The materials were hauled about 1 mile from railway to site of work.

Cement, including freight and haulage, cost $1.97 per barrel. Limestone

and screenings cost 50 cts. per cu. yd. f. o. b. at quarry. No freight

charges are included in cost of any of the materials except cement. The

cost of the 306 ft. of culvert was as follows:

Item. Total. Per lin. ft. Per cu. yd.

Labor $443.14 $1.45 $3.35

Stone and screenings 78.50 0.25 0.60

Cement 307.53 1.01 2.34

Forms 12.00 0.04 0.09

------- ----- -----

Total $841.17 $2.75 $6.38

[Illustration: Fig. 171.--Small Culverts, Pennsylvania R. R.]

~26-FT SPAN ARCH CULVERT.~--The culvert was 62 ft. long and 26-ft. span

and was built of 1-8 and 1-10 concrete mixed by hand. The wages paid

were: General foreman, 40 cts. per hour; foreman, 25 cts. per hour;

carpenters, 22½ to 25 cts. per hour, and laborers, 15 cts. per hour. The

cost of the concrete in place, exclusive of excavation but including

wing walls and parapet, was as follows:

Per cu. yd.

0.96 bbl. cement, at $1.60 $1.535

1.03 tons coarse gravel, at $0.19 0.195

0.40 tons fine gravel, at $0.21 0.085

0.32 tons sand, at $0.36 0.115

Tools, etc. 0.078

Lumber for forms and centers 0.430

Carpenter work on forms (23 cts. hr.) 0.280

Carpenter work platforms and buildings 0.050

Preparing site and cleaning up 0.210

Changing trestle 0.085

Handling materials 0.037

Mixing and laying, av. 15½ cts. per hr. 1.440

------

Total per cu. yd $4.540

There were 1,493 cu. yds. of concrete in the work. The excavation cost

$463 and the total cost was $7,243.

~COST OF RAILWAY CULVERT.~--The culvert was for a single track railway and

contained 113 cu. yds. of concrete and required 36 cu. yds. of

excavation. The figures are given by C. C. Williams as follows:

Cost of Material.

Kind and Amount of Material. Unit Price. Cost.

Stone, 113.2 tons $.70 $ 79.24

Sand, 46.8 yds. .55 25.74

Cement, 137 bbls. .85 116.45

-------

Total $221.43

Lumber 52.50

Rail and bolts 36.60

-------

Total $ 89.10

Excavation.

Labor, 189 hours at .15 $ 28.35

Foreman, 60 hours at .30 18.00

-------

Total $ 46.35

Concrete.

Labor, 683 hours at .15 $102.45

Foreman, 130 hours at .30 39.00

-------

Total $141.45

Forms.

Carpenters, 313 hours at .225 $ 70.42

Labor, 30 hours at .15 4.50

-------

Total $ 74.92

Handling Materials.

Moving material, 245 hours at .15 $ 36.75

Unloading material, 95 hours at .15 14.25

Foreman, 20 hours at .30 6.00

-------

Total $ 57.00

Superintendence and Office.

Superintendent, 6 hours at .50 $ 3.00

Office 10.00

-------

Total $ 13.00

-------

Grand total $643.25

Proportional Costs.

Per cent.

Cost of Total

Per Yard Cost of

Item. Cost. Concrete. Concrete.

------

Concrete material $221.43 $1.96 7.1

Laying concrete 141.45 1.25 23.6

Lumber 52.50 .46 08.7

Rail and bolts 36.60 .32 06.1

Building forms 74.92 .67 13.3

Handling material 56.90 .50 09.0

Superintendent and office 13.00 .12 02.2

----- ------

Total $5.28 100.00

Excavation 46.35 1.28

-------

Total $643.15

Contractor's Receipts.

113 yds. concrete at $5.95 $672.35

36 yds. excavation at .30 10.80

-------

Total $683.15

Total cost 643.15

-------

Profit, 5.9% of contract price $ 40.00

~12-FT. CULVERT, KALAMAZOO, MICH.~--A portion 1,080 ft. long of a new

channel built in 1902-3 for a small stream flowing through the city of

Kalamazoo, Mich., was constructed as an arch culvert of the form shown

by Fig. 172. The concrete section is reinforced on the lines indicated

by a double layer of woven steel wire fabric. The concrete was

approximately a 1 cement, 6 sand and gravel mixture.

[Illustration: Fig. 172.--Cross-Section of Culvert at Kalamazoo, Mich.]

The centers were built in sections 12½ ft. long of the form and

construction shown by Fig. 173, and a sufficient number was provided to

lay twelve sections of invert and six sections of arch. The arch centers

were arranged to be uncoupled at the crown; this with the hinges at the

quarter points permitted the two halves to be separated and each half to

be folded so that it could be carried from the rear of the work through

the forms still in place and erected again for new work. When in place

the center ribs rested on the side forms which set on the invert

concrete and are braced apart by the hinged cross-strut. This

cross-strut was the key that bound the whole structure together; the

method of removing this key is indicated by Fig. 174. From his

experience with these centers the engineer of the work, Mr. Geo. S.

Pierson, remarks:

"In work of this kind it is very important to have the centering

absolutely rigid so it will not spring when concrete is being tamped

against it and thus weaken the cohesion of the concrete. It is also

important to have the arrangement such that all the centering can be

removed without straining or jarring the fresh concrete. The centers

were generally removed in about three or four days after the concrete

arch was in place."

[Illustration: Fig. 173.--Center for Culvert at Kalamazoo, Mich.]

The invert concrete was brought to form by means of templates, Fig. 173,

and straight edges. The side forms were then placed and braced apart by

the struts and concreting continued to the skewback plane indicated in

Fig. 173. The arch form was then placed; it rested at the edges on the

side forms and was further supported by center posts bearing on boards

laid on the bottom of the invert. A template, Fig. 175, was used to get

the proper thickness and form of arch ring. Outside forms were used to

confine the concrete at the haunches but nearer the crown they were not

required.

[Illustration: Fig. 174.--Hinged Cross Strut for Center for Culvert at

Kalamazoo, Mich.]

Much of the work was done when the thermometer, during working hours,

ranged from 12° to 25° above zero. When the temperature was below

freezing, hot water was used in mixing the concrete and on a few of the

coldest days salt was dissolved in the water. In addition each section

of the work was covered with oiled canvas as soon as completed, and the

conduit was kept closed so far as was practicable to retain the heat.

Concreting was never stopped on account of cold weather.

[Illustration: Fig. 175.--Templet for Arch Ring for Culvert at

Kalamazoo, Mich.]

Account was kept of the cost of all work, and the figures obtained are

given in the following tables:

Labor Force, Materials Used and Progress of Work.

Average progress per day in feet 18.0

Greatest number of feet laid in one day 28

Average number of laborers per day mixing and wheeling 10.04

Average number of laborers per day placing concrete 5

Average number of laborers per day setting up forms 4.57

Cubic yards of concrete mixed and wheeled per day per man 1.96

Cubic yards of concrete placed per day per man 3.54

Cubic yards of concrete per lin. ft. 0.95

Barrels of cement per lin. ft. 1.18

Barrels of cement per cu. yd. 1.24

Proportion of cement to sand and gravel 1-6

Itemized Cost per Lineal Foot.

Sand and gravel $0.42

Cement 2.44

Mixing and wheeling concrete 0.98

Labor placing concrete 0.47

Forms and templates 0.30

Metal fabric 0.39

Setting up forms 0.43

Finishing 0.09

Tools, general and superintendence 0.43

-----

Total per lineal foot $5.95

The cost per cubic yard was thus $6.26. Wages were $1.75 per day.

~METHOD AND COST OF MOLDING CULVERT PIPE, CHICAGO & ILLINOIS WESTERN R.

R.~--During 1906, the Chicago & Illinois Western R. R., Mr. O. P.

Chamberlain, Chief Engineer, built a number of culverts of concrete pipe

with an interior diameter of 4 ft., and 6-in. shells. Fig. 176 shows the

forms in which the pipe was molded. Both forms are of ordinary wooden

tank construction. The inner form has one wedge-shaped loose stave which

is withdrawn after the concrete has set for about 20 hours, thus

collapsing the inner form and allowing it to be removed. The outer form

is built in two pieces with 2×5/8-in. semi-circular iron hoops on the

outside, the hoops having loops at the ends. The staves are fastened to

the hoops by wood screws 1¾ ins. long driven from the outside of the

hoop. When the two sides of the outer form are in position, the loops on

one side come into position just above the loops on the other side, and

four ¾-in. steel pins are inserted in the loops to hold the two sides

together while the form is being filled with concrete and while the

concrete is setting. After the inner form has been removed, the two pins

in the same vertical line are removed and the form opened horizontally

on the hinges formed by the loops and pins on the opposite side. The

inner and outer forms are then ready to be set up for building another

pipe.

[Illustration: Fig. 176.--Form for Molding Culvert Pipe.]

The concrete used in manufacturing these pipes was composed of American

Portland cement, limestone screenings and crushed limestone that has

passed through a ¾-in. diameter screen after everything that would pass

through a ½-in. diameter screen had been removed. The concrete was mixed

in the proportions of one part cement to three and one-half parts each

of screenings and crushed stone. All work except the building of the

forms was performed by common laborers. In his experimental work Mr.

Chamberlain used two laborers, one of whom set the forms, and filled

them and the other of whom mixed the concrete. The pipes were left in

the forms till the morning of the day after molding. The two laborers

removed the forms filled the day before, the first thing in the morning,

and proceeded to refill them. The average time the concrete was allowed

to set before the forms were removed was 16 hours. Mr. Chamberlain

believes that with three men and six forms the whole six forms could be

removed and refilled daily. Based on the use of only two forms with two

laborers removing and refilling them each day, and on the assumption

that a single set of forms costing $40 can be used only 50 times before

being replaced, Mr. Chamberlain estimates the cost of molding 4-ft.

pipes as follows:

2 per cent, of $40 for forms $0.80

1.1 cu. yds. stone and screenings at $1.85 2.04

0.8 bbls. cement at $2.10 1.68

10 hours' labor at 28 cts. 2.80

-----

Total per pipe $7.32

This gives a cost of $1.83 per lineal foot of pipe or practically $7 per

cu. yd. of concrete. The pipe actually molded cost $2.50 per lin ft., or

$9.62 per cu. yd. of concrete, owing to the small scale on which the

work was carried on--the laborers were not kept steadily at work.

The pipes were built under a derrick and loaded by means of the derrick

upon flat cars for transportation. At the culvert site they were

unloaded and put in by an ordinary section gang with no appliances other

than skids to remove the pipes from the cars. As each four-foot section

of this pipe weighs about two tons, it was not deemed expedient to build

sections of a greater length than 4 ft., to be unloaded and placed by

hand. On a trunk line, however, where a derrick car is available for

unloading and placing the pipes, there is no reason why they should not

be built in 6 or 8-ft. sections.

CHAPTER XIX.

METHODS AND COST OF REINFORCED CONCRETE BUILDING CONSTRUCTION.

If we set aside concrete block construction, virtually all concrete used

in building construction is reinforced; plain monolithic or mass

concrete now, as in the past, is one of the secondary building

materials. It is reinforced concrete building construction that is

discussed in this chapter. In no class of concrete work is the

contractor's responsibility for the successful outcome of the work

greater than in reinforced concrete building construction. No degree of

excellence in design can make up for incompetent, careless or dishonest

work in construction. This is true not merely in the general way that it

is true of all engineering construction--it is true in a special way

peculiar to the material. Except for the reinforcing steel, the

contractor for concrete building work has no guarantee of the quality of

any element of his work except his own faithful care in performing every

task that combines to produce that element. The quality of his concrete

depends upon the care with which he has chosen his cement, sand and

stone, and on the perfection with which he has incorporated them into a

homogeneous mixture. The quality of his beam or column, then, depends

upon the care with which the concrete is placed in position with the

reinforcement and with which the supporting forms are maintained until

the member is amply strong to do without support. There is no certainty

of any detail except the certainty that is had by performing every part

of the work as experience has taught that it should be performed if

perfect results are to be attained. We have dwelt thus emphatically on

the responsibility in concrete building work of the contractor for the

reason that in the past it has been upon the contractor that the burden

of failure has been generally shifted.

The construction work of buildings is divided into (1) construction,

erection and removal of forms; (2) fabrication and placing of

reinforcement; (3) mixing, transporting and placing concrete.

CONSTRUCTION, ERECTION AND REMOVAL OF FORMS.

The stereotyped text-book statement that forms must be true to

dimensions and shape and rigid enough in construction to maintain this

condition under all loads that they have to sustain mentions only one of

the factors that the constructing engineer or the contractor has to keep

in mind in designing such forms. His design must be made true and rigid

at the least possible cost for first construction of lumber and

carpenter work; it must be made with the plan in mind of using either

the same forms as a whole or the same form material several times in one

structure; it must be made with a view to convenience in taking down,

carrying and re-erecting the forms the second or third time; and it must

be made with the object in sight of securing the greatest salvage value

either in forms fit for use again or in form lumber that can be sold or

worked up for other purposes.

The general conditions governing the computation and design of economic

form work are discussed in Chapter IX.

~COLUMN FORMS.~--Concrete columns are usually square or rectangular in

section, with, commonly, chamfered or beveled corners. The popularity of

these sections is due very largely to the simplicity of the forms

required. When hooped reinforcement is used, the column section is

always circular or polygonal. Hollow sections, T-section and channel

sections are rarely employed and then only for wall columns.

