Offsets and molding decorations were easily made, although they were

quite numerous on the building in question, at least more so than would

ordinarily be the case in mill building construction. The offset of 1

ft. at every column was made very readily by sliding wooden shoulder

pieces into place on the inner face of the form, which pieces in turn

received 2-in. faced planking, the latter being slid into place from

above. Thus the entire system was collapsible and small alterations were

easily made whenever the form was shifted. Flat surfaces or offsets

could be obtained at will by either removing or setting in the shoulder

pieces. Molding effects were made on the front face of the wall by

tacking molding strips to the form wherever necessary. The entire work

was done with common labor and the finished building presented a smooth,

homogeneous surface which required very little dressing.

[Illustration: Fig. 237.--Details of Cantilever Girders for Mezzanine

Floor for Four-Story Garage.]

~FLOOR AND ROOF CONSTRUCTION FOR FOUR-STORY GARAGE.~--The building was

53×200 ft., and 4 stories high, with provision for 2 additional stories

in the design of footings and columns. Two rows of wall columns

connected by transverse girders carrying the floor and roof slabs made a

comparatively simple construction, except for a mezzanine floor carried

on cantilever beams and except for the use of cantilever footings;

these two special details are shown by Figs. 236 and 237. The amount of

concrete in the building was 1,910 cu. yds., distributed as follows:

Cu. yds.

Footings, reinforced 190

Columns, reinforced 450

Floors and roof, reinforced 1,100

Floor on ground, not reinforced 170

-----

Total 1,910

The amount of reinforcing metal used was 237 tons, distributed as

follows:

Item. Tons. Lbs. per cu. yd.

Footings 42 442

Columns 20 90

Floors and roof 175 318

--- ---

Total and average 237 272

This is equivalent to 2 per cent. of steel in 1,910 - 170 = 1,740 cu.

yds.

_Forms._--The total area of concrete covered by forms (1,740 cu. yds.)

was 94,000 sq. ft., distributed as follows:

Footings, sq. ft. 4,000

Columns, sq. ft. 20,000

Floors and girders, sq. ft. 70,000

------

Total, sq. ft. 94,000

For the work 50,000 ft. B. M. of old lumber was used and 170,000 ft. B.

M. of new lumber was bought, the cost being as follows:

50 M. ft. B. M. at $13 per M. $ 650

170 M. ft. B. M. at $26 per M. 4,420

------

220 M. ft. B. M. at $23 $5,070

This is equivalent to 126 ft. B. M. per cu. yd. of concrete. New forms

were made for each floor except the sides of the girder molds which were

re-used so far as they would fit, but the roof forms were made from

lumber used for the floors. In all no more than 20 per cent of the form

lumber was used a second time. In round figures new lumber was required

for 80,000 sq. ft. of concrete; this gives a cost for lumber of 6.4 cts.

per sq. ft. The construction of the column and floor forms is shown by

Fig. 238. A force of 15 carpenters at $4.40 per day under a foreman at

$35 per week erected and tore down forms; the carrying was done by

laborers at $1.70 per day working under a foreman at $35 per week;

carpenters worked an 8-hour and laborers a 10-hour day. Forms for one

floor were framed and erected in 8 to 10 days. The cost of forms for

1,740 cu. yds. and 80,000 sq. ft. of concrete and per M. ft. B. M. was

as follows:

Item. Per cu. yd. Per sq. ft. Per M. ft.

Lumber $2.90 $0.064 $23.00

Framing, erecting and removing. 2.00 } 15.67

} 0.057

Handling lumber 1.10 } 8.70

----- ------ ------

Totals $6.00 $0.121 $47.37

[Illustration: Fig. 238.--Column and Floor Forms for Four-Story Garage.]

The lumber had a considerable salvage value which is not allowed for in

the above figures.

_Concrete._--The concrete was a Portland cement, ¾-in. trap rock

mixture, mixed wet in two Chicago Improved Cube Mixers equipped with

charging buckets. The mixers were located on the ground floor, one at

the rear and one at the front of the building, both discharging directly

to a hoist. With a gang of 30 men at $1.70 per 10-hour day under a

foreman at $35 per week a floor was concreted in 2 days, the columns

being concreted the first day and the floor being concreted the second

day. The labor cost for mixing and placing concrete and for fabricating

and setting reinforcement was as follows:

Item. Per cu. yd.

Mixing and placing concrete $1.95

Erecting and setting steel 2.05

-----

Total $4.00

The cost of concreting includes the cost of granolithic surface for the

floor slabs. The girder reinforcement was made up into unit frames and

the frames were set as a unit, horses set over the molds being used to

suspend and lower them into place. The cost of $2.05 per cu. yd. is

equivalent to ¾ ct. per lb. Summarizing, we have the following cost for

materials and labor on forms and for labor mixing and placing concrete

and reinforcement:

Per cu. yd.

Lumber for forms $ 2.90

Labor on forms 3.10

Labor on concrete 1.95

Labor on steel 2.05

-----

Total $10.00

This $10 total does not include the cost of the concrete nor of the

steel.

CHAPTER XX.

METHOD AND COST OF BUILDING CONSTRUCTION OF SEPARATELY MOLDED MEMBERS.

This chapter deals exclusively with the methods and cost of molding and

erecting separately molded wall blocks, girders, columns and slabs. The

structural advantages and disadvantages of this type of construction as

compared with monolithic construction will not be considered. The data

given in succeeding paragraphs show how separate piece work has been

done and what it has actually cost to do it in a number of instances.

~COLUMN, GIRDER AND SLAB CONSTRUCTION.~--European engineers have developed

several styles of open web or hollow girder and column shapes, but in

America solid columns and girders have been used except in the

comparatively few cases where one of the European constructions has been

introduced by its American agents.

~Warehouses, Brooklyn, N. Y.~--In constructing a series of warehouses in

Brooklyn, N. Y., the columns and girders were molded in forms on the

ground. For molding the columns, forms consisting of two side pieces and

one bottom piece, were used, saving 25 per cent. in the amount of lumber

required for a column form, and doing away with yokes and bolts, since

only simple braces were required to hold the side forms in place. It was

found that the side forms could readily be removed in 24 to 48 hours,

thus considerably reducing the time that a considerable portion of the

form lumber was tied up. It was figured by Mr. E. P. Goodrich, the

engineer in charge of this work, that this possible re-use of form

lumber reduced the amount required another 50 per cent. as compared with

molding in place. Girders were molded like columns in three-sided forms;

the saving in form work was somewhat less than in the case of columns,

but it was material. In general, Mr. Goodrich states, the cost of

hoisting and placing molded concrete members is higher per yard than

when the concrete is placed wet. That is in mass before it is hardened.

[Illustration: Fig. 239.--Sketch Showing Forms and Reinforcement for

Visintini Girder.]

~Factory, Reading, Pa.~--In constructing a factory at Reading, Pa., an

open or lattice web type of girder invented by Mr. Franz Visintini and

extensively used in Austria was adopted; columns were molded in place in

the usual manner with bracket tops to form girder seats. The girders

were reinforced with three trusses made up of top and bottom chord rods

connected by diagonal web rods; one truss was located at the center of

the beam and one at each side. The method of molding was as follows: The

trusses were made by cutting the chord rods to length and threading the

web diagonals and verticals onto them. To permit threading the web

pieces were bent, when rods were used, with an eye at each end; when

straps were used the ends were punched with holes. The work was very

simple and was done mostly by boys in the machine shop of the company

for which the building was being erected. The girders were molded two at

a time in forms constructed as shown by the sketch. Fig. 239. A form

consisted of a center board, two side boards, two end pieces and the

proper number of cast iron cores, all clamped together by three yokes.

Triangular cast iron plates, A, were screwed to the bottom boards for

spacers. The side, center and end boards were then set up and the end

clamps were placed. The cast iron hollow cores, B, were then set over

the spacers, and the form was ready for pouring. A layer of concrete was

placed in the bottom of the mold and the first side truss was placed;

the concrete was then brought half way up and the middle truss was

placed; concreting was then continued up to the plane of the second side

truss which was placed and covered. Cores and forms were all cleaned and

greased each time they were used. The cores were removed first by means

of a lever device and generally within three or four hours after the

concrete was placed. The remainder of the form was taken down in two to

four days and the beam removed.

~Kilnhouse, New Village, N. J.~--In constructing a kiln house for a cement

works one story columns with bracket tops and 50-ft. span roof girders

were molded on the ground and erected as single pieces. The columns by

rough calculation averaged about 2 cu. yds. of concrete and 675 lbs. of

reinforcement each or about 337 lbs. of steel per cubic yard. The

girders averaged by similar calculation 5 cu. yds. of concrete and 2,260

lbs. of steel, or 452 lbs. per cubic yard of concrete. The average

weight of columns was thus not far from 41.3 tons and of girders fully

11 tons.

[Illustration: Fig. 240.--Arrangement for Molding Ten Single-Bracket

Columns.]

Several combinations of arrangements were used for molding the columns

and girders. For wall columns having one bracket the arrangement shown

by Fig. 240 was adopted. The concrete slab molding platform was covered

with paper, and on this the two outside and the middle columns were cast

in forms. When those columns had set the forms were removed, the

intervening spaces were papered and the two remaining columns were cast.

Ten columns, five sets of two columns in line, were cast on each base.

The remaining columns were cast in combination with girders as shown by

Fig. 241. The two outside lines of columns (1) were molded in forms,

allowed to stand until set and then stripped. Using a column surmounted

by a shallow side form for one side and a full depth side form for the

other side molds were fashioned for the two outside girders, Nos. 2 and

3. One full depth side form and the side of girder No. 2 formed the mold

for girder No. 4. Girder No. 5 was then molded between girders No. 3 and

No. 4.

[Illustration: Fig. 241.--Arrangement for Molding Four Four-Bracket

Columns and Four Roof Girders]

[Illustration: Fig. 242.--Forms for 50-ft. Roof Girders.]

The construction of the girder forms is shown by Fig. 242. This drawing

shows one of the four main sections making up a complete form. A full

size form of this construction contained about 1,100 ft. B. M. of

lumber, and three were built, so that 3,300 ft. B. M. of form lumber

were used for molding 20 girders, or 33 ft. B. M. per cubic yard of

concrete. A full size column form contained about 225 ft. B. M. of

lumber, and eight were constructed, so that 1,800 ft. B. M. of form

lumber were used for molding 56 columns, or about 16 ft. B. M. per cubic

yard of concrete.

The following was the cost of erecting a full column form including

lining, plumbing, bracing and yoking, but excluding lumber and original

construction:

1 carpenter, 3 hrs., at $0.25 $0.750

1 helper, 3 hrs., at $0.175 0.525

1 helper, 1 hr., at $0.175 0.175

1-5 boss carpenter, 3 hrs., at $0.30 0.180

------

Total $1.630

This gives a cost of $7.25 per M. ft. B. M. for erecting column forms.

The cost of erecting a full size girder form including lining, plumbing,

bracing and setting six bolts was as follows:

2 carpenters, 5 hrs., at $0.25 $2.50

2 helpers, 5 hrs., at $0.175 1.75

2 laborers, ½ hr., at $0.15 0.15

¼ boss carpenter, at $0.30 0.375

------

Total $4.775

This gives a cost of $4.35 per M. ft. B. M. for erecting girder forms.

The reinforcement was erected inside the forms for both columns and

girders. The cost of erection for one column was:

2 laborers, 4 hrs., at $0.15 $1.20

1/3 foreman, 4 hrs., at $0.225 0.30

-----

Total $1.50

This gives a cost of about 0.22 cts. per pound for erecting column

reinforcement, including the bending of the horizontal ties or hoops.

The girder reinforcement was erected by piece work at a cost of $1.80

per girder--or about 0.08 ct. per pound.

The concrete used was a 1-6 mixture of Portland cement and crusher run

stone all passing a ½-in. sieve and 10 per cent. passing a 200 mesh

sieve. No trouble was had in handling this fine aggregate. It was mixed

in a Ransome mixer, elevated so as to deliver the batches into cars on a

standard gage track. This track ran between the base slabs on which the

molding was done. Each car held about 3 cu. yds. and discharged through

a side gate and spout directly into the forms, the mixture being made so

wet that it would flow readily. The company used its own cement and

stone for concrete and charged up the cement at $1 per barrel and the

stone at 60 cts. per cubic yard. At these prices, and assuming that a

cubic yard of concrete of the mixture above described would contain

about 1.25 bbl. of cement and 1.5 cu. yd. of stone, we have the

following cost of materials per cubic yard of concrete:

1.25 bbls. of cement, at $1 $1.25

1.5 cu. yds. stone, at $0.60 0.90

-----

Total $2.15

The actual cost of mixing the concrete and delivering it to the cars was

as follows:

Item. Per cu. yd.

1 foreman, at 20 cts per hour $0.0300

3 men shoveling stone, at 15 cts. per hour 0.0675

3 men filling hopper, at 15 cts. per hour 0.0675

1 man bringing cement, at 18 cts. per hour 0.0225

1 man dumping cement, at 15 cts. per hour 0.0225

9 h.p., at ½ ct. per h.p. hour 0.0450

Superintendence, repairs, etc. 0.0270

-------

Total $0.2820

The cost of hauling the concrete from mixer to forms ran about 2.7 cts.

per cubic yard, so that we have a cost for concrete in place of:

Concrete materials, per cu. yd. $2.150

Mixing concrete, per cu. yd. 0.281

Hauling concrete, per cu. yd. 0.027

------

Total cost, per cu. yd. $2.458

The cost, then, per column or girder molded, assuming that it was

necessary to erect a full form, was about as follows:

Columns:

2 cu. yds. concrete, at $2.46 $ 4.92

675 lbs. steel, at 2½ cts. 16.77

Erecting steel, at 0.22 ct. per lb. 1.50

Erecting forms 1.63

------

Total $24.82

Girders:

5 cu. yds. concrete, at $2.46 $12.30

2,260 lbs. steel, at 2½ cts. 56.50

Erecting steel, at 0.08 ct. per lb. 1.80

Erecting forms 4.77

-----

Total $75.37

[Illustration: Fig. 243.--View Showing Method of Hoisting Molded

Columns.]

