[Illustration: Fig. 80.--Sketch Plan of Concrete Mixing Plant for

Buffalo Breakwater.]

Figure 80 shows the arrangement of the mixing plant. The mixer was a

5-ft. cube mixer holding 125 cu. ft., mounted on a trestle and operated

by a 9×12-in. horizontal engine taking steam from a 4×10-ft. locomotive

boiler, also supplying steam to two derrick engines. The material scow

contained two pockets for sand, one for gravel and one housed over for

cement. Two inside cement men passed out the bags in lots of six to one

outside cement man who cut and emptied them into the charging bucket.

Three sand shovelers each loaded a 3.6 cu. ft. barrow and wheeled them

tandem to the bucket, and two gravel men each loaded a 2.7 cu. ft.

barrow and wheeled them tandem to the bucket. The broken stone was

loaded by eight shovelers into another bucket, also containing 21.6 cu.

ft. The two buckets were alternately hoisted and emptied into the mixer

hopper, there being a dump man on the mixer who dumped the buckets and

attended to the water supply. A charger put the mixer in operation and

when the charge was mixed the car men dumped it into a skip resting on

a small car which was then run out on the track under the mixer to the

derrick which handled the skip to the work. Derrick A handled the

materials from the scows and derrick B handled the mixed concrete. The

force on the derricks consisted of two enginemen, four tagmen and the

fireman.

The ten parapet wall sections containing 841 cu. yds. were built in 46

hours, making 17 batches of 1.07 cu. yds., or 18.2 cu. yds. placed per

hour. The 17 parapet deck sections containing 1,720 cu. yds. were built

in 88 hours, making 18.8 batches of 1.08 cu. yds., or 19.5 cu. yds.

placed per hour. For the parapet deck work the force was increased by 2

men handling materials and 1 man on the mixer. The labor cost of mixing

and placing the concrete was as follows:

Per Per

Loading Gang-- day. cu. yd.

1 assistant foreman 2.00 $0.011

3 cement handlers 5.25 0.029

3 sand shovelers 5.25 0.029

2 gravel shovelers 3.50 0.020

8 stone shovelers 14.00 0.076

1 hooker on 1.75 0.010

------ ------

Totals $31.75 $0.175

Mixer Gang--

1 dumpman $ 1.75 $0.010

1 charging man 1.75 0.010

2 car men 3.50 0.020

2 enginemen at $3.25 6.50 0.035

4 tagmen at $2 8.00 0.044

1 fireman 2.00 0.011

------ ------

Totals $23.50 $0.130

Wall Gang--

1 Signalman $ 1.75 $0.010

1 dumper 1.75 0.010

6 shovelers at $2 12.00 0.065

4 rammers 7.00 0.038

1 foreman 4.00 0.022

------ -----

Totals $26.50 $0.145

Grand totals $81.75 $0.450

[Illustration: Fig. 81.--Concrete Blocks for Pier at Port Colborne

Harbor.]

[Illustration: Fig. 82.--Forms for Molding Blocks, Port Colborne Harbor

Pier.]

[Illustration: Fig. 83.--Device for Handling Blocks, Port Colborne

Harbor Pier.]

~PIER CONSTRUCTION, PORT COLBORNE, ONT.~--In constructing the new harbor

at Port Colborne, Ont., on Lake Erie, the piers consisted of parallel

rows of timber cribs set the width of the pier apart and filled in and

between with stone blasted and dredged from the lake bottom in deepening

the harbor. The tops of the cribs terminated below water level and were

surmounted by concrete walls set on the outer edges. These walls were

filled between with stone and the top of the filling was floored part

way or entirely across, as the case might be, with a thick concrete

slab. The footings of the walls to just above the water level were made

of concrete blocks 4½×4×7 ft., constructed as shown by Fig. 81. The wall

above the footing course and the floor slab were of concrete molded in

place. The concrete work consisted of molding and setting concrete

blocks and of molding concrete wall and slab in place.

The blocks were molded on shore, shipped to the work on scows and set in

place by a derrick. Figure 82 shows the construction of the forms for

molding the blocks; the bottom tie rods passed through the partitions

forming the ends of the molds. The sides were removed in 48 hours and

used over again. Figure 83 shows the hooks used for handling the molded

blocks. Considerable trouble was had in setting these blocks level and

close jointed, owing to the difficulty of leveling up the stone filling

under water.

[Illustration: Fig. 84.--Scow Plant for Mixing and Placing Concrete,

Port Colborne Harbor Pier.]

The mass concrete was mixed and placed by the scow plant, shown by Fig.

84. The scow was loaded with sufficient sand and cement for a day's work

and towed to and moored alongside the pier. Forms were set for the wall

on top of the block footing. These forms were placed in lengths of 60 to

75 ft. of wall and resembled the block forms with partitions omitted.

The bottoms of the rear uprights were held by being wedged into the

grooves in the blocks, and the bottoms of the front uprights were held

by bolts resting on top of the blocks. The tops of the uprights were

held together across the wall by tie bolts. The forms being placed, the

mode of procedure was as follows:

The crusher fed directly into a measuring box. After some 6 ins. of

stone had run into the box the door of the crusher spout was closed. A

wheelbarrow load of sand was spread over the stone in the box and over

this were emptied and spread two or three bags of cement. Another layer

of stone and then of sand and of cement were put in and these operations

repeated until the box was full. The box was then hoisted and dumped

into the hopper of a gravity mixer of the trough type which ran along a

track on the scow and fed directly into the forms. The gang worked

consisted of 1 foreman, 1 derrickman and 18 common laborers. This gang

placed from 65 to 75 cu. yds. of concrete per day at a labor cost of 50

cts. per cu. yd.

[Illustration: Fig. 85.--Cross-Section of Concrete Pier, Superior, Wis.]

~CONCRETE BLOCK PIER, SUPERIOR ENTRY, WIS.~--The methods and cost of

constructing a concrete pier 3,023 ft. long and of the cross-section

shown by Fig. 85 at Superior entry, Wisconsin, are given in the

following paragraphs.

_Molds and Molding._--About 80 per cent. of the concrete was deposited

in molds under water, according to a plan devised by Major D. D.

Galliard, corps of engineers. In brief the concrete was built in place

in two tiers of blocks, the lower tier resting directly on piles and

being entirely under water and the upper tier being almost entirely

above water. As shown by Fig. 85, a pile trestle was built on each side

of the proposed pier and a traveler for raising and lowering the molds

spanned the space between trestles.

The molds were bottomless boxes built in four pieces, two sides and two

ends, held together by tie rods. Fig. 86 shows an end and a side of one

of the shallow water molds and Fig. 87 shows in detail the method of

fastening the end to the side. It will be seen that the 1¼-in.

turnbuckle rods pass through the ends of beams that bear against the

outside of the mold. These tie rods have eyes at each end in which rods

with wedge-shaped ends are inserted. The molds were erected on the

trestle by a locomotive crane and were then lifted by the mold traveler,

carried and lowered into place. The largest one of these molds with its

iron ballast, weighed 40 tons. To remove a mold, after the block had

hardened, the nuts on the wedge-ended rods were turned, thus pulling the

wedge end from the eye of the tie rod and releasing the sides of the

mold from the ends. The locomotive crane then raised the ends and sides,

one at a time, and assembled them ready to be lowered again for the next

block. The time required to remove one of these 40-ton molds, reassemble

and set it again rarely exceeded 60 minutes and was sometimes reduced to

45 minutes.

[Illustration: Fig. 86.--Mold for Concrete Block for Pier at Superior,

Wis.]

The concrete was deposited in alternate blocks and the molds described

were for the first blocks; for the intermediate blocks molds of two side

pieces alone were used, the blocks already in place serving in lieu of

end pieces. The two side pieces were bolted together with three tie rods

at each end; the tie rods were encased in a box of 1-in. boards 4×4 ins.

inside which served as a strut to prevent the sides from closing

together and as a means of permitting the tie rods to be removed after

the concrete had set. The mold was knocked down just as was the full

mold described above and the boxes encasing the tie rods were left in

the concrete.

[Illustration: Fig. 87.--Device for Locking End and Side of Mold for

Concrete Blocks for Pier at Superior, Wis.]

An important feature was the device for handling the molds; this, as

before stated, was a traveler, which straddled the pier site, it having

a gage of 31 ft. It carried a four-drum engine, the drums of which were

actuated, either separately or together, by a worm gear so as to operate

positively in lowering as well as in raising. The load was hung from

four hooks, depending by double blocks and 5/8-in. wire rope from four

trolleys suspended from the trusses of the traveler; this arrangement

allowed a lateral adjustment of the mold. The hoisting speed was 6 ft.

per minute and the traveling speed 100 ft. per minute. The locomotive

crane also deserves mention because it was mounted on a gantry high

enough to permit material cars to pass under it on the same trestle,

thus making it practicable to work two cranes.

[Illustration: Fig. 88.--Bucket for Depositing Concrete Under Water for

Pier at Superior, Wis.]

The concrete was received from the mixer into drop bottom buckets of the

form shown by Fig. 88. The buckets were taken to the work four at once

on cars, and there lifted by the locomotive crane and lowered into the

mold where they were dumped by tripping a latch connected by rope to the

crane. To prevent the concrete from washing, the open tops of the

buckets were covered with 3×4 ft. pieces of 12-oz. canvas in which were

quilted 110 pieces of 1/16×1×3-in sheets of lead. Two covers were used

on each bucket and were attached one to each side of the bucket top so

as to fold over the top with a lap. This arrangement was entirely

successful for its purpose.

_Concrete Mixing._--The proportions of the subaqueous concrete were

1-2½-5 by volume, or 1-2.73-5.78 by weight, cement being assumed to

weigh 100 lbs. per cu. ft.; the proportions of the superaqueous concrete

were 1-3.12-6.25 by volume, or 1-3.41-7.22 by weight. The dry sand

weighed 109.2 lbs. per cu. ft., the voids being 35.1 per cent.; the

pebbles weighed 115.5 lbs. per cu. ft., the voids being 31 per cent.

The pebbles for the concrete were delivered by contract and were

unloaded from scows by clam-shell bucket into a hopper. This hopper fed

onto an endless belt conveyor which delivered the pebbles to a rotary

screen. Inside this screen water was discharged under a pressure of 60

lbs. per sq. in. from a 4-in. pipe to wash the pebbles. From the screen

the pebbles passed through a chute into 4-cu. yd cars which were hauled

up an incline to a height of 65 ft. by means of a hoisting engine. The

cars were dumped automatically, forming a stock pile. Under the stock

pile was a double gallery or tunnel provided with eight chutes through

the roof and from these chutes the cars were loaded and hauled by a

hoisting engine up an inclined trestle to the bins above the concrete

mixer. The sand was handled from the stock pile in the same manner. The

cement was loaded in bags on a car in the warehouse, hauled to the mixer

and elevated by a sprocket chain elevator.

Chutes from the bins delivered the materials into the concrete mixer,

which was of the Chicago Improved Cube type, revolving on trunnions

about an axial line through diagonal corners of the cube. The mixer

possessed the advantage of charging and discharging without stopping. It

was driven by a 7×10-in. vertical engine with boiler. The mixer

demonstrated its ability to turn out a batch of perfectly mixed concrete

every 1-1/3 minutes. It discharged into a hopper provided with a cut-off

chute which discharged into the concrete buckets on the cars.

_Labor Force and Costs._--In the operation of the plant 55 men were

employed, 43 being engaged on actual concrete work and 12 building molds

and appliances for future work. The work was done by day labor for the

government and the cost of operation was as follows for one typical

week, when in six days of eight hours each, the output was 1,383 cu.

yds., or an average of 230 cu. yds. per day. The output on one day was

considerably below the average on account of an accident to the plant,

but this may be considered as typical.