Column forms should be made in units which can readily be assembled,

taken apart and re-assembled. The number, arrangement and size of the

units are determined by the shape and size of the column and the means

adopted for handling the forms. For square or rectangular columns there

will be usually four units of lagging, one for each side, plus the

number of clamps or yokes used to bind the sides together. Yokes or

clamps will seldom be spaced over 3 ft. apart unless very heavy lagging

is used; 2 ft. spacing for yokes is common. For circular columns two

units of lagging are necessary and this is the number commonly used; the

yokes or hoops are spaced about as for rectangular columns. Metal forms

can be used to good advantage for cylindrical columns. Forms for

polygonal columns are difficult to construct in convenient units. Forms

built complete a full story high and concreted from the top are

essential where wet and sloppy concretes are used. In Europe, where

comparatively dry concretes are employed and where the reinforcement is

commonly placed a piece at a time as concreting progresses, three sides

of a rectangular form are erected full height and the fourth side is

built up as the concrete and metal are placed. This construction is now

less common, even abroad, than it was, since wetter mixtures are coming

to be approved by European engineers to a greater extent now than

formerly. It is a time consuming method and with wet mixtures it has

nothing to recommend it. For lagging 1¼ and 2-in. plank are commonly

used; with yokes spaced 2 ft. apart the lighter plank is amply strong

and reduces the weight of the units to be handled as well as the amount

of form lumber required.

[Illustration: Fig. 177.--Form for Rectangular Column for Factory

Building, Cincinnati, O.]

Column forms should always be constructed with an opening at the bottom

by means of which the reinforcement can be adjusted and sawdust,

shavings and other material cleaned out.

~Rectangular Columns.~--The form shown in section by Fig. 177 was used in

constructing a factory building at Cincinnati, O. Two 2×4-in. studs at

each corner carry the horizontal side lagging boards and are clamped

together by yokes composed of four hardwood corner saddles connected

around the form by a hooked rod with center turnbuckle on each side. No

nails are used in assemblying the parts; the same studding and yokes

serve for several sizes of column, the lagging alone being changed. The

lumber required for studding is 5½ ft. B. M. per foot of column length.

The lumber required for lagging, using 1 in. boards, would be 2-2/3 ft.

B. M. for a 12-in. column, and 2/3 ft. B. M. would be added for every

2-in. increase in size of the column. About 3½ ft. B. M. is required for

each set of four corner saddles. With the studs rabbeted at the mill,

the carpenter work is reduced to the simple task of sawing the boards

and struts to length. The form is taken down by simply unscrewing the

turnbuckles; it can be erected by common labor in charge of one

carpenter to attend to the plumbing and truing-up. The form can be used

over and over and for columns of different sizes without change except

in the length of the lagging boards.

The form shown by Fig. 178 was used in constructing a nine-story

warehouse at St. Paul, Minn.; it is a design which has become almost

standard with a number of large building contractors. In this

construction lagging boards the full length of the column are used and

are held without nails by yokes. The yokes consist of two heads of wood

held together by threaded rods with nuts; between the rods and the

lagging are struts or blocks serving both as spacers and to hold the

lagging to plane and surface. The yoke proper is adjustable to the

extent of the threaded portions of the tie rods. It is to be noticed

that the lagging boards are not connected by battens or cleats,

therefore, two or three widths of stock serve for all ordinary changes

in size of columns and carpenter work is limited to sawing them to

length. Furthermore as the boards are full column length, their salvage

value when removed from the forms is high. Common laborers under a

carpenter foreman can assemble and erect the form. For a 12-in. column

and using 3×4-in. yokes spaced 2 ft. apart and 1¼-in. lagging, this form

requires about 12 ft. B. M. of lumber per foot length of column. The

column form shown by Fig. 226 for the six-story building described in a

succeeding section differs from the one described only in the details

of the yoke construction. In place of the struts between the wooden

heads of the yoke a cleat is nailed across the projecting ends which has

to be pried loose every time the yoke is removed and nailed into place

again every time the yoke is put onto another form; these repeated

nailings soon destroy the yoke heads. This form as constructed requires

about 8¾ ft. B. M. of lumber per foot length of 12-in. column, which is

3¼ ft. B. M. less than is required for the form shown by Fig. 177. The

saving comes entirely in the yoke construction.

[Illustration: Fig. 178--Form for Rectangular Column for Warehouse at

St. Paul, Minn.]

The form shown by Fig. 238 is of the same general type as are the two

just described, the chief difference in detail being in the yoke

construction and in the forming of the lagging boards into a panel or

unit for each side by means of battens. This panel construction makes a

lagging unit which is more convenient to handle, but less convenient to

adapt to changes in size of column. The salvage value of the lumber is

also reduced by the nailing. Assuming 1¼-in. lagging and a yoke spacing

of 2 ft., to permit direct comparison, this form requires 10½ ft. B. M.

of lumber per foot length of 12-in. column as compared with 12 ft. B. M.

for the form shown by Fig. 177 and 8¾ ft B. M. for the form shown by

Fig. 178. As actually constructed with 2-in. lagging the form shown by

Fig. 238 requires about 14 ft. B. M. of lumber per foot length of 12-in.

column.

The French constructor, Hennebique, uses the column form construction

shown by Fig. 179. Three sides of the forms are built full length of

vertical plank and the fourth is built up of horizontal lagging nailed

on a board at a time as concreting progresses. In place of rectangular

yokes, steel clamps of special form are used to hold the lagging in

place. To tear down this form requires drawing the nails in the

horizontal lagging and the knocking loose of the clamps. The vertical

lagging is of necessity connected by battens into panels to make it

possible to hold it in place by the form of clamp used. Assuming 2-in.

vertical lagging with 7/8×3-in. battens every 3 ft., and 7/8-in.

horizontal lagging this form requires about 12 ft. B. M. of lumber for

every foot length of 12-in. column. This form seems to offer no

particular merits to American eyes: there is practically no saving in

lumber over forms with rectangular yokes and the clamp shown, while

adjustable, is not nearly so rigid and secure a bond for the lagging as

is a good yoke.

[Illustration: Fig. 179.--Form Used by Mr. Hennebique for Rectangular

Columns.]

[Illustration: Fig. 180.--Form for Rectangular Column for a Factory

Building, New York City.]

The form shown by Fig. 180 is an extreme example of nailed construction

throughout, no yokes or clamps being used. It was used in constructing a

factory building in New York City. Horizontal lagging nailed to

vertical studs was used for all four sides; three sides were built up

full height and the fourth side was placed a board at a time as

concreting progressed. This form required 7-1/3 ft. B. M. of lumber per

foot length of 12-in. column, which is probably about as low in lumber

as column form construction can be got. The labor of tearing down and

re-erecting the form would be high as also would the waste of lumber.

Nailed forms of this type are rarely used.

[Illustration: Fig. 181.--Form for T-Section Wall Column.]

[Illustration: Fig. 182.--Form for Corner Wall Column.]

The form shown by Fig. 181 was used for molding T-section wall columns

for a power station. It is noteworthy for its section; because of the

provision for molding grooves in the two sides to which the curtain

walls join, and because of the manner in which three of the eight sides

were built up as the concreting progressed. The sides a b c, d e and

f g h were erected in full column units and the sides c d, e f and

h a were erected in sections 2 ft. high as concreting progressed. The

yokes were spaced 2 ft. apart. Using 1¼-in. stuff for yokes and lagging

this form as built required about 16 ft. B. M. per foot length of

column. Except for the beveling of the mold for the curtain wall

recesses, the framing is all plain saw and hammer work.

[Illustration: Fig. 183.--Core Form for Hollow Column.]

A corner wall column form is shown by Fig. 182 and as this was an

example of hollow column work the section of the concrete within the

form is shown. Forms of this shape and of T-section are properly classed

as special form work so that the examples given here are helpful merely

as indicating general methods that may be followed. This particular form

required 15¾ ft-B. M. of 7/8-in. lagging per foot of column length, and,

neglecting the special top frame, about 16 ft. B. M. of "staging" per

foot to support the lagging. The core forms for molding the hollow

spaces in the columns of this particular building are shown in Fig. 183.

The cross pieces or keys carried on the 5/8-in. bolts as pivots are

revolved a quarter turn to slip clear of the slots and permit the sides

to close together and free the core for withdrawal. In many cases the

contractor will find it preferable to use thin sheet metal core molds or

light wooden cores and leave them in place. In one case known to the

authors where hollow wall columns were used as hot air ducts for a

heating system the duct was laid up of one row of bricks, encircled by

the column form and the annular space concreted around the brick duct as

a core. The rare use of irregular columns makes form and core

construction for them a special problem requiring special detailed

estimates in each case. The channel section wall column form shown by

Fig. 230 is a case in point; here the form became practically a portable

mold for duplicating columns as many times as was desired.

[Illustration: Fig. 184.--Form for Large Rectangular Columns.]

As an example of form work for very large columns or pillars that shown

by Fig. 184 is particularly good; it was used for constructing eight

3-ft. square pillars for a water tank tower. The lagging consists of

four panels made by nailing horizontal boards to vertical studs. The

panels are clamped together by rectangular yokes spaced 3 ft. apart.

There are nearly 27½ ft. B. M. of lumber per foot length of 3-ft. column

in this form.

[Illustration: Fig. 185.--Adjustable Form for Rectangular Columns.]

The form shown by Fig. 185 was used by Mr. R. W. Maxton in constructing

a large factory building at St. Louis, Mo., and is notable for the means

adopted for centering the forms and for reducing their lateral

dimensions to fit them for molding the decreasingly smaller columns of

the upper floors. To center the forms the short angles A A are molded

into the concrete so as to project slightly above the tops of the floor

slab. Also the pieces of wood C are molded into the floor slab. The

form is set over the angles and lined up truly by nailing the blocks B

to the blocks C. It will be noticed also that the column mold bears

only at the four corners the lagging being cut away somewhat on each

side so as to afford an opening for cleaning. The lagging for the sides

of the column mold is battened together to form four units or panels

which are held together by iron clamps of the form shown. Lag screws

are used everywhere in place of nails. The notable feature, however, is

the piecing out of the lagging panels with 1-in. strips, one or more of

which can be ripped off on each side to reduce the size of the forms as

the columns grow smaller toward the top of the building.

~Polygonal Columns.~--Forms for polygonal columns require more lumber and

more carpenter work and are less susceptible of ready arrangement into

units than forms for rectangular columns. There is no approach to a

uniform practice in their construction and the few forms shown here are

merely specific examples.

[Illustration: Fig. 186.--Form for Octagonal Column for a Factory

Building.]

The form shown by Fig. 186 was used for interior columns of octagonal

section with hooped reinforcement for a factory building. This form for

a 12-ft. octagonal column 24 ins. across between sides requires

approximately 325 ft. B. M. of lumber. The form shown by Fig. 187 was

used by the same engineer in another building; it is, as will be noted,

in four units coming apart in joints at diagonally opposite corners.

This form for an octagonal column 18 in. across between sides required

about 13 ft. B. M. of lumber per foot of column length, with yokes

spaced 3½ ft. apart.

The form shown by Fig. 188 was used in a large warehouse at Chicago,

Ill. It will be noted from the dotted lines that one yoke clamps the

sides a a, the next the sides b b and so on. This does away with

triangular blocking to hold the corner boards that is used in the form

shown by Fig. 187. Six pairs of yokes were used for each column so that

the yoke spacing was about 2 ft. With 2×6-in. yokes and 1½-in lagging a

form for a column 18 ins. between sides would require some 17 ft. B. M.

per foot of column length.

[Illustration: Fig. 187.--Form for Octagonal Column for Factory

Building.]

[Illustration: Fig. 188.--Form for Octagonal Column for a Warehouse,

Chicago, Ill.]

~Circular Columns.~--Circular columns have been most frequently molded in

steel forms, and these are by all odds the best for general work. Made

in two parts of sheet steel and in sections that are set end to end one

on another a form is obtained which is easy to erect, remove and

transport. Wood forms for circular columns are rather clumsy affairs and

are expensive to construct. Such a form, Fig. 190, is described in the

succeeding section; another is shown by Fig. 189. This form was used

successfully for filling and encasing steel columns for a fireproof

building in Chicago, Ill., and is a favorite circular form construction

in Europe. It is apparent that the hooping needs to be very heavy and

that the form is one that will be hard to handle and rather expensive to

make.

In several instances, where hooped reinforcement has been used, the

hooping has been wrapped with, or made of, expanded metal or other

mesh-+work, and the concrete deposited inside the cylinder thus formed,

without other form work. A six-story factory building in Brooklyn, N.

Y., was built with circular interior columns from 28 ins. to 12 ins. in

diameter, reinforced by a cylinder of No. 10 3-in. mesh expanded metal,

stiffened lengthwise by four round rods 1 in. in diameter for larger

columns to ½ in. in diameter for smaller columns. This reinforcement was

set in place and wrapped with No. 24 ½-in. mesh metal lath, and the

cylinder was filled with concrete and plastered outside. A moderately

dry concrete is essential for such construction.

[Illustration: Fig. 189.--Form for Circular Column.]

The method of molding shells with the hooping embedded described for the

Bush terminal factory work in another section is another way of avoiding

form work of the usual type.

Light steel forms as well as the special construction noted must be

supplemented by staging to hold them in line and to carry the ends of

the girder forms that are ordinarily carried by the column forms. Four

uprights arranged around the column so as to come under the connecting

girders are commonly used; they are set close enough to the column to

hold the form plumb by means of blocks or wedges.

~Ornamental Columns.~--Forms for ornamental columns call for special

design and construction. For many purposes, such as porch and portico

work, the best plan is to mold the columns separately and erect them as

stone columns of like character are erected. Metal forms of various

patterns are made by firms manufacturing concrete block molds and can be

purchased from stock or made to order. Where the column is to be molded

in place form construction becomes a matter of pattern making, the

complexity and cost of which depends entirely upon the architectural

form and ornament to be reproduced. The molding of ornament and

architectural forms in concrete is discussed in Chapter XXIII, and the

two examples of ornamental column form work given here from recent work

indicate the task before the builder.