These figures give a unit cost of $12.41 per cu. yd. for molded columns,

and of $15.07 per cu. yd. for molded girders, The columns were erected

by a Browning locomotive crane, which lifted and carried them to the

work and up-ended them into place. To facilitate lifting the columns

from the molding bed a 1½-in. pipe 8 ins. long was cast into both ends;

pins inserted into these sockets provided hitches for the tackle. The

column was lifted off the molding bed and blocked up, then iron clamps

were attached, one at each end, as shown by Fig. 243. A gang of 1

foreman and 14 men erected from 5 to 7, or an average of 6 columns per

10-hour day. The average wages of the erecting gang were 21 cts. per

hour. The cost then of column erection was (14 × $2.10) ÷ 6 = $5.25 per

column, or $2.63 per cu. yd. of concrete.

[Illustration: Fig. 244.--Sketch Showing Sling for Erecting 50-ft. Roof

Girders.]

The roof girders had 1-in. eye-bolts 24 ins. long cast into them

vertically about 4 ft. from the ends. They were lifted off the molding

bed by tackle by the locomotive crane to these eye-bolts and blocked up

to permit the adjustment of the sling. This sling is shown by the

sketch, Fig. 244, and as will be observed acts as a truss. At first it

was used without the vertical, but the cantilever action of the

unsupported ends caused cracks. The girders were loaded onto cars by the

locomotive crane and taken to the work, where they were hoisted and

placed by a gin pole. The girder erecting gang consisted of 1 foreman

and 14 men, working a 10-hour day at 21 cts. per hour. This gang erected

four girders per day, at a cost of (15 × $2.10) ÷ 4 = $7.87 per girder,

or $1.57 per cu. yd. of concrete.

The cost of girders and columns in place was thus about as follows:

Columns: Per unit. Per cu. yd.

Molding $25.00 $12.50

Erecting 5.25 2.63

------ ------

Totals $30.25 $15.13

Girders:

Molding $75.00 $15.00

Erecting 7.87 1.57

------ ------

Totals $82.87 $16.57

[Illustration: Fig. 245.--View Showing Method of Handling Roof Slabs.]

In this same building the roof was composed of 12×6¼ ft.×4-in. slabs

molded in tiers; a slab was molded and when hard was carpeted with paper

and the form moved up and a second slab molded on top of the first. This

operation was repeated until a tier of slabs had been molded. By molding

each slab with a 3-in. overlap, as shown by Fig. 245, they could be

easily separated by lifting on hooks inserted under the overhanging

ends. Each slab contained 0.925 cu. yd. of concrete and about 116¾ lbs.

of reinforcement. The cost of molding one roof slab, including

materials, forms and labor, was as follows:

Materials: Per slab. Per cu. yd.

1 bbl. cement, at $1 $1.000 $1.081

1.06 tons stone, at $0.60 0.636 0.687

116¾ lbs. steel, at 2¼ cts. 2.647 2.862

------ ------

Total $4.283 $4.630

Forms:

Lumber and making $0.104 $0.112

92 sq. ft. paper, at 33-1/3

cts. per 500 sq. ft. 0.055 0.059

Labor erecting and removing 0.5625 0.608

------- ------

Total $0.7215 $0.779

Mixing, Hauling and Placing:

Mixing $0.222 $0.240

Hauling 0.025 0.027

Placing concrete and steel 0.170 0.183

------ ------

Total $0.417 $0.450

General Expenses:

Housing and heating $0.700 $0.757

Superintendence, power, etc. (10%) 0.612 0.661

------ ------

Total $1.312 $1.418

Grand totals $6.7335 $7.277

The roof slabs were raised from the casting beds by means of the

locomotive crane and hooks, as shown by Fig. 245, and loaded onto cars;

eight slabs made a carload. The cars were run to the work, where the gin

poles hoisted the slabs one at a time to cars running on a track built

on timbers laid on top of the roof girders. A small derrick on rafters

picked the slabs from the hand car and set them in place. A gang of 15

men erected from 18 to 20 slabs per 10-hour day. With average wages at

21 cts. per hour the cost of erection was (15 × $2.10) ÷ 19 = $1.66 per

slab, or $1.79 per cu. yd. The total cost of slabs in place was thus:

Item. Per slab. Per cu. yd.

Molding $6.73 $7.27

Erecting 1.66 1.79

----- -----

Total $8.39 $9.06

In studying these cost figures their limitations must be kept in mind.

Because of the character of the available data quantities had in several

cases to be estimated from the working drawings. The cost of lumber for

and of framing column and girder forms is not included, but this is

partly balanced at least by the assumption that each form was erected

complete for each column and girder, which was not the case, as has been

stated. Cost of plant is not included nor is cost of shoring the columns

until girders and struts were placed, nor are several minor

miscellaneous items.

~HOLLOW BLOCK WALL CONSTRUCTION.~--Three general processes of molding

hollow wall blocks of concrete are employed: (1) A dry mixture is

heavily tamped into a mold and the block is immediately released and set

aside for curing; (2) a liquid is poured into molds, where the block

remains until hard: (3) a medium wet mixture is compressed into a mold

by hydraulic presses or other means of securing great pressure. The

molds used may be simple wooden boxes with removable sides or mechanical

molds of comparative complexity. Generally mechanical molds, or concrete

block machines as they are commonly called, will be used. There are a

score or more kinds of block machines all differing in construction and

mode of operation. None of them will be described here, but those

interested may consult "Concrete Block Manufacture" by H. H. Rice or

"Manufacture of Concrete Blocks and Their Use in Building Construction"

by H. H. Rice, Wm. M. Torrance and others.

~Factory Buildings, Grand Rapids, Mich.~--The buildings ranged from one to

four stories high and altogether occupied some 74,000 sq. ft. of ground.

The owners installed a block making plant fully equipped with curing

racks, two Ideal machines, two National concrete mixers, 5 h.p. gasoline

engine, platens, tools and a Chase industrial railway.

The walls were constructed of 24-in. square pilasters of blocks arranged

as shown by Fig. 246, connected by curtain wall belt courses of single

blocks. The blocks were 8×8×16 ins., and after molding the faces were

bush hammered and the edges tooled. The pilasters, consisting of four

blocks laid around an 8×8-in. hollow space, were solidified by pouring

the 8×8-in. space and all but the three outside block cavities with wet

concrete. The interior of the building was of regulation mill

construction, and as the pilasters reached the heights for beam supports

cast iron plates with downward flanges were set in the concrete. These

plates had a cast pin projecting upward to fasten the beam end.

[Illustration: Fig. 246.--Concrete Block Pilaster for a Factory

Building.]

The materials used for the block were Sandusky Portland cement and ¾-in.

bank gravel well balanced from fine to coarse. The blocks were molded

with 1-3 mortar faces, the mortar being waterproofed by a mixture of

Medusa waterproofing compound. All concrete was machine mixed. The men

operating the block machines were paid 1 ct. for each block molded, so

that their pay depended upon the energy with which they worked. The men

handling materials and engaged in handling and curing the blocks were

paid $1.75 per day. The gravel was shoveled from the railway cars onto

the screens and from the screen piles to the mixers. The gang was

organized as follows:

Item. Per day.

8 men handling materials, at $1.75 $14.00

5 men operating molds, at 1 ct. per block 15.00

1 man mixing facing mortar, at $1.75 1.75

2 men loading blocks onto trucks, at $1.75 3.50

2 men unloading blocks from trucks, at $1.75 3.50

3 men sprinkling blocks, at $1.75 5.25

------

Total, 21 men molding and curing blocks $43.00

The average daily run was 1,500 blocks, or 300 blocks per machine.

This output was easily maintained after the gang got broken in;

sometimes it ran higher and sometimes lower, but the average was as

given. The men operating the block machines thus earned $3 each per day.

The labor cost of molding and curing per block was thus 2.87 cts. As the

blocks had about 25 per cent. hollow space, each block 8×8×16 ins.

contained 0.45 cu. ft. of concrete; a cubic yard of concrete, therefore,

made 60 blocks, so that the labor cost of making the blocks was 60 ×

2.87 cts. = $1.72 per cubic yard. This cost does not include foreman's

time, materials, interest, depreciation or general expenses. It was

estimated by the owners that the blocks cost them 9 cts. apiece cured,

or about $5.40 per cubic yard of concrete. This 9 cts. evidently

includes materials and labor alone.

Upon removal from the molds the blocks were loaded onto cars, taken to a

large shed and there unloaded onto shelving arranged to hold five rows

of blocks one above the other, two blocks opposite each other on each

shelf. The blocks were left in the shed 24 to 48 hours to get the

preliminary set, then they were loaded on small cars and taken to the

yard, where they were removed from the cars and stacked. They were

sprinkled every day for six days, being kept covered meanwhile with

oiled cotton cloth. The labor costs given above include molding,

sprinkling and handling the blocks up to this point.

To lay the blocks they were again loaded on cars and run to an elevator

in a wooden tower outside the building. The elevator lifted the car to

the floor on which the blocks were to be used, where it was run off onto

a track reaching the full length of the building. The blocks were

unloaded directly behind the masons. Where the walls were high enough

for scaffolding the blocks were unloaded directly onto the first

scaffold and, when necessary, handed up to the scaffolds above. The

masons employed were regular stone masons receiving the regular scale of

wages of $3.50 per day. The number of blocks laid by each mason was 125

per day in building pilasters and 200 per day in building plain wall.

Sometimes 250 blocks per day per man were laid in plain wall work. The

cost per block of laying above was thus 2.8 cts. pilasters and 1.75 cts.

in plain wall. This cost does not include transporting the blocks from

yard or of handling them to the scaffold behind the masons, nor does it

include the cost of materials and labor for mixing and delivering

mortar.

One of the features of this work was the method of transporting the

blocks by cars. A complete system of tracks was provided covering the

block plant and yard, the building sites and the several floors of the

buildings themselves. All blocks and other materials were transported by

cars running on these tracks, both cars and tracks being of the type

made by the Chase Foundry & Manufacturing Co. of Columbus, Ohio.

~Residence, Quogue, N. Y.~--The following record of methods and cost of

constructing a concrete block residence is furnished by Mr. Noyes F.

Palmer: A mixture of sand and pebbles was had on the site; screening was

necessary merely to sort out the odd size stones. A mixture of 1 cement

and 5 sand was really a 1-2-3 mixture, the 2 being the finest grades of

sand and the 3 being various gravel sizes--none too large, none too

small--so that the proportion was 2/5 fine sand and 3/5 gravel.

The concrete was hand mixed, and as the gravel had always just been

excavated it contained moisture and did not have to be wetted. The sand

and gravel were mixed and turned three or four times and spread out

thin, and the cement was carefully spread over them in a uniform layer.

The mass was then turned three or four times until the eye could detect

no difference in color; that is, each grain large enough for the eye to

discern seemed to be coated with cement. After this dry mixing, water

was added in a fine spray--not a deluge from a pail--but only enough to

moisten the mixture. The mass was then turned three or four times. The

mixture was then shoveled into the mold, no special face mixture being

used, so as to about half fill it, and was then tamped by two men, one

standing on each side of the machine. Altogether three layers of

material were so placed and tamped and then a shovelful of sand and

cement mixture was spread over the top to permit an even "strike-off."

As each block was molded it was carried on the working plate and set

down on skids properly spaced to fit the marks on the plate. This is an

important detail and Mr. Palmer comments on it as follows: "The writer

saw inexperienced men careless about it and who would break the backs of

many blocks by not having the skids properly placed. After the blocks

have been at rest for half an hour commence to spray them with a

revolving garden sprinkler or by carefully wetting with a sprinkling pot

on the center of the block only. The blocks should not be allowed to dry

out for at least ten days after removal from the working plate. The

removal from the working plate can be done the morning after molding and

should never be done before even if the block was made in the morning.

In removing the green block from the skids let there be cones of sand

between the rows of blocks and up-end each working plate so as to let

the end of the block come upon the sand cushion. Don't twist and turn

the block, and to remove the working plate pass a stick through the core

holes in both block and plate so that the plate will not fall when

loosened. A slight rap on the center of the plate will loosen it. As

soon as the blocks are up-ended commence the spraying and soak the sand

underneath the block. It may seem unnecessary to dwell on these points

so long, but barrels of cement and barrels of money have been wasted by

neglecting to supply the hardening block with water. Curing is just as

important as molding in making concrete blocks."

The block construction had been detailed by the architect from cellar to

roof, so that it was known beforehand how many blocks of given size were

to be made. The unit of length was 32 ins.; this afforded fractional

parts of 8 ins., 16 ins. and 24 ins., therefore all openings were in

multiples of 8 ins. Odd sizes were made, by inserting "blanks" in the

mold box, to inches or fractions of an inch if desired. This unit

length was less mortar joints, while the unit of height was 9 ins., or

the same as four ordinary bricks with joints. The floor levels were

calculated in multiples of 9 ins., so that the wall could be finished

all around where the beams were to be seated. This beam course was made

of solid blocks; that is, no cores were used in molding them. With the

machine used no change was required to mold these solid blocks except to

remove the cores. The core holes in the working plate were simply

covered with pieces of tin. The shape of the block was the same and the

same materials were used.