Pebbles from Stock Pile to Mixer-- Per cu. yd.

4 laborers at $2 $0.0348

1 engineman at $3 0.0131

Coal, oil and waste at $1.03 0.0043

Sand from Stock Pile to Mixer--

5 laborers at $2 $0.0434

1 engineman at $2.50 0.0109

Coal, oil and waste at $0.82 0.0035

Cement from Warehouse to Mixer--

5 laborers at $2 $0.0434

Mixing Concrete--

1 engineman at $2.50 $0.0109

1 mechanic at $2.50 0.0108

Coal, oil and waste at $1.29 0.0056

Transporting Concrete--

4 laborers at $2 $0.0348

1 engineman at $3 0.0130

Coal, oil and waste at $0.66 0.0028

Depositing Concrete in Molds--

4 laborers at $2 $0.0348

1 engineman at $3 0.0130

1 rigger at $3 0.0130

Coal, oil and waste at $1.18 0.0051

Assembling, Transporting, Setting and Removing Molds--

4 laborers at $2 $0.0347

1 engineman at $3.25 0.0141

1 carpenter at $3 0.0130

1 mechanic at $2.50 0.0109

Coal, oil and waste at $1.39 0.0060

Care of Tracks--

1 laborer at $2 $0.0086

1 mechanic at $2.50 0.0109

Supplying Coal--

3 laborers at $2 $0.0260

Blacksmith Work--

1 laborer at $2 $0.0086

1 blacksmith at $3.25 0.0141

1 waterboy at $0.75 0.0032

-------

Total per cubic yard $0.4473

Add 75% of cost of administration 0.1388

-------

Total labor per cu. yd. $0.5861

The total cost of each cubic yard of concrete in place was estimated to

be as follows:

Per cu. yd.

Ten-elevenths cu. yd. pebbles at $1.085 $0.9864

Ten-twenty seconds cu. yd. sand at $0.00 0.0000

1 26 bbls. cement at $1.77 2.2302

Labor as above given 0.5861

Cost of plant distributed over total yardage 0.8400

-------

Total $4.6427

It will be noted that the sand cost nothing as it was dredged from the

trench in which the pier was built, and paid for as dredging. The cost

of the plant is distributed over this south pier and over the proposed

north pier work on the basis of only 20 per cent. salvage value after

the completion of both piers. It is said, however, that 80 per cent. is

too high an allowance for the probable depreciation.

~DAM, RICHMOND, INDIANA.~--The dam shown in cross-section in Fig. 89 was

built at Richmond, Ind. It was 120 ft. long and was built between the

abutments of a dismantled bridge. The concrete was made in the

proportion of 1 bbl. Portland cement to 1 cu. yd. of gravel; old iron

was used for reinforcement. The foundations were put down by means of a

cofferdam which was kept dry by pumping. On completion it was found that

there was a tendency to scour in front of the apron and accordingly

piling was driven and the intervening space rip-rapped with large

stone. Labor was paid as follows per day: Foreman, $3; carpenter, $2.50;

cement finisher, $2; laborers, $1.50. The concrete was mixed by hand and

wheeled to place in wheelbarrows. The cost of the work was as follows:

Materials-- Per cu. yd.

204 bbls. cement at $1.60 $1.485

Sand and gravel 0.800

Lumber 0.610

Tools, hardware, etc. 0.445

------

Total materials $3.34

Labor--

Clearing and excavating $0.96

Setting forms and mixing concrete 1.01

Pumping 0.27

-----

Total labor $2.24

Total materials and labor $5.58

[Illustration: Fig. 89.--Concrete Dam at Richmond, Ind.]

~DAM AT ROCK ISLAND ARSENAL, ILLINOIS.~--The dam was in the shape of an L

with one side 192 ft. and the other side 208 ft. long; it consists of a

wall 30½ ft. high, 3½ ft. wide at the top and 6½ ft. wide at the bottom

with a counterfort every 16 ft., 26 in all. Each counterfort extended

back 16 ft. and was 4 ft. thick for a height of 6 ft. and then 3 ft.

thick. There were 3,500 cu. yds. of concrete in the work, which was done

by day labor under the direction of the U. S. Engineer in charge.

The forms consisted of front and back uprights of 8×10-in. stuff 24 ft.

high, connected through the wall by ¾-in. rods which were left in the

concrete. The lagging was 2×12-in. plank dressed down 1¾ ins. placed

inside the uprights. These forms were built full height in 16-ft.

sections with a counterfort coming at the center of each section. Each

section contained 95 cu. yds. of concrete and was filled in a day's

work. The concrete was a 1-4-7 mixture wet enough to quake when rammed.

Run of crusher limestone was used of which 50 per cent. passed a 1-in.

sieve, 17 per cent. a No. 3 sieve and 9 per cent. a No. 8 sieve. The

concrete was mixed in Cockburn Barrow & Machine Co.'s screw-feed mixer

which discharged into 2-in. plank skips 2 ft. wide 5-1/3 ft. long and 14

ins. deep, holding ¼ cu. yd. These skips were taken on cars to a derrick

crane overhanging the forms and by it hoisted and dumped into the forms.

The derrick was moved along a track at the foot of the wall as the work

progressed. The concrete was spread and rammed in 6-in. layers. The men

were paid $1.50 per 8-hour's work and the work cost including footing,

as follows:

Item-- Total. Per cu. yd.

Cement $1,500.00 $0.429

Sand 400.00 0.114

Storing and hauling cement 460.00 0.131

Taking sand from barge to mixer 96.00 0.027

Crushing stone 1,450.00 0.414

Mixing concrete 4,825.00 1.378

Placing concrete 1,670.00 0.477

Lumber for forms, etc. 600.00 0.171

Erecting and taking down forms 2,450.00 0.700

---------- ------

Totals $13,451.00 $3.841

~DAM AT McCALL FERRY, PA.~--The dam was 2,700 ft. long and 48 ft. high of

the cross-section shown by Fig. 90 and with its subsidiary works

required some 350,000 cu. yds. of concrete. The plant for mixing and

placing the concrete was notable chiefly for its size and cost. Parallel

to the dam, which extended straight across the river, and just below its

toe a service bridge consisting of a series of 40-ft. concrete arch

spans was built across the river. This service bridge was 50 ft. wide

and carried four standard gage railway tracks besides a traveling crane

track of 44 ft. gage. This very heavy construction of a temporary

structure was necessitated by the frequency of floods against which only

a solid bridge could stand; it was considered cheaper in the long run to

provide a bridge which would certainly last through the work than to

chance a structure of less cost which would certainly go out with the

floods. The concrete service bridge was designed to be destroyed by

blasting when the dam had been completed. The method of construction was

to build the dam in alternate 40 ft. sections, mixing the concrete on

shore, taking it out along the service bridge in buckets on cars and

handling the buckets from cars to forms by traveling cranes.

[Illustration: Fig. 90.--Steel Forms for McCall Ferry Dam.]

The concrete mixing plant is shown by Fig. 91. Cars loaded with cement,

sand and stone were brought in over the tracks carried on the wall tops

of the bins and were unloaded respectively into bins A, B and C,

of which there were eight sets. Each set supplied material by means of

measuring cars to a 1 cu. yd. Smith mixer. Two sets of cars were used

for each mixer so that one could be loading while the other was

charging. The mixers discharged into 1 cu. yd. buckets set two on a car

and eight cars were hauled to the work in train by an 18-ton "dinky." At

the work the buckets were picked up by the traveling cranes and the

concrete dumped into the forms. Figure 90 shows the construction of the

steel forms. Six sets of forms were used. Each set consisted of five

frames spaced 10 ft. apart and braced together in the planes parallel to

the dam, and each set molded 40 ft. of dam. The lagging consisted of

wooden boxes 8½ ft. wide and 10 ft. long. For the vertical face of the

dam these boxes were attached by bolts to the vertical post, for the

curved face they were bolted to a channel bent to the curve and held by

struts from the inclined post of the steel frame.

[Illustration: Fig. 91.--Concrete Mixing Plant for McCall Ferry Dam.]

In construction the footing and the body of the dam to an elevation of 5

ft. above the beginning of the curve were built continuously across the

river; above this elevation the dam was built in alternate 40-ft.

sections. The strut back to the service bridge shown in the lower right

hand corner of Fig. 90, shows the manner of bracing the first 30-ft.

section of the inclined post to hold the lagging for the continuous

portion. The lagging was added a piece at a time as concreting

progressed. The ends of each set of frames for a 40-ft. section were for

the isolated sections closed by timber bulkheads carrying box forms to

mold grooves into which the concrete of the intermediate sections would

bond.

[Illustration: Fig. 92.--Traveler for Concreting Dam, Chaudiere Falls,

Quebec.]

The concrete used was a 1-3-5 mixture, the stone ranging in size from 2

to 5 ins. Rubble stone from one man size to ½ ton were bedded in the

concrete. The capacity of the concrete plant was 2,000 cu. yds. per day

or about 250 cu. yds. per mixer per 10-hour day.

~DAM, CHAUDIERE FALLS, QUEBEC.~--The dam was 800 ft. long and from 16 to

20 ft. high, constructed of 1-2-4 concrete with rubble stone embedded.

The rubble stones were separated at least 9 ins. horizontally and 12

ins. vertically and were kept 20 ins. from faces. At one point the

rubble amounted to 40 per cent. of the volume, but the average for the

dam was 25 to 30 per cent. The stone was broken at the work, some by

hand, but most by machine, all to pass a 2-in. ring. Hand-broken stone

ran very uniform in size and high in voids, often up to 50 per cent.

Stone broken by crusher with jaws 2 ins. apart would run 20 to 30 per

cent. over 2 ins. in size and give about 45 per cent. voids; with

crusher jaws 1½ ins. apart from 98 to 100 per cent. was under 2 ins. in

size and contained about 42 per cent. of voids. It was found that if the

crushers were kept full all the time the product was much smaller,

particularly with Gates gyratory crusher, though a little more than

rated power was required when the crusher was thus kept full. This

practice secured increased economy in both quantity and quality of

product. The concrete was made and placed by means of a movable traveler

shown by Fig. 92. Concrete materials were supplied to the charging

platform of the traveler by means of a traveling derrick moving on a

parallel track. In placing the concrete on the rock bottom it was found

necessary in order to secure good bond to scrub the rock with water and

brooms and cover it with a bed of 2 ins. of 1-2 mortar. The method of

concreting in freezing weather is described in Chapter VII.

CHAPTER XII.

METHODS AND COST OF CONSTRUCTING BRIDGE PIERS AND ABUTMENTS.

The construction of piers and abutments for bridges is best explained by

describing individual examples of such work. So far, in America, bridge

piers have been nearly always of plain concrete and of form and section

differing little from masonry piers; where reinforcement has been used

at all it has consisted of a surface network of bars introduced chiefly

to ensure monolithic action of the pier under lateral stresses. In

Europe cellular piers of reinforced concrete have been much used. Plain

concrete abutments differ little in form and volume from masonry

abutments. Reinforced concrete abutments are usually of L-section with

counterforts bracing the upright slab and bridge seat to the base slab.

Form work for reinforced abutments is somewhat complex; that for plain

abutments and piers is of simple character, the only variations from

plain stud and sheathing construction being in the forms for moldings

and coping and for cut-waters. For piers of moderate height the form is

commonly framed complete for the whole pier, but for high piers it is

built up as the work progresses by removing the bottom boards and

placing them at the top. Opposite forms are held together by wire ties

through the concrete. Movable panel forms have been successfully

employed, but they rarely cheapen the cost much. Sectional forms, which

can be shifted from pier to pier where a number of piers of identical

size are to be built, may frequently be used to advantage. An example of

such use is given in this chapter.