[Illustration: Fig. 190.--Form for Molding Fluted Cylindrical Column.]

The form shown by Fig. 190 was used for molding in place fluted columns

used in a court house constructed at Mineola, N. Y. The lagging in the

form of staves forms a 24-sided polygon and is held in position by hoops

and yokes. The molds for the flutes were formed by inserting screws from

the outside so as to penetrate the staves and molding half-round ribs of

plaster of Paris over them by means of the simple device shown. To

dismantle the form the screws were removed and the lagging taken down

leaving the plaster of Paris in place as a protection to the thin edges

until the final finishing of the building.

The methods illustrated by Fig. 191 were employed in molding columns in

place for a church at Oak Park, Ill. The bottom portions of these

columns were plain square sections molded in place in square molds. The

top portions were heavily paneled. The four corner segments were cast in

glue molds backed by wood with wires embedded as shown. After becoming

hard they were set on end on the plain column and tied and braced as

shown. The side openings were then closed by wooden forms and the

interior space was filled with concrete. The surface facing for these

columns was bird's-eye gravel and cement, with very little sand, mixed

very dry and placed and tamped with the coarse concrete backing.

[Illustration: Fig. 191.--Form for Ornamental Column for Church at Oak

Park, Ill.]

~SLAB AND GIRDER FORMS.~--Slab and girder construction for roofs and

floors is of three kinds: (1) Concrete slab and steel beam construction

in place; (2) concrete slab and girder construction in place (3)

separately molded slab and beam construction. The third method of

construction is distinct from the others in respect to form work as well

as other details and is considered separately in Chapter XX.

~Slab and I-Beam Floors.~--Centers for floor slabs between steel I-beams

are made by suspending joists from the beam flanges and covering them

with lagging. Frequently the joists and lagging are framed together into

panels of convenient size for carrying and erecting. The construction is

a simple one in either case where slabs without haunches or plain arches

form the filling between beams. Figure 192 shows an arch slab center;

plain hook bolts, with a nut on the lower end, passing through holes in

the joists are more commonly employed. For 1-in. lagging the joist

spacing is 2 ft., for 1½-in lagging, 4 ft., and for 2-in. lagging, 5 ft.

[Illustration: Fig. 192.--Form for Arch Slab Between I-Beams.]

[Illustration: Fig. 193.--Form for Flat Slab Floor Between I-Beams.]

A more complex centering is required where the slab has to be haunched

around the I-beams. The center shown by Fig. 193 was designed by Mr. W.

A. Etherton for the floor construction of the U. S. Postoffice Building

erected at Huntington, W. Va., in 1905. The center consists essentially

of the pieces A (2×4 ins. for spans not exceeding 6 ft.) and the

2×3-in. triggers B, which rest on the lower flanges of the floor beams

and thus support the forms. The trigger is secured at one end to the

piece A by a 1×3-in. cleat C and at the other end by 1×3-in. cleats

D on either side of A, which serve also as supports for the batter

boards E. The six-penny nail F is but partly driven and it is to be

drawn before removing the forms. When the supports of the beams are not

fireproofed the cleats D extend to the bottom of the trigger B, but

otherwise one cleat extends lower to secure the cross-strip G. To

remove the forms, draw the partly driven nail F; knock off the strip

G or loosen it enough to draw the nails in B>; pull the triggers on

one beam, and the forms will drop. If the soffit board H is used it is

necessary first to remove the strip G. For larger beams use the

spacing blocks H as shown; for smaller beams omit the trigger B and

extend A to rest on the flange of the beam, then to remove the form

A must be cut preferably near the beam.

No complete records of the cost of these forms were obtained, but the

following partial information is furnished by Mr. Etherton: Considering

a panel 6 ft. span by 19 ft. long on 15-in. I-beams, the lumber

consisting of 1-in. boards supported by 2×4-in. cross-pieces on 2×3-in.

triggers spread 3 ft. on centers, soffit of beams not fireproofed, it

required one carpenter five hours at 30 cts. per hour to complete the

panel. Figuring from this alone I should say that 10 cts. per sq. yd. is

a fair estimate for carpenter work. In working over the forms for

another floor the 1-in. boards require more time to handle and I should

say that the saving in cost of work over the first floor would be not

over 2 cts. per sq. yd. Two laborers moved their scaffolding and took

down the forms from three completed panels of 13 sq. yds. each in one

hour. Smaller panels require a longer time per yard. Counting for the

proper piling of lumber I should allow one hour for one man to take down

the forms for a 13-sq. yd. panel when conditions are the best. We

contracted with two laborers to remove the forms from the third floor

and roof and pile them in good shape on the ground just outside of the

building for an amount averaging about 4½ cts. per sq. yd., and the men

made but small wages on the contract. The lumber was used on three

floors and the roof, and the best of the 1-in. boards and all of the

2×4-in. and 2×3-in. stuff were used on a second job. For a safe estimate

based on the data secured I should figure the cost of labor and

materials for a three or four-story building about as follows:

Per sq. yd.

Lumber at $20 per thousand 28 cts.

Carpenter work at 30 cts. per hour 10 cts.

Labor tearing down at 15 cts. per hour 4 cts.

-------

Total per square yard 42 cts.

Figure 194 shows an arrangement of centering between steel beams which

is novel in that it provides for molding a slab with girders. The form

was used in building the roof of a locomotive roundhouse. This

roundhouse was of the usual circular form and had a radial width of 80

ft. Each radial roof girder, which was an 18-in. I-beam was carried by

an outside wall pier and three I-beam columns encased in concrete. The

space between main roof girders was spanned by reinforced concrete

girders and roof slab. The center illustrated was employed for molding

the concrete girders and slab, and carries out the idea of making a

stiff and light center for considerable spans of slab without support by

staging. The truss construction of the frames supporting the girder box

will be noted.

[Illustration: Fig. 194.--Form for Slab and Girder Floor Between

I-Beams]

~Concrete Slab and Girder Floors.~--The construction of forms for this

type of floor should be such that the slab centers and the sides of the

girder molds can be removed without disturbing the bottoms of the girder

molds. This permits the beams to be supported as long as desirable and

at the same time releases the greater part of the form work for use

again. It is of advantage also to lay bare the concrete as soon as

possible to the hardening action of the free air. The slabs may be

similarly supported by uprights wedged up against plank caps; no very

great amount of lumber is required for this staging and it gives a

large assurance of safety. It is well also to give the girder molds a

camber or to crown them to allow for settling of the falsework.

The form shown by Fig. 195 was used in constructing girders from 14 to

23 ft. long in a factory building at Cincinnati, O. The sides are

separate from the bottom, being supported at the ends by cleats on the

column form and at intermediate points by struts under the yokes. The

floor lagging is carried by 2×4-in. stringers supported by the yokes.

Uprights set under the bottom plank keep the girder supported after the

sides and slab centers are removed. It will be noted that the form is

given a camber of 1-in. The structural details are evident from the

drawing. The form shows a method of molding a bracket for wind bracing;

a simple modification fits it for molding girders without brackets. A

rough computation gives 10 ft. B. M. of lumber per lineal foot of girder

form as shown.

[Illustration: Fig. 195.--Girder and Slab Form for Factory Building,

Cincinnati, O.]

[Illustration: Fig. 196.--Girder and Beam Forms for Factory Building,

Beverly, Mass.]

The form construction shown in Fig. 196 was employed in building the

slab and girder floors for the United Shoe Machinery Co.'s factory at

Beverly, Mass. In these buildings the main girders cross the building at

20-ft. intervals and midway between the main girders is a bridging beam

also reaching across the building. Floor beams span the 10-ft. spaces

between bridging beams and main girders at intervals of 3 and 4 ft.

Referring first to the main girder form, tall horses are set up at 3-ft.

intervals and connected by stringers laid on the caps. These stringers

carry a cross piece, with a cleat at each end, over each horse. The

bottom boards of the mold rest on these cross pieces and the side pieces

are set up between verticals wedged tight between the cleats. The beam

molds are a modification of the girder molds. The slab centers consist

of panels just large enough to span the openings between beams and

girders and composed of 1-in. boards fastened together by four 1×5-in.

cleats. Except in attaching the quarter round and triangular moldings

for fillets no nailing is necessary in erecting and taking down the

forms.

[Illustration: Fig. 197.--Girder and Slab Form for Concrete Building

Work.]

The form construction shown by Fig. 197 is one used by a large firm of

reinformed concrete builders. The slab centers can be struck and the

sides of the girder mold removed without disturbing the support for the

bottom of the beam. This form runs quite low in lumber, requiring for a

9×12-in. beam box including posts some 9 ft. B. M. per lineal foot of

box. The joists and lagging as shown require about 2 ft. B. M. per

square foot of floor slab. The practice is to give these girder boxes a

camber of ½-in. in 10 ft.

The construction shown by Fig. 198 is designed to provide adjustability,

to enable quick erection and removal and to do away with all nailing.

The construction is as follows: Wooden posts carry at their tops steel

T-beam cross-arms knee braced to the posts by steel straps. The

cross-arms carry the two jaws of a clamp, each consisting of a vertical

plate, and two diagonal braces, slotted so as to slide on the T-beam. A

cut nail or other piece of metal driven into the slots fastens the jaws

on the T-beam. The cross-arms carry the bottom boards of the girder

molds and the vertical plates of the jaws support the side pieces. A

blocking piece slipped between the braces carries the end of the joist

for the floor slab centers. This form is the invention of Mr. W. H.

Dillon and was used in constructing the nine-story, 260×150-ft.

wholesale hardware store Of Farwell, Osman & Kirk Co., St. Paul, Minn.

[Illustration: Fig. 198.--Girder and Slab Form for Warehouse at St.

Paul, Minn.]

[Illustration: Fig. 199.--Girder and Slab Form for Factory Building, New

York, N. Y.]

The form shown by Fig. 199 was used in constructing a factory building

in Long Island City, N. Y., and it is given here chiefly for the purpose

of exhibiting the unnecessary complexity of form work. Comparing this

form with that of nearly any of the preceding designs will bring out

the point. The design, however, was one of the earlier ones to recognize

the advantage of stripping the slab centers and the sides of the girder

boxes without disturbing the bottom plank of the boxes or the staging.

The drawing shows the independent support of the bottom board and side

pieces of the girder mold on the transverse caps of the staging posts.

These posts are 6×8 ins. in section and are spaced from 6 to 8 ft.

apart. Briefly described the bottom board is a single plank from 1 to 3

ins. thick, to which the side pieces are lag-screwed at the bottom. The

side pieces are panels composed of 4×7/8-in. vertical boards nailed to

top and bottom 2×4-in. horizontal timbers. A third horizontal timber

near the top serves as a seat for the ends of the joists carrying the

slab lagging and is braced from the bottom horizontal by vertical

stiffeners. The edge boards of the slab lagging are nailed to the top

edges of the side pieces of the girder mold and the tops of these side

pieces are connected across the trough by strips of board; all the slab

lagging boards except those at the edges of the girder molds are laid

loose. In the building referred to, after the floor concrete had set

about seven days the joists carrying the slab lagging were turned a

quarter over thus dropping the slab form about 2 ins. A few days later

the joists and lagging were taken down and the side pieces of the girder

mold were unscrewed and removed. The bottom board and staging posts were

left in position about three weeks longer and then dropped about 1 in.

by removing fillers from the staging post caps. In another week the

bottom boards and staging posts were taken down. This construction of

form and method of removing it permitted the concrete to be stripped so

that the air could get at it as fast as it was safe to take the support

from any part and at the same time kept the supports in such position

that they form a safety platform in case of collapse. A more important

advantage is that the form timber can be removed as fast as any part of

it is free and used again. Thus the lagging boards and joists and the

side pieces for the girder molds were free for use again about every two

weeks and yet the main supports of the girders were undisturbed until

they were fully a month old.

Other examples of girder and slab forms are shown in the succeeding

sections describing the construction of a six-story building and of a

garage constructed at Philadelphia, Pa.

[Illustration: Fig. 200.--Collapsible Core Forms for Girder and Slab

Floors.]

Another type of slab and girder form construction that deserves brief

mention because of its variation from usual practice and also because of

its extensive use by one prominent builder is shown by Fig. 200. Cores,

or inverted boxes, with four vertical sides and rounded corners, are set

side by side, with ends on stringers carried by the column forms, at

intervals wide enough to enable the beam to be molded between. A plank

resting on cleats on the sides of the cores forms the bottom of the beam

mold. The main girders are molded in similar spaces between the ends of

the cores in one panel and of those in the next panel. To permit the

core to be loosened readily it is hinged; when in place spacers inside

the core keep the sides from closing. These are knocked out, the core

sides close together and the core is removed for use in another place.

Cores similar to these were used in molding the ribbed floor for the

Bush terminal factory building described in a succeeding section. These

cores are capable of repeated use so that while they are somewhat

expensive to frame they give a very low cost of form work when the beam

and girder spacing is arranged largely in duplicate from floor to floor.

It will ordinarily be cheaper to have these cores made to pattern by

regular woodworking shops, and shipped to the building ready to erect.

~WALL FORMS.~--Wall work in modern commercial and manufacturing buildings,

when we come to eliminate windows and wall columns and girders, is

confined very largely to isolated curtain wall panels between windows

and framework. In such buildings, therefore, wall forms consist merely

of wooden panels, one for each face of the wall, constructed to fit the

spaces to be walled up. Where these spaces are duplicated from bay to

bay or story to story the same form panels will serve repeatedly. For

residences and other buildings having greater proportionate area of

blank wall the builder has a choice between continuous forms carried by

staging and movable panel forms.

[Illustration: Fig. 201.--Continuous Form for Wall Construction.]