The best record in making blocks for this work was 30 blocks, 8×9×32

ins., in one hour, working six men, three mixing and three on the

machine, and using one barrel of cement for 16 blocks. This was a record

run, however, a fair average being 20 blocks per hour, or 200 per ten

hours, which was the day worked. We have then the cost of making blocks

as follows:

1 foreman, at $2.50 $ 2.50

5 helpers, at $2 10.00

13 barrels cement, at $2 26.00

10 cu. yds. sand and gravel, at $1 10.00

Interest and depreciation on machine 2.00

------

Total for 200 blocks $50.50

This gives a cost per block of $50.50 ÷ 200 = 25¼ cts. The displacement

in the wall of each block is 1.75 cu. ft., or the same as 30 bricks.

The cost of laying blocks is the most uncertain item in the whole

industry. Mr. Palmer states that he has known of instances where it cost

only 5 cts. per block and of other instances where, because of the

difficulty of getting help and its inexperience, it cost 15 cts. per

block. In this particular building one mason and three helpers laid 100

blocks per day. The building had no long walls, but it did have many

turns. The cost of laying, then, was as follows:

1 mason, at $4 $ 4.00

3 helpers, at $2 6.00

-----

Total for 100 blocks $10.00

This gives a cost for laying of 10 cts. per block. We have, then:

Making 2,000 blocks $505

Laying 2,000 blocks 200

----

Total $705

This gives a cost of 35¼ cts. per block for making and laying.

The use of a derrick for laying the blocks proved a considerable item of

economy in this work. This derrick cost $50 and two men could mount and

move it on the floor beams. It had a boom reaching out over the wall and

was operated by a windlass. A plug and feather to fit the center 6-in.

hole in the block was used for hoisting the blocks. By this means blocks

only seven days old were laid without trouble. It may be noted that the

walls were kept drenched with water to make sure that the blocks did not

dry out until they were at least 28 days old. In laying the blocks a

thin lath was used to keep the mortar back about one inch from the face.

This precaution will prevent much labor in cleaning the walls from

mortar slobber.

~Two-Story Building, Albuquerque, N. M.~--The following record of cost of

making 9×10×32-in. hollow blocks in a Palmer machine and of laying 2,000

of them in two-story building walls is given by Mr. J. M. Ackerman. Sand

cost 60 cts. per cu. yd., and cement cost $3 per barrel. Lime cost 30

cts. per bushel. One barrel of cement made 20 blocks, using a 1-4 sand

mixture. In making 2,000 blocks about 100 blocks, or 5 per cent., were

lost by blocks breaking in hauling from yard to building or by cutting

blocks to fit the work. The blocks were molded by piece work for 5 cts

per block, all materials, tools and plant being supplied to the molders.

Three men with one machine made from 100 to 150 blocks per day. The cost

was as follows:

Item. Per block.

Cement, at $3 per bbl. $0.15

Molding, at 5 cts. per block 0.05

Sand, at 60 cts. per cu. yd. 0.03

Carting, yard to building 0.02

Lime and sand for mortar 0.03

Laying in wall 0.10

Loss in making and cutting 0.01

-----

Total $0.39

As each block gave 9 × 32 = 288 sq. ins., or 2 sq. ft., of wall surface,

the cost of the wall per square foot was 19.5 cts. Assuming 40 per cent.

hollow space, each block contained 1 cu. ft. of concrete, which cost 23

cts., or $6.21 per cu. yd., for materials and molding. Blocks in the

wall cost $10.55 Per cu. yd. of concrete.

~General Cost Data.~--The following data are given by Prof. Spencer B.

Newberry. The average weights of three sizes of hollow blocks are as

follows:

Size, ins. P. C. Hollow Space. Weight, lbs.

8×9×32 33-1/3 120

10×9×32 33-1/3 150

12×9×32 33-1/3 180

Costs of materials are assumed as follows:

Item. Per 100 lbs.

Cement, at $1.50 per bbl. $0.40

Hydrated lime, at $5 per ton $0.25

Sand, gravel or screenings, at 25 cts. per ton $0.012

Mixed in batches of 750 lbs., sufficient for six 8-in. or four 12-in.

blocks, the cost of materials per batch and per block will be for a 1-4

mixture as follows:

Item. Per Batch. 8-in. Block. 12-in. Block.

150 lbs. cement $0.60 $0.10 $0.15

600 lbs. sand 0.072 0.012 0.018

------ ------ ------

Total $0.672 $0.112 $0.168

In general a factory producing 600 8-in. blocks per day will require 25

men to operate it. At an average wage of $1.80 per day the following is

considered as a fair estimate of cost:

Item. Per Day. Per Block.

Materials for 600 blocks $ 60 $0.10

25 men, at $1.80 45 0.075

Repairs 10 0.017

Office and miscellaneous 20 0.034

---- ------

Total $135 $0.226

This gives for 8×9×32-in. blocks a cost of about $6.78 per cu. yd. of

concrete for materials and molding or of 11.3 cts. per sq. ft. of face.

Mr. L. L. Bingham gives the following as the average cost per square

foot of face for 10-in. wall from data collected from a large number of

block manufacturers operating in Iowa in 1905:

Cement at $1.60 per bbl. 4.5 cts.

Sand 2.0 cts.

Labor at $1.83 per day 3.8 cts.

---------

Total cost per square foot 10.3 cts.

Assuming one-third hollow space, the cost for materials and molding was

$5.05 per cu. yd. of concrete not including interest, depreciation,

repairs, superintendence or general expenses.

CHAPTER XXI.

METHODS AND COST OF AQUEDUCT AND SEWER CONSTRUCTION.

Aqueducts and sewers in concrete are of three kinds: (1) Continuous

monolithic conduits, (2) conduits laid up with molded concrete blocks,

and (3) conduits made up of sections of molded pipe. Block conduits and

conduits of molded pipe are rare in America compared with monolithic

construction; examples of each are, however, given in succeeding

sections, where forms, methods of molding, etc., are described. The

following discussion refers to monolithic construction alone.

~FORMS AND CENTERS.~--Forms and centers for conduit work have to meet

several requirements. They have to be rigid enough not only to withstand

the actual loads coming on them, but to keep from being warped by the

alternate wetting and drying to which they are subjected. They have also

to be constructed to give a smooth surface to the conduit. To be

economical, they have to be capable of being taken down, moved ahead and

re-erected quickly and easily. The carpenter costs run high in

constructing conduit forms, so that each form has to be made the most of

by repeated use.

Three different constructions of traveling forms are described in the

succeeding sections. For small work, such forms appear to offer certain

advantages, but for conduits of considerable size their convenience and

economy are uncertain. The experience with the large traveling form

employed on the Salt River irrigation works in Arizona was, when all is

said, rather discouraging. The authors believe that for work of any size

where the concrete must be supported for 24 hours or more, forms of

sectional construction will prove cheaper and more expeditious than any

traveling form so far devised.

No class of concrete work, perhaps, offer so good an opportunity for the

use of metal forms as does conduit work. The smooth surface left by

metal forms is particularly advantageous, and there is a material

reduction in weight and a large increase in durability due, both to the

lack of wear and to freedom from warping. Steel forms of the Blaw type

shown by Fig. 247, have been used for conduits up to 25 ft. in diameter.

The form illustrated, Fig. 247, was for a 12-ft. 3-in. sewer; in this

case a roof form alone was used, but full circular and egg-shape forms

are made. The Blaw collapsible Steel Centering Co., of Pittsburg, Pa.,

make and lease steel forms of this type.

[Illustration: Fig. 247.--Blaw Collapsible Steel Centering for Conduit

Construction.]

Sectional wooden forms for conduits of large diameters are shown by the

drawings in several of the succeeding sections. Figures 248 and 249 show

such forms for small diameters. The form shown by Fig. 248 is novel in

the respect that after being assembled a square timber was passed

through it lengthwise, occupying the holes B and having its ends

projecting and rounded to form gudgeons. The form was mounted with

these gudgeons resting on horses, so that it could be rotated and thus

wound with a narrow strip of thin steel plate. Thus sheathed, the form

was lowered into the trench and the concrete was placed around it. When

the arch had been turned, the wedges A were driven in until the ribs

C dropped into the slots a and clear of the steel shell; the arch form

was then pulled out and finally the invert form, leaving the steel shell

in place to hold the concrete until hard. The strip of steel was then

removed by pulling on one end until it unwound like cord from the inside

of a ball of twine. Steel strips 6 ins. wide and 1/24 in. thick were

used successfully in constructing a 5-ft. egg-shaped sewer in

Washington, D. C. The forms were made in sections 16 ft. long, and were

taken out as soon as the concrete had been placed.

[Illustration: Fig. 248.--Sectional Steel Wrapped Wooden Form for

Conduit Construction.]

[Illustration: Fig. 249.--Invert Form for Conduit Construction.]

The form shown by Fig. 249, is an invert form, used in constructing the

sewer shown by Fig. 249, built at Medford, Mass., in 1902, by day labor.

The concrete was 1-3-6 gravel. The forms for the invert were made

collapsible and in 10-ft. lengths. The two halves were held together by

iron clamps and hook rods. The morning following the placing of the

concrete the hook rods were removed and turnbuckle hooks were put in

their places, so that by tightening the turnbuckle the forms were

carefully separated from the concrete. The concrete was then allowed to

stand 24 hours, when the arch centers were set in place. These centers

were made of 7/8×1½-in. lagging on 2-in. plank ribs 2 ft. apart, and

stringers on each side. Wooden wedges on the forward end of each section

supported the rear end of the adjoining section. The forward end of each

section was supported by a screw jack placed under a rib 2 ft. from the

front end. To remove the centers, the rear end of a small truck was

pushed under the section about 18 ins.; an adjustable roller was

fastened by a thumb screw to the forward rib of the center; the screw

jack was lowered allowing the roller to drop on a run board on top of

the truck; the truck was then pulled back by a tail rope until the

adjustable roller ran off the end of the truck; whereupon the truck was

pulled forward drawing the center off the supporting wedges of the rear

section. Each lineal foot of sewer required 1¼ cu. yds. of excavation

which cost 74.2 cts. per foot, and 1 cu. ft. of brick arch which cost

$12.07 per cu. yd., or 44.2 cts. per lineal foot of sewer. The invert

required 4 cu. ft. of concrete per foot, which cost as follows:

Item. Per cu. yd.

Portland cement at $2.15 per bbl. $2.292

Labor mixing and placing 3.017

Cost of forms 0.187

Labor screening gravel 0.471

Carting 0.592

Miscellaneous 0.146

------

Total $6.705

The cost of the invert was thus $1.002 per lin. ft. of sewer.

Collapsible metal forms for manholes and catch basins are made by

several firms which make block and pipe molds. A cylindrical wooden form

construction is shown by Fig. 250. The outside form consists of three

segments of a cylinder made of 2-in. lagging bolted to hoops. Bent lugs

on the ends of the hoops, were provided with open top slots and were

bolted together through 1×3/8-in. bars which extended the full length of

the form between lugs. The assembled form was collapsed by pulling up on

the bars, thus lifting the bolts out of the slots. The inner mold is

also made in three sections with strap hinges at two of the joints and

at the third joint a wedge-shaped stave. The other details are shown by

the drawing. To mold the top of the basin two cone-shaped forms are

used, an outer form made in one piece and an inner form made in

sections. Some 26 catch basins were built in Keney Park, Hartford,

Conn., by Mr. H. G. Clark, at a cost of $7 apiece for concrete in place,

and there was closely 1 cu. yd. of concrete in each.

[Illustration: Fig. 250.--Form for Circular Catch Basin or Manhole.]

~CONCRETING.~--Except for pipes of small diameter, the concreting is done

in sections, each section being a day's work. Continuity of construction

has not proved successful, except for pipes of moderate size, in the few

cases where it has been tried. Examples of continuous construction

methods are given in succeeding sections. Methods of molding and laying

cast concrete pipe are also best shown by the specific examples given

further on. In concreting large diameters, the work may be done by

molding successive full barrel sections, or by molding first the invert

and then the roof arch, each in sections. The engineer's specifications

generally stipulate which plan is to be followed. Construction joints

between sections are molded by bulkhead forms framed to produce the type

of joint designed by the engineer; the most common type is the tongue

and groove joint.

[Illustration: Fig. 251.--Cross-Section of Pinto Creek Irrigation

Conduit.]

For small diameters built with traveling forms, a comparatively dry

concrete is essential, but when the centers are left in place until the

concrete has set, a wet mixture is preferable, as it is more easily

placed and worked around the reinforcement in the thin shells. Mixers

are commonly specified even for small work, because of their generally

more uniform and homogeneous product. Portable mixers hauled along the

bank and discharging into the forms through chutes, furnish a cheap and

rapid arrangement where the section being built has a considerable

yardage. The examples given in succeeding sections present various

methods of mixing and placing concrete in conduit work.

[Illustration: Fig. 252.--Traveling Form for Pinto Creek Conduit.]

~REINFORCED CONDUIT, SALT RIVER IRRIGATION WORKS, ARIZONA.~--The pipe had

the cross-section shown by Fig. 251, and formed a syphon carrying water

under the bed of a creek. The concrete was a 1-2½-4 fine gravel mixture,

mixed by hand on boards 150 ft. apart along the line. The shell was

reinforced as shown.

The forms consisted of an outside form constructed as shown by Fig. 251,

by inserting 2½-in.×5½ ft. lagging strips in the metal ribs. The inside

form was designed to permit continuous work by moving the form ahead as

the concreting progressed. It consisted as shown by Fig. 252, of an

invert form on which an arch form was carried on rollers. The invert

form was pulled along by cable from a horsepower whim set ahead, being

steered, aligned and kept to grade by being slid on a light wooden

track. It had the form of a long half cylinder, with its forward end

beveled off to form a scoop-like snout. The arch center consisted of

semi-circular rings 2 ft. long, set one at a time as the work required.