Derricks are the recognized appliances for hoisting and placing the

concrete in pier work; they are the only practicable appliance where the

pier is high and particularly where it stands in water and mixing barges

are employed. For abutment work and land piers of moderate height

derricks and wheelbarrow or cart inclines are both available and where

much shifting of the derricks is involved the apparently more crude

method compares favorably in cost.

The methods of placing concrete under water for pier foundations are

described in Chapter V, and the use of rubble concrete for pier

construction is illustrated by several examples in Chapter VI. The

following examples of pier and abutment construction cover both large

and small work and give a clear idea of current practice.

[Illustration: Fig. 93.--Pier and Cofferdam for a Railway Bridge.]

~COST OF CONSTRUCTING RECTANGULAR PIER FOR A RAILWAY BRIDGE.~--This pier,

Fig. 93, was built in water averaging 5 ft. deep. The cofferdam

consisted of triple-lap sheet piling, of the Wakefield pattern, the

planks being 2 ins. thick, and spiked together so as to give a cofferdam

wall 6 ins thick. The cofferdam enclosed an area 14×20 ft., giving a

clearance of 1 ft. all around the base of the concrete pier, and a

clearance of 2 ft. between the cofferdam and the outer edge of the

nearest pile. The cofferdam sheet piles were 18 ft. long, driven 11 ft.

deep into sand, and projecting 2 ft. above the surface of the water.

The concrete base resting on the foundation piles was 12×18 ft. The

concrete pier resting on this base was 7×13 ft. at the bottom, and 5×11

ft. at the top. The pier supported deck plate girders. There were 100

cu. yds. of concrete in the pier and base.

The cost of this pier, which is typical of a large class of concrete

pier work, has been obtained in such detail that we analyze it in

detail, giving the costs of cofferdam construction and excavation as

well as of mixing and placing the concrete.

Setting up and taking down derrick and platform:

4 days foreman at $5.00 $ 20.00

¾ days engineman at $3.00 2.25

¾ days blacksmith at $3.00 2.25

¾ days blacksmith helper at $2.00 1.50

22 days laborers at $2.00 44.00

-------

Total $ 70.00

Cofferdam--

7 days foreman at $5.00 $ 35.00

4 days engineman at $3.00 12.00

38 days laborers at $2.00 76.00

1 ton coal at $3.00 3.00

-------

Total labor on 7,900 ft. B. M. at $16.00 $126.00

7,900 ft. B. M. at $20.00 158.00

-------

Total for 58 cu. yds. excavation $284.00

Wet Excavation--

1.8 days foreman at $5.00 $ 9.00

1.5 days engineman at $3.00 4.50

9 days laborers at $2.00 18.00

½ ton coal at $3.00 1.50

-------

Total labor on 58 cu. yds. at 57c. $ 33.00

Foundation Piles--

960 lin. ft. at 10c $ 96.00

4 days setting up driver and driving 24 piles at $20 per

day for labor and fuel 80.00

-------

Total $176.00

Concrete--

100 cu yds. stone at $1.00 $100.00

40 cu. yds. sand at $0.50 20.00

100 bbls. cement at $2.00 200.00

5 days foreman at $5.00 25.00

50 days laborers at $2.00 100.00

5 days engineman at $3.00 15.00

2 tons coal at $3.00 6.00

-------

Total, 100 cu. yds. at $4.66 $466.00

8 days carpenters at $3.00 24.00

2,400 ft. B. M. 2-in. plank at $25.00 60.00

1,000 ft. B. M. 4×6-in. studs at $20.00 20.00

Nails, wire, etc 2.00

-------

Total forms for 100 cu. yds. at $1.06 $106.00

Summary--

Setting up derrick, etc. $ 70.00

Cofferdam (7,900 ft. B. M.) 284.00

Wet excavation (58 cu. yds.) 33.00

Foundation piles (24) 176.00

Concrete (100 cu. yds.) 466.00

Forms (3,400 ft. B. M.) 106.00

---------

Total $1,135.00

Transporting plant 20.00

20 days rental of plant at $5.00 100.00

---------

Total cost of pier $1,252.00

Regarding the item of plant rental, it should be said that the plant

consisted of a pile driver, a derrick, a hoisting engine, and sundry

timbers for platforms. There was no concrete mixer. Hence an allowance

$5 per day for use of plant is sufficient.

It will be noted that no salvage has been allowed on the lumber for

forms. As a matter of fact, all this lumber was recovered, and was used

again in similar work.

Referring to the cost of cofferdam work, we see that, in order to

excavate the 58 cu. yds. inside the cofferdam, it was necessary to spend

$284, or nearly $5 per cu. yd. before the actual excavation was begun.

The work of excavating cost only 57 cts. per cu. yd., but this does not

include the cost of erecting the derrick which was used in raising the

loaded buckets of earth, as well as in subsequently placing the

concrete. The sheet piles were not pulled, in this instance, but a

contractor who understands the art of pile pulling would certainly not

leave the piles in the ground. A hand pump served to keep the cofferdam

dry enough for excavating; but in more open material a power pump is

usually required.

The above costs are the actual costs, and do not include the

contractor's profits. His bid on the work was as follows:

Piles delivered 12 cts. per ft.

Piles driven $5 each

Cofferdam $37 per M.

Wet excavation $1.00 per cu. yd.

Concrete $8.00 per cu. yd.

In order to ascertain whether or not these prices yielded a fair profit,

it is necessary to distribute the cost of the plant transportation and

rental over the various items. We have allowed $120 for plant

transportation and rental, and $70 for setting up and taking down the

plant, or $190 in all. The working time of the plant was as follows:

Per cent. Prorated

Days. of time. plant cost.

Cofferdam 7 39 $74

Excavation 2 11 21

Foundation piles 4 22 42

Concrete 5 28 53

-- --- ----

Totals 18 100 $190

As above given, the labor on the 7,900 ft. B. M. in the cofferdam cost

$126, or $16 per M.; but this additional $74 of prorated plant costs,

adds another $9 per M., bringing the total labor and plant to $25 per

M., to which must be added the $20 per M. paid for the timber in the

cofferdam, making a grand total of $45 per M. This shows that the

contractor's bid of $37 per M. was much too low.

The labor on the excavation cost 57 cts. per cu. yd., to which must be

added the prorated plant cost of $21 distributed over the 58 cu. yds.,

or 36 cts. per cu. yd., making a total of 93 cts. per cu. yd. This shows

that the bid of $1 per cu. yd. was hardly high enough.

The labor on the 24 foundation piles cost $80, or $3.33 each. The

prorated plant cost is $42, or $1.75 per pile, which, added to $3.33,

makes a total of $5.08. This shows that the bid of $5 Per pile for

driving was too low. However there was a profit of 2 cts. per ft., or 80

cts. per pile, on the cost of piles delivered.

The concrete amounted to 100 cu. yds. Hence the prorated plant cost of

$53 is equivalent to 53 cts. per cu. yd. Hence the total cost of the

concrete was:

Per cu. yd.

Cement, sand and stone $3.20

Foreman (at $5) 0.25

Labor (at $2) 1.00

Engineman (at $3) 0.15

Coal (at $3) 0.06

Carpenters (at $3) 0.24

Forms (at $23.50, used once) 0.80

Wire, nails, etc 0.02

Prorated plant cost 0.53

-----

Total $6.25

Since the contract price for concrete was $8 per cu. yd., there was a

good profit in this item.

~BACKING FOR BRIDGE PIERS AND ABUTMENTS.~--Six piers and two abutments of

the City Island bridge were constructed in 1906 at New York city, of

masonry backed with 1-2-4 concrete below and 1-3-5 concrete above high

water. The piers and abutments were all sunk to rock or hard material by

means of timber cofferdams. Table XVI gives the labor cost of mixing and

placing the concrete backing for one abutment and three piers, after the

materials were delivered on the scows. The concrete was mixed by a

rectangular horizontal machine mixer and deposited by 2-cu. yd. bottom

dump buckets handled by derrick scows and stiff leg derricks. The high

cost of concreting on Pier 2 was due to the fact that the concrete was

improperly deposited and had to be removed and the higher cost in

Abutment 1 was probably due to the fact that the abutment was so long

and narrow that it was difficult to handle the bucket.

TABLE XVI.--COST OF CONCRETE BACKING FOR MASONRY PIERS.

[Transcriber's note: Table split to be less than 80 column width]

Abutment No. 1. Pier No. 2.

Wages Cost Cost

per No. Total per No. Total per

Hour. hrs. Cost. cu. yd. hrs. Cost. cu. yd.

Superintendent 70 24 $16.80 $0.03 47 $32.90 $0.09

Foreman 35 160 56.00 0.09 128 44.80 0.13

Laborers 15-20 2555 383.25 0.65 2038 313.60 0.92

Engineman 30 365 109.50 0.19 196 58.50 0.19

Timekeeper 40 86 34.40 0.06 46 18.40 0.06

Pier No. 3. Pier No. 4.

Wages Cost Cost

per No. Total per No. Total per

Hour. hrs. Cost. cu. yd. hrs Cost. cu. yd.

Superintendent 70 72 $50.40 $0.05 16 $11.20 $0.03

Foreman 35 324 113.40 0.12 54 18.90 0.06

Laborers 15-20 3513 526.95 0.56 940 141.00 0.44

Engineman 30 244 73.20 0.08 60 18.00 0.06

Timekeeper 40 81 32.40 0.04 10 4.00 0.01

Summary.

Wages Total Total Av.

Hrs. cost. per cu. yd.

Superintendent 70 159 $111.30 $0.05

Foreman 35 666 233.10 0.11

Laborers 15-20 9046 1364.90 0.62

Engineman 30 865 259.50 0.12

Timekeeper 40 223 89.20 0.04

~PNEUMATIC CAISSONS, WILLIAMSBURG BRIDGE.~--Mr. Francis L. Pruyn, Assoc.

M. Am. Soc. C. E., gives the following costs of concreting the pneumatic

caissons for the Brooklyn tower of the Williamsburg bridge at New York

city. The work comprised the mixing and placing of some 13,637 cu. yds.

of concrete in two caissons. Table XVII shows the itemized costs for one

caisson and Table XVIII shows them for the other caisson. The methods of

work were as follows:

After each caisson was built it was towed to its proper site, where it

was held in place by temporary pile dock built completely around it. On

these docks the concrete was placed; a 2 cu. yd. cubical mixer of the

usual pattern being used for mixing. The concrete materials, consisting

of sand, stone and cement was handled direct from barges alongside, into

the mixer. The concrete was placed by a derrick located in the center of

the caisson, which was a bad feature as the caisson was usually out of

level and considerable difficulty was experienced in swinging the

derrick. On the South caisson ¾ cu. yd. bottom dump buckets were used in

placing the concrete, on the North caisson the size of these was

increased to 1½ cu. yd. which reduced the cost of placing 15 cts. per

cu. yd. There were placed in the South caisson 3,827 cu. yds. in 32 days

of actual working time--120 cu. yds. per day of 10 hrs. The gross time

was 2 months. On the North caisson 5,693 cu. yds. were placed in 46 days

worked--124 cu. yds. per day. The gross time was 4 months.

The rates of labor were as follows per 10-hour day:

Foreman $5.00

Assistant foreman 2.50

Hoisters 2.50

Fireman 1.60

Laborer 1.50

Proportions concrete were 1: 2.5: 6.

The low price of sand in the North caisson was brought about by the

finding of good building sand in the excavation for the anchorage, which

work was done by the same contractor.