For one and two-story buildings, with the usual variation in

architectural detail, panel work and window work, the continuous form

has many advantages, and the superior economy of movable panels in

retaining and other plain wall work is by no means always true here. One

good type of continuous wall form construction is shown by Fig. 201. The

gallows frames are spaced about 6 ft. apart along the wall and connected

by horizontal stringers nailed to the uprights or by diagonal bracing.

Each frame may be made up of 6×6-in. posts connected by 2×4-in.

cross-struts and diagonals with bolted connections so that the frame can

be taken down and put together easily and so that the bracing can be

removed as the wall is built upward. The other details of the form work

are shown by the drawing. This construction leaves a clear space for

placing the concrete and the cross pieces give support to runways; it

has been successfully used in a large amount of low building work.

[Illustration: Fig. 202.--Sectional Form for Wall Construction.]

Movable panel forms are of great variety in detail but are generally of

either one or the other types shown by Figs. 202 to 204.

The form shown by Fig. 202 was used in constructing a church at Oak

Park, Ill. For the back of the wall it consists of continuous lagging

held by 2×4 studs. For the face 1×6-in. lagging 12 ft. long was nailed

to 2×4-in. studs to form panels. It will be noted that the ends of the

studs are scarfed so as to interlock in succeeding panels. This

construction also shows a method of supporting the reinforcing bars

inside the form.

The form shown by Fig. 203 was used in constructing a large factory

building, and consisted of two side pieces or panels 3 ft. high and 16

ft. long, the distance between wall columns. For the first course these

were seated on the carefully leveled and rammed ground and securely

braced by inclined or horizontal struts inside and outside of the

building. After the concrete had set for three days the molds were

loosened and lifted until the lower edges were 2 ins. below the top of

the concrete and there they were held by horizontal bolts through their

lower edges and across the top of the concrete by ties nailed across

their tops every 3 ft. and by bracing to the falseworks supporting the

column and floor forms. The cross bolts passed through pasteboard

sleeves which were left permanently embedded in the wall. By starting

the molds level and finishing each course level with their tops no

difficulty was had in keeping the forms plumb and to level as they were

moved upward. This type of form has to be exteriorly braced to staging

or adjacent column forms, etc.

[Illustration: Fig. 203.--Sectional Form for Wall Construction.]

The type of movable panel form shown by Fig. 204 depends for all support

on the wall alone. The sketch shows the form filled ready to be shifted

upward; this operation consists in removing the bottom bolts and

loosening the top bolts enough to permit the studs to be slid upward the

full length of the slots. The lagging boards left free are then removed

and placed on top and the bolts are tightened, completing the form for

another section of wall.

[Illustration: Fig. 204.--Movable Panel Form for Wall Construction.]

[Illustration: Fig. 205.--Sullivan's Plank Holders for Wall Forms.]

A type of wall form construction intended to do away with studding and

bracing is illustrated by Figs. 205 and 206. In both cases metal plank

holders are used in place of studs, and practically the only difference

between the two is in the shape and material of the holders. The mode of

procedure is to work in horizontal courses one plank high around the

wall, removing the bottom plank and placing it on top as each new course

is begun after the first few courses have been laid. Using the

arrangement shown by Fig. 205 in constructing a building 100×54 ft. in

plan and 36 ft. high with 12-in. walls, a height of two 12×2-in planks

was all the form work that was ever necessary at any one time, so that

the amount of form lumber required for the building was 2,464 ft. B. M.

plus 205 ft. B. M. of 2×4-in. flooring strip, or altogether 2,669 ft. B.

M., or 0.24 ft. B. M. per square foot of exterior wall surface, or 6½

ft. B. M. per cubic yard of concrete. This same form lumber with 16

additional plank was then used to construct a building 100×100 ft.×16

ft. high, so that some 3,000 ft. of form lumber sufficed for 17,548 sq.

ft. (exterior surface) of wall or for 617 cu. yds. of concrete in 12-in.

wall, which gives 0.17 ft. B. M. per square foot or 4.8 ft. B. M. per

cubic yard of concrete.

[Illustration: Fig. 206.--Farrell's Plank Holders for Wall Forms.]

~ERECTING FORMS.~--The organization of the erecting gang will depend very

largely on the manner in which the forms have been constructed. If they

have been constructed in sections which go together with wedges and

clamps common laborers with a foreman carpenter in charge to direct and

to line and level the work will do the erecting, but if they have to be

largely built in place carpenters are necessary for all the work except

carrying and handing. There should be at least one foreman for every 15

to 20 men and a head foreman in charge of all form work. The mode of

procedure will differ for every job, but the following general

directions apply to all work in greater or less measure.

Clamps, bolts and wedges and not nails should be used wherever possible

in assembling parts of forms in erection; these devices are not only

quickly and easily applied in erection but they are just as quickly and

easily loosened in taking down forms and they can be loosened without

jarring the concrete member.

Lining girder forms and lining and plumbing column and wall forms is

high-class carpenter work and should be directed by competent

carpenters. A column or girder which is out of line or plumb not only

looks bad but may be required to be removed and corrected by the

engineer. The expense for one such correction will be many times that

which would have been involved by proper care in the first place.

Supports or staging for the forms should be used freely and well braced

in both directions. Uprights should be set on wedges and bear against a

cap piece and on a sill piece to distribute the load.

Erect, line and plumb the column forms first; then erect, line and level

the girder forms and set the girder staging, and finally erect and level

the slab centers and their supports.

Leave the foot of each column form open on one side at the bottom so

that the column reinforcement can be adjusted and connected up and so

that a clear view can be had through the form to detect any object that

may have fallen into the form and become wedged; this same opening makes

it possible to clean the form.

Give the forms a final inspection before concreting to check line and

level, to close open joints and to tighten up clamps and wedges. Finally

clean each form and wet it down thoroughly before placing the

concrete--do this just before placing the concrete.

~REMOVING FORMS.~--Good judgment and extreme care are essential in

removing centers. It goes without saying that forms should never be

removed until the concrete has set and hardened to such strength that it

will sustain its own dead weight and such live load as may come upon it

during construction. The determination of this condition is the matter

that calls for knowledge and judgment. Some cements set and harden more

rapidly than others, and concrete hardens more and more slowly as the

temperature falls. These and other circumstances must all be taken into

account in deciding upon the safe time for removal. Many large

contractors mold a cube of concrete for each day's work and leave it

standing on the finished floor exposed to the same conditions as the

concrete in the forms; examination of this sample block gives a line on

the condition of the concrete in the work and on the probable safety of

removing the forms at any time. In all cases it should be the

superintendent's duty to determine when to remove forms, and he should

satisfy himself by personal inspection that the concrete is in condition

to stand without support. It is also wise at least as a matter of

precaution for the contractor to secure the engineer's or the

architect's approval before removing any formwork.

Care in removing forms is essential for the reason that green concrete

is particularly susceptible to injury from shock or sudden strain. It is

well, therefore, to have a separate gang always doing the work. These

men will in a few days become trained under an experienced foreman so

that they will not only do the work with greater safety but also more

rapidly. This gang should, furthermore, be required to follow a regular

system in its work; a system which may not be departed from without

direct orders from the superintendent. An example of such a system is

outlined below.

The time of beginning this work of removal shall be given by the

superintendent. In warm, dry weather, with other conditions favorable,

removal may be begun after seven days. Then the following schedule may

be followed: At the end of seven days remove the sides of the column

forms. This gives an opportunity to determine the soundness of the

column casting and also serves the further desirable purpose of baring

the concrete to the curing and hardening action of the air. At the end

of 14 days loosen the wedges of the posts supporting the slab centers

and drop these centers a couple of inches: leave the centers in this

position for another day, meanwhile examining the tops of the slabs to

note their condition. Then remove the sides of the beam molds and the

slab centers, replacing the latter with temporary uprights supporting a

plank bearing against the underside of the slab. This precaution is

often neglected and with very little reason considering the importance

of the safeguard thus secured. Ordinarily the shores need not be left in

place more than a week, so that the amount of lumber thus tied up is

small. At the end of three weeks remove the uprights under the beam and

girder molds and strip the bottom plank. In this schedule it is assumed

that the floor is free from any great load and that no unusual loading

is put upon it; if a load of any consequence is to come on the floor the

shores and uprights should be left in place longer. No schedule of

removal can be blindly followed, and that given above is certain only

when the conditions are right and as stated.

FABRICATION AND PLACING OF REINFORCEMENT.

The amount of reinforcing steel used varies from 50 lbs. to 275 lbs. per

cu. yd. of concrete; the highest figure will be had only in very heavy

work and where very heavily reinforced raft foundations are employed,

and the lowest only in one-story buildings consisting of walls and roof.

A fair average is perhaps 150 lbs. per cu. yd. The cost of fabricating

and placing reinforcement will run from 1/3 ct. to 1½ cts. per pound,

but the last figure is exceedingly high; ¾ ct. per pound for fabricating

and placing is a reasonable labor charge.

Contractors frequently have their choice whether the steel shall be

fabricated into frames and placed as units or whether it shall be placed

in separate bars. For girders and columns the difference in cost of the

two methods is not so very great for steel in place when the fabrication

is done in the field. The unit frames cost considerably more than

separate bars to fabricate, but the cost of handling and placing them in

the forms is materially less; on an average the differences balance each

other. Where the frames are made up in regular mills unit frames

generally cost less to fabricate and place than do separate bars. The

use of unit frames in wall and floor slab reinforcement is generally

more expensive than the use of separate bars. The chief gain that comes

from the use of unit frames is the gain due to the certainty that the

reinforcing bars, stirrups, etc., are all there and are properly spaced

and placed.

~FABRICATION.~--Fabrication includes all the work necessary to prepare the

reinforcement ready to place in the forms. It amounts to very little

where separate bar types of reinforcement are used. Plain bending and

shearing operations comprise the whole task. Where the beam or column

reinforcement has to be made up into complete frames which can be

handled and placed as units this task is more complex and considerable

apparatus is essential to rapid and economical work. For this reason it

is wise usually to contract with some metal working shop to assemble and

connect up the various units and to furnish them ready for installation.

In many cases these unit frame types of reinforcement are patented and

the proprietors contract to fabricate and furnish them complete

according to the plans of the engineer or architect. Even where the

frame construction is not so controlled it will be economy generally to

have the fabrication done at regular shops where the necessary tools and

skilled workmen are had. In any case the bars should be ordered cut to

length at the mill so far as possible.

[Illustration: Fig. 207.--Rack for Storing Reinforcing Bars.]

Assuming the fabrication to be done in the field, the mode of procedure

will be as follows: Order the bars or rods to be shipped in bundles of

corresponding sizes and lengths of pieces with each bundle tagged with

its proper shop number or mark. The bundles should weigh about 200 lbs.;

this is a load easily handled by two men and so long as possible all

handling should be done in the original package, for when once broken it

is very hard to get men to carry a full load. As received, the bars of

each size and length should be stored by themselves. For ordinary bars

not having long prongs a rack of the general form shown by Fig. 207

serves the purpose excellently. When a great deal of metal must be kept

stored for some time it is wise to roof over the racks, not only to

protect the metal from rain and snow, but to enable the men to work dry

shod in stormy weather. Usually it will pay to have one man whose sole

duty it is to receive and check all metal and to attend to its

systematic arrangement on the racks; this same man will also direct the

removal of the metal to the shop where it is bent and otherwise worked

up, and can, if he is competent, earn his pay many times over in time

saved all along the line in handling and working up the reinforcement.

The authors have seen enough time wasted in hauling over and rehandling

metal in piles to get at what was wanted to pay for shed, racks and the

wages of a storekeeper several times during a moderate sized job. In

large work provide the storekeeper with a schedule showing the order in

which the metal is wanted for the work so that he can arrange it in that

order and can check up his receipts from the mills and report missing

items in time for the deficit to be made up before some part of the work

has to be stopped because of material missing. System in receiving and

storing the metal is absolutely essential to rapid and accurate work at

the bending and erecting tables.

The work done on the metal consists chiefly of bending. The metal can

usually be bent cold, but for sizes 1½-in. and upward some makes of bars

require heating; this can be done by laying the bars side by side on the

ground and arranging sticks and shavings on top of them in a strip 18

ins. to 2 ft. wide across the portion where the bend is to be. Only

moderate heating is usually required. Ordinary bending is a simple

process and can be done with very simple apparatus. Figures 208, 209 and

210 show frequently used devices, any of which can be made by an

ordinary carpenter. For heavy bars, 1½ and 2 ins., the device shown by

Fig. 210, with its heavy, swinging beam, is particularly efficient. An

example of more elaborate methods is had in the following description of

the processes employed in fabricating girder frames and hooped column

reinforcement for a large factory building. The building was 500×75 ft.,

with six stories and a basement, built for the Bush Terminal Co.,

Brooklyn, N. Y., in 1905. Three longitudinal rows of round columns and

two rows of rectangular wall columns carry heavy longitudinal girders

supporting floor slabs with corrugated undersides as shown by Fig. 211,

which also shows the floor slab reinforcement. About 12,000 cu. yds. of

concrete and 1,000 tons of reinforcing steel were required; hence 167

lbs. of steel were required for each cubic yard of concrete. The floors,

however, were designed to carry a load of 800 lbs. per sq. ft. The

particular feature of interest in this building was the fabrication of

all the column and girder reinforcement into unit frames and cylinders

in temporary workshops on the site.

[Illustration: Fig. 208.--Table for Bending Reinforcing Bars.]

[Illustration: Fig. 209.--Table for Bending Reinforcing Bars.]

[Illustration: Fig. 210.--Table for Bending Reinforcing Bars.]

[Illustration: Fig. 211.--Column and Floor Slab Construction for Factory

Building.]

