the chalk is one of the tricks

of the trade which must be mastered early. It consists in rotating

the chalk about its hemispherical axis while being worked backward and

forward along the line, the line being held between the chalk and the

ball of the thumb. Otherwise the line would soon sever the chalk.

[Illustration: Fig. 104. Shingling. Toe Holds]

Cut nails should be used in preference to wire nails because of their

greater rust-resisting quality. Dry shingles should not be laid tight

together, ⅛ inch between is not unusual with dry shingles. It is best

to split shingles over 10 inches wide before laying them. Each shingle

should have at least two nails, the average is two nails for every four

to six inches of shingle.

Scaffolding for roof work, or toe hold, is usually constructed by

nailing shingles to 2" × 4" as shown in Figs. 103 and 104. Other

forms are equally common. Apparently the holes left by the nails

used to fasten the toe hold to the roof would cause a leak in the

roof. To avoid any such danger, tho such danger is slight because

of the swelling of the wood fiber upon the application of moisture,

the shingles having such holes are driven down the roof slightly by

striking their surfaces a glancing stroke.

=54. Shingling Hips and Valleys; Flashing; Saddle or Comb

Boards.=--Hip and valley shingles are usually sawed to shape before

being taken to the roof, the face cut being the same as that used

across the face of the roof boards and plancher members intersecting

about a corner of a hipped roof where plancher lies in the plane of the

roof. The cut across the edge of such shingles is made square to the

face.

[Illustration: Fig. 105. Shingle Tins]

[Illustration: Fig. 106. Valley]

Of the many ways of protecting the intersection of hip shingles when

in place upon a roof, the simplest is that of employing tin shingles.

Such shingles should be of sufficient length to allow the corners to be

turned under as shown in Fig. 105, and still extend far enough under

the next course of shingles to permit the nails holding the tins to

be covered. It is not good practice to nail thru these tins after the

roof has been covered, that is, to place these tins after the roof has

been shingled because the action of the weather "lifts" the nails when

exposed thus.

Valleys are covered with a strip of metal to a width of 20 inches. Upon

steep roofs and short valleys this width may be reduced to 16 inches.

Space must be left between the edges of valley shingles as shown in

Figs. 106 and 107. The amount will depend upon the length of the valley

and the steepness of the roof. For a ½ pitch with a length of twelve to

fourteen feet of valley, the space at the top of the valley may well

be 1 inch to each side of the valley center line, widening gradually

toward the lower end to 2½ inches to each side. Chalk lines snapped

upon the tin or other metal forming the valley indicate the location of

shingle edges. Nails in valley shingles should be kept well back from

the valley edge of the shingles.

[Illustration: Fig. 107. Shingling Valley]

Flashing consists in placing tin shingles or other material about

the members making up a joint so that the joint shall "turn water."

Counterflashing consists in placing a double layer of tins in such a

way as to doubly insure turning water from a joint.

Fig. 108 is an illustration of flashing where shingles meet lap siding.

Shingle tins are forced under the siding on one side and either under

or over the shingles, several inches of lap being allowed all about.

Fig. 109 illustrates a counterflashed chimney. A layer of tins is

placed as in flashing against siding except their top edges are not

inserted. Over these tins a second layer is placed as shown, the

top edges being inserted ¾" between the layers of brick, the mortar

being raked out so that this can be done. These turned edges are held

in place by the insertion of a wedging nail or tack, after which

the cracks are filled with cement, or better, an elastic roofing

composition.

Tins should be carried high enough to prevent drifted snow from

entering; 2½ or 3 inches at the narrowest place.

[Illustration: Fig. 108. Flashing Fig. 109. Flashed and Counter-flashed]

Saddle or comb boards are of various forms. They are used to give the

ridge a finished appearance and to turn any water which might happen to

strike thereon; also to hold the last course of shingles in place. A

simple form is obtained by creasing to the appropriate angle a strip of

tin eight inches in width. Place this on the ridge and nail its edges

at intervals of 3 or 4 inches. Where boards are used, one board should

overlap the other and extend a half inch beyond to turn water from the

joint so made. Galvanized ridge rolls may be purchased in stock styles.

=55. Finishing Exterior Walls.=--With the roof completed, side

walls are next covered except where porches are to be attached.

Fig. 110 illustrates the manner of constructing an exterior wall having

a water table and lap siding, also the relation of the various parts of

an exterior wall.

[Illustration: Fig. 110-b. Exterior Wall Detail]

A belt course is sometimes used between the first and second stories of

a building. Such a course is often constructed like the water table.

Like the water table or base, this belt course is furred out in order

to throw the course into greater relief. In case this furring is not

done, the lower edge of the belt board must be rabbeted to receive

the top edge of the siding. Frieze boards, too, are frequently furred

instead of being rabbeted. More elaborate belt courses are common.

Building paper should be stripped about the openings for doors and

windows before the frames are set, to insure warmth; also about corner

boards and cornice.