When the caissons had been sealed the iron material shafts were removed.

This left holes 5 ft.×6 ft. extending from the roof of the caisson up

to Mean H.W. which were filled with concrete. These shaft holes were 80

ft. deep on the South caisson and 100 ft. deep on the North caisson.

They were partially filled with water and the concrete had to be placed

with considerable care. Wooden chutes were used on the South caisson;

they rested on the caisson roof, were filled with concrete and then

raised allowing concrete to flow out at the bottom. The shaft holes were

too deep on the North caisson for chutes and 20 cu. ft. bottom dump

buckets were used. They had to be lowered to bottom of shaft each trip

before dumping, a slow operation, which greatly added to the cost.

Proportion for concrete 1-2.5-6.

The proportion for concrete in working chamber was the same as for all

other concrete. The specifications called for 6 in. of mortar, of 1 part

of cement to 2½ parts of sand, between the concrete and all bearing

areas; that is, under the cutting edge and directly under the roof of

the working chamber. The concrete was mixed in the cubical mixer and

dumped on the bottom door of the material lock, the top door of the lock

was then closed, the bottom door opened and the concrete fell through

the shaft to the working chamber. It was then shoveled by the sand hogs

into place. A 6-in. space was left below all bearing surfaces into which

damp mortar was tightly rammed. Concreting the South caisson took 10¼

working days of 24 hours, the gangs working night and day in twelve

2-hour shifts; 1,566 cu. yds. of concrete and mortar were placed, or at

the rate of 140 cu. yds. per 24 hours. The gross time including Sundays

was 14½ days. The sand hogs worked in shifts of 2 hours each and

received $3.50 for the two hours work. The twelve foremen received 1

dollar more: the average gang consisted of 12 sand hogs.

On the North caisson the organization was much better, owing to the

experience gained on the first caisson; and in spite of the fact that

the sand hogs, on account of the increased depth, received $4.00 for 1½

hours' work, or an increase of $22.00 per man per 24 hrs. over that on

the South caisson, the work was done for less money. There were placed

1,566 cu. yds. of concrete in 7 working days of 24 hrs., or at the rate

of 224 cu. yds. per day. The gross time was 11½ days including Sundays.

The average number of men in the sand hog gangs was 18, with one

foreman, who received $5 for 1½ hours work.

TABLE XVII.--ITEMIZED COST OF CONCRETING SOUTH CAISSON FOR BROOKLYN

TOWER OF THE WILLIAMSBURG BRIDGE: COST OF CONCRETING CAISSONS ABOVE

ROOF.

South Caisson (3,827 cu. yds.).

Materials. Quantity. Rate. Amount.

Cement 4,480 bbls. $1.57 $7,034.00

Sand 1,288 cu. yds. .60 773.00

Broken stone 3,421 cu. yds. 1.50 5,132.00

Water 36.00

------- ------ ---------

Total 3,827 cu. yds. $3.39 $12,975.00

Labor.

Mixing and placing 3,827 cu. yds. $0.90 $3,432.00

Plant charges 2,280.00

Plant labor 742.00

------- ------ ---------

Total plant 3,827 cu. yds. $0.79 $3,022.00

------- ------ ---------

Total cost 3,827 cu. yds. $5.08 $19,429.00

General expenses, 10% 3,827 cu. yds. .51 1,943.00

------- ------ ---------

Grand total 3,827 cu. yds. $5.59 $21,372.00

COST OF CONCRETING SHAFTS.

South Caisson.

Materials. Quantity. Rate. Amount.

Concrete 612½ bbls. $1.57 $962.00

Sand 193 cu. yds. .40 77.00

Stone 493 cu. yds. 1.10 542.00

------- ------ ---------

Total 541 cu. yds. $2.92 $1,581.00

Labor.

Handling, mixing and placing 541 cu. yds. $0.96 $519.00

Plant charges, etc. 541 cu. yds. 1.06 576.00

------- ------ ---------

Total 541 cu. yds. $4.94 $2,676.00

General expenses, 10% 541 cu. yds. .49 267.00

------- ------ ---------

Grand total 541 cu. yds. $5.43 $2,943.00

COST OF CONCRETE IN WORKING CHAMBERS.

South Caisson. (1,435 cu. yds.)

Materials. Quantity. Rate. Amount.

Cement for concrete 1,666 bbls. $1.57 $2,615.00

Cement for mortar 459 bbls. 1.57 720.00

Sand for both 670 cu. yds. .40 268.00

Broken stone 1,181 cu. yds. 1.10 1,299.00

------- ------ ---------

Total materials 1,435 cu. yds. $3.42 $4,902.00

Labor.

Top labor, mixing and placing 1,435 cu. yds. $1.09 $1,575.00

Pneumatic labor 1,435 cu. yds. 4.93 7,117.00

Compressor house labor 1,435 cu. yds. .19 275.00

------- ------ ---------

Total labor 1,435 cu. yds. $6.21 $8,967.00

Plant.

Coal at $2.40 per ton 1,435 cu. yds. .10 140.00

Concrete plant 1,435 cu. yds. .79 1,145.00

Pneumatic plant 1.435 cu. yds. 1.05 1,522.00

-------- ------ ---------

Total plant 1,435 cu. yds. $1.94 $2,807.00

Totals 1,435 cu. yds. $11.57 $16,676.00

General expenses, 10% 1,435 cu. yds. 1.16 1,667.00

-------- ------- ----------

Grand total 1,435 cu. yds. $12.73 $18,343.00

TABLE XVIII.--ITEMIZED COST OF CONCRETING NORTH CAISSON FOR BROOKLYN

TOWER OF THE WILLIAMSBURG BRIDGE:

COST OF CONCRETING CAISSON ABOVE ROOF (5,692 cu. yds.)

Materials. Quantity. Rate. Amount.

Cement 6,707½ bbls. $1.57 $10,531.00

Sand 2,133 cu. yds. .40 845.00

Broken stone 4,938 cu. yds. 1.10 5,432.00

Water 51.00

------- ------ ---------

Total 5,692 cu. yds. $2.96 $16,859.00

Labor.

Mixing and placing 5,692 cu. yds. $0.73 $4,159.00

Plant charges 2,952.00

Plant labor 517.00

------- ------ ---------

Total 5,692 cu. yds. $0.61 $3,469.00

Total cost 5,692 cu. yds. $4.30 $24,487.00

General expenses, 10% 5,692 cu. yds. .43 2,448.00

Grand total 5,692 cu. yds. $4.73 $26,935.00

COST OF CONCRETING SHAFTS.

Materials. Quantity. Rate. Amount.

Cement 614½ bbls. $1.57 $965.00

Sand 204 cu. yds. .40 82.00

Stone 521 cu. yds. 1.10 574.00

------- ------ ---------

Total 576 cu. yds. $2.82 $1,621.00

Labor.

Mixing and placing 576 cu. yds. 1.70 982.00

Plant charges, etc. 576 cu. yds. 1.36 795.00

------- ------ ---------

Total 576 cu. yds. $5.88 $3,398.00

General expenses, 10% 576 cu. yds. .59 339.00

------- ------ ---------

Grand total 576 cu. yds. $6.47 $3,737.00

COST OF CONCRETING WORKING CHAMBERS (1,566 cu. yds.).

Materials. Quantity. Rate. Amount.

Cement for concrete 1,559 bbls. $1.51 $2,446.00

Cement for mortar 442 bbls. 1.51 $694.00

Sand for both 630 cu. yds. .40 252.00

Broken stone 1,380 cu. yds. 1.10 1,518.00

------- ------ ---------

Total 1.566 cu. yds. $3.14 $4,910.00

Labor.

Top labor, mixing and placing 1,566 cu. yds. $0.78 $1,198.00

Pneumatic labor 1,566 cu. yds. 4.91 7,694.00

Compressor house labor 1,566 cu. yds. .11 180.00

------- ------ ---------

Total labor 1,566 cu. yds. $5.80 $9,072.00

Plant.

Coal at $2.40 per ton 1,566 cu. yds. .06 87.00

Concrete plant 1,566 cu. yds. .86 1,352.00

Pneumatic plant 1,566 cu. yds. .81 1,272.00

------- ------ ---------

Total plant 1,566 cu. yds. $1.73 $2,711.00

------- ------ ---------

Totals 1,566 cu. yds. $10.67 $16,693.00

------- ------ ---------

General expenses, 10% 1,566 cu. yds. 1.06 1,669.00

------- ------ ---------

Grand total 1,566 cu. yds. $11.73 $18,362.00

~COST OF FILLING PIER CYLINDERS.~--The following costs were obtained in

mixing and placing concrete in steel cylinder piers. The sand and gravel

were wheeled 100 ft. to the mixing board at the foot of the cylinder,

mixed and shoveled into wooden skips, hoisted 20 ft. by horsepower and

dumped into the cylinder. The foreman worked on the mixing board and the

men worked with great energy. The costs were as follows:

Item-- Per day. Per cu. yd.

6 men wheeling materials and mixing at 15

cts. per hour 9.00 $0.45

2 men dumping skips and ramming at 15 cts.

per hour 3.00 0.15

1 team and driver at 40 cts. per hour 4.00 0.20

1 foreman at 30 cts. per hour 3.00 0.15

----- ----

Totals $19.00 $0.95

~PIERS, CALF KILLER RIVER BRIDGE.~--The following methods and costs of

building two new piers and extending three old piers with concrete are

given by Mr. J. Guy Huff. The work was done by the railway company's

masonry gangs. Figure 94 shows the arrangement of the several piers and

the character of the work on each and Fig. 95 gives the detail

dimensions of the three main piers.

The sand and aggregate, consisting of blast furnace slag, were unloaded

from cars to platforms on a level with the top of rail, placed about 100

ft. south from the south end of the bridge. A cubical 1/6 cu. yd. mixer

was used. This was operated by a gasoline engine, and was located on a

platform about 50 ft. south of the south end pier. A tank near the mixer

to supply water was elevated enough to get the desired head, and was

kept filled by a pump run by another gasoline engine located down by the

river bank. The cement house was located between the mixer platform and

slag pile.

[Illustration: Fig. 94.--Diagram Arrangement of Piers, Calf Killer River

Bridge.]

[Illustration: Fig. 95.--Details of Pier for Calf Killer Elver Bridge.]

Slag and sand were delivered to the mixer by means of wheelbarrows. The

mixer was so placed that it would dump onto a platform, and the concrete

could then be shoveled into a specially designed narrow-gage car. This

car ran on one rail of the main track and an extra rail outside. A

turnout for clearing passing trains was provided at both ends of the

bridge. The track over the bridge from the mixer had a descending grade

of about 1 per cent., so that with a little start the concrete car would

roll alone down to the required points on the bridge. Only in returning

the empty cars to the mixer was it necessary to push them by hand, and

then only for a distance of never more than 400 ft.

Over the piers on the bridge in the center of the concrete car track

openings were sawed to let the concrete pass to the forms below. To get

the concrete into the forms, there were used zig-zag chutes with arms

about 10 ft. long, which sections were removed as the concrete in the

forms was increased. These chutes were a convenience by their ends

alternating from one side to the other as the arms were removed in

coming up.

The cost of the concrete work was as follows:

Unloading Material.

Rate Total days Per cu. yd.

per day. worked. Total. concrete.

Foreman $3.40 5 $17.00 $0.04

11 laborers 1.36-8/10 52 71.14 .15

-----

Total for unloading material $0.19

Building Forms, Bins, Etc.

Foreman $3.40 18 $61.20 $0.14

9 carpenters 2.25 166 373.50 .81

New lumber, 23.7 M. ft.

at $17.80 421.86 .92

Old lumber, 6 M. ft. at

$8.33 49.98 .11

-----

Total for building forms, bins, etc. $1.98

Cofferdam Excavation (45 cu. yds.)