The circular interior columns, varying from 30 ins. to 12 ins., in

diameter were molded in permanent shells of cinder concrete. The shells

were made in sections about 30 ins. long, with walls 1½ ins. thick,

which were set one on another with mortar joints to form the column

mold. In fabricating the shells the first step was to wind a helix of

steel wire on a collapsible mandrel about 4 ft. long; the mandrel was

set with the axis horizontal and was revolved by hand, the wire being

fed on also by hand and under a slight tension. After the wire helix was

completed it was wrapped with a sheet of expanded metal, the

longitudinal edges of which lapped a few inches and were tied by wire

ties. The expanded metal covering was also wire tied to the helix. Each

of these cylinders of expanded metal and wire was 30 ins. long and

formed the inner mold for making the shell. The outer mold consisted of

a sheet metal cylinder in two parts assembled and supported by wooden

yokes and framework. The two molds were assembled on a plank platform,

one inside the other, and about a common center. The annular space was

then filled with a 1-5 cinder concrete mixed moderately dry so that

while it would exude slightly through the expanded metal mesh it would

not waste to any extent. After from 18 to 24 hours the outer mold was

removed for reuse and the shell was left standing on the molding

platform until safe to handle. The larger shells, 30×30×1½ ins., weighed

about 150 lbs. each.

[Illustration: Fig. 212.--Device for Bending Reinforcing Rods.]

Some 2,000,000 lbs. of plain round steel rods from ¼ in. to 1½ ins. in

diameter were required for reinforcing the concrete. For the main

girders these rods were cut, bent and assembled into frames or trusses

which were placed as units. The main rods were ordered cut to length,

but the stirrup rods were ordered in lengths of 20 ft. and cut to

lengths as required. The rods were brought to the work in carload lots

and were stored according to lengths and sizes in racks under sheds.

Another shed was provided for the steelworkers, who cut and bent the

rods and assembled the girder frames ready for the workmen on the

building. There were about 50 different patterns of frames required.

They were made entirely by hand. For bending large size rods, heavy

compound levers were used; the lighter rods were bent by the device

shown in Fig. 212. The assembling of the trusses was accomplished as

shown by Fig. 213, using the steel framework of the erection shed as a

staging. Across the horizontals of the framework were placed two false

temporary top chord bars marked to the stirrup spacing of the truss

being assembled. On these bars, at the spaces marked, were suspended

stirrups with their lower ends hooked. The lower chord bars were then

suspended in the stirrup hooks and the whole assemblage of bars and

stirrups was then clamped rigid by the lever bars and intermediate

clamps. The loop ends of the stirrups were then bent by special wrenches

to the position shown at _2_, then closed by hammering to the position

shown at _3_, and finally they were wire tied. The process was a simple

one, and by adopting a regular routine the men became so expert that two

of them could complete many trusses in a working day. The contract price

for shaping the steel and assembling it into frames was 1 ct. per lb.;

the cost of the work to the contractor has been stated by Mr. E. P.

Goodrich, Engineer, Bush Terminal Co., to have been about ¾ ct. per lb.

The cost of placing the steel in the building was ¼ ct. per lb.

[Illustration: Fig. 213.--Sketches Showing Methods of Fabricating Girder

Reinforcing Frames.]

~PLACING.~--With unit frame reinforcement the number, size and location of

the bars have been made certain in the shops where the frames are

fabricated so that the erector has nothing to do but to line and level

up the frames in the forms, place such temporary braces as are needed to

hold them true, and make the end connections with abutting frames. Such

frames are usually provided with "chairs" to hold the bottom bars up

from the form so that little bracing or none is required. With separate

bar reinforcement the erector may either place the reinforcement

complete in the form by wire-tying the bars to each other, to temporary

braces or templates and to the forms, or he may insert the various

pieces of reinforcement in the concrete as the pouring advances,

depending on the surrounding concrete to retain them where inserted.

Generally a combination of both methods is employed.

The processes in detail of placing reinforcement are particularized in

several places in other sections; they will differ for nearly every job.

Here, therefore, general rules only will be given.

(1) See that the correct number and size of reinforcing bars, splices

and stirrups are used and that they are spaced and placed strictly

according to the working plans.

(2) Bars must be properly braced, supported and otherwise held in

position so that the pouring of the concrete will not displace them.

(3) Splices are the critical parts of column reinforcement. See that the

bars butt squarely at the ends and are held by pipe sleeves or wired

splice bars; see that the longitudinal rods are straight and vertical;

see that the horizontal ties or hooping are tight and accurately spaced.

When the reinforcement is built up inside the form one side is left open

for the work; ordinarily the column reinforcement will be fabricated

into unit frames, then an opening in the form at the bottom to permit

splicing will suffice.

(4) Take extreme care that beam and girder reinforcement is placed so

that the bottom bars lie well above the bottom board of the mold; use

metal or concrete block chairs for this purpose.

(5) See that the end connections and bearings of beam and girder frames

are connected up and have the bearings called for by the plans.

(6) See that line and level of all bars and of the reinforcement as a

whole are accurate; make particularly certain that expanded metal or

other mesh-work reinforcement lies smooth and straight.

(7) Give all reinforcement a final inspection just previous to pouring

the concrete; this is particularly essential where the reinforcement is

placed some time in advance of the concreting.

MIXING, TRANSPORTING AND PLACING CONCRETE.

A reinforced concrete building requires from 0.2 to 0.5 cu. yd. of

concrete per 100 ft. of cubical volume of the building, assuming walls,

floors and roof to be all of concrete. The amount of concrete to be

mixed, transported and placed is, therefore, large enough, even for a

building of moderate dimensions, to warrant close study of and careful

planning for this portion of the work. A few general principles can be

set down, but as a rule there is one best way for each building and that

way must be determined by individual conditions.

~MIXING.~--Concrete for building work has to be of superior quality so

that no chances may be taken either in the process of mixing or with the

type of mixer employed. Machine mixing and batch mixers should always be

employed. Machine mixing gives generally a more homogeneous and uniform

concrete than does hand mixing and is cheaper. Batch mixers are

generally superior and more reliable than continuous mixers where a

uniformly well mixed concrete is required. The capacity of the mixing

plant is determined by the amount of concrete to be placed and the time

available for placing it. Its division and arrangement is determined by

the area of the work and the type and arrangement of the plant for

transporting the materials and the mixed concrete. The following general

principles may be laid down: Make the most use possible of gravity; it

is frequently economy to carry all materials to the top of bins from

which point they can move by gravity down through the mixer to the hoist

buckets, and where natural elevations or basement floors below street

level permit gravity handling they should be taken advantage of. The

mixing should be done as near the place of concreting as practicable; in

building work this is the point on the ground which is directly under

the forms being filled. It is, of course, impracticable to secure so

direct a route as this from mixer to forms, but it can be more or less

closely approached; using two mixers, for example, one at the front and

one at the rear of a building cuts down the haul from hoist to forms

one-half. Other ways will suggest themselves upon a little thought. In

the matter of the mixing itself, it must never be forgotten that a batch

of concrete without cement which goes into a girder or column will

result in the failure of that member and possibly the failure of the

building. In massive concrete work a batch without cement will not

endanger the stability of the structure, but in column and floor work in

buildings it is certain disaster. Formanship at the mixer is, therefore,

highly important and a cement man who realizes the responsibility of his

task is equally important.

~TRANSPORTING.~--Transporting the mixed concrete is divided into three

operations--delivering concrete from mixer to hoist, hoisting, and

delivering hoisted concrete to the forms. The delivery from mixer to

hoist may be by direct discharge into hoist bucket, by carts or

wheelbarrows, or by cars carrying concrete or concrete buckets. Hoisting

may be done by platform hoists or elevators, by bucket hoists, or by

derricks. Handling from hoist to form may be direct in buckets, by carts

or wheelbarrows, or by cars. These several methods can be worked in

various combinations, and the following examples of plants show such

combinations as are most typical of current practice.

In any system of transportation it is getting the concrete to the hoist

and from hoist to form that eats up the money. Hoisting makes but a

small part of the total transportation cost, and, moreover, the

difference in cost of operation for different hoists is very small. Mr.

E. P. Goodrich states that on three buildings the actual costs for the

hoists installed and removed after the completion of the work were as

follows:

Platform hoist $330

Bucket hoist 465

Derrick 225

In figuring on the form of hoist to be adopted, the capability of the

hoist for general service has to be kept in mind. Platform hoists and

derricks can be used for hoisting form lumber and reinforcing steel as

well as for hoisting concrete, while bucket hoists cannot be so used

except where they may be fitted with special carriages for lumber or

steel. On the other hand, the bucket hoist is usually the quickest

method of hoisting concrete, and it can readily be extended upward as

the work progresses. The last is true also of platform hoists. The use

of derricks necessitates frequent shifting for high work or else the

building of expensive staging to raise the derrick into a position to

command the final height of the building. The probable costs of moving

and extending must be allowed for in choosing the hoist to be used.

Direct discharge of the mixer into the hoisting bucket is, of course,

the ideal manner of transporting the concrete from mixer to hoist, and

this can generally be obtained by planning, particularly where bucket

hoists or derricks are employed. For platform hoists direct discharge is

impossible; it can be somewhat closely approached, however, where

conditions permit car tracks to be laid on the floors being built, so

that a car holding a batch of concrete can be run onto the platform,

hoisted and then run to shoveling boards near the forms that are being

filled. The successful use of such an arrangement of car tracks is

described in Chapter XX, but it was for handling concrete blocks. A

direct discharge from hoisting bucket to forms is frequently possible

where derricks are used for hoisting, but with bucket and platform

hoists, wheeling or carting is necessary.

Where wheeling or carting has to be done either at the bottom or at the

top of the hoist, or at both points, a great factor in the economy of

work is the arranging of the operations in cycles. For example, in

wheeling concrete to forms from a hopper fed by a bucket hoist, arrange

the runways so that each man makes a circuit, passing by the form at one

end and by the hopper at the other end, and goes and comes by a

different route. The speed gained by avoiding confusion and delay saves

many times the additional cost of runways which is small. In fact it is

economy to employ a few extra men to arrange runways and keep them

clean, because of the additional speed thus gained. Good organization

effects more economy than special methods of hoisting as far as the

labor of handling the concrete is concerned.

[Illustration: Fig 214.--Bucket Hoist for Building Work

(Wallace-Lindesmith).]

~Bucket Hoists.~--A bucket hoist construction which has been extensively

used in building work on the Pacific coast is shown by the drawings of

Figs. 214 to 216. Two T-bar guides made in sections connected by

fishplates furnish a track for an automatic dumping bucket hoisted and

lowered by steel cable from engine on the ground to head sheaves as

shown. The sectional construction of the T-bar guides permits the hoist

to be any height desired, it being lengthened and shortened by adding

and taking out sections. The bucket is dumped automatically at any point

desired by means of a tripping device attached to a chute which receives

the contents of the bucket and delivers them to carts, wheelbarrows, or

other receptacle. The hoist is set outside of the building with the

mixer arranged, if possible, to discharge directly into the bucket. By

setting the guide frame in a pit or on blocking any height of edge of

bucket can be secured. The buckets are ordinarily 13½ or 20 cu. ft.

capacity. It is recommended, when greater hoisting capacity is

necessary, to use two hoists set side by side and operated by one cable

in the same manner as double wheelbarrow cages; as the weight of one

bucket counterbalances the weight of the other, the power required for

hoisting is reduced. To adapt this hoist to handling form lumber the

bucket is replaced by the lumber carriage shown by Fig. 216; this

carriage discharges over the head of the mixer and the spring buffer

shown by Fig. 214 is to take the shock of the rising carriage. This

buffer is omitted when concrete only is to be hoisted. In one case this

device has hoisted 520 batches of 12 cu. ft. each to the fourth floor in

8 hours, or nearly 19 cu. yds. per hour. In another case 65 trips per

hour were averaged to the fifth floor with a 12-cu. ft. load each trip;

this is nearly 30 cu. yds. per hour. With the lumber carriage 8 men have

unloaded 14,000 ft. B. M. of 2×10-in. stuff from car to the second floor

and distributed it in 43 minutes. A ½-cu. yd. combination outfit for

concrete and lumber, with 40 ft. of guide track, weighs 1,750 lbs.,

without the lumber carriage the outfit weighs 1,600 lbs. This hoist is

made by the Wallace-Lindesmith Co., Los Angeles, Cal.

[Illustration: Fig, 215.--Wallace-Lindesmith Hoist Bucket in Discharging

Position.]

[Illustration: Fig. 216.--Lumber Carriage for Wallace-Lindesmith Hoist.]

[Illustration: Fig. 217.--Mixer Plant with Gravity Feed from Material

Bins to Hoisting Bucket.]

A popular construction for automatic bucket hoists is that shown by

Figs. 217 and 218 by Mr. E. L. Ransome. The bucket is held upright by

guides at its front and rear edges; to dump it a section of the front

guide is removed at the desired dumping point which allows the bucket to

overturn as shown. A friction crab hoist operated from the mixer engine

runs the bucket. The mixer is located as shown. Figure 218 shows the

foot of the hoist set in a pit with the mixer at surface level, but the

hoist can be set on the surface and the mixer mounted on a platform. In

the latter case a charging bucket, traveling from stock pile up an

inclined track to the mixer platform, is generally used. A hoist like

that illustrated, equipped with a ½-cu. yd. Ransome mixer, will cost

about $1,500 and will deliver 15 cu. yds. of concrete per hour. Mr. F.

W. Daggett gives the following figures of the cost of operation:

Mixing Gang:

Total 1 hr.