Each ring, when set, was flange-bolted to the one behind, and each was

hinged at three points on the circumference to make it collapsible. In

operation, the invert form was intended to be pulled ahead and the arch

rings to be placed one after another in practically a continuous

process. So that the arch rings might continue supported after the

invert form was drawn out from under them, invert plates similar to the

arch plates were inserted one after another in place of the shell of the

invert form. The plan provided very nicely for continuous work, but

continuous work was found impracticable for all but about 2,500 ft. of

the 6,000 ft. of conduit built. The reason for this seems to have been

at least in a great measure, the slow setting cement made at the cement

works established by the Government, at Roosevelt. In building the first

300 ft. of conduit, a commercial cement was used and a progress of 120

lin. ft. of pipe per 24 hours was easily made. This work was done in

June. Later, but still in warm weather, using the Government cement and

70 ft. of arch plates, not more than 70 ft. of pipe could be completed

in 24 hours; if the plates were taken down sooner, patches of concrete

fell out or peeled off with them. As the weather grew colder, this

difficulty increased, until finally, the idea of continuous work was

abandoned and for some 3,500 ft. of conduit only one 8-hour shift per

day was worked. In December and January the plates had to remain in

place three days, so that the progress was only 24 ft. per day; in warm

weather this rate was increased to 40 ft. per day.

Costs were kept on two sections of one of the lines and the figures

shown in the accompanying table were obtained.

A gang consisted of a foreman at $175 per month, a sub-foreman at $3.50

per day, and the following laborers at $2.50 per day: one bending the

reinforcement rings; two placing the reinforcement; four taking down,

moving and erecting the stationary plates; four placing the concrete and

outside lagging; two wheeling concrete; six mixing concrete; one

wheeling sand and gravel; one watering the finished pipe; four laying

track for the steering apparatus, moving the superstructure and hangers,

mixing boards, runways, etc.; one pointing and finishing inside the

pipe; and one on the whim and doing miscellaneous work. The labor was

principally Mexican, and only fairly efficient.

It is important to note that the costs given in the table are labor

costs only of mixing and placing concrete and moving forms; they do not

include engineering, first cost of forms, concrete materials,

reinforcement or grading.

May, '06. July, '06.

Wages 714 1,009 Cost Per

Per Lin. Ft. Lin. Ft. Per Cu.

Day. Cost. Cost. Lin. Ft. Yd.

{ Laying track for

{ steering alligator $ 5.00 $ 71.48 $ 43.98 $0.0670 $0.16

4 men { Moving and erecting

{ superstructure 5.00 299.94 358.44 0.3821 0.93

4 men Moving plates 10.00 202.50 253.44 0.2646 0.65

Repairs to alligator 58.50 2.50 0.0354 0.08

1 man Bending rings 2.50 32.87 59.87 0.0538 0.13

2 men Placing reinforcement 5.00 126.94 138.13 0.1538 0.38

12 men Mixing and placing

concrete 30.00 709.68 949.74 0.9631 2.34

1 man Watering finished pipe. 2.50 45.00 78.27 0.0716 0.17

1 man Painting and

brush-coating inside 2.50 96.50 117.37 0.1241 0.31

Blacksmith's work 30.00 25.00 0.0319 0.08

1 man Whim 2.50 23.87 28.75 0.0306 0.07

1 man Screening and hauling

sand and gravel 2.50 183.13 300.00 0.2804 0.68

--------- --------- ------- -----

Total $1,880.41 $2,335.49 $2.4584 $5.98

~CONDUITS, TORRESDALE FILTERS, PHILADELPHIA, PA.~--At the Torresdale plant

of Philadelphia filtration system the clear water conduits are

reinforced concrete. The following description is composed from

information furnished the authors in 1904 by the Bureau of Filtration,

Mr. John W. Hill, then chief engineer. The lengths of the several

conduits are as follows: 576 ft. of 7½-ft., 782 ft. of 8-ft., 1,050 ft.

of 9-ft., and 1,430 ft. of 10-ft. horseshoe conduit. All sizes of

conduit have the same cross-sectional form--the cross-section of the

9-ft. conduit is shown by Fig. 253, and all are reinforced by expanded

metal arranged as indicated. The concrete is a 1-3-5, ¾-in. stone

mixture. The conduits were first designed with circular sections, but

before construction had been begun on these plans, experience had been

obtained in building a circular sewer that made a change to the

horseshoe section appear desirable. In the circular sewer work, great

difficulty had been found in properly placing and ramming the concrete

in the lower quarters of the circular section.

[Illustration: Fig. 253.--Section of 9-ft. Conduit, Philadelphia Filter

Plant.]

_Forms._--The forms used for the several sizes of conduit were all of

the same general type, but improvements in detail were made as

successive sizes were built. The last form to be designed was that for

the 9-ft. section and this was the best one; it is shown by Fig. 254.

The forms were built in sections from 12 ft. to 13½ ft. long. They were

covered with No. 27 galvanized sheet iron, and this covering was found

of advantage both in giving a smooth finish and in prolonging the life

of the centers. The important feature is the construction in sections

which could be set up and broken down by simply inserting and removing

the connecting bolts. Three sets of forms were made for each size of

conduit.

[Illustration: Fig. 254.--Form for 9-ft. Conduit Philadelphia Filter

Plant.]

_Procedure of Work._--The first operation in building a section of

conduit was to set to exact line and grade and the length of the form in

advance of the finished work the bulkhead shown by Fig. 255. In this

space the invert concrete was deposited and formed to a plane 1 in.

below the finished invert bottom. The two bottom sections of the form

were then assembled and located by bolting one end to the last preceding

form and inserting the other end into the bulkhead. About two tons of

pig iron were then placed on the invert form to keep it from floating

while the liquid granolithic mixture was being poured into the 1-in.

space between the form and the invert concrete. In building up the sides

a facing form was used for placing the granolithic finish. This

consisted of "boards" of sheet steel ribbed transversely on one side

with ¾-in. pipe and on the other side with 1½-in. pipe. Two boards were

used on each haunch, slightly lapping in the center, as follows: The

board was placed with the small ribs against the form and the larger

ribs kept the expanded metal just 3 ins. from the face of the form. A

6-in. depth of concrete was placed between the metal board and the

outside form or planks, then 6 ins. of granolithic was poured into the

1-in. space between the center and the board and finally the board was

raised 6 ins. and the concrete and granolithic mixture tamped together.

With the board in its new position, another layer of concrete and

granolithic was placed. Toward the crown the granolithic mixture was

made stiff and simply plastered onto the mold. The expanded metal was

cut into sheets corresponding to the length of the sides of the form and

lapped 6 ins. in all directions; the bulkhead having a slot as shown to

permit the metal to project 6 ins. from the face of the concrete in

order to tie two sections together and also having a rib which formed a

mortise in the face of the shell of concrete to key it to the succeeding

section.

[Illustration: Fig. 255.--Bulkhead Form for Conduits, Philadelphia

Filter Plant.]

All the conduits were built in sections from 12 ft. to 13½ ft. long, and

there was very little, if any, difference in the labor required to build

a section, in from eight to ten hours, of any of the three sizes. One

foreman and 18 men on the top of the trench mixed and handled the

concrete and granolithic mortar while one foreman, one carpenter and

seven men in the trench set the forms and placed and rammed the concrete

for one section in generally eight hours. About one-third of the

concrete for the whole work was mixed in a portable cubical mixer of ½

cu. yd. capacity, and the remainder was mixed by hand. Owing to the

relatively small amount of concrete used per day, about 20 cu. yds., it

was found that there was practically no difference in the cost of

machine mixing and of hand mixing. The 9-ft. conduit as an average of

the three sizes, contained 20 cu. yds. of concrete, 1,200 sq. ft. of

expanded and required 125 bags of cement for a section 13½ ft. long. The

cost of the work excluding excavation and profit, but including forms,

metal, concrete materials and labor, was about $10.50 per cu. yd.

~CONDUIT, JERSEY CITY WATER SUPPLY.~--In constructing the 8½-ft.

reinforced concrete conduit for the Jersey City water supply, use was

made of forms without bottoms. Each form was made of segmental sections

12½ ft. long of wood covered with sheet steel. They were set end to end

in the trench, resting on 6-in. concrete cubes which were finally

permanently embedded in the invert concrete. In each form there was a

scuttle about 2 ft. square at the crown, and the bottom was open between

the curves of the invert haunches. The form being set and greased and

the reinforcement placed, the concrete was deposited on the outside and

forced by means of tamping bars down the curve of the invert haunches

until it filled the whole space between the form and the earth and

appeared at the edges of the bottom opening in the form. Concrete was

then thrown through the scuttle and the invert screeded into shape. The

concreting of the sides and crown of the arch was then completed, using

outside forms except for about 5 ft. of the crown, the scuttle, of

course, being closed by a fitted cover. The centers were left in place

about 48 hours. The concrete was a 1 cement 7 sand and run of the

crusher 2-in. broken stone mixture, and was made so wet that it would

flow down an incline of 1 on 8. The mixing was done in portable Ransome

mixers, set on the trench bank alongside the work and discharging by

chute into dished shoveling boxes provided with legs to set on the

erected forms. Coal scoops were used in shoveling from the box into the

forms and were found superior to shovels in keeping the relative

proportions of water and solids constant.

~TWIN TUBE WATER CONDUIT AT NEWARK, N. J.~--In constructing the Cedar

Grove Reservoir, at Newark, N. J., two conduits side by side were built

across the bottom from gate house to tunnel outlet. A section of one of

the conduits showing the form construction and the arrangement of the

reinforcement is given by Fig. 256. The concrete was a 1-2-5 1½-in.

stone mixture and the reinforcement was No. 10 3-in. mesh expanded

metal. The method and cost of construction are given as follows, by Mr.

G. C. Woollard, the engineer for the contractors.

[Illustration: Fig. 256.--Conduit for Cedar Grove Reservoir, Newark. N.

J.]

"The particular thing that was insisted upon by both Mr. M. R. Sherrerd,

the chief engineer of the Newark Water Department and Mr. Carlton E.

Davis, the resident engineer at Cedar Grove Reservoir, in connection

with these conduits, was that they be built without sections in their

circumference, that the whole of the circumference of any one section of

the length should be constructed at one time. They were perfectly

willing to allow us to build the conduit in any length section we

desired, so long as we left an expansion joint occasionally which did

not leak.

"The good construction of these conduits was demonstrated later, when

the section stood 40 lbs. pressure to the square inch, and, in addition,

I may say that these conduits have not leaked at all since their

construction. This shows the wisdom of building the conduit all round in

one piece, that is, in placing the concrete over the centers all at one

time, instead of building a portion of it, and then completing that

portion later, after the lower portion had had an opportunity to set.

"The centers which I designed on this work were very simple and

inexpensive, as will be gathered from the cost of the work, when I state

that this conduit, which measured only 0.8 cu. yd. of concrete to the

lineal foot of single conduit, cost only $6.14 per cu. yd., built with

Atlas cement, including all labor and forms and material, and expanded

metal. The forms were built in 16 ft. lengths, each 16 ft. length having

five of the segmental ribbed centers such as are shown in Fig. 256,

viz., one center at each end and three intermediate centers in the

length of 16 ft. These segments were made by a mill in Newark and cost

90 cts. apiece, not including the bolts. We placed the lagging on these

forms at the reservoir, and it was made of ordinary 2×4 material,

surfaced on both sides, with the edges beveled to the radius of the

circle. These pieces of 2×4 were nailed with two 10d. nails to each

segment. The segments were held together by four ½-in. bolts, which

passed through the center, and 1½-in. wooden tie block. There was no

bottom segment to the circle. This was left open, and the whole form

held apart by a piece, B, of 3×2 spruce, with a bolt at each end

bolted to the lower segment on each side.

"The outside forms consisted of four steel angles to each 16 ft. of the

conduit, one on each end, and two, back to back, in the middle of each

16 ft. length. These angles were 2×3, with the 2-in. side on the

conduit, and the 3-in. side of the angle had small lugs bolted on it at

intervals, to receive the 2×12 plank, which was slipped down on the

outside of the conduit, as it was raised in height. The angles were held

from kicking out at the bottom by stakes driven into the ground, and

held together at the top by a 2½-in. tie-rod.

"The conduit was 8 ins. thick, save at the bottom, where it was 12 ins.

The reason for the 12 ins. at the bottom was that the forms had to have

a firm foundation to rest on, in order to put all the weight required by

the conduit on them in one day or at one time, without settling. We

therefore excavated the conduit to grade the entire length, and

deposited a 4-in. layer of concrete to level and grade over the entire

length of the conduit line. This gave us a good, firm foundation, true

and accurate to work from, and this is the secret of the good work which

was done on these conduits. If you examine them, you will say that they

are one of the neatest jobs of concrete in this line that has been

built, especially with regard to the inside, which is true, level and

absolutely smooth. [The authors can confirm this statement.] When the

conduit is filled with water, it falls off with absolutely no point

where water stands in the conduit, owing to its being out or the proper

amount of concrete not being deposited.

"The centers were placed in their entirety on a new length of conduit to

be built, resting upon four piles of brick, two at each end as shown.

The first concrete was placed in the forms at the point marked X and

the next concrete was dropped in through a trap door cut in the roof of

the conduit form at the point marked Y. This material was dropped in

to form the invert, and this portion was shaped by hand with trowels and

screeded to the exact radius of the conduit. The concrete was then

placed continuously up the sides, and boards were dropped in the angles

which I have mentioned, and which served as outside form holders till

the limit was reached at the top, where it was impossible to get the

concrete in under the planking and thoroughly tamped. At this point the

top was formed by hand and with screeds.