Foreman $3.40 8 $27.20 $0.06

9 laborers 1.15 6/10 74½ 86.12 .19

-----

Total for cofferdam excavation $0.25

Cofferdam Concrete (37 cu. yds.)

Foreman $3.40 8 $27.20 $0.06

11 laborers 1.36 3/10 79 107.68 .23

Cofferdam lumber, 2.25

M. ft. at $20.00 45.00 .09

----

Total for cofferdam concrete $0.38

Concrete Mixing and Placing.

Foreman $3.40 30 $102.00 $0.22

9 laborers 1.15 6/10 282 325.99 .71

Cement, 452 bbls. at

$1.55 701.00 1.52

Slag, 437 cu. yds. at $0.20 87.40 .19

Sand, 220 cu. yds. at

$0.30 66.00 .14

-----

Total for mixing and placing $2.78

Taking Down Forms and Clearing Up.

Foreman $3.40 13 $44.20 $0.09

11 laborers 1.17 1.43 107.31 .36

-----

Total for taking down forms, etc. $200.00 $0.45

Engineering and supervision .43

-----

Grand total, 460 cu. yds. concrete $6.46

The wages given are the average wages. The men worked a 10-hour day. The

concrete was a 1-3-6 mixture. The cofferdam work was done in connection

with the construction of the fourth pier, this pier being the only one

coming in the bed of the river to be built entirely new. The work on

this was started in water about 6 ft. deep. The 37 cu. yds. of concrete

is included in the total of 460 cu. yds. in the above tabulation. By

itself the cost of the cofferdam work, not including cost of cement,

sand and slag was as follows:

Per cu. yd.

Total. Concrete.

Lumber $ 45.00 $1.21

Labor, excavating 113.32 3.06

Labor, concrete 134.88 3.64

-----

Total 37 cu. yds. concrete $7.91

[Illustration: Fig. 96.--Details of Piers for K. C., M. & O. Ry.

Bridge.]

~METHOD AND COST OF CONSTRUCTING 21 BRIDGE PIERS.~--The following account

of the methods and cost of constructing 21 concrete piers for a railway

bridge consisting of 20 50-ft. plate girder spans has been compiled from

records kept by Mr. W. W. Colpitts, Assistant Chief Engineer, Kansas

City, Mexico & Orient Ry. The shape and dimensions of the piers are

shown by Fig. 96 and Fig. 97 shows the construction of the forms. Sheet

pile cofferdams to solid rock were used for constructing the

foundations.

[Illustration: Fig. 97.--Forms for Piers for K. C., M. & O. Ry. Bridge.]

The 1-3-5 concrete was mixed in a Smith mixer having a batch capacity of

9 cu. ft. The mixer was located on the slope of the embankment

approach, with the main track at its rear and facing a temporary

material track. This temporary track turned out from the main track

about 500 ft. beyond the mixer and extended diagonally down the

embankment approach on a 3 per cent. grade and across the river bottom

alongside the pier sites. The portion of the track in the river bottom

was supported on bents of spliced ties, jetted to the rock, and wired to

the cofferdam to avoid the danger of loss in case of high water. The

sand and crushed rock were delivered by cars from the main line track,

immediately above the mixer, and the cement was stored in a shanty at

one side of the mixer. The concrete materials and machinery were, in

this manner, very conveniently located for rapid work and well above the

high water line. The concrete was transported to the pier sites in

improvised dump boxes, set on push cars. These dump boxes were hinged

longitudinally and discharged directly into the cofferdams. The grade of

the temporary track carried the push cars by gravity to the cofferdams

and they were returned by teams, for which purpose a straw and brush

road had been built paralleling the track. As the work progressed

farther into the stream, more cars were added properly to balance the

work. While the concrete in the base was still fresh, a number of steel

reinforcing bars, 8 ft. in length, were set in place along each end to

insure a good bond between the base and shaft.

In general, the work of putting in the bases was organized so that about

the same time was required in filling a cofferdam with concrete, in

excavating the sand from the next, and in driving the sheet piling for

the third. These three operations were thus carried on simultaneously

and, although interruptions in one part of the work or the other

occurred frequently, the gangs were interchangeable and no appreciable

loss was suffered, except in time, because of such delays.

In piers 19 and 20, where the rock was from 17 to 19 ft. below the

surface, some difficulty was encountered due to the presence of fissures

in the rock, from which it was necessary to remove the sand to fill with

concrete. In such cases, the larger leaks were stopped as much as

possible by driving sheet piles against the outside face of the

cofferdam and into the fissures, and the smaller leaks by manure in

canvas bags rammed into the openings.

Upon the completion of all the bases, the forms for several shafts were

set in position and the work of filling with concrete proceeded as in

the case of the bases, except that a derrick erected on a flat car and

stationed at the pier was utilized to raise the dump boxes in depositing

the concrete in the forms. As soon as the concrete in one shaft had set

sufficiently to permit of it, the forms were removed and placed on the

pier ahead. Four sets of forms were used for the shafts.

The following are the average prices paid for materials and labor:

Materials.--Lumber for forms, etc., $16.50 per M. ft., B. M.; cement,

Kansas Portland, $1.50 per bbl.; broken limestone, 45c per cu. yd.;

sand, Arkansas River, 15c per ton.

Labor.--General foreman, $110 per month; assistant foreman, $75 per

month; timekeeper, $60 per month; riveters, 35c per hour; blacksmith,

30c per hour; blacksmith assistant, 20c per hour; carpenters, 22½c and

25c per hour; enginemen, 25c per hour; firemen, 20c per hour; night

watchman, 20c per hour; laborers, 17½c and 20c per hour; team (including

driver), 40c per hour. The prices quoted for lumber, cement, limestone

and sand are prices f. o. b., Louisiana, Iola, Kan., El Dorado, Kan.,

and Wichita, Kan.

The total and unit cost of constructing the concrete piers and abutments

and of erecting the steel superstructure are given in the following

tabulation. Altogether there was about 2,300 cu. yds. of concrete in the

substructure, most of which, as stated above, was a 1-3-5 mixture.

Machinery and Supplies.

Concrete mixer, 20% of cost $ 152.10

Supplies, freight, hauling, setting up 505.04

--------

Total $ 657.14

Centrifugal sand pump, 20% of cost $ 27.00

Supplies, freight, hauling, setting up 277.50

Rent of traction engine to operate 83.25

--------

Total $ 387.75

Water pump and pipe, 20% of cost $ 29.00

Supplies, freight, hauling, setting up 177.32

--------

Total $ 206.32

Pile driver engine, 20% of cost $ 100.00

Supplies, freight, hauling, setting up 243.65

--------

Total $ 343.65

--------

Grand total $1,594.86

Cofferdams.

Materials, lumber and nails $1,285.26

Freight and train haul 306.33

Labor making piles 696.82

Labor driving piles 1,384.05

---------

Total $3,672.46

The sheet piling took 63,500 ft. B. M. of lumber; the cost per 1,000 ft.

B. M. for the sheet piling was then:

Materials, lumber and nails $ 20.08

Freight and haulage 4.82

Labor making piles 10.97

Labor driving piles 21.80

--------

Total $ 57.67

Forms, Platforms and Runways.

Lumber, hardware, etc. $ 224.59

Freight and train haul. 40.20

Labor making, removing and placing. 556.51

---------

Total $ 821.30

Concrete Materials.

Cement, freight, unloading and storing. $4,617.48

Sand, freight, unloading, etc. 1,336.05

Broken stone, freight, unloading, etc. 2,026.92

---------

Total $7,980.45

This gives us for 2,300 cu. yds. of concrete a cost of $3.47 per cu. yd.

for materials, including freight, storage, and unloading charges of all

kinds. A line on the proportion of the cost contributed by these latter

items may be got by taking the prices of the materials f. o. b. at the

places of production and assuming the proportions for a 1-3-5 concrete.

According to tables in Chapter II, a 1-3-5 broken stone concrete

requires per cubic yard 1.13 bbls. cement, 0.48 cu. yd. sand and 0.80

cu. yd. broken stone. We have then:

1.13 bbls. cement, at $1.50 $1.69

0.48 cu. yd. sand, at 20c .10

0.80 cu. yd. stone, at 45c .36

-----

Total $2.15

This leaves a charge of $1.32 per cubic yard of concrete for freight and

handling materials. The cost of mixing concrete and placing it in the

forms was $3,490.87, or $1.52 per cu. yd. We have then:

Cost of concrete materials per cu. yd. $3.47

Cost of mixing and placing concrete. 1.52

-----

Total. $4.99

The miscellaneous expenses of the work comprised:

Watchman, tools, telephone, etc. $ 722.48

Shanties, furnishings, supplies, etc. 829.04

---------

Total. $1,551.52

To this has to be added $1,134.28, the cost of excavating the

cofferdams. The total and unit costs of the different items of the

concrete substructure work can now be summarized as follows:

Item. Total. Per cu. yd.

Machinery and supplies 1,594.86 $ .69

Cofferdams 3,672.49 1.60

Forms, etc 821.30 .36

Concrete materials 7,980.45 3.47

Mixing and placing concrete 3,490.87 1.53

Excavating cofferdams 1,134.28 .49

Miscellaneous 1,551.52 .67

---------- -----

Total $20,245.74 $8.81

~COST OF PERMANENT WAY STRUCTURES KANSAS CITY OUTER BELT & ELECTRIC

RY.~--The following cost of concrete work including retaining walls,

abutments and box culverts, for the permanent way of the Kansas City

Outer Belt & Electric Ry., is given by Mr. W. W. Colpitts. These figures

are of particular interest, for the variation in prices of materials

during the two-year period while work was in progress and as giving the

average cost of the work on the whole line as well as for individual

structures. The culverts were all box culverts with wing walls and the

abutments were for girder bridges. Walls and abutments were of L section

with triangular or trapezoidal counterforts at the back between base

slab and coping. The form work was thus rather complex.

All work was reinforced concrete, and was done by contract under the

following conditions: The work of preparing foundations, including

excavation, pile driving, diversions of streams, etc., was done by the

railroad company, which also bore one-half the cost of keeping

foundations dry while forms were being built and concrete placed. The

railroad company also furnished the reinforcing bars at the site of each

opening. The concrete work was let at $9 per cu. yd., which figure

covered all the labor and materials necessary to complete the work,

other than the exceptions mentioned. The concrete proportions were

1-3-5. The cement used was Iola Portland and Atlas Portland. The sand

was obtained from the bed of the Kansas River in Kansas City. The rock

used was crushed limestone, passing a 2-in. ring and freed from dust by

screening. Corrugated reinforcing bars, having an elastic limit of from

50,000 to 60,000 lbs. per sq. in., manufactured by the Expanded Metal &

Corrugated Bar Co. of St. Louis, Mo., were used exclusively. The

concrete in the smaller structures was mixed by hand, in the larger by a

No. 1 Smith mixer. In the first structures built 2-in. form lumber was

used, with 2 by 6-in. studs placed 3 ft. on centers. This was abandoned

later for 1-in. lumber with 2 by 6-in. studs, 12 ins. on centers, and

was found to be more satisfactory in producing a better face. The

structures were built in the period from April, 1905, to May, 1907.