1 mixer foreman, also engineer, 25c. $.25

1 man charging mixer, 20c. .20

1 man running hoist, 20c. .20

2 men wheeling sand, 17½c. .35

4 men wheeling and shoveling stone, 17½c. .70

1 man helping up runway, 17½c. .17½

2 men carrying cement, 17½c. .35

Gang Placing Cement:

1 foreman, 25c. .25

9 men wheeling concrete, 17½c. 1.57½

3 men tamping concrete, 17½c. .52½

1 man filling carts, 17½c. .17½

------

Total labor cost per hour $4.75

Fuel, etc. .50

------

5.25

This gives a cost of 35 cts. per cu. yd. for mixing and placing

concrete.

In this particular case the mixer was charged by wheelbarrows.

Frequently the stone and sand bins can be arranged to chute the

materials directly into the charging hopper as shown by Fig. 217. In

place of barrows two-wheeled carts of the type shown by Fig. 12 can be

used. Mention has already been made of operating the charging bucket on

an incline from stock pile to mixer. Such arrangements are described in

Chapter IV.

[Illustration: Fig. 218--Bucket Hoist for Building Work (Ransome).]

In constructing a 9-story store at St. Paul, Minn., the concrete was

hoisted by continuous bucket elevators. A lay-out of the construction

plant is shown by Fig. 219. In the alley near the center of the north

side of the building the surface grade was about 6 ft. above the third

story level. A hopper was constructed at grade and provided with two

chutes running to the basement. These chutes discharged on opposite

sides of a vertical partition separating the sand and stone bins, and by

closing either chute at its top by a suitably arranged deflector plate

either sand or stone could be dumped into the same hopper and chuted to

its proper bin. Cement was brought to the work in cars over the tracks

shown and was wheeled from the cars over runways leading to the charging

platforms near each mixer. Other runways connecting with these platforms

provided for wheeling the sand and stone to the mixers. The runways were

placed at the proper height to permit the barrows to be emptied directly

into the charging hoppers. Two Smith mixers were used, located as shown,

and each discharged through a chute into one of the bucket elevator

boots. There were two elevators which were "raised" two stories at a

move as the work progressed. Each elevator discharged into a hopper

holding 1½ batches, and from these hoppers the concrete was fed into

wheelbarrows and wheeled to the forms. The bucket elevators were carried

no higher than the eighth floor. When this floor had been completed the

hoppers were moved down to the fifth floor and the wheelbarrows were

taken to platform elevators and carried to the remaining floors and

roof. Special 4-cu. ft. wheelbarrows were used for handling the

concrete. A maximum of 155 cu. yds. of concrete was mixed, transported

and placed in a 10-hour day with a gang of 28 men.

~Platform Hoists.~--The common builders' hoist or elevator, operating

single or double platforms or cages, needs no special description. The

wheelbarrow, cart or car containing the concrete is run onto the

platform, hoisted and then run to the forms. The chief advantage of this

device in concrete work is that it will handle all classes of material

without any change of carriage or arrangement, it can thus be used for

handling form lumber and reinforcing steel as well as for handling

concrete.

[Illustration: Fig. 219.--Plan of Concrete Mixing and Handling Plant for

9-Story Building.]

~Derricks.~--The use of derricks for hoisting in concrete building work is

limited by the necessity of supporting them independently of the

structure being built; the formwork or the completed concrete work

cannot be utilized to carry derricks during construction. For low

structures the derrick can be set on the ground, but for high buildings

a supporting tower or staging is necessary. The arrangement of such

falsework can be illustrated best by specific examples.

In constructing a 7-story factory at Cincinnati, O., concrete was mixed

on the ground and hoisted by a derrick with an 80-ft. boom mounted on a

tower 55 ft. high. The derrick was located to one side of the building.

For the lower floors the boom swing covered so large an area that the

bucket was dumped at various places, but for the upper floors it was

found more economical to dump buckets into a hopper from which

wheelbarrows were filled. By this plan less time was consumed in placing

the bucket and no tag rope man was required, as the engineman could

swing the boom to a certain point on the wall which would bring the

bucket directly over the hopper. A Smith mixer discharged directly into

derrick buckets, which rested on a track long enough to hold two

buckets. The buckets were filled and emptied alternately by shuttling

the truck and attaching first one and then the other to the derrick.

In constructing an 11-story and basement office building in New York

City a four-legged tower starting from the bottom of the excavation was

erected at about the center of the lot. It was built of timber and

extended upward as the progress of the work demanded until it overtopped

the roof 11 stories above the street. The tower was square in plan and

was divided into stories corresponding approximately to the several

stories of the building. A floor was constructed in the tower at each

story to be used in storing materials. For hoisting a 75-ft. boom was

swung from each leg of the tower, each boom being operated by a separate

engine and having a nominal capacity of 5 tons. The four booms covered

the whole building area and were kept about two stories above the work

by being shifted upward as the work progressed. This arrangement of

derricks was used to handle the steel, lumber and concrete, the building

being built up around the tower, which was so located that its only

interference with the building structure was in the shape of square

holes left in the floor slabs to accommodate the tower legs.

In constructing an 8-story warehouse covering some three acres of ground

in Chicago, Ill., the derrick plant shown by Figs. 220 to 222 was

installed. Some 7,500 tons of reinforcing steel, 125,000 cu. yds. of

concrete and 4,000,000 ft. of form lumber had to be handled.

Incidentally it is worth noting that there were about 120 lbs. of

reinforcing steel and 32 ft. B. M. of form lumber used per cubic yard of

concrete.

The controlling conditions governing the arrangement and character of

the construction plant were as follows: The building, to be built

entirely of reinforced concrete, was 135 ft. high. Its west front

abutted on the river and its south front on the street; at the north

end there was some ground available for plant and along the east front

there was a strip about 20 ft. wide between the building wall and the

main line tracks of a railway. At best, therefore, the area outside of

the building and available for plant and storage was limited, while

inside the building area the contractor was confronted by the insistence

of the architect that an unbroken monolithic construction be obtained as

nearly as possible, by reducing the floor openings for construction work

to a minimum. The sketch plan, Fig. 220, shows the plant designed to

meet the conditions.

To get the large amount of construction material onto the work a side

track was built along the 20-ft. area on the east side of the building

and another was turned into the area at the north end of the building.

These side tracks handled all construction materials coming onto the

work. Over the first there were built two sets of storage bins for sand

and gravel and all concrete materials brought in in carload lots are

unloaded at these two points, as will be described further on. Lumber

for forms and steel for reinforcement shipped in similar manner were

taken by the second siding to the lumber yard and steel mill at the

north end of the building.

[Illustration: Fig. 220.--Plan of Concrete Mixing and Handling Plant for

Large Warehouse Building.]

The raw materials after being worked up in the mixer plants and the saw

and steel mills were distributed over the work by an industrial railway.

The track system of this railway is shown by the dotted lines; it was

located on the basement floor, with rampes leading to the No. 1 mixer

plant and to the saw and steel mill tracks. The two main lines of track

passed close to or under the elevator and stairway shaft openings in the

several floors. This permitted the derrick buckets, lowered and hoisted

through the shafts, to be loaded directly from the car tracks. All mixed

concrete, forms and reinforcing frames were distributed by this railway

to the several shafts and thence hoisted and placed by the derrick

plant.

[Illustration: Fig. 221.--Derrick for Handling Concrete for Large

Warehouse Building.]

The derrick plant consisted of four derricks arranged as shown by the

circles in Fig. 220. The view, Fig. 221 shows the first derrick

installed and illustrates the general construction quite clearly.

Briefly the derrick consisted of a vertical steel-work tower 10 ft.

square and 85 ft. high, within which operated a steel mast 135 ft. high

and carrying an 80-ft. boom connected just above the tower. The mast was

pivoted at the bottom and had rollers turning against a horizontal ring

inside the tower at the top. It was operated by a bull wheel above the

top of the tower, the turning ropes running down inside the mast to the

foot block and thence horizontally to the operating motor. The topping

and hoisting lines also followed this route. The top of the tower was

guyed by four ropes to anchorages in the basement floor. The boom

commanded a circle 170 ft. in diameter and could lift 150 ft. above the

base of the mast. The derrick was operated by a 25-HP. double drum

electric hoist with a derrick swinging spool; this hoist was set on the

basement floor. It will be noted that the guys are below the bull wheel

so that the boom has a clear swing through a complete circle.

As stated above, four of these derricks were employed. Together they did

not cover the entire building area, but by the use of a derrick bucket

so designed that it could be used as a storage bin for feeding

wheelbarrows, it was found possible to keep the number of derricks down

to four.

This derrick plant possessed several advantages of importance. In the

first place the derricks would handle all classes of material--concrete,

forms, steel frames--equally well and could be transferred from one

class of work to the other with practically no delay. In the second

place, for a large area of the building, they handled the material from

the basement direct to the place it was to occupy in the work, and did

it in one operation. Finally they permitted the handling and erection

of the forms and reinforcement in large units. Thus a column form would

be assembled complete at the mill, moved as a unit by car to the proper

shaft and then hoisted and set in place as a unit by the derrick. Girder

forms, floor slab forms, girder and column reinforcing, etc., could be

similarly assembled and handled. The derricks occupied only the area of

four floor panels, the remainder of the area of each floor was left

unobstructed for the work to be done. No materials or supplies needed be

stored on the floors until they were in perfect condition to accommodate

them, and not then, even, so far as the prosecution of form erection and

concreting were concerned.

The sand and gravel for concrete were brought in by bottom or side dump

gondola cars from pits located about 30 miles out on the Chicago,

Milwaukee & St. Paul Ry. The cars were switched onto the main side track

and unloaded under the bins which straddle this track. A receiving

hopper, with its top at rail level and long enough to permit two cars to

be unloaded at once, received the sand or gravel and distributed it

through twelve gate openings onto an 18-in. horizontal belt conveyor 65

ft. long. This conveyor discharged into a second conveyor, 133 ft. long,

which ran up a 22° incline, extending away from the bins and discharged

onto a third conveyor 117 ft. long, which doubled back on a 22° incline

reaching to and over the top of the bins. This third conveyor had two

fixed trippers and an end discharge to distribute its cargo. All three

conveyors were operated by a 35-HP. motor located at the junction of the

two inclined conveyors, both of which were driven from the same shaft. A

chain belt from the idler shaft of the first incline conveyor to the

driving shaft of the horizontal conveyor operated that unit of the

plant. This belt was operated as a cross belt by reversing alternate

links. No manual labor was required to handle the sand and gravel from

the cars to the storage bins.

The mixer arrangement at the two bins differed. At the No. 1 bins the

mixer was located as shown in Fig. 220, close to the bin. Chutes led

directly from the sand and gravel bins to the charging hopper and the

bags of cement were stacked alongside this hopper. The mixer discharged

either directly into the bucket of the first derrick or into cars for

transportation on the railways. At the No. 2 bins a belt conveyor took

the concrete materials down into the basement to a mixer located close

enough to one of the distribution tracks to permit it to discharge

directly into the cars.

[Illustration: Fig. 222.--Special Concrete Bucket for Large Warehouse

Building.]

The derrick buckets by which the concrete was hoisted and handled to the

work were of special construction. A bucket was desired which would

serve several distinct purposes. It must first be able to hold a full

mixer batch of material, since, with the derrick arrangement, economy in

hoisting necessitated hoisting in large units and also because storage

capacity was required of the bucket for wheelbarrow work. The four

derricks did not command the entire area of a floor; there were corners

and other irregular areas outside of the circles covered by the several

booms over which the concrete must be distributed by barrows or carts.

A bucket large enough to supply the barrows, while a second bucket was

being lowered, charged from the mixer and hoisted, was required. In the

second place, a bucket was required whose contents could be discharged

all at once or in smaller portion at will. Finally a bucket was desired

which could be made to distribute its load along a narrow girder form or

in a thin sheet for a floor slab.

To meet these requirements the bucket shown in Fig. 222 was designed. It

held 42 cu. ft., or about 1.55 cu. yds. of concrete. It had a hopper

bottom terminating in a short rectangular discharge spout closed by a

lever operated under cut gate, which could be opened as much or as

little as desired. To the underside of the bucket there was attached a

four-leg frame in which the bucket stood when not suspended. Ordinarily,

that is within the circles commanded by the derricks, the buckets were

discharged suspended and directly into the forms, the character of the

discharge gate permitting a thin sheet to be spread for floor slabs or a

narrow girder or wall form to be filled without spilling or shock. For

wheelbarrow work outside the reach of the derricks the mode of procedure

was as follows: A timber platform about 3 ft. high and having room for

standing two buckets was set just on the edge of the circle commanded by

the derrick boom. Two buckets were used. A full bucket was hoisted and

set on the platform, with its spout overhanging. This bucket served as a

storage bin for feeding the wheelbarrows while the second bucket was

being lowered, charged and hoisted to take its place on the platform,

and serve in turn as a storage hopper.

~PLACING AND RAMMING.~--A wet concrete is usually used in building work

except on occasions, for exterior wall work and except for pitch roof

work, where a wet mixture would run down the slope. Placing and tamping

are therefore, essentially pouring and puddling operations. The pouring

should be done directly from the barrows, carts, or buckets if possible;

dumping onto shoveling boards and shoveling makes an extra operation and

increases the cost by the wages of the shoveling gang. Where shoveling

boards are necessary, take care that they are placed close to the forms

being filled, as it is wasteful of time to carry concrete in shovels,

even for a half dozen paces. Before pouring any concrete, the inside of

the forms should be wet down thoroughly with a hose or sprinkler, if a

hose stream is not available. The final inspection of forms and

reinforcement just before concreting will have made certain that they

are ready for the concrete, so far as line and level of forms and

presence and proper arrangement of the reinforcement are concerned, but

the concrete foreman must watch that no displacement occurs in pouring

and puddling, and must make certain particularly that the forms are

clean.