"Each 16-ft. length of this conduit was made with opposite ends male and

female respectively, that is, we had a small form which allowed the

concrete to step down at one end to 3 ins. in thickness for 8 ins. back

from the end of the section, and on the other end of the section it

allowed it to step down to 3 ins. in thickness in exactly the opposite

way, making a scarf joint. This was not done at every 16 ft. length,

unless only 16 ft. were placed in one day. We usually placed 48 ft. a

day at one end of the conduit with one gang of men. This was allowed to

set 24 hours, and, whatever length of conduit was undertaken in a day,

was absolutely completed, rain or shine, and the gang next day resumed

operations at the other end of the conduit on another 48 ft. length.

This was completed, no matter what the weather conditions were, and,

towards the close of this day the forms placed on the preceding day were

being drawn and moved ahead.

"The method used in moving these forms ahead for another day's work is

probably one of the secrets of the low cost of this work, and it is one

which we have never seen employed before. The bolt at A, Fig. 256, was

taken out, and the tie brace B thrown up. We had hooks at the points

C. A turnbuckle was thrown in, catching these hooks, and given several

sharp turns, causing the entire form to spring downward and inwards,

which gave it just enough clearance to be carried forward, without doing

any more striking of forms than pulling the bolt at A. This method of

pulling the forms worked absolutely satisfactorily, and never gave any

trouble, and we were able to move the forms very late in the day and get

them all set for next day's work, giving all the concrete practically 24

hours' set, as we always started concreting in the morning at the

furthest end of the form set up and at the greatest distance from the

old concrete possible in the 48 ft. length, as the furthest form had, of

course, to be moved first, it being impossible to pass one form through

the other.

"Six 16-ft. sections of these forms were built, and three were used each

day on each end, as shown by the diagram MN, Fig. 256, which gives the

day for the month for the completion of each of seven 48-ft. sections.

"A gang of men simply shifted on alternate days from end to end of the

conduit, although several sections were in progress at one time; and of

course, finally, when a junction was made between any division, say of

1,000 ft. to another 1,000 ft., one small form was left in at this

junction inside of the conduit, and had to be taken down and taken out

the entire length of the conduit.

"The centers for a 16-ft. length of this conduit cost complete for labor

and material, $18.30, but they were used over and over again; and, after

this conduit was completed, they were taken away for use at other

points, so that the cost is hardly appreciable, and the only charge to

centers that we made after the first cost of building the centers, was

on account of moving them daily. Part of this conduit was built double

(two 6-ft. conduits) and part single, the only difference being that,

where the double conduit was built, two forms were placed side by side,

and not so much was undertaken in one day.

"These conduits, when completed and dried out, rung exactly like a

60-in. cast-iron pipe, when any one walked through them or stamped on

the bottom."

Mr. Woollard gives the following analysis of the cost per cubic yard of

the concrete-steel conduit above described:

Per cu. yd.

1.3 bbl. cement $1.43

10 cu. ft. sand 0.35

25 cu. ft. stone 1.10

26 sq. ft. expanded metal, at 3 cts. 0.78

Loading and hauling materials 2,000 ft.

to the mixing board (team at $4.50) 0.50

Labor mixing, placing, and ramming 1.38

Labor moving forms 0.60

-----

Total $6.14

Wages were 17½ cts. per hr. for laborers and 50 cts. per hr. for

foremen. The concrete was 1-2-5, a barrel being assumed to be 3.8 cu.

ft. The concrete was mixed by hand on platforms alongside the conduit.

The cost of placing and ramming was high, on account of the expanded

metal, the small space in which to tamp, and to the screeding cost. When

forms were moved they were scraped and brushed with soft soap before

being used again.

From Mr. Morris R. Sherrerd, Engineer and Superintendent, Department of

Water, Newark, N. J., we have received the following data which differ

slightly from those given by Mr. Woollard. The differences may be

explained by the fact that the cost records were made at different

times. Mr. Sherrerd states (Sept. 26, 1904,) that each batch contains 4

cu. ft. of cement, 8 cu. ft. of sand, and 20 cu. ft. of stone, making 22

cu. ft. of concrete in place. One bag of cement is assumed to hold 1

cu. ft. He adds that a 10-hour day's work for a gang is 63 lin. ft. of

single 6-ft. conduit containing 47.4 cu. yds. of concrete and 1,260 sq.

ft. of expanded metal. This is equivalent to ¾ cu. yd. of concrete per

lin. ft. The total cost of material for one complete set of forms 64 ft.

long was $160; and there were 7 of these sets required to keep two gangs

of men busy, each gang building 63 lin. ft. of conduit a day. Since the

total length of the conduit was 3,850 ft., the first cost of the

material in the forms was 18 cts. per lin. ft.

Cost of Labor on 6-ft. Conduit:

Per day. Per cu. yd.

1 foreman on concrete $ 3.35 $0.07

1 water boy 0.75 0.01

11 men mixing at $1.75 19.25 0.39

5 men mixing at $1.50 7.50 0.16

4 men loading stone at $1.40 5.60 0.12

4 men wheeling stone at $1.40 5.60 0.12

2 men loading sand at $1.40 2.80 0.06

2 men wheeling sand at $1.40 2.80 0.06

1 man placing concrete at $1.75 1.75 0.04

6 men placing concrete at $1.50 9.00 0.19

2 men supplying water at $1.50 3.00 0.06

1 man placing expanded metal at $2. 2.00 0.04

1 man placing expanded metal at $1.50 1.50 0.03

------ -----

Total labor on concrete $64.90 $1.35

Cost of Labor Moving Forms:

Per day. Per cu. yd.

4 carpenters placing forms $13.00 $0.27

2 helpers placing forms 4.00 0.08

1 carpenter putting up boards

for outside forms 2.75 0.06

1 helper putting up boards

for outside forms 2.25 0.05

2 helpers putting up boards

for outside forms 3.50 0.07

1 team hauling timber 4.50 0.09

1 helper hauling lumber 1.75 0.04

------ -----

Total labor moving $31.75 $0.66

It will be noted that it required two men to bend and place the 700

lbs., or 1,260 sq. ft., of expanded metal required for 63 lin. ft. of

conduit per day, which is equivalent to ½c per lb., or 3 cts. per sq.

ft., for the labor of shaping, placing and fastening the metal.

~CIRCULAR SEWER, SOUTH BEND, INDIANA.~--In building 2,464 ft. of 66-in.

circular reinforced concrete sewer at South Bend, Ind., in 1906, the

method of construction illustrated in Figs. 257, 258 and 259 was

employed. The sewer has a 9-in. shell buttressed on the sides and is

reinforced every 12 ins. by a 3/16×1-in. peripheral bar in the sides and

roof and 3 ins. in from the soffit. Each bar is composed of three

pieces, two side pieces from 15 ins. below to 6 ins. above springing

lines and a connecting roof bar attached to the side bars by cotter

pins. Two grades of concrete were used, a 1-3-6 bank gravel concrete for

the invert and a 1-2-4 bank gravel concrete for the arch. The invert was

given a ½-in. plaster coat of 1-1 mortar as high as the springing lines.

[Illustration: Fig. 257.--Form for South Bend Sewer (First Stage).]

[Illustration: Fig. 258.--Form for South Bend Sewer (Second Stage).]

[Illustration: Fig. 259.--Form for South Bend Sewer (Third Stage).]

Forms and Concreting.--In constructing the sewer the trench was

excavated so as to give a clearance of 1 ft. on each side and was

sheeted as shown by Fig. 257. The sewer was built in 12 ft. sections as

follows: The bottom of the trench was shaped as nearly as possible to

the grade and shape of the base of the sewer. Four braces to each 12 ft.

section were then nailed across the trench between the lowest rangers on

the trench sheeting. A partial form consisting of a vertical row of

lagging was set on each of the outside lines of the sewer barrel as

shown by Fig. 257. Each section of this lagging was held by stakes

driven into the trench bottom and nailed at their tops to the cross

braces as shown by Fig. 258. A template for the invert was then

suspended from the cross braces by pieces nailed to the four ribs of the

template and to the cross braces as shown by Fig. 257. The concrete was

now placed and carried to the top of the template, which was then

removed. The side pieces of the reinforcing bars were then set and

fastened as shown by Fig. 258. The side forms extending up to the

springing lines were then placed. They were held in position by braces

nailed to their ribs at the tops and by other braces fitting into

notches in the ends of their ribs at the bottom. The concrete was then

carried up to the springing lines, the arch centers in two pieces were

placed; the arch bar of the reinforcement was placed and the extrados

forms erected up to the 45° lines, all as shown by Fig. 259. The placing

of the arch concrete completed the sewer barrel. The outside forms and

bracing were removed about 24 hours after the completion of the arch and

back filling the trench was begun immediately, but the inside forms were

left in place for two weeks; they were then removed by the simple

process of knocking out the notched braces. By building several lengths

of invert first and following in succession by the side wall

construction and then by the arch construction, the form erection and

the concreting proceeded without interruption by each other. It was also

found that, by making bends in the form of polygons with 10 ft. sides

instead of in the form of curves, there was a material saving in

expensive form work. To overcome the friction of the angles in such

bends an additional fall was provided at these places. All concrete was

made in a Smith mixer mounted on trucks so that it could be moved along

the bank of the trench and discharging into a trough leading to the

work.

_Labor Force and Cost._--With a gang of 12 men from 24 to 36 ft. of

sewer was built per 10-hour day, working only part of the time on actual

concreting. The disposition of the force mixing and laying concrete and

the wages were as follows:

Item. Per day.

Six wheelers, at 18.5 cts. per hour $11.10

One mixer, at 22.5 cts. per hour 2.25

One dumper, at 18.5 cts. per hour 1.85

Four placers, at 22.5 cts. per hour 9.00

------

Total $24.20

There were 0.594 cu. yd. of concrete per lineal foot of sewer and its

cost is given as follows:

Item. Per cu. yd.

Cost of gravel $0.774

Cost of sand 0.36

Cost of cement 1.50

Cost of steel reinforcement 0.84

Cost of labor, mixing and placing concrete 1.094

Cost of moving forms, templates, etc. 0.757

Cost of forms, templates, etc. 0.589

Cost of finishing, plastering, etc. 0.639

Cost of tools and general expenses 0.841

------

Total $7.394

~SEWER INVERT, HAVERHILL, MASS.~--In constructing sewers with concrete

inverts at Haverhill, Mass., in 1905, use was made of the traveling form

or mold shown by Fig. 260. The form consists of an inner and an outer

shell, the annular space between which forms the mold; in operation the

annular space is filled with concrete, then the outer shell is pulled

ahead from underneath, leaving the inner shell in place. A second inner

shell is then adjusted to the outer shell in its new position, the

annular mold is concreted and the outer shell again pulled ahead.

Continued repetition of the operations described completes the invert.

The merit of the device lies in the fact that the inner shell is not

moved until the concrete has attained some degree of rigidity; when, in

such devices, the inner mold is slid ahead on the green concrete it is

likely so to "drag" forward the material that a rough and pitted surface

results.

_Mold Construction._--Referring to the drawings of Fig. 260, A is the

outer mold of sheet steel bent to the required shape of the outer

surface of the conduit to be constructed. A rib, or angle, B, is

riveted to the inside of the mold at its front end and a diaphragm C

of plank is securely fastened to the rear side of the rib. The opposite

or rear end of the mold is open. Angles D forming tracks are riveted

inside the mold a short distance below the edges and reaching their full

length. The inner mold comprises a steel shell E curved to the form of

the inside of the conduit; inside this steel shell is a reinforcing

lagging, and at each end there is a wooden diaphragm F. Passing

through both end diaphragms and having its ends flush with the end

planes of the mold is a timber G. Rearward projecting lips e are

secured to the lagging at the rear end of the mold and on each side of

the timber G. The diaphragms F have each two arms f which project

horizontally beyond the surface of the inner mold and engage the tracks

D; locking dogs H are pivoted to the arms f so as to hook under

the track angles D and hold the inner form from rising. Setting on the

inner mold is an inverted V-shaped deflector I; its edges are flush

with the sides of the mold and its purpose is to facilitate the placing

of the concrete. There is also a movable diaphragm K, fitting loosely

inside the outer mold A and bearing against the end of the inner mold

E. The length of the inner mold E is about one-half that of the

outer mold A; as a rule several inner molds are provided with one

outer mold.

[Illustration: Fig. 260.--Traveling Invert Form for Sewer Construction.]

_Mode of Operation._--In using the device described the outer mold A

is first placed in the trench with its rear end at the end of the

trench. An inner mold E is then suspended on the tracks of the outer

mold and locked therein by the dogs H, with its rear end flush with

the rear end of the outer mold. The partition K is then placed in

position against the forward end of the inner mold and a jack J of any

suitable form is interposed between diaphragms K and C, the jack

being extended sufficiently to press diaphragm K firmly against the

front end of the inner mold. The deflector I is next placed in

position on the inner mold and the concrete is forced down with an iron

rammer between the two molds, so as to fill completely the annular

space. The deflector aids in directing the concrete into this space, as

will be obvious. After the mold has been filled and the concrete

compacted as much as possible, the jack is operated to separate the

diaphragms K and C, and as the partition K is pressed against one

end of the mass of concrete which has been laid, the opposite end of

which abuts against the end of the trench, it follows that any backward

movement of the diaphragm K will compress the concrete. This movement

will be practically inappreciable in distance, but enough to compact

thoroughly the concrete and fill any voids. The action of the jack will

also push forward the diaphragm C and the outer mold A, the latter

being withdrawn from beneath the inner mold and the newly laid concrete,

the tracks D of the outer mold being drawn from beneath the arms f

of the inner mold, leaving the latter behind resting on the freshly laid

concrete. Further compression of the concrete after it has been left by

the outer mold will fill the spaces between the inner mold and the

surface of the trench. The outer mold is moved forward in this manner a

distance equal to the length of the inner mold, and then the diaphragm

K is drawn forward and another inner mold is lowered into the outer

mold exactly as was the first one. The jack is then placed, the concrete

deposited and the outer mold again advanced exactly as before. As the

outer mold advances, the inner molds become disengaged one after another

and are set ahead; in practice, enough inner molds are provided to

enable the concrete to harden sufficiently to keep its position when it

becomes necessary to take up successively the rearmost molds and place

them ahead.