Corner boards and casing edges should be very slightly beveled so that

the siding may take a slight squeeze as it is placed. Care in setting

frames and in making casing edges true will insure a saving of time in

placing siding.

=56. Setting Window and Door Frames.=--Two men usually work

together in setting frames, as in fact they do on much other carpentry

work. In setting door frames on outer walls (1) the rough floor, etc.,

must be cut away so that the top of the sill may rest on a level with

finished floor when that is in place. (2) When this is done the door

sill is carefully leveled, Fig. 111, and shingle points inserted under

the sill where needed to give solidity and support. (3) The casing is

given a nail close to the sill at each side of the frame and (4) the

sides of the jambs, are plumbed and the casings finish nailed. If the

work is carefully done the frame should be square.

[Illustration: Fig. 111. Leveling Door Sill]

Where heads of several windows are a given distance from the floor,

a stiff stick may be cut this length and used in placing windows in

position for height. The window sills will be leveled as are door

sills; the jambs are plumbed, Fig. 112, and casings nailed at intervals

of about a foot.

[Illustration: Fig. 112. Plumbing Frame]

[Illustration: Fig. 113. Using Siding Stick]

=57. Siding.= Preparatory to siding, a siding stick should be

made. Such a stick is made by planing parallel edges upon a piece of

Y% inch stock about 1 inch in width. Upon this stick marks will be

made which will indicate the spacing of the siding; these marks being

transferred to corner boards and casing edges, Fig. 113. To lay off

this stick a given space is taken, water table drip cap to the lower

edge of a window sill for example. (1) This space may be transcribed

upon the stick easiest by setting the stick upon the drip cap and

against the casing edge, marking under the sill upon the stick. (2)

This space is "stepped off" by means of a pair of dividers set to the

amount of exposure desired. Exposures will run from 4¼ to 4¾ inches on

ordinary lap or bevel siding. (3) Should there be a remainder, and

there almost always is, the exposure must be increased or decreased,

whichever is necessary, an amount sufficient to give an equal or even

number of divisions. In practice this amount is found by stepping off

as suggested and then making necessary adjustments by guess and again

stepping. This is continued until the desired result is attained. The

difference is thus divided equally over the whole space instead of over

the last courses as in shingling.

[Illustration: Fig. 114. Marking Length of Siding Fig. 115. Using

Siding Hook]

In a similar manner a stick, or another space of the same stick is

laid off and stepped for the space between the bottom of the window

sill and the top of the drip cap above the head casing of the window,

etc. On long lateral spaces this stick will be used to keep the lower

edges of the boards in position between the casings, by transferring

its marks to the building paper, stepping down from one of these marks

with a pair of dividers to the lower edge of the siding board being

placed. (4) A bunch of siding boards should have one end of each sawed

square across the face, but sawed under on the back side slightly so

as to insure a fit on the surface. (5) One end is next fitted, with

block plane if necessary, after which (6) the length is marked by

turning the board upside down and marking on the lower edge of the

board, which is uppermost, with a knife, Fig. 114. Another way to mark

length is indicated in Fig. 115. This tool is called a siding hook or

tool and this method possesses the advantage of caring for any lack of

squareness in the frame or trim.

In nailing, care must be taken to place the nail so that it shall pass

thru both boards where lapped. Under windows it will be necessary to

trim off part of the upper edges of the siding boards. Saw kerfs at

either side of the part to be cut, and a sharp, deep knife scoring

along a straight-edge should be used to outline the part to be removed.

To determine the amount to be removed, set the dividers to the amount

of spacing used for the boards in the space under the window, plus the

depth of rabbet, or groove in the under side of the window sill into

which the upper edge of the siding board must fit. Set off this amount

on the siding board from the butt or under edge at each end of proposed

cut, and connect with straight-edge; scoring with knife.

[Illustration: Fig. 116. Siding Circular Tower]

Occasionally the carpenter is called upon to side a circular tower or

rounded corner of a building. That the lower edge of each board may

rest in a horizontal plane it will be necessary to shape that edge

before applying the board to the side of the building. To determine

the amount of curvature to give such an edge proceed as follows: (1)

Plot a curve to represent the plan of the tower, Fig. 116. Draw this

upon a scale sufficiently large and make use of accuracy such as

will insure a result equal to the requirements of the occasion. (2)

Draw the line _A-B_ of indefinite length. (3) Place a section

of a clapboard in the position it will have on the sheeting, as at

_abc_, Fig. 116, and (4) extend a line along the face surface to

meet _A-B_. (5) With a radius equal to _B-C_ describe an arc

with _B_ as a center which shall cut the siding board as shown,

taking an equal amount off the edge at each end.

Occasionally it becomes necessary to fit a casing against a sided

wall. This casing is scribed as indicated in Fig. 117, a pair of sharp

dividers being made to follow the contour of the wall with one point

while the other marks or scribes the casing. A saw will be used to cut

to these lines, sawing under slightly to insure a fit at the face.

[Illustration: Fig. 117. Scribing against Irregular Surface]