In pouring columns it is essential that the operation be continuous to

the bottom of the beam or girder. It is also advisable to pour columns

several hours ahead of the girders. Puddling should be thorough, as its

purpose is to work the concrete closely around the reinforcement and

into the angles of the mold and to work out air bubbles. A tool

resembling a broad chisel is one of the best devices for puddling or

slicing. In slab and girder construction, the pouring should be

continuous from bottom of girder to top of slab. Work should never be

stopped-off at horizontal planes. As in columns, careful puddling is

essential in pouring beams. In slab work, the concrete is best compacted

by tamping or rolling. A broad faced rammer should be used for tamping

wet concrete, or a wooden roller covered with sheet steel, weighing

about 250 lbs., and having a 30-in. face.

Theoretically, concreting should be a continuous operation, but

practically it cannot be made so. Bonding fresh concrete to concrete

that has hardened, though it has been done with great perfection by

certain methods as described in Chapter XXIV, must still be held as

uncertain. Ordinarily, at least, a plane of weakness exists where the

junction is made and in stopping off work it should be done where these

planes of weakness will cause the least harm. Experts are by no means

agreed on the best location of these planes, but the following is

recognized good practice. Work once started, pouring a column, should

not be stopped until the column is completed to the bottom of the

girder. For beams and girders; stop concrete at center of girder with a

vertical face at right angles to the girder, or directly over the center

of the columns; in beams connecting with girders, stop concrete at

center of span, or directly over center of connecting girder; stop

always with a vertical face and never with a sloping face, and never

with a girder partly filled. For slabs; stop concrete at center of span,

or directly over middle of supporting girder or beam; stop always with

vertical joints. If for any cause work must be stopped at other points,

than those stated, the fresh concrete and the hardened concrete must be

bonded by one of the methods described in Chapter XXIV.

~CONSTRUCTING WALL COLUMNS FOR A BRICK BUILDING.~--The columns, 12 in

number, were constructed to strengthen the brick walls of a power

station and were built as shown by Figs. 223 and 224, one at a time. The

staging, 50 ft. high and 4×6 ft. in plan, was erected against the wall

which had been shored, a portion of the wall was cut out and forms

erected and the concrete column substituted for the section of wall

which was removed. The staging was then moved into position for another

column.

[Illustration: Fig. 223.--Section of Rectangular Wall Column.]

Two men, with sledge and drill, cut out the brick work amounting to

about 12 cu. yds. for each column in 15 hours, at a cost of about 70

cts. per cu. yd., including removal to the street. The cost of moving

and re-erecting the scaffolding was $2.94 per each move. The character

of the reinforcement is shown by Fig. 223; it was erected as the

concreting progressed, the main bars being in sections 15 ft. long,

spliced with and distanced by side bars and cross bolts at the splices.

[Illustration: Fig. 224.--Staging and Forms Used in Building Column

Shown by Fig. 223.]

The concrete was hand mixed in 6-cu. ft. batches at the foot of the

column, by three men with a fourth turning over and filling the buckets.

The buckets, 12 ins. in diameter and 16 ins. high, were hoisted by a

pulley line arranged as shown and pulled by a mule driven by a man, at

$1 per day for the mule and $1.50 for the man, the cost of hoisting

being 25 to 40 cts. per cu. yd., depending on the rapidity of the man

inside the form. This man tamped the concrete which was emptied from the

buckets by a man on the scaffolding. Each batch raised the level in the

form 15 ins., and between batches a set of ties for the column rods was

placed by the man during the tamping. It took from 1½ to 2 days to

concrete a column of 12 cu. yds. The concrete was a 1-3.8-5.7 limestone

screenings mixture, mixed wet enough to be easily pushed into the forms

and worked around the reinforcement. The form construction is shown by

Fig. 224. The form for one column required 650 ft. B. M. of lumber, and

on an average, each form was used twice. As a matter of fact, the side

strips and outside braces were used three times, while much of the

7/8-in. sheathing was destroyed by being used once. The lumber for

shoring cost $23 per M. ft. B. M., and the light lumber for forms cost

$18 per M. ft. B. M. All lumber was yellow pine. All labor was negro, at

15 cts. per hour; foremen who worked. 22½ cts. per hour. The cost of the

several parts of the work compiled from records furnished by Mr. Keith

O. Guthrie, engineer in charge, was as follows:

Cost per Cost per

Concrete. column cu. yd.

Lumber for forms $ 4.81 $0.40

Setting up and removing forms 11.32 0.95

Cement, 10.17 bbls. at $2.40 24.40 2.03

Sand, 5.87 yds. at $0.90 5.28 0.44

Stone, 8.75 yds. at $1.35 10.94 0.91

Mixing and wheeling 15.73 1.31

Hoisting by mule with driver 4.80 0.40

Handling bucket on scaffold 2.93 0.25

Tamping inside column 2.93 0.25

Painting with grout 3.89 0.32

Clearing away rubbish 1.97 0.16

Rigging, etc. 2.64 0.21

Tools 0.59 0.05

Moving scaffold 2.94 0.25

Moving mix board and rigging hoist 1.62 0.14

------ -----

Total cost of concrete $96.79 $8.07

Cost per Cost cts. per

Reinforcement. column. lb. of bars.

Iron bars, 1,034 lbs. $20.68 $2.00

Drilling iron bars 1.44 0.14

Setting iron bars in place 1.23 0.12

Bolts for splicing and spacing 3.98 0.40

Wire cross ties at 2½, cts. lb. 1.39 0.14

Labor forming 130 cross ties 1.13 0.11

------ -----

Total cost of iron and steel $29.85 $2.91

Summary of Cost.

Per column. Per cu. yd.

Concrete in place $96.79 $8.07

Steel in place 29.85 2.49

Cutting out and removing brick 8.36 0.70

Shoring floors and roof, labor 5.87 0.49

Ditto for lumber used 3 times 3.44 0.29

------- ------

Total $144.31 $12.04

[Illustration: Fig. 225.--Girder Plan for 6-Story Building.]

~FLOOR AND COLUMN CONSTRUCTION FOR SIX-STORY BUILDING.~--The building was

91×112 ft.; 56 columns spaced 16 ft. apart carried the girder system

shown by Fig. 225, which in turn supported a 3½-in. floor slab. The

walls and partitions were not concrete. The following records were kept

by the authors:

_Forms._--The column forms were built as shown by Fig. 226. The boards

were 1½-in. stuff, surfaced on four sides; the yokes were spaced 2 ft.

apart. The 1×6-in. pieces were nailed to the 2×4's with 8-d. nails with

heads left projecting for easy pulling. The girder forms, Fig. 227,

rested on the column forms and on intermediate posts half-way between

columns. These intermediate posts were 3×4's with 4×4×12-in. head blocks

nailed to their tops and wedges under their bottoms. The girder molds

were 1½-in. stuff, and to the side pieces were nailed 1×4-in. cleats;

the bottom and side pieces were connected by 3/8×4-in. lag screws spaced

28 ins. apart. The floor slab stringers were carried on the 1×4-in.

cleats; they were spaced 28 ins. apart and were not nailed; neither were

the 1×6-in. lagging boards nailed to the stringers. The point to be

noted is the design and construction of the forms so that they could be

put together and taken apart easily. The lumber required for forms for

one floor 91×112 ft., or, say, 10,200 sq. ft., was as follows:

Lumber for columns, ft. B. M. 9,000

Lumber for 10×10-in. beams, ft. B. M. 7,600

Lumber for 5×10-in. beams, ft. B. M. 2,700

Intermediate 3×4-in. posts, ft. B. M. 1,000

Lagging, 1×6-in. boards, ft. B. M. 9,000

Stringers, 3×4 ins., ft. B. M. 4,500

------

Total ft. B. M. 33,800

[Illustration: Fig. 226.--Column Form for 6-Story Building.]

In round numbers, we can say that 34,000 ft. B. M. of lumber were used

for 10,000 sq. ft. of floor area, or 3.4 ft. B. M. per 1 sq. ft. Enough

forms were provided to erect two complete floors; the forms for the

lower floor being removed and erected again for the second floor above,

thus using all the lumber three times. With carpenters at $3.50 for 8

hours, the forms were framed ready for erection for $4 per M. ft. B. M.

The lumber framed ready to erect cost them:

Lumber, cost per M. ft. B. M. $26.00

Labor, framing per M. ft. B. M. 4.00

------

Total per M. ft. B. M. $30.00

[Illustration: Fig. 227.--Girder and Slab Forms for 6-Story Building.]

Since the lumber was used three times, $30 ÷ 3 = $10 is the charge

against each 1,000 ft. B. M. needed to encase the concrete on a floor.

There were nearly 34,000 ft. B. M. per floor, hence the cost of lumber

ready for erection was $340 per floor. There were as shown below, 200

cu. yds. of concrete per floor, so that the cost was $340 ÷ 200 = $1.70

per cu. yd. of concrete for forms ready for erection. It took a gang of

5 men 7 days to tear down and carry up the forms for one floor; hence 5

× $2 × 7 = $70 per floor, or practically $2 per M. ft. B. M., or $0.35

per cu. yd. of concrete for taking down and carrying forms two stories.

It took a gang of 10 carpenters 7 days to erect these forms, which at

$3.50 per day was $245 per floor, or $7 per M. ft. B. M., or $1.20 per

cu. yd. of concrete.

_Concrete._--The amount of concrete per floor was as follows:

Floor slab 3½ ins. thick, 10,200 sq. ft. 110 cu. yds.

Beams, 10×10 ins. 40 cu. yds.

Beams, 5×10 ins. 20 cu. yds.

Columns, 15×15 ins. (average) 30 cu. yds.

-----

Total concrete per floor 200 cu. yds.

A concrete mixer, a hoist and a gang of 14 men mixed and placed the

concrete for a floor in 7 days. At $2 per day for labor this gives 14 ×

7 × $2 = $196, or say $1 per cu. yd. for mixing and placing the

concrete.

_Reinforcement._--In each of the 10×10-in. beams there were 4, 1-in.

round rods, 2 straight and 2 bent, and stirrups of 1/8×1-in. straps

spaced 5 ins. apart at columns and 15 ins. at the center. In each

5×10-in. beam there was half as much steel as in a 10×10-in. beam. The

floor slab reinforcement consisted of ¼-in. rods spaced 5 ins. apart and

2 cross-rods in 7-ft. panel. The column reinforcement consisted of 4

rods averaging 1 in. in diameter. In round numbers the amount of steel

required for each floor was, therefore, as follows:

Lbs. steel rods in 10×10-in. beams 16,200

Lbs. steel rods in 5×10-in. beams 4,000

Lbs. stirrups in beams 3,000

Lbs. steel rods in floor slabs 3,800

Lbs. steel rods in columns 1,400

------

Total pounds steel per floor 28,400

This is equivalent to 142 lbs. of steel per cubic yard of concrete, or

about 1 per cent of the total volume of reinforced concrete was steel.

The steel in the beams was about 3 per cent. It required a gang of 5

laborers 7 days at $2.25 per day, to bend and place the steel for each

floor or $86 for labor on 28,400 lbs. of steel. This is equivalent to

0.3 ct. per lb., or 45 cts. per cu. yd. of concrete.

_Summary of Costs._--Summarizing the figures given we have the following

cost per cubic yard of concrete in floors and columns:

Per cu. yd.

142 lbs. steel at 2½ cts. $ 3.55

1 bbl. cement 2.50

1 cu. yd. gravel 1.10

½ cu. yd. sand 0.55

170 ft. B. M. lumber ready to erect at $10 (1/3 of $30) 1.70

170 ft. B. M. torn down at $2 0.35

170 ft. B. M. erected by carpenters at $7 1.20

Mixing and placing concrete 1.00

Shaping and placing steel 0.45

Superintendence 0.25

------

Total $12.65

~WALL AND ROOF CONSTRUCTION FOR ONE-STORY CAR BARN.~--The barn was 50 ft.

wide and 190 ft. long, divided into three rooms by two transverse

partitions and covered with a 4-in. roof having a pitch of ½ in. per

foot. The main walls were 12 ins. thick and the partition walls 10 ins.

thick. The main room 110 ft. long had four car tracks its whole length

with pits under each and a 6-in. reinforced concrete floor slab between.

The floor girders, one under each rail, were 12 ins. square, each

reinforced by three 1¾-in. rods, and were carried on 12×12-in. pillars.

The total yardage of concrete was 874 cu. yds. divided as follows:

Walls and foundations, cu. yds. 614

Pillars and girders in track pits, cu. yds. 44

Reinforced floors, cu. yds. 55

Roof 160

---

Total, cu. yds. 873

A 1-2½-5 concrete was used for floors, roofs and girders and a 1-3-6

concrete for foundations and walls. There were 26½ tons of reinforcing

steel, or 61 lbs. per cu. yd., or 0.45 per cent. of the volume of the

concrete was steel. The wages paid were: Foreman, $2.50; blacksmith, $2;

engineer, $1.75; laborers, $1.50; two-horse team and driver, $3.67;

one-horse team and driver, $2.92; carpenter, $2.25; carpenters worked 9

hours; all others 10 hours.

_Forms._--Carpenters framed and erected forms and common laborers under

foreman carpenter took them down. Lagging was all 2-in. stuff and

uprights 3×4-in. stuff. Props for roof forms were 18-ft. round timber

procured on the job. They were 6 ins. in diameter at the top and cost 50

cts. each, 91 being used. These props are not included in the lumber

listed below, but their cost is included in the costs given. No record

was kept of the number of times the lumber was used, but as 54,643 ft.

B. M. were bought and about twice this much would be needed to enclose

the concrete if used only once, we will assume that all lumber was used

twice. Including the props there were about 60,000 ft. B. M., or 70 ft.

B. M. per cu. yd. of concrete. The cost of the lumber was $1,520.86, and

the cost of labor on the forms was $1,660.60, so that the cost of forms

was:

Item. Per cu. yd. Per M. ft. Per sq. ft.