The cost of materials and the wages paid labor were as follows:

Cement--

Per barrel at structure, April, 1905 $1.25

Per barrel at structure, April, 1907 1.92

Average cost per barrel at mill 1.42

Freight per barrel 0.21

Hauling 1½ miles and storage 0.12

Average cost at structure 1.75

Average cost per cu. yd. concrete (1.1 bbls.) 1.93

Sand--

Per cu. yd. at structure, April, 1905 $0.625

Per cu. yd. at structure, April, 1907 0.75

Average cost per cu. yd., river bank 0.30

Freight per cu. yd 0.22

Hauling 1½ miles 0.20

Average cost at structure 0.72

Average cost per cu. yd. concrete (½ cu. yd.) 0.36

Stone--

Per cu. yd. at structure, April, 1905 $1.10

Per cu. yd. at structure, April, 1907 1.75

Average cost per cu. yd. at crusher 0.65

Hauling 4 miles 0.84

Average cost at structure 1.49

Average cost per cu. yd. concrete (0.9 cu. yd.) 1.34

Lumber--

Per M. ft. at structure, April, 1905 $15.00

Per M. ft. at structure, April, 1907 22.50

Average cost per M. at structure 19.00

Average cost per cu. yd. concrete 0.49

Labor-- Max. Min.

Common labor, cts. per hour 20 17

Carpenters, cts. per hour 40 30

With these prices and wages the average cost of concrete work for the

whole line was:

Item. Per cu. yd.

Form building and removing $1.98

Mixing and placing concrete 0.74

Placing reinforcement 0.10

Wire, nails, water, etc. 0.20

1.1 bbls. cement at $1.75 1.93

½ cu. yd. sand at $0.72 0.36

0.9 cu. yd. stone at $1.49 1.34

Lumber for forms 0.49

------

Total $7.14

The following are the costs of specific structures built at different

times:

Example I.--Indian Creek Culvert. 14×15 ft., 250 long, completed

November, 1905:

Per cu. yd.

Cement $1.37

Sand .34

Stone 1.10

Labor 2.48

Lumber .76

Miscellaneous .18

Total $6.23

Example II.--Third Street Abutments and Retaining Wall. Completed

November, 1906:

Per cu. yd.

Cement $1.78

Sand .35

Stone 1.35

Lumber .74

Labor 2.75

Miscellaneous .16

-----

Total $7.13

Example III.--Abutments, Overhead Crossing with Union Pacific and Rock

Island. Completed May, 1907:

Per cu. yd.

Cement $1.92

Sand .32

Stone 1.74

Lumber .98

Labor 2.96

Miscellaneous .16

-----

Total $8.08

~COST OF PLATE GIRDER BRIDGE ABUTMENTS.~--The following record of the

construction of 20 abutments for 10 four-track plate girder bridges over

streets in Chicago, Ill., are given by Mr. W. A. Rogers. The work was

done between May 1 and Oct. 1, 1898, in which time 8,400 cu. yds. of

concrete were placed, all the work being done by company labor. The

forms were made of 2-in. plank and 6×6-in. posts bolted together at the

top and bottom with ¾-in. rods. The lumber was used over and over again.

When the dressed plank became too poor for the face it was used for the

back. The concrete was 1 Portland cement, 3 gravel and 4 to 4½ limestone

(crusher run up to 3-in. size). A mortar face 1½ ins. thick was built up

with the rest of the concrete. The concrete was made quite wet, and each

man ramming averaged 18 cu. yds. a day rammed. The concrete was mixed by

a machine of the Ransome type, operated by a 12-HP. portable gasoline

engine. The load was very light for the engine, and 8 HP. would have

been sufficient. The engine made 235 revolutions per minute, and the

pulley wheels were proportioned so that the mixer made 12 revs, per

minute. One gallon of gasoline was used per hour, and the mixing was

carried on day and night so as not to give the concrete time to set. The

time required for each batch was 2 to 3 mins., and about ½ cu. yd. of

concrete was delivered per batch. The average output was 70 cu. yds. per

10-hr, shift, with a crew of 28 men; but as high as 96 cu. yds. were

mixed in 10 hrs. The concrete was far superior to hand mixed concrete.

The water for the concrete was measured in an upright tank and

discharged by a pipe into the mixer. The sand and stone were delivered

to the mixer in wheelbarrows, and the concrete was taken away in

wheelbarrows. No derricks were used at all. Each wheelbarrow of concrete

was raised by a rope passing over a pulley at the top of a gallows

frame, one horse and a driver serving for this raising. A small gasoline

hoisting engine would have been more satisfactory than the horse which

was worked to its full capacity. After the barrows were raised (12 ft.),

they were wheeled to the abutment forms and dumped. The empty

wheelbarrows were lowered by hand, by means of a rope passing over a

sheave and provided with a counterweight to check the descent of the

barrow. The cost of the concrete (built by company labor) was as

follows:

Per cu. yd.

Cement, gravel and stone delivered $3.28

Material in forms (used many time) .11

Carpenters building and taking down forms .34

Labor 1.18

-----

Total per cu. yd $4.91

The labor cost includes moving plant from one bridge to the next,

building runways, gasoline for engine, oil for lights at night and

unloading materials, as well as mixing, transporting and placing

concrete. Wages were $1.75 per 10-hour day for laborers and $2.50 for

carpenters.

~COST OF ABUTMENTS AND PIERS, LONESOME VALLEY VIADUCT.~--Mr. Gustave R.

Tuska gives the following on the concrete substructure of the Lonesome

Valley Viaduct, near Knoxville, Tenn. There were two U-shaped abutments

and 36 concrete piers made of a light limestone that deteriorates

rapidly when used for masonry. Derricks were not needed as would have

been the case with masonry piers, and colored labor at $1 for 11 hrs.

could be used. The piers were made 4 ft. square on top, from 5 to 16 ft.

high, and with a batter of 1 in. to the foot. The abutments average 26

ft. high, 26 ft. long on the face, with wing walls 27 ft. long; the wall

at the bridge seat is 5 ft. thick, and the wing walls are 3½ ft. wide on

top. Batters are 1 in. to the foot.

The forms were made of 2-in. tongued and grooved plank, braced by posts

of 2×10-in. plank placed 3 ft. c. to c. for the abutments, and at each

corner for the piers. At the corners one side was dapped into the other,

so as to prevent leakage of cement. The posts were braced by batter

posts from the earth. For the piers a square frame was dropped over the

forms and spiked to the posts. The abutment forms were built up as the

concreting progressed. The north abutment forms were made in sections 6

ft. high, held by ¾-in. bolts buried in the concrete. The lower sections

were removed and used again on the upper part of the work, thus saving

plank. The inside of forms was painted with a thin coat of crude black

oil. The same form was used for several piers.

The concrete was 1-2-5, the barrel being the unit of measure, making

about ¾ cu. yd. of concrete per batch. The mortar was mixed with hoes,

but shovels were used to mix in the stone. By passing the blade of a

shovel between the form and the concrete, the stone was forced back and

a smooth mortar face was secured. Rammers weighing 30 to 40 lbs. were

used for tamping. Two days after the completion of a pier the forms were

removed. The concrete was protected from the sun by twigs, and was

watered twice a day for a week. It was found by actual measurement that

1 cu. yd. Of concrete (1-2-5), the ingredients being measured in

barrels, consisted of 1¼ bbls. of Atlas cement, 10 cu. ft. of sand, and

26½ cu. ft. of stone. The total amount of concrete was 926 cu. yds. of

which two-thirds was in the two abutments. The work was done (in 1894)

by contract, for $7 per cu. yd., cement costing $2.80 per bbl., sand 30

cts. per cu. yd., and wages $1 a day. A slight profit was made at this

price. A gang of 15 men and a foreman would mix and lay about 40 cu.

yds. in 11 hrs. when not delayed by lack of materials. The cost of

making the concrete, with wages at $1 a day, was:

Cts. per cu. yd.

1 man filling sand barrels and handling water 2.7

2 men filling rock barrels 5.4

4 men mixing sand and cement 10.6

4 men mixing stone and mortar 10.6

2 men wheeling concrete 5.3

1 man spreading concrete 2.7

1 man tamping 2.7

1 foreman 5.0

----

Total labor 45.0

~COST OF HAND MIXING AND WHEELBARROW WORK FOR FOUR BRIDGE PIERS.~--The

following figures of the cost of hand-mixed concrete for bridge piers

and abutments are given by Mr. Fred R. Charles of Richmond, Ind. The

figures cover three jobs. All concrete was mixed by hand and with one

exception noted below was moved to place in wheelbarrows. The concrete

was a 1-2½-5½ mixture. In this connection it is well to note that in one

or two of the jobs where the proportion of the aggregate seems too small

for the yardage of concrete the difference is accounted for by the fact

that large stones were placed in the foundations, these stone being on

the ground and costing nothing but the labor to throw them in.

_Job I._--The first job consisted of the construction of one abutment

and six piers for a bridge over the Miami River at Fernald, O. The stone

was procured on the site and crushed by a portable crusher run by a

traction engine. The rough stone cost 10 cts. a cubic yard, and this,

with the cost of handling, fuel and hire of engine and crusher, made the

cost of crushed stone about $1 per cu. yd. Sand was obtained close to

the work, but the cement had to be teamed 10 miles. Labor was paid $1.75

per day. The cost of materials and labor per cubic yard of concrete in

place was as follows:

Item. Per cu. yd.

1.16 bbls. cement at $2.10 $1.58

Sand 0.35

Stone 0.75

Lumber 0.64

Tools, hardware, etc. 0.20

Labor (including 15 cts. per cu. yd. for pumping) 2.78

-----

Total materials and labor $6.30

_Job II._--The second job was the construction of two abutments

containing 434 cu. yds. of concrete for a viaduct at Ernst Street,

Cincinnati, O. The abutments were constructed at the street and the

excavation was clay and shale. Labor received $1.75 per day. The cost of

materials and labor per cubic yard of concrete in place was as follows:

Materials-- Per cu. yd.

376 bbls. cement at $1.70 $1.48

224 cu. yds. sand at $1.20 0.64

255 cu. yds. stone at $1.55 1.00

Lumber 0.40

Tools, hardware, etc. 0.06

Total materials $3.58

Labor--

Clearing and excavating $1.12

Mixing and placing concrete 1.13

Building forms, etc. 0.25

-----

Total labor $2.50

Total labor and materials $6.08

_Job III._--This job consisted in placing 570 cu. yds. of concrete in

the pedestals for a viaduct at Quebec Avenue, Cincinnati, O. The

pedestals were 5 ft. square on top and from 8 to 20 ft. high. The

location of the work was very inconvenient for the delivery of

materials, all materials having to be teamed or wheeled. Labor was paid

$1.75 per day. The cost of labor and materials per cubic yard of

concrete in place was as follows:

Item. Per cu. yd.

500 bbls. cement at $1.60 $1.40

239 cu. yds. sand at $1.25 0.53

560 cu. yds. stone at $1.88 1.84

Lumber 0.38

Tools, hardware, etc. 0.05

Labor 2.96

-----

Total labor and materials $7.16

_Job IV._--This job consisted in placing 2,111 cu. yds. of concrete in a

railway viaduct at Cincinnati, O. For one pier 56 ft. high the concrete

was raised to place by a derrick; for the remainder of the work it was

wheeled or teamed to place. Labor was paid $1.75 per day. The cost of

labor and materials per cubic yard of concrete in place was as follows:

Item. Per cu. yd.

1,908 bbls. cement at $1.60 $1.44

1,105 cu. yds. sand at $1.95 0.50

1,468 cu. yds. stone at $1.48 1.03

Lumber 0.54

Tools, hardware, etc. 0.25

Water 0.03

Labor 3.44

-----

Total labor and materials $7.23

CHAPTER XIII.

METHODS AND COST OF CONSTRUCTING RETAINING WALLS.