_Haverhill Sewer Work._--The work at Haverhill, Mass., previously

mentioned in which the form just described was used, was a 24-in.

circular sewer with 6-in. walls. The outer form was 36 ins. in diameter

and 6 ft. 2 ins. long; the inner form was 24 ins. in diameter and 3 ft.

long. Angle B was 3 ins. and the track angles D were 1½ ins.; diaphragm

K was made of two thicknesses of 3-in. plank and diaphragm C of one

thickness of 3-in. plank, the other diaphragms were of 2-in. plank. The

shells of the molds were of ¼-in. steel plate; the jack was an ordinary

screw jack. Eight inner molds were used.

The form used at Haverhill was built by the city carpenter, the metal

portions being made in a boiler shop. Its cost was not ascertained, but

was, it is thought, about $75. The concrete used was a 1-3-5 stone

mixture, with cement costing $2 per barrel, sand $1.50 per load of 36

cu. ft., and stone $2.50 per load of 36 cu. ft. The men were paid 25

cts. per hour. Records kept on 265 ft. of invert, or, theoretically,

19.3 cu. yds. of concrete, gave the following figures:

Per Per

lin. ft. cu. yd.

Labor, setting and moving

forms, 42 hours, at 25 cts. $0.05 $0.67

Labor, mixing, placing and wheeling

concrete, 179 hours, at 25 cts. 0.16 2.19

----- -----

Total labor cost $0.21 $2.86

With the ordinary 1-3-5 mixture the cost of materials would run about as

follows:

Per cu. yd.

Cement, 0.96 bbl., at $2. $1.92

Sand, 0.47 cu. yd., at $1.13 0.53

Stone, 0.78 cu. yd., at $1.88 1.47

-----

Total cost materials $3.92

Two men were worked in the trench, one alternately ramming the concrete

into place and working the jack, and the other shaping the trench ahead

and assisting in bringing the rear forms ahead.

The form described was invented by Mr. Robert R. Evans, of Haverhill,

Mass., and has been patented by him.

~29-FT. SEWER, ST. LOUIS, MO.~--The following account of the method and

cost of constructing 162 ft. of very large sewer section at St. Louis,

Mo., is compiled from information furnished by Mr. Curtis Hill.

The cross-section of the sewer is given by Fig. 261, which also shows

the arrangement of the reinforcing bars. Johnson corrugated bars, old

style, are used for reinforcement. The sections of the various

reinforcing bars are: Longitudinal bars, 0.18 sq. in.; invert bars, 0.7

sq. in., and arch bars, 0.7 sq. in. The spacing of the bars and the

arrangement of the splices are indicated on the drawings of Fig. 261.

All splices have a lap of 36 ins. Some gravel concrete has been used in

the invert, but most of the concrete has been crushed limestone and

Mississippi River channel sand. The proportions were 1-3-6 in the invert

and 1-2-5 in the arch. The arch was computed by Prof. Greene's method.

The ultimate strength of concrete in compression was taken as 2,000 lbs.

per sq. in. and the working strength at 500 lbs. per sq. in. The elastic

limit of the reinforcing bars was taken at 50,000 lbs.

[Illustration: Fig. 261.--Harlem Creek Sewer, St. Louis, Mo.]

The trenching was done by wheel scrapers to the amount of waste. Then a

cableway was erected spanning the entire length of the section and the

remainder of the material taken out. The last 4 or 5 ft. in depth were

in limestone and the excavated rock was taken by cableway to dump carts

which took it to the crusher and returned with crushed rock to be used

for concrete. This rock foundation was taken advantage of to reduce the

amount of invert concrete.

In constructing the sewer proper the invert was first concreted to

template to the height shown in Fig. 262. The arch forms were then

placed as shown in Fig. 262, and the roof arch concreted. Both templates

and arch forms were constructed of wood. The arch forms were moved ahead

on iron rails and jacked into place. The ribs were 2×10-in. pieces and

were spaced 4 ft. on centers; the lagging was 2-in. tongue and grooved

stuff and was smeared with crude oil. The reinforcing bars shown in Fig.

261 were bent to proper radius by means of a wagon tire bender and were

held in place by templates. The concrete was all mixed by two Chicago

Improved Cube mixers operated by electric power.

[Illustration: Fig. 262.--Center for Harlem Creek Sewer.]

The cost records of constructing the section of 29-ft. sewer so far

built are not susceptible of complete analysis, but the following

figures can be given. The prices of materials were as follows:

Cement, per barrel $1.80

Sand, per cubic yard 0.75

Broken stone, per cubic yard 1.00

Reinforcing bars, per pound 0.02

Vitrified brick, per 1,000 12.00

The wages paid different classes of labor were:

Per hour.

Firemen $0.50

Laborers 0.175

Laborers 0.20

Laborers 0.25

Laborers 0.28

Laborers 0.3025

Bricklayers 0.66 2/3

Helpers $0.25

Carpenters 0.55

Engineers 0.50

Timekeepers 0.25

Watchmen 0.175

Hostlers 0.175

Teams 0.60

Taking up the several items of work in order, the excavation amounted to

21,400 cu. yds., of which 1,400 cu. yds. were rock excavation. The cost

of excavation was as follows:

Total. Per cu. yd.

Earth, excavation $7,640 $0.38

Earth bracing 2,000 0.10

Rock excavation 1,400 1.00

Rock, dynamite, tools, etc. 560 0.40

The cost of crushing the excavated rock and returning it to the mixer

was $1 per cu. yd.

The cost of the concrete work was as follows:

Per cu. yd.

1.30 bbl. cement at $1.80 $2.34

.044 cu. yd. sand at 75 cts. 0.33

1 cu. yd. broken stone at $1 1.00

-----

Total concrete materials $3.67

There were 1,600 cu. yds. of concrete placed at a cost of for:

Total. Per cu. yd.

Mixing and placing $1,180 $0.7375

Forms 2,000 1.25

Moving forms 400 0.25

------ -------

Total for forms and labor $3,580 $2.2375

For reinforcing the concrete 86,600 lbs. of steel, or about 55 lbs. per

cu. yd. were used. The cost of placing and bending this steel was as

follows:

Total. Per lb.

Cost of placing $172 0.1986 ct.

Cost of bending 52 0.06 ct.

We can now summarize the cost of the concrete work proper of this sewer

as follows:

Items. Per cu. yd.

Cement, sand and stone $3.67

55 lbs. steel at 2 cts. 1.10

Forms, labor and materials 1.25

Mixing and placing concrete labor 0.74

Placing steel at 0.1986 ct. per lb. 0.11

Bending steel at 0.06 ct. per lb. 0.03

Moving forms 0.25

-----

Total labor and materials $7.15

To get the total cost of the sewer proper we must add the cost of the

vitrified brick invert paving. There were 71 cu. yds. of this paving and

its cost was as follows:

Per cu. yd.

0.6 bbls. cement at $1.80 $1.08

0.25 cu. yd. sand at 75 cts. 0.19

450 bricks at $12 per M. 5.40

Labor laying, 71 cu. yds. at $180.33 2.54

-----

Total $9.21

None of the preceding figures includes the plant charges. The plant cost

$12,000 and the cost of running it during the work described was $2,000.

In explanation it should be noted that the plant served for building

some 1,340 lin. ft. of 27-ft. sewer as well as for the section

described.

~SEWER AT MIDDLESBOROUGH, KY.~--In constructing an oval sewer 4 ft. high

at Middlesborough, Ky., two steel forms in 10-ft. sections were used. As

shown in Fig. 263, T-iron ribs were spaced 5 ft. apart, fastened

together at the top by longitudinal angle irons, and at the bottom by a

sheet of steel 22 ins. wide, forming the bottom of the invert. The

lagging for the sides consists of movable 5-ft. lengths of channel iron,

secured by sliding bolts. After the bottom of the trench has been

roughly shaped with concrete, a 10-ft. section of invert forms is

lowered and suspended by the cross-beams, and the space beneath packed

with concrete; then a channel iron is slid into place and bolted, and

concrete packed behind it, and so on until the invert is made. The next

10-ft. section is then built while the first is hardening. Upon the

completion of the second section, the channel iron sides of the first

section are removed, and then the rib framework is lifted out. Wood arch

centers are then put in place and an inch of 1:2 plaster spread over the

lagging before placing the concrete for the arch, which is 6 ins. thick.

[Illustration: Fig. 263.--Invert Form for Sewer Construction.]

The cost per 100 ft. of this sewer was as follows (prices being assumed

for cement and labor):

Bottom concrete. Cost per 100 ft.

18.5 bbls. cement, at $1.50 $ 27.75

2.7 cu. yds. sand, at $1.00. 2.70

15 cu. yds. stone, at $1.00 15.00

17 days labor, at $1.50 25.50

Bottom concrete. Cost per 100 ft.

25.25 bbls. cement, at $1.50 37.85

7.5 cu. yds. sand, at $1.00 7.50

22 days labor, at $1.50 33.00

Sewer Arch.

26 bbls. cement, at $1.50 39.00

3.9 cu. yds. sand, at $1.00 3.90

13.6 cu. yds. stone, at $1.00 13.60

21 days labor, at $1.50 31.50

-------

Cost per 100 ft. $237.30

[Illustration: Fig. 264.--Sewer at Cleveland, Ohio.]

~INTERCEPTING SEWERS, CLEVELAND, O.~--An intercepting sewer some 3½ miles

long, of the form and construction shown in Fig. 264, was built at

Cleveland, Ohio, in 1904. The construction consists of a plain concrete

invert lined with two courses of shale bricks, and having two rows of

anchor bars set in the side walls so that the bars of one row are

staggered with respect to those of the other row. The anchor bars are

2×½-in. steel, and are spaced 30 ins. apart in each row. To the anchor

bars are bolted arch reinforcing bars arranged as shown, and these arch

bars have bolted to them eight lines of 1½×¼-in. longitudinal bars. A

natural cement concrete is used for the invert and side walls. The arch

is Portland cement concrete of normally a 1-3-7½, 1½-in. screened stone

mixture, but where the voids in the broken stone exceeded 40 per cent.,

it is a 1-3-6 mixture. The invert bricks are laid in Portland cement

mortar and the arch has a mortar lining and is waterproofed with 1-in.

of mortar on top.

_Forms._--Separate forms were used for the invert and for the arch ring.

Regarding these, the engineer, Mr. Walter C. Parmley, remarks:

One of the first forms used in the sewer was like a piece of segmental

arch centering inverted, and with the lagging nailed fast to the ribs.

The trouble with this form is that it is difficult to tamp concrete

under the bottom portion of the form, and hence a very rough surface is

produced. Much better results were obtained by omitting the lagging

boards on the bottom and at the sides till a point was reached where the

inclination of the concrete surface was about 45°. The concrete for the

bottom could then be worked down between the ribs, thorough tamping

done, and a good surface obtained. The ribs serve as a guide, so that

the workman produces the proper shape. From this point up to the

vertical, good results can be secured with the ribs attached to the

lagging. Some contractors found it more convenient to use ribs that were

connected with each other by a skeleton framework only, and then to slip

the lagging in, one piece at a time. For some of the sewers, in which

the brick lining was not carried quite up to the spring line, a separate

side form of skeleton ribs and loose lagging was set upon brace legs

bearing on the bottom of the invert. This form carried the concrete from

about 2 ft. below to about 2 ft. above the springing line. The arch ribs

then became segmental and rested upon the middle braces. This method has

the advantage of using ribs that are lighter and more easily handled

than those that are semi-circular. For arch centering, it is necessary

and convenient to use independent ribs and loose lagging, for the

centers can then be carried forward piece-meal, the falsework upholding

the green arch and re-erected at the advance end of the work. In these

matters each contractor prefers to use his own ingenuity, and so long as

the work is properly built, the engineer can well give him considerable

latitude as to use of methods. One thing, however, the engineer must

insist upon--that all centering and falsework be as nearly rigid as

possible. Even a slight settlement of the centers at the crown under the

load of concrete and back-fill will cause the arch to kick out at the

quarters, and if the green concrete arch is not cracked at the crown, it

will be crushed on the inside, about half way between the crown and

springing line. A reinforced arch is no more immune to this danger than

is a plain concrete arch. However, with a few days of hardening,

although the damage may be serious, the danger of actual collapse is

less. A point to be guarded against, especially in reinforced

construction, is any foolish act on the part of contractor or workman,

due to his overconfidence in the strength of the structure because it

contains embedded steel.

The mode of procedure in constructing the arch ring was to erect the

centers with lagging complete. The lagging was then covered with

building paper waterproofed with paraffine. The arch reinforcing bars

were then bolted to the anchor bars and the longitudinals connected up.

The lining of Portland cement mortar was first laid on the lagging.