Lumber $1.74 $13.50 $0.038

Labor 1.90 14.07 0.041

----- ------ ------

Total $3.64 $27.57 $0.079

If the lumber had been used only once the cost per cubic yard would have

been $5.38, and per M. ft. B. M., $41.07.

_Concrete._--A railway track was run the full length of the building

upon what was eventually the fourth track of the car barn and a Ransome

mixer was set up as close to the track as possible allowing a platform

to be built between it and the track. Cars were brought up to this

platform and the materials handled by wheelbarrows direct from cars to

mixer. Both platform and mixer were moved twice as the work progressed.

The concrete was taken by wheelbarrows on runways to the side walls. For

the roof it was hoisted by a horse by means of a mast having an arm with

a three-quarters swing; the barrows were hoisted direct using a hook for

the wheel and two rings for the handles.

The cost of the concrete for materials was:

1.1 bbl. cement at $1.21, per cu. yd. $1.33

¾ ton sand at 75 cts., per cu. yd. 0.55

Aggregate, per cu. yd. 0.88

61 lbs. steel at 1.9 cts., per cu. yd. 1.15

Lumber, 70 ft. B. M. at $27, per cu. yd. 1.74

-----

Total per cu. yd. $5.65

The cost of labor per cubic yard was:

Forms, per cu. yd. $1.900

Mixing, per cu. yd. 0.210

Placing, per cu. yd. 0.310

Finishing, per cu. yd. 0.143

Handling cement, per cu. yd. 0.017

Handling sand, per cu. yd. 0.104

Handling steel, per cu. yd. 0.270

Handling aggregate, per cu. yd. 0.222

Coal, at $4.25 per ton, per cu. yd. 0.010

Foreman, per cu. yd. 0.133

Teams and laying pipe line, per cu. yd. 0.087

------

Total, per cu. yd. $3.406

Summarizing, we have the following cost per cubic yard:

Concrete materials, per cu. yd. $2.76

Labor mixing and placing concrete 1.01

Forms, materials and labor 3.64

Reinforcement, materials and labor 1.42

Fuel, foreman and pipe line labor 0.23

-----

Total, per cu. yd. $9.06

The cost for handling steel, making stirrups, welding, etc., was $8.90

per ton, or 0.45 ct. per lb.

_CONSTRUCTING WALL COLUMNS FOR A ONE-STORY MACHINE SHOP._--The building

was 53×600 ft.; each side wall consisted of 40 columns of channel

section carried on footings of channel section somewhat heavier than

that of the column. The columns were spaced 15 ft. on centers and each

was 7½ ft. wide so that there were 7½ ft. spaces between columns, which

were filled with 3-in. curtain walls extending 7½ ft. above the floor.

Figures 228 and 229 show the column and footing construction. Each

column contained 125 cu. ft., or 4.63 cu. yds. of 1-3-5 1-in. crushed

slag concrete above the footing and the costs given here relate only to

the columns above footings. In the 80 columns there were 370 cu. yds. of

concrete.

_Forms._--A column form is shown by Fig. 230; it contains approximately

1,000 ft. B. M. of lumber. Ten of these forms were used, so that 10,000

ft. B. M. of form lumber were required for 370 cu. yds. of concrete, or

27 ft. B. M. per cu. yd. of concrete. Each column had a superficial area

excluding ends of about 420 sq. ft., so that 420 × 80 = 33,600 sq. ft.

was the superficial area of all the columns and 10,000 ft. B. M. ÷

33,600 sq. ft. = 0.3 ft. B. M., or, say, 1/3 ft. B. M., of form lumber

was used per square foot of concrete enclosed. The cost of the forms per

1,000 ft. B. M., and, therefore, per form, was:

Lumber, 1,000 ft. B. M., at $31.75 $31.75

Labor constructing form 16.39

------

Total per 1,000 ft. B. M. $48.14

[Illustration: Fig. 228.--Channel Section Wall Column for Factory

Building.]

This gives us a cost per cubic yard of concrete for materials and labor

constructing forms of $480 ÷ 370 = $1.30, and per square foot of outside

wall area of $480 ÷ (146 × 80) = 4.1 cts.

The erection and taking down of the forms, owing to the weight of some

of the pieces, was done by means of special derricks. The footings were

brought to within ½ in. of grade and a tenon form of the exact shape of

the channel section of the column was placed on top and filled with

grout to a depth of 1 in. These tenons served as guides in setting the

column forms, and proved to be much quicker and more accurate than

points.

[Illustration: Fig. 229.--Footing for Wall Column Shown by Fig. 228.]

The forms were assembled on the ground and erected by a 35-ft. A-frame

derrick mounted on wheels. The construction is shown by Fig. 231. This

derrick had a capacity of about 4 tons and carried a Ransome friction

crab hoist driven by a 5 h.p. Meitz & Weiss kerosene oil engine. It was

the practice to set a number of forms before filling any. This enabled

the carpenter gang to be plumbing up the first form while the erecting

gang were setting others. The forms had to be very securely guyed and

braced to withstand the impact of the falling concrete. Very little

trouble was had in keeping them well lined up.

[Illustration: Fig. 230.--Form for Molding Wall Column Shown by Fig.

228.]

Two gangs were employed in assembling forms and a portion of the men in

each gang also shaped and placed the reinforcement and placed and tamped

the concrete in the forms so that no exact division of labor is

possible. The organization of these gangs and the wages paid were as

follows:

Derrick Gang:

1 foreman, at 36 cts. per hour $ 3.94

1 crabman, at 30 cts. per hour 2.70

2 topmen, at 27 cts. per hour 4.86

2 bottom men, at 23 cts. per hour 4.14

------

Total per 9-hour day $15.64

Assembling Gang:

1 boss carpenter, at 47 cts. per hour $ 4.23

2 carpenters, at 36 cts. per hour 6.48

2 carpenters, at 30 cts. per hour 5.40

2 carpenters' helpers, at 25 cts. per hour 4.50

4 men forming and placing reinforcing steel

and rethreading bolts, at 23 cts. per hour 8.28

------

Total per 9-hour day $28.89

------

Grand total $44.53

These gangs assembled and erected the molds and concreted 80 columns in

22 working days, including 2 days lost on account of cold weather, so

that 4 columns were completed per day of 9 hours. We can subdivide the

cost as follows:

Item. Per cu. yd.

Erecting forms and concreting $0.81

Assembling forms and reinforcement 1.56

-----

Total $2.37

Charging the 4 men placing reinforcement and rethreading bolts to

forming and placing reinforcement alone we can figure the cost of

fabrication and erection of reinforcement very closely. There were 160

lbs. of reinforcing steel in each column, hence $8.28 ÷ (160 × 4) = 1.3

cts., was the cost per pound of forming and placing it. This includes

handling.

The stripping of the forms was carried on by another gang using a

derrick similar to the first one described, except it could be of

lighter construction as it had to handle only the separate parts of each

form and not the forms assembled. The derrick shown in Fig. 232 was a

33-ft. A-frame, with wheels at the bottom of each leg. It had a friction

crab hoist driven by an electric motor, both of which were fastened to

the derrick frame between the shear legs.

[Illustration: Fig. 231.--Derrick for Erecting Wall Column Forms Shown

by Fig. 230.]

The operation of stripping required only four men and the crabman. The

outside flat panel was removed first, and left leaning up against the

concrete while the inside trough shaped panel was pried loose and

lowered onto the ground with its inside face uppermost. The side panels

being comparatively light, were stripped without the use of the derrick,

and these panels were assembled on the ground with the inside piece. The

derrick then picked up the outside panel again, and placed it in its

proper place. After the bolts were put in place, the assembled form was

moved on rollers to another point in the line of columns where it was

again erected. The arrangement of derricks for erecting and stripping

forms is shown in Fig. 233.

The gang stripping forms was made up as follows:

1 foreman, at 30 cts. per hour $ 2.70

1 crabman, at 27 cts. per hour 2.43

1 topman, at 27 cts. per hour 2.43

2 bottom men, at 23 cts. per hour 4.14

------

Total per 9-hour day $11.70

[Illustration: Fig. 232.--Derrick for Stripping Wall Column Forms Shown

by Fig. 230.]

This gang of five men stripped 4 columns containing 18.52 cu. yds. of

concrete each day, so that the cost of stripping was $11.70 ÷ 18.52 =

62.7 cts. per cu. yd.

_Concrete._--The concrete was mixed in a No. 2 Ransome mixer and

delivered to the work in Ransome concrete carts. These carts were pushed

along a runway which terminated in a slight incline under the derrick so

that their contents could be emptied into the derrick buckets.

The concrete was hoisted in an 8-ft. bottom dump bucket, using the

derrick described above. It was necessary to stir up the concrete

thoroughly with long-handled slicers as it was being deposited in order

to prevent segregation. This expedient combined with a wet mixture and

tight molds was found to overcome this difficulty very effectually.

The gang mixing and wheeling concrete was made up as follows:

1 mixer foreman and engineer at 27 cts. per hour $ 2.43

4 laborers charging mixer at 18 cts per hour 6.48

4 laborers wheeling concrete at 18 cts. per hour 6.48

------

Total per 9-hour day $15.39

This gang mixed and wheeled concrete for four columns, or 18.52 cu.

yds., hence the cost per cubic yard was 82.6 cts.

With cement at $1.60 per bbl., sand at $1 per cu. yd. and slag at $1.10

per cu. yd. the cost of materials per cubic yard of concrete was $3.

[Illustration: Fig. 233.--Arrangement of Derricks for Erecting and

Stripping Forms.]

Summarizing the above figures we have the following cost per cubic yard

of concrete in place:

Item. Per cu. yd.

Concrete materials $3.00

Reinforcing steel 0.73

Forms, lumber and framing 1.30

Forms, erecting and concreting 0.81

Forms, assembling and reinforcement 1.56

Forms, stripping 0.63

Mixing and wheeling concrete 0.83

-----

Total $8.86

~CONSTRUCTING ONE-STORY WALLS WITH MOVABLE FORMS AND GALLOWS FRAMES.~--In

constructing the walls for an 85×30-ft. factory building at Old Bridge,

N. J., Mr. A. E. Budell made use of movable forms and gallows frames to

construct the curtain walls and columns in one piece. Each side wall was

built its full height in successive 50-ft. lengths by depositing the

concrete between two forms which were moved upward as the concreting

progressed. Fig. 234 indicates the mode of procedure. The form was

raised and lowered by means of two gallows frames fitted with blocks and

tackle. A steel cable, with a trolley affixed, extending from one frame

to the other, provided a convenient mode of hoisting material to the

form, and the gallows frames took the place of ladders for climbing onto

the structure. No scaffolding whatever was used and only one man was

required overhead to dump the buckets and tamp the concrete into place.

[Illustration: Fig. 234.--Gallows Frame Supporting Wall Form Panels for

One-Story Building.]

[Illustration: Fig. 235.--Details of Wall Form Panel for One-Story

Building.]

The two walls were carried up simultaneously, one form being shifted

into place and filled while the other was left in place until the

concrete was sufficiently hard. It was found that 18 hours was amply

sufficient to allow the concrete to set hard, after which the form was

removed and lifted to a higher level. Thus the men were continuously

engaged in lifting and filling first one form and then the other. The

average length of time required to remove, raise and fill one form was 5

to 6 hours. Thus, two forms could be raised and filled almost every day.

The construction of the forms and of the gallows frames is shown by

Figs. 234 and 235. The cost of one set of forms and gallows frames was

as follows:

320 ft. B. M. of 2×10 in.×10 ft. plank at $34 $ 10.88

150 ft. B. M. of 3×4 in.×16 ft. spruce at $33 5.25

135½ ft. B. M. 1×8 in. yellow pine at $30 4.08

335 ft. B. M. 1¼×6 in. spruce at $33 11.05

4 posts 6×8 in.×26 ft. = 416 ft. B. M. at $30 12.48

4 sills 6×8 ins.×16 ft., 2 caps 6×6 ins.×9 ft.,

4 braces 6×6 ins.×16 ft. = 490 ft. B. M. at $30. 14.70

3 pieces 3×10 ins.×20 ft. = 150 ft. B. M. at $30 4.50

-------

Total lumber (1,996.5 ft. B. M.) $ 62.94

Accessories:

Bolts for trussing, 675 lbs. at 2 cts. $ 13.50

Iron guy rope and clips 7.00

Blocks 8.00

One coil of ¾-in. rope 28.00

-------

Total accessories $ 56.50

Labor making one outfit:

2 men, 8 days, at $2.75 per 9 hrs. $ 44.00

-------

Grand total $163.44

This sum covered the cost of forms for one side of the building 85 ft.

long and containing 150 cu. yds. of concrete, hence the cost of forms

was in round figures $1.10 per cu. yd. of concrete. Each cubic yard of

concrete required 1,997 ÷ 150 = 13-1/3 ft. B. M. of form lumber.

The concrete was a 1-2½-4½ mixture. A careful record for 15 days, showed

an average of 2.8 cu. yds. of concrete placed in 6 hours by a gang of

6.3 men. From this we can figure the cost of concrete in place to be

about as follows:

2.8 cu. yds. concrete at $3 for materials $ 8.40

6.3 men 6 hours at 15 cts. 5.67

1 foreman 6 hours at $4 per day 2.00

------

Total per cu. yd. $16.07

Thus the cost of concrete in place was $16.07 ÷ 2.8 = $5.73 per cu. yd.

Adding the cost of forms we get $5.73 + $1.10 = $6.83 per cu. yd. as the

cost for labor and materials in constructing forms and mixing and

placing concrete.

[Illustration: Fig. 236.--Detail of Column and Cantilever Column Footing

for Four-Story Garage.]