Concrete retaining walls may for construction purposes be divided into

two classes: Plain concrete walls of gravity section and reinforced

concrete walls consisting of a thin slab taking the thrust of the earth

as a cantilever anchored to a base slab or as a flat beam between

counterforts. The reinforced wall requires much less concrete for a

given height than does the plain, gravity wall, but the concrete is more

expensive owing to the reinforcement and to the more complex form of

construction, and, in some measure, to the greater cost of placing the

mixture in narrow forms and around reinforcement. It is common, too, to

require a richer concrete for the reinforced than for the plain wall.

[Illustration: Fig. 98.--Comparison of Plain and Reinforced Sections for

Retaining Walls (C. E. Graff).]

~COMPARATIVE ECONOMY OF PLAIN AND REINFORCED CONCRETE WALLS.~--Prior to

the construction of some 2,000 ft. of retaining wall ranging in height

from 2 ft. to 38 ft., at Seattle, Wash., calculation was made by the

engineers of the Great Northern Ry. to determine the comparative economy

of plain concrete and reinforced concrete sections. The sections assumed

were those shown by Fig. 98, and comparisons were made at heights of 10,

20, 30 and 40 ft., with the following results:

Height in Plain. Reinforced. Per cent.

feet. Cu. yds. per ft. Cu. yds. per ft. Saving.

10 1.63 1.29 20.4

20 4.08 2.59 36.4

30 8.40 4.73 43.3

40 14.70 8.07 45.0

The saving in concrete increased as the height of the wall increased;

for a 40-ft. wall reinforced concrete at nearly double the cost per

cubic yard in place would be as cheap as plain concrete.

[Illustration: Fig. 99.--Comparison of Plain and Reinforced Sections for

Retaining Wall (F. F. Sinks).]

Taking substantially the section of reinforced wall being used on the

Chicago track elevation work of the Chicago, Burlington & Quincy R. R.,

and comparing it with a plain wall as shown by Fig. 99, Mr. F. F. Sinks

obtained the following results:

Plain Wall, Cost per Lineal Foot--

4.8 cu. yds. concrete at $4 $19.20

115 ft. B. M. of forms at $31 3.56

------

Total 4.8 cu. yds. at $4.74 $22.76

Reinforced Wall, Cost per Lineal Foot--

3.46 cu. yds. concrete at $4.10 $14.18

115 ft. B. M. of forms at $31 3.56

109 lbs. reinforcing steel at 3¼ cts. 3.54

1.34 cu. yds. extra fill at 20 cts. 0.27

0.32 cu. yd. extra excavation at 20 cts. 0.06

-----

Total, 3.46 cu. yds. concrete at $6.25 $21.61

The saving in this case was $1.15 per lineal foot of wall with the unit

cost of reinforced concrete in place 24 per cent. greater than the unit

cost of plain concrete. It will be noted that there is some 28 per cent.

less concrete per lineal foot of wall in the reinforced section and also

that this section is so designed that the form work is about as simple

for one section as for the other. Another point to be noticed is that

there is no saving in excavation by using a reinforced section instead

of a gravity section, in fact the excavation runs slightly more for the

reinforced section.

[Illustration: Fig. 100.--Forms for Retaining Wall Work, N. Y. C. & H.

R. R. R.]

~FORM CONSTRUCTION.~--Retaining wall work often affords an opportunity for

constructing the forms in panels and this opportunity should be taken

advantage of when possible. Several of the walls described later give

examples of form work that may be studied with profit in this respect.

Figure 100 shows a panel form construction employed on the New York

Central & Hudson River R. R. The 3×8-in. studs are erected, care being

taken to get them in proper line and to true batter and also to brace

them rigidly by diagonal props. Generally the studding is erected for a

section of wall 50 ft. long at one time. The lagging, made in panels 2½

ft. wide and 10 ft. long, by nailing 2-in. plank to 2×4-in. cleats, is

attached to the studding a panel at a time and beginning at the bottom,

by means of the straps, wedges and blocks shown. Five bottom panels

making a form 2½ ft. high and 50 ft. long are placed first. When the

concrete has been brought up nearly to the top of these panels, a second

row of panels is placed on top of the first. When it is judged that the

concrete is hard enough the lowermost panels are loosened and made free

by removing the wedges, blocks and straps and the panels are drawn out

endwise from behind the studding and used over again for one of the

upper courses. The small size of the panels makes it practicable to lay

bare the concrete while it is yet soft enough to work with a float or to

finish by scrubbing as described in Chapter VIII. In cases where this

object is not sought, panels of much larger size may be used. Working

with panels 2¼×12½ ft. of 2-in. plank it was found that each panel could

be used 16 times before becoming unfit for further use, but as, owing to

the nicety of molded surface demanded, panels were discarded when

showing comparatively small blemishes, this record cannot be taken as a

true indication of the life of such forms. These panel forms are used by

the railway named for long abutments and piers as well as for retaining

walls.

A different type of sectional form construction is illustrated by Figs.

101 and 102. It has been extensively used for retaining wall work by the

Chicago, Burlington & Quincy R. R. The studding and waling are framed in

units as shown. The lagging is framed in panels for the rear of the

wall, for the face of the coping, and for the inclined toe of the wall,

and is ordinary sheathing boards for the main face of the wall. The

make-up of the several panels is shown by the drawings. The reason for

using ordinary sheathing instead of panels for the face of the wall is

stated by Mr. L. J. Hotchkiss, Assistant Bridge Engineer, to be that

"the sections become battered and warped with use, do not fit closely

together, and leave the wall rough when they are removed." The manner of

bracing the form and of anchoring it down against the up-thrust of the

wet concrete is shown by Fig. 102.

Two other examples of sectional form construction are given in the

succeeding descriptions of work for the Grand Central Station terminal

in New York City and for the Chicago Drainage Canal. In the former work

it is notable that panels 51×20 ft. were used, being handled by

locomotive crane. The panels used on the drainage canal work and in the

forms previously described are of sizes that can be taken down and

erected by hand, and the means of handling them should always be given

consideration in deciding on the sizes to be adopted for form panels not

only in wall construction but in any other class of work where sectional

forms may be used. Wet spruce or yellow pine will weigh 4½ lbs. per ft.

B. M., so that a panel 10×2½ ft. made of 2-in. plank and three 2×4-in.

battens will weigh some 225 lbs. In form work where the panels are

removed and re-erected in succession facility in handling is an

important matter. When one figures that he may handle both the concrete

and the form panels with it a cableway or a locomotive crane becomes a

tool well worth considering in heavy wall work.

[Illustration: Fig. 101.--Forms for Retaining Wall Work, C., B. & Q. R.

R.]

Three details in retaining wall form work that are often sources of

annoyance out of proportion to their magnitude are alignment, coping

construction and wall ties. Small variations from line in the face of

the wall are seldom noticeable, but a wavy coping shows at a glance.

For this reason it is often wise to build the coping after the main body

of the wall has been stripped, or if both are built together to provide

in the forms some independent means of lining up the coping molds. In

the form shown by Fig. 101 the latter is done by bracing the coping

panel so as to permit it to be set and lined up independently of the

main form. A separate form for molding the coping after the main body of

the wall is completed may be constructed as shown by Fig. 103. Bolts at

B and C permit the yokes to be collapsed and the form to be shifted

ahead as the work advances. This mold provides for beveling the top

edges of the coping and also the edge of the overhang, and the beveling

or rounding of these edges should never be omitted where a neat

appearance is desired. It is not essential, however, that this finishing

be done in the molds. By stripping the concrete while it is still

pliable the edges can be worked down by the ordinary cement sidewalk

edger.

[Illustration: Fig. 102.--Sketch Showing Method of Bracing Form Shown by

Fig. 101.]

[Illustration: Fig. 103.--Sectional Form for Constructing Coping.]

Wall ties are commonly used to hold the face and back forms to proper

spacing, but occasionally they are not permitted. In the latter case the

bracing must be arranged to hold the forms from tipping inward as well

as from being thrust outward. A good arrangement is that shown by Fig.

102. In fastening the forms with ties the choice is usually between long

bolts which are removed when the molds are taken down and wire ties

which are left embedded in the concrete. The selection to be made

depends upon the character of the work. When sectional forms are used

like the one shown by Fig. 101, for long stretches of wall of nearly

uniform cross-section bolts are generally more economical and always

more secure. If the bolts are sleeved with scrap gas pipe having the

ends corked with waste the bolts can be removed ordinarily without

difficulty. To make the pipe sleeve serve also as a spacer the end next

the face may be capped with a wooden washer which is removed and the

hole plastered when the forms are taken down. With bolt ties the forms

can be filled to a depth of 15 to 20 ft with sloppy concrete. This is

hardly safe with wire ties unless more wire and better tieing are

employed than is usual. It takes four strands of No. 10 to give the same

working stress as a ½-in. threaded rod and the tieing in of four strands

of wire so that they will be without slack and give is a task requiring

some skill. Bolts are much more easily placed and made tight. In the

matter of cost of metal left in the wall, the question is between the

cost of scrap gas pipe and of wire; the pound price of the wire is

greater but fewer pounds are used and the metal is in more convenient

shape to cut to length and to handle. This convenience in shaping the

tie to the work gives the advantage to wire ties for isolated jobs or

jobs which involve a continual change in the length and spacing of the

ties. In general the contractor will find bolts preferable where

sectional forms are used and wire ties preferable when using continuous

forms.

One objection urged against the use of wire ties is that the metal is

exposed at the face of the work when they are clipped off unless the

concrete is chipped and the cavity plastered. To obviate this objection

various forms of removable "heads" have been devised. Two such devices

are shown by Figs. 104 and 105. In both the bolt is unscrewed, leaving

the "heads" embedded. The head shown by Fig. 104 has the advantage that

it can be made by any blacksmith, while the head shown by Fig. 105 is a

special casting.

[Illustration: Fig. 104.--Tie for Wall Forms.]

[Illustration: Fig. 105.--Tie for Wall Forms.]

~MIXING AND PLACING CONCRETE.~--Where a long stretch of wall is to be

built the system of mixing and handling the concrete must be capable of

being shifted along the work. For isolated walls of short length this

problem is a simpler one. Where the mixer can be installed on the bank

above, wheeling to chutes reaching down to the work is the best

solution. As shown in Chapter IV concrete can be successfully and

economically chuted to place to a greater extent than most contractors

realize. Where the mixer has to be installed at the foot of the wall

wheelbarrow inclines, derricks, gallows frames, etc., suggest themselves

as means of handling the concrete. It is not this class of work,

however, but the long stretches of heavy section walls such as occur in

depressed or elevated railway work in cities that call for thought in

the arrangement and selection of mixing and handling plant.

In building the many miles of retaining wall in the work of doing away

with grade crossings in Chicago, Ill., trains made up of a mixer car and

several material cars have been used. The mixer is mounted on a flat car

set at the head of the train and is covered by a decking carrying two

charging hoppers set above the mixer. The material cars are arranged

behind, the sand and stone or gravel being in gondola cars. Portable

brackets hooked to the sides of the gondola cars carry runways for

wheelbarrows. Sand and stone or gravel are wheeled to the charging

hoppers, the work being continuous since one hopper is being filled

while the other is being discharged into the mixer. The mixer discharges

either into a chute, wheelbarrows or buckets. The foregoing is the

general arrangement; it is modified in special instances, as is

mentioned further on. The chief objection to the method is the

difficulty of loading the wheelbarrows standing on runways level with

the tops of the gondola sides. The lift from the bottom of the car is

excessive, and as pointed out previously, shoveling stone or gravel by

digging into it from the top is a difficult task.