Before this mortar had set, concrete was rammed in between it and the

sheeting to a height of 18 ins. above the springing line, and then the

remainder of the concrete placed without outside forms. The top of the

arch ring was finally finished with a 1-in. mortar coat. In regard to

the concrete, Mr. Parmley remarks:

"Concrete will flush up to the forms and produce a better surface, and

the voids in the stone will be much better filled if it is so wet as to

require but little tamping; moreover there is less danger of obtaining a

weak, porous wall should a workman neglect thorough tamping, than there

is where only a moist mixture is used. It is also to the contractor's

interest to use wet concrete for much less labor is required in mixing

and placing it. Small broken stone or gravel is preferable in concrete

for sewers. The walls being comparatively thin, unless there be a

considerable excess of mortar, if coarse stones are used, the concrete

will be honeycombed with voids. The stones should be well graded in size

from large to fine, but the largest fragments should not exceed 1½ ins.

in greatest dimension."

_Cost._--A number of records of cost of constructing short sections of

the sewer described are given by Mr. Parmley, as follows:

Labor placing anchor bars. Per day.

1 man, at $3.50 $3.50

1 man, at $1.75 1.75

4 hours carrying steel at 20 cts. 0.80

-----

$6.05

The anchor bars were placed for 40 lin. ft. of sewer, or about 1,504

lbs. of metal at a cost of 0.4 ct. per lb.

The concreting gang for the sides consisted of:

5 men wheeling and mixing at $1.75 $8.75

1 man tamping 1.75

2/3 time man lowering brick and concrete at $2.25 1.50

1 man carrying concrete 1.75

------

$13.75

This gang built the side wall for 40 ft. of sewer daily, or 13 cu. yds.

Cost of labor per cu. yd. was, therefore, $1.06. The concrete was tamped

behind the brick lining as the latter was built up by the mason.

Cost of single ring brick lining at sides:

2 masons at 70 cents per hour $1.20

1 man mixing mortar 2.25

1/3 time man lowering at $2.25 0.75

3 men wheeling sand, filling buckets and dumping 5.25

------

Total labor for 40 lin. ft. of sewer $19.45

Quantity of brick masonry laid, cu. yd. 6.38

Labor per cu. yd. 3.05

An account was kept of labor performed on 85 lin. ft. of arch work, or

14 1-6 ft. daily. The force was as follows:

1 man putting mortar lining on centering $1.75

2 men mixing mortar, screening and wheeling sand 3.50

1 man tamping concrete 1.75

8 men on mixing board at $1.75 14.00

------

$21.00

No. cu. yd. placed daily 25.64

Labor per cu. yd. 0.82

Placing centering and arch bars:

2 men at $1.75 $3.50

1 man at $3.50 3.50

-----

$7.00

Costs, for 14 1-6 ft. daily, $0.49 per lin. ft.

As nearly as could be judged, about two-thirds of the labor was used in

erecting the centering and one-third in putting the steel in place. The

amount of steel placed daily was 785 lbs., at cost, therefore, of 0.3 of

a cent per lb., and the cost of erecting and moving centers, $0.33 per

lin. ft. of arch.

Another record of 39.27 ft. on a curve, gave for the cost of the brick

work at sides the same result as above, but the inspector's record of

men working on concrete backing at sides showed a less cost, as follows:

4 men mixing at $1.75 $7.00

2/3 time man lowering at $2.25 1.50

1 man in bottom 1.75

-----

$10.25

They placed 12.7 cu. yd. at a cost of $0.81 per cu. yd. This figure

probably more nearly represents the average cost than the $1.06 reported

in the first instance.

The cost of placing the anchor bars on straight sewer, representing

average progress, at another time, was found to be:

1 man $3.50

1 man 1.75

-----

$5.25

They placed the steel for 44 ft. of sewer or 1,650 lb. at a cost of 0.32

of a cent per lb.

Further notes for 6 days' work, when it seemed to represent as nearly as

possible the general average for the whole were:

Labor on arch concrete:

Daily progress was 13 1-6 ft.

The force employed was:

7 men making concrete, at $1.75 $12.25

1 man plastering the center 1.75

1 man mixing mortar 2.00

1 man tamping 1.75

-----

$17.75

On straight arch work they placed 24.1 cu. yd. daily at a cost of $0.74

per cu. yd. In three days' work on a curve, the same gang placed 26.37

cu. yd. daily at a cost of $0.675 per cu. yd.

On centering and steel for arch, three men kept up with the regular

progress of the arch-concreting gang. The cost, therefore, is:

1 man $3.50

2 men at $1.75 3.50

-----

$7.00

They averaged 13 ft. daily, or at a total cost of about $0.54 per lin.

ft. of sewer.

Two-thirds of this labor was on the centering or $0.36 per lin. ft. of

arch; $0.18 per lin. ft. placed the steel ready for embedding, or about

55.5 lb. per ft. of arch, at a cost of 0.32 of a cent per lb.

For the double ring brick lining at the bottom, the regular daily rate

of progress was 28 ft. or 11.15 cu. yd. with:

2 bricklayers $11.20

5 men at $1.75 8.75

1 man at $2.25 2.25

-----

$22.20

or at a cost of $1.98 per cu. yd. This is given only because it is of

interest in connection with the cost of the concrete.

Other observations on cost of placing steel skeleton and concrete did

not vary materially from the figures given. It will be observed that no

charge for superintendence or anything for the general expenses is

included in the estimates of cost. These charges were, of course,

impossible to obtain. On another contract with machine mixing, as high

as 36 lin. ft. of 13 ft. 6 in. arch were built in a day, but no data as

to cost were taken, though it was evidently less than for the work with

hand-mixed concrete.

~REINFORCED CONCRETE SEWER AT WILMINGTON, DEL.~--Records of a notable job

of sewer construction at Wilmington, Del., in 1903, are furnished by Mr.

T. Chalkley Hatton. The sewer was built by day labor for the city; its

cross-section at various points is shown by Fig. 265. The cross-section

of sewers in trenches deep enough to cover the arch are marked "deep

cutting"; the sections where the arch projects above the ground surface

are marked "light cutting." The section through the marsh was 700 ft.

long, the cutting being 8 ft. deep, and at high tide the marsh was

flooded 1 to 4 ft. The material was a soft mud that would pull a tight

rubber boot from a workman's foot. The cost of this marsh excavation

including cofferdams, underdraining, pumping, etc., was $4.60 per cu.

yd. For 1,100 ft. the 9¼ ft. sewer was through a cut 22 to 34 ft. deep,

the material being clay underlaid by granite. A Carson-Lidgerwood

cableway was used. Although the crown of the arch was but 8 ins. thick,

it withstood the shock of dumping 1 cu. yd. buckets of earth and rock

from heights of 3 to 10 ft.; and the weight of 25 ft. of loose filling

caused no cracks in the concrete.

Concrete was placed in 4-in. layers (the depth of the lagging) and well

rammed, since it was found that "wet" concrete left small honeycombed

spaces on the inner surface. Concrete for the invert was 1-2-6, the

stone being 1½-in. and smaller, and the sand being crusher dust. The

arch was 1-2-5.

The reinforcing metal used in the 9½-ft. sewer was No. 6 expanded metal,

6-in. mesh, in sheets 8×5½ ft., supplied by Merritt & Co., of

Philadelphia. A single layer was placed around the sewer, 2 ins. from

the inner surface, its position being carefully maintained by the men

ramming, and with but little difficulty as the sheets were first bent to

the radius of the circle. Each sheet was lapped one mesh (6 ins.) over

its neighbor at both ends and sides, and no sheets were wired except the

top ones, which were liable to displacement by men walking over them.

[Illustration: Fig. 265.--Cross-Sections of Sewer at Wilmington, Del.]

The metal used on the rest of the work was a wire-woven fabric furnished

by the Wight-Easton-Townsend Co., of New York. This fabric comes in

rolls 5½ ft. wide and 100 ft. to the roll. The wire is No. 8, with a

6×4-in. mesh. This fabric was placed by first cutting the sheets to the

required length to surround the sewer entirely, embedding it in the

concrete as fast as concrete was placed, in the same manner as was done

with the expanded metal except over the center where, on account of its

pliability, the fabric was held the proper distance from the lagging by

a number of 2-in. blocks which were removed as the concrete was placed.

The wire cloth, being all in one sheet, can be placed a little more

expeditiously than expanded metal, but, on the other hand, the expanded

metal holds its position better in the concrete, since it is more rigid.

We quote now from Mr. Hatton's letter: "The major portion of concrete

was mixed by machine at a cost of 66 cts. per yard, including wheeling

to place, coal and running of mixing machine, wages being $1.50 per day

of 8 hrs, Stone was delivered alongside of machine and all material had

to be wheeled in barrows upon the platform, and after mixing to the

sewer. Placing and ramming concrete around the forms cost 39 cts. per

cu. yd., additional. Setting forms in invert cost 2 cts. per cu. yd.,

setting centers 7 cts. per cu. yd. Cost of setting forms and centers

includes placing steel metal. Each lineal foot of 9¼ ft. sewer contained

1 cu. yd. of concrete, although the section only calls for 0.94 cu. yd.

The excess was usually wasted by falling over sides of forms or being

made too thick at crown.

"This yard of 1-2-5 concrete cost in place as follows (record taken as

an average of several-days' run):

Cement, 1.31 bbls. at $1.30 $1.703

Stone, 0.84 cu. yds. at $1.21 1.016

Stone dust, 0.42 cu. yd. at $1.21 0.508

Labor at 18¾ cts. per hour 0.987

Labor setting forms and setting metal 0.045

Cost of forms (distributed over 1,800 ft. of sewer) 0.082

40 sq. ft. expanded metal at 4¼ cts. 1.700

Labor plastering invert 0.070

------

Cost per ft., or per cu. yd. $6.111

"The forms for the invert were made of 2-in. rough hemlock boards cut

out 4 ins. less diameter than the diameter of the sewer, except for 18

ins. at the bottom of the form which coincided with the inside form of

sewer. The bottom of the sewers was laid to the bottom of this form

before it was set. Then the lagging, consisting of 2×6-in.×16-ft.

hemlock planed, was placed against each side of the form, one at a time,

and the concrete brought to the line of this top in 6-in. layers until

the whole invert was finished. These forms were set in 16-ft. sections,

five to each section.

"The centers consisted of seven ribs of 2-in. hemlock upon which was

nailed 1½-in. lagging, 2 ins. wide, tongued and grooved, and were 16 ft.

long, non-collapsible, but had one wing on each side, 9 ins. wide, which

could be wedged out to fit any inaccuracies in the invert. We used four

of these centers setting two at each operation and worked from two ends.

We left the centers in for 18 hours before drawing.

"The cost of the concrete on the smaller sewers was the same as are the

larger sewers, but the steel metal cost less, as it was wire woven metal

that cost 2½ cts. per sq. ft. It was much easier handled and cut to no

waste as it came in long rolls and was very pliable.

"After training our men, which occupied about one week or 10 days, we

had no difficulty in getting the concrete well placed around the metal,

preserving the proper location of the latter, which, however, bore

constant watching, as a careless workman would often take the temporary

supporting blocks and allow the metal to rest against the wooden center,

in which case the metal would show through the surface inside of the

sewer. The metal was kept 2 ins. away from the inside forms and the

arch. To keep it at this location we had several 2-in. wooden blocks cut

which were slipped under the wire or expanded metal and as soon as some

concrete was pushed under the wire at this point the block was removed.

"After the forms were removed the invert needed plastering, but the arch

was practically like a smoothly plastered wall except where it joined

the invert, where it frequently showed the result of too much hurry in

depositing the first loads of concrete on the arch. We remedied this by

requiring less concrete to be deposited at the start, thus giving the

rammers time to place the material properly.

"An interesting result was obtained in the smoothness of the inside

surface by using a mixture of different sized stones. When ¾-in. stones

or smaller were used in the arch, the inside was honeycombed; but, where

1 to 1½-in. stones (nothing smaller) were used, the inside was perfectly

smooth, and the same was true of the invert, showing that the use of

larger stones is an advantage and secures more monolithic work. When the

run of the crusher from 1½ to ¾-in. stones was used the work was not at

all satisfactory.

"The difference in cost of mixing by hand and machine is practically

nothing on this kind of work. As the moving of the machine to keep pace

with the progress of the work equals the extra cost of mixing by hand

when the mixing can be done close to the point where the cement is being

placed."

The total cost of the sewers, including excavation, etc., was:

Cost per lin. ft.

9¼-ft. sewer through marsh $32.00

9¼-ft. sewer in cut averaging 24½ ft. 24.00

6½-ft. sewer in cut averaging 12 ft. 10.00

5-ft. sewer in cut averaging 11½ ft. 6.70

~SEWER WITH MONOLITHIC INVERT AND BLOCK ARCH.~--The following records of

construction for a sewer built at Coldwater, Mich., in 1901, are given

by Mr. H. V. Gifford. The sewer had a monolithic invert and a block

arch.

The sewer was circular, having an inner diameter of 42 ins., the

thickness of the invert and the arch alike was 8 ins. Figure 266 is a

cross-section. The concrete was 1 of Portland cement to 6 of gravel.

There were 11 concrete blocks in the ring of the arch, each block being

24 ins. long, 8 ins. thick, 8 ins. wide on the outside of the arch and

5¾ ins. wide on the inside of the arch. A block weighed 90 lbs. which

was too heavy for rapid laying; blocks 18 ins. long would have been

better. Some 8,500 blocks were made. Molds were of 2-in. lumber, lined

with tin, for after a little use it was found the concrete would stick

to the wood when the mold was removed. The four sides of the mold formed

the extrados, the intrados, and the two ends of the block; the other two

sides being left open. When put together the mold was laid upon a 1-in.

board, 12×30 ins., reinforced by cleats across the bottom. The sides of

the molds were held together with screws or wedge clamps. When the

blocks had set, the sides of the molds were removed, and the blocks were

left on the 12×30-in. boards for 3 days, then piled up, being watered

several times each day for a week.

A gang of 14 men made the blocks; 2 screening gravel through 1-in. mesh

screen; 4 mixing concrete; 4 molders; 3 shifting and watering blocks,

and 1 foreman. With a little practice each molder could turn out 175

blocks a day; and since each block measured ¾ cu. ft., the output of the

14 men was 19½ cu. yds. a day. Mr. Gifford informs us that the wages

were $1.50 a day for all the men, except the foreman. The daily wages of

the 14 men were $22, so that the labor of making the blocks was $1.10

per cu. yd.

[Illustration: Fig. 266.--Sewer with Monolithic Invert and Block Arch.]

Each batch of concrete, containing ½ bbl. of Portland cement costing

$1.35 per bbl., made 18 blocks. (1 bbl. per cu. yd.) Since the gravel

cost nothing, except the labor of screening it, the total cost of each

block was 11 to 12 cts., which includes 0.85 cent for use of molds and

mold boards, which were an entire loss. At 12 cts. per block the cost

was $4.32 per cu. yd.

The contract price was $3 per lin. ft. of this sewer, as against a bid

of $3.40 per ft. for a brick sewer.

When the trenching had reached to the level of the top of the invert,

two rows of stakes were driven in the bottom, stakes being 6 ft. apart

in each row, and rows being a distance apart ¼-in. greater than the

outer diameter of the sewer. These stakes were driven to such a grade

that the top of a 2×4-in. cap or "runner" set edgewise on top of them

was at the proper grade of the top of the invert. The excavation for the

invert was then begun, and finished to the proper curve by the aid of a

templet drawn along the 2×4-in. runners. In gravel it was impossible to

hold the true curve of the invert bottom. Concrete was then placed for

the invert. To hold up the sides of the invert concrete, a board served

as a support for the insides, but regular forms were more satisfactory

in every respect except that they were in the way of the workmen. A form

was tried, its length being 6 ft. It was built like the center for an

arch, except that the sheeting was omitted on the lower part of the

invert. It was suspended from the cross-pieces resting on the "runners."

After the concrete had been rounded in place, the form was removed and

the invert trued up. This form worked well in soil that could be

excavated a number of feet ahead, so that the forms could be drawn ahead

instead of having to be lifted out; but in soil, where the concreting

must immediately follow the excavation for the invert, the form is in

the way. The invert was trued up by drawing along the runners a

semi-circular templet having a radius of 21½ ins. Then a ½-in. coat of

1-2 mortar was roughly troweled on the green concrete. Another templet

having a 21-in. radius was then drawn along the runners to finish the

invert.

When the plaster had hardened, two courses of concrete blocks were laid

on each shoulder of the invert, using a 1-2-¼ mortar, the ¼ part

being lime paste. The lime made the mortar more plastic and easier to

trowel. Then the form for the arch was placed, and as each 8-ft. section

of the arch was built, a grout of 1-1 mortar was poured over the top

to fill the joints. Earth was thrown on each shoulder and tamped, and

the center moved ahead.

Common laborers were used for all the invert work, except the plastering

which was done by masons who were paid 30 cts. per hr. Masons were also

used to lay the concrete blocks in the arch. Mr. Gifford states that two

masons would lay at the rate of 100 lin. ft. of arch per day, if enough

invert were prepared in advance. As there were 11 blocks in the ring of

the arch, this rate would be equivalent to 7½ cu. yds. of arch laid per

mason per day.

[Illustration: Fig. 267.--Concrete Block Manhole.]

~COST OF BLOCK MANHOLES.~--The following costs of constructing concrete

block manholes for electric conduit at Rye, N. Y., were recorded by Mr.

Hugh C. Baker, Jr. The arrangement of the blocks, their size and shape

and the dimensions of the completed manholes are shown by Fig. 267. The

blocks were molded of 1-2-5¾-in. broken stone concrete in 30 wooden

molds made by a local carpenter at a cost of from $3.50 to $12 each. The

concrete was placed in the molds very wet, with very little tamping, and

was allowed to set for seven days before the blocks were moved to the

work. The molds were left in place from 24 to 36 hours. With the

facilities at hand six complete sets of top blocks were made each day by

four men, when no wall blocks were being made, and half a set (15) wall

blocks and two sets of top blocks were made each day by four men. The

cost of the block manholes complete was as follows, per manhole:

30 wall blocks, 2½ cu. yds. $21.00

6 cover blocks, 1½ cu. yds. reinforced 4.27

I-beams for cover, in place 5.40

Supervision, freight, hauling 5.6 tons concrete 9.38

Labor placing cover, 3 hrs. at 15 cts. 0.45

Labor placing walls, 20 hrs. at 15 cts. 3.00

------

Total, exclusive of iron cover $43.50

~CEMENT PIPE, CONSTRUCTED IN PLACE.~--In constructing 8-in. cement sewer

for the Foster Armstrong Piano Co.'s works at Rochester, N. Y., a gang

of seven men averaged 300 ft. of pipe per 10-hour day, using a Ransome

pipe mold. The mold is shown by Fig. 268. It is made of sheet steel,

with an inner core 10 ft. long, the front end of which is surrounded

with a sheet steel shell that serves as an outer form for the pipe. The

mortar mixed rather dry was packed into the annular space between core

and shell by one man, using a short wooden rammer. A second man kept the

mold slowly moving forward by operating the lever, which by means of a

ratchet and drum winds up a wire rope stretched ahead to a deadman in

the trench bottom. As the mold moves ahead it leaves behind it the

cement pipe. A third man carefully filled under the invert and over the

haunches of the green pipe with earth to give it support. The following

was the itemized cost per day, 300 ft. of pipe laid:

6 men at $1.70 per 10-hour day $10.20

1 foreman 3.00

3 bbls. cement at $1.25 3.75

3.3 cu. yds. sand at 85 cts. 2.80

Water 0.15

------

Total for 300 lin. ft. $19.90

This is equivalent to 6.63 cts. per lin. ft. of pipe.

[Illustration: Fig. 268.--Ransome Continuous Mold for Concrete Pipe

Construction.]

In Trans. C. E., Vol. 31, 1894, p. 153, James D. Schuyler gives the cost

of cement pipe made by the Ransome system for the Denver Water Works.

There is a wrought iron shell of the size of the inner diameter of the

pipe forming the inner mold. To this shell is attached a "leader" and

"saddle" of larger diameter forming the outer mold. These molds are

drawn slowly along the trench by a cable and horse whim, and the

concrete is shoveled continuously into the core space between the molds

and rammed on a long incline. The top half, or arch, of the pipe is

supported by sheet iron plates (2 ft. wide), placed one after another on

the forward end of the mold; and, being clamped together at the top and

sides, remain in position after the mold is slid out from under them.

After the mold has passed along, these iron plates are supported by

upright sticks and by horizontal clamping rods. The plates are left in

place for 24 to 48 hrs. The concrete, made 1-3½, river sand and gravel,

was machine mixed. A gang of 30 men mixed, wheeled, shoveled and tamped

the concrete, attended to the plates, cleaning and greasing them, etc.

This gang would make short runs at the rate of 900 lin. ft. of pipe a

day, but counting stoppages, the average rate was 300 ft. a day. The

inner diameter of the pipe was 38 ins., and its bottom was molded flat

for a width of 18 ins. The concrete shell was 2½ to 3 ins. thick. The

pipe was washed with pure cement grout, applied with brushes after

removing the iron plates. With cement at $3.75 per bbl., gravel at $1.25

per cu. yd., and labor at $1.75 to $2 per day, the cost of this pipe was

$1.35 to $1.50 per ft., after the gang was well organized.

~PIPE SEWER, ST. JOSEPH, MO.~--In constructing extensions to 36-in.,

42-in., 48-in. and 72-in. sewers at St. Joseph, Mo., reinforced concrete

pipe of the form shown by Fig. 269 was employed. The thickness of shell

for the various sizes was 4 ins., 4½ ins., 5 ins., and 7 ins. All sizes

were made in 3-ft. lengths, one end of which is rebated and beveled to

form a spigot and the other end of which is chamfered on the inner edge

to receive the bevel of the spigot. This jointing leaves a

circumferential groove, into which the hooked ends of the longitudinal

reinforcing bars project in such a way that a circular hoop can be

threaded through them to connect successive lengths. The reinforcement

is of the same form for all sizes of pipe, but seven longitudinals were

used in the 72-in. size and five for all smaller sizes; the

circumferential bars were in all cases spaced one 9 ins. from each end.

The pipe, as described, is the standard pipe made by the Reinforced

Concrete Pipe Co., of Jackson, Mich., and is covered by patents. The

practice of this company is to manufacture the pipe itself on the ground

and furnish it to the contractor. It does not contract to build sewers

nor does it dispose of rights to manufacture to contractors.

[Illustration: Fig. 269.--Jackson Concrete Sewer Pipe.]

_Pipe Molding._--The pipe is molded endwise. A bottom plate so shaped as

to form the hub or receiving end of the pipe is set up. On the upper or

inner flange of this cast iron bottom plate is set the core defining the

inside diameter of the pipe; this core is in four segments of sheet

steel. The longitudinal reinforcing bars are next inserted in slots in

the bottom plate and the outside form of sheet steel is then set up on

the lower and outer flange of the bottom plate. Spacing clips on the top

edge of the outer shell hold the tops of the reinforcing bars in

position. The concrete is then shoveled into the annular mold and tamped

until it reaches the level for the first circumferential reinforcing

bar; this is then placed by removing the spacing clips, threading the

hoop over the longitudinal bars and sliding it down to position. Filling

and tamping then proceeds until the second hoop is to be placed; this is

placed exactly like the first, and filling and tamping then proceeds

until the mold is filled. At the St. Joseph work a 1-2-3 mixture, with

crushed limestone aggregate ranging from pea size to 1-in. stone was

used. The molding was done in tents which were heated by coke fires in

salamanders in freezing weather.

_Pipe Laying._--In laying, the pipes are handled and lowered into

position just as are cast iron water pipe. Successive lengths are placed

by inserting the spigot ends into the chamfered hub ends and then

threading the tie hoop through the hooked ends of the projecting

longitudinal reinforcing bars. A strip of galvanized iron is then passed

under the pipe and bent up so as to girdle the circumferential groove

except for a space at the top; the groove is then poured with a wet 1-2

cement mixture, which, when hardened, completes the joint.

~COST OF MOLDING SMALL CEMENT PIPE.~--Mr. Albert E. Wright gives the

following account of the method and cost of molding and laying 6 to

12-in. cement pipe for irregular work at Irrigon, Ore.: The pipe was 6

to 12 ins. inside, made of Portland cement and clean, sharp sand of all

sizes up to very coarse. The mortar was mixed rather dry, but very

thoroughly, using 14.1 cu. ft. of sand to 1 bbl. of cement, or very

closely a 1 to 4 mixture. From six to seven buckets of water were used

to each barrel of cement, except for the 6-in. pipe, for which the

mortar had to be made somewhat stiffer in order to remove the inner

form, which was not made collapsible as in the larger sizes.

The forms were sheet iron cylinders with a longitudinal lap joint that

could be expanded after molding the pipe, and removed without injuring

the soft mortar. The inner form was self-centering, so that there was

little variation in the thickness of the pipe.

Four men were required in making cement pipe by hand; one mixed the

mortar, and wheeled it to the place of work; another threw it into the

form a little at a time with a hand scoop; a third rammed it with a

tamping iron, and a fourth kept the new pipe sprinkled, and applied a

coat of neat cement slurry to the inside when it was sufficiently hard.

In molding, the form of the bell at the bottom was secured by an iron

ring that was first dropped into the form, and the reverse or convex

form at the top was made with a second ring. While still in its form

the pipe was rolled or lifted into its place in the drying yard, and the

form was then carefully removed. A very slight blow in removing the form

would destroy the pipe, and a considerable number, especially of the

larger sizes, collapsed in this way, and had to be remolded. To avoid

handling, the pipe was stacked on end a few feet from the place of

mixing, the form being moved as the yard filled with pipe. One crew of

four men could make about 250 joints or 500 lin. ft. of pipe a day.

As soon as hard enough, the pipe was turned end for end, and was then

kept wet for several weeks before being laid. The coating of neat cement

on the inside was applied with a short whitewash brush, and was a small

item in the cost.

In laying, the trench was carefully finished to grade in order to have

the joints close nicely, and the ends were well wet with a brush. The

mason then spread mortar, mixed 1 to 2, on the end of the pipe, and laid

a bed of mortar at the bottom of the joint. He then jammed the section

into place, and swabbed out the inside of the joint with a stiff brush,

to insure a smooth passage for the water. A band or ring of mortar was

spread round the outside of the joint as an additional reinforcement.

One barrel of cement would joint about 300 sections of pipe. The

materials cost as follows: Portland cement, per bbl., $4.45; labor, per

day, $2; foremen, per day. $2.50 to $3; hauling, per load mile (1 cu.

yd.), 20 cts.; sand, free at pit; water, free.

The pipe was all of a 1-4 sand and cement mortar, and the amount of

cement in one foot of pipe was arrived at by assuming that where the

sand has voids in excess of the cement used, the mortar will occupy 1.1

(see Chapter II) times the space of the dry sand, which yields the

following formula:

Where--

c = cost per bbl. of cement, or $4.45.

n = cu. ft. in one bbl. (taken at 3.5 here).

s = ratio of sand to cement, or 4.

d = inside diameter in inches.

t = thickness of pipe in inches.

l = length of pipe considered, or 1 ft. here.

Then:

c × l × [pi] × (dt + t²)

Cement-cost per foot = --------------------------,

n × s × 1.1 × 144

which gives here =

4.45 × 1 × 3.142(dt + t²)

------------------------------- = 0.00631(dt + t²).

3.5 × 4 × 1.1 × 144

This gave the following cement costs per lineal foot:

Concrete Construction: Methods and Costs · 第 32 / 34 章