The delivery of the concrete into the forms was accomplished by chute

where possible, otherwise by wheelbarrows or cranes, and in one case by

belt conveyor. In the last instance the mixer car was equipped with a

Drake continuous mixer and was set in front. Behind it came three or

four gondola cars of sand and stone, and at the rear end a box car of

cement. All material was wheeled on side runways to two charging hoppers

over the mixer. The mixer discharged onto a belt conveyor carried by a

25-ft. boom guyed to an A-frame on the car and pivoted at the car end to

swing 180° by means of a tag line. The outer end of the conveyor was

swung over the forms. A ¾-in. wire rope wrapped eight times around two

drums on the mixer car and passing through slots in the floor to anchors

placed one 500 ft. in front and one 500 ft. to the rear enabled the

train to be moved back and forth along the work. This scheme of

self-propulsion saved the hire of a locomotive. In another case the

mixer was discharged into buckets which were handled by a crane

traveling back and forth along a track laid on two flat cars.

[Illustration: Fig. 106.--Side Elevation of Traveling Mixer Plant,

Galveston Sea Wall.]

Another type of movable mixer plant used in constructing a sea-wall some

3½ miles long at Galveston, Tex., is shown by Figs. 106 and 107. Two of

these machines mixed and placed some 127,000 cu. yds. of concrete, in 1

cu. yd. batches. Two 12-HP. engines operated the derricks and one 16-HP.

engine operated the Smith mixer; all engines took steam from a 50-HP.

boiler. The rated capacity of each machine was 300 to 350 cu. yds. per

day. The method of operation is clearly indicated by the drawings.

[Illustration: Fig. 107.--End Elevation of Traveling-Mixer, Galveston

Sea Wall.]

Placing the concrete in the forms is generally required to be done in

layers; with wet mixtures this means little more than distributing the

concrete somewhat evenly along the wall and slicing and puddling it to

get rid of air and prevent segregation. Where mortar facing is required

the face form described in Chapter VIII may be used. A reasonably good

surface can be secured without mortar facing by spading the face. With

dry concrete, placing and ramming in layers, calls for such care as is

necessary in dry concrete work everywhere. Where new concrete has to be

placed on concrete placed the day before, good bond may be secured and

the chance of efflorescence be reduced by the methods described in

Chapter VIII.

~WALLS IN TRENCH.~--In canal excavation, in subway work in cities, and the

like, it is often necessary to dig trenches and build retaining walls in

them before excavating the core of earth between the walls. The

following examples of such work are taken from personal records:

_Example I._--A Smith mixer was used, the concrete being delivered where

wanted by a Lambert cableway of 400 ft. span. The broken stone and sand

were delivered near the work in hopper-bottom cars which were dumped

through a trestle onto a plank floor. Men loaded the material into

one-horse dump carts which hauled it 900 ft. to the mixer platform. This

platform was 24×24 ft. square, and 5 ft. high, with a planked approach

40 ft. long and contained 7,300 ft. B. M. The stone and sand were dumped

at the mouth of the mixer and shoveled in by 4 men. Eight men, working

in pairs, loaded the broken stone into the carts, and 2 men loaded the

sand. Each cart was loaded with about 70 shovelfuls of stone on top of

which 35 shovelfuls of sand were thrown. It took 3 to 5 minutes to load

on the stone and 1 minute to load the sand. The carts traveled very

slowly, about 150 ft. a minute--in fact, all the men on the job,

including the cart drivers, were slow. After mixing, the concrete was

dumped into iron buckets holding 14 cu. ft. water measure, making about

½ cu. yd. in a batch. The buckets were hooked on to the cableway and

conveyed where wanted in the wall. Steam for running the mixer was taken

from the same boiler that supplied the cableway engine. The average

output of this plant was 100 cu. yds. of concrete per 10-hour day,

although on many days the output was 125 cu. yds., or 250 batches. The

cost of mixing and placing was as follows, on a basis of 100 cu. yds.

per day:

Per day. Per cu. yd.

8 men loading stone into carts $12.00 $ .12

2 men loading sand into carts 3.00 .03

1 cart hauling cement 3.00 .03

8 carts hauling stone and sand 24.00 .24

4 men loading mixer 6.00 .06

1 man dumping mixer 1.50 .01

2 men handling buckets at mixer 3.00 .03

6 men dumping buckets and ramming 9.00 .09

12 men making forms at $2.50 30.00 .30

1 cable engineman 3.00 .03

1 fireman 2.00 .02

1 foreman 6.00 .06

1 waterboy 1.00 .01

1 ton coal for cableway and mixer 4.00 .04

------- -----

Total $107.50 $1.07

In addition to this cost of $1.07 per cu. yd. there was the cost of

moving the whole plant for every 350 ft. of wall. This required 2 days,

at a cost of $100, and as there were about 1,000 cu. yds. of concrete in

350 ft. of wall 16 ft. high, the cost of moving the plant was 10 cts.

per cu. yd. of concrete, bringing the total cost of mixing and placing

up to $1.17 per cu. yd. As above stated, the whole gang was slow.

The labor cost of making the forms was high, for such simple and heavy

work, costing $10 per M. of lumber placed each day. The forms were 2-in.

sheeting plank held by 4×6-in. upright studs 2½ ft. apart, which were

braced against the sides of the trench. The face of the forms was

dressed lumber and all cracks were carefully puttied and sandpapered.

The above costs relate only to the massive part of the wall and not the

cost of putting in the facing mortar, which was excessively high. The

face mortar was 2 ins. thick, and about 3½ cu. yds. of it were placed

each day with a force of 8 men! Two of these men mixed the mortar, 2 men

wheeled it in barrows to the wall, 2 men lowered it in buckets, and 2

men put it in place on the face of the wall. If we distribute this labor

cost on the face mortar over the 100 cu. yds. of concrete laid each day,

we have another 12 cts. per cu. yd.; but a better way is to regard this

work as a separate item, and estimate it as square feet of facing work.

In that case these 8 men did 500 sq. ft. of facing work per day at a

cost of nearly 2½ cts. per sq. ft. for labor.

_Example II._--The building of a wall similar to the one just described

was done by another gang as follows: The stone and sand were delivered

in flat cars provided with side boards. In a stone car 5 men were kept

busy shoveling stone into iron dump buckets having a capacity of 20 cu.

ft. water measure. Each bucket was filled about two-thirds full of

stone, then it was picked up by a derrick and swung over to the next car

which contained sand, where two men filled the remaining third of the

bucket with sand. The bucket was then lifted and swung by the derrick

over to the platform of the mixer where it was dumped and its contents

shoveled by four men into the mixer, cement being added by these men.

The mixer was dumped by two men, loading iron buckets holding about ½

cu. yd. of concrete each, which was the size of each batch. A second

derrick picked up the concrete bucket and swung it over to a platform

where it was dumped by one man; then ten men loaded the concrete into

wheelbarrows and wheeled it along a runway to the wall. One man assisted

each barrow in dumping into a hopper on the top of a sheet-iron pipe

which delivered the concrete. The two derricks were stiff-leg derricks

with 40-ft. booms, provided with bull-wheels, and operated by double

cylinder (7×10-in.) engines of 18-HP. each. About 1 ton of coal was

burned daily under the boiler supplying steam to these two hoisting

engines. The output of this plant was 200 batches or 100 cu. yds. of

concrete per 10-hr. day, when materials were promptly supplied by the

railroad; but delays in delivering cars ran the average output down to

80 cu. yds. per day.

On the basis of 100 cu. yds. daily output, the cost of mixing and

placing the concrete was as follows:

Per day. Per cu. yd.

5 men loading stone $ 7.50 $.07½

2 men loading sand 3.00 .03

4 men charging mixer 6.00 .06

2 men loading concrete into buckets 3.00 .03

1 man dumping concrete from buckets .50 .01½

10 men loading and wheeling concrete .00 .15

1 man dumping wheelbarrows 1.50 .01½

3 men spreading and ramming 4.50 .04½

2 enginemen 5.00 .05

1 fireman 2.00 .02

1 waterboy 1.00 .01

1 foreman 6.00 .06

10 men making forms 25.00 .25

1 ton coal 4.00 .04

Total 85.00 $.85

In addition there were 8 men engaged in mixing and placing the 2-in.

facing of mortar as stated above.

~CHICAGO DRAINAGE CANAL.~--The method and cost of constructing some 20,000

ft. of concrete wall by contract in building the Chicago Drainage Canal

is compiled from records kept by Mr. James W. Beardsley. The work was

done on two separate sections, Section 14 and Section 15. In both cases

a 1-1½-4 natural cement concrete was used with a 3-in. facing and a

3-in. coping of 1-3 Portland cement mortar.

_Section 14._--The average height of the wall was 10 ft., and the

thickness at base was one-half the height. The stone for the concrete

was obtained from the spoil bank of the canal, loaded into wheelbarrows

and wheeled about 100 ft. to the crusher; some was hauled in wagons. An

Austin jaw crusher was used, and it discharged the stone into bins from

which it was fed into a Sooysmith mixer. The crusher and the mixer were

mounted on a flat car. Bucket elevators were used to raise the stone,

sand and cement from their bins to the mixer; the buckets were made of

such size as to give the proper proportions of ingredients, as they all

traveled at the same speed. Only two laborers were required to look

after the elevators. The sand and cement were hauled by teams and dumped

into the receiving bins. There were 23,568 cu. yds. on Section 14 and

the cost was as follows:

Typical Wages per Cost per

General force: force. 10 hrs. cu. yd.

Superintendent 1.0 $5.00 $0.026

Blacksmith 1.1 2.75 0.016

Timekeeper 0.5 2.50 0.007

Watchman 0.6 2.00 0.007

Waterboys 3.9 1.00 0.022

Wall force:

Foreman 0.9 2.50 0.013

Laborers 8.6 1.50 0.073

Tampers 2.3 1.75 0.022

Mixer force:

Foreman 1.2 2.50 0.017

Enginemen 1.8 2.50 0.025

Laborers 6.7 1.50 0.057

Pump runner 1.0 2.00 0.010

Mixing machines 1.7 1.25 0.012

Timber force:

Foreman 0.6 2.50 0.008

Carpenters 4.7 2.50 0.057

Laborers 1.2 1.50 0.010

Helpers 5.3 2.50 0.075

Hauling force:

Laborers 2.6 1.75 0.026

Teams 6.3 3.25 0.116

Crushing force:

Foreman 0.5 2.50 0.007

Engineman 1.7 2.50 0.023

Laborers 3.5 1.50 0.032

Austin crushers 1.7 1.20 0.011

Loading stone:

Foreman 1.7 2.50 0.023

Laborers 32.9 1.50 0.280

------

Total for crushing, mixing and placing $0.975

The daily costs charged to the mixers and crushers include the cost of

coal, at $2 a ton, and the cost of oil.

The gang "loading stone" apparently did a good deal of sledging of large

stones, and they also wheeled a large part of it in barrows to the

crusher.

The plant cost $9,600, distributed as follows:

2 jaw crushers $3,000

2 mixers 3,000

Track 1,260

Lumber 500

Pipe 840

Sheds 400

Pumps 600

-----

Total $9,600

If this first cost of the plant were distributed over the 23,568 cu.

yds. of concrete it would amount to 41 cts. per cu. yd.

The cost of the concrete was as follows:

Per cu. yd.

Utica cement, at $0.65 per bbl. $0.863

Portland cement, at $2.25 per bbl. 0.305

Sand, at $1.35 per cu. yd. 0.465

Stone and labor, as above given 0.975

------

Total $2.608

First cost of plant $0.407

_Section 15._--The conditions on this section were much the same as on

Section 14, just described, except that the limestone was quarried from

the bed of the canal, and was crushed in a stationary crusher, No. 7

Gates. The stone was hauled 1,000 ft. to the crusher on cars drawn by a

cable from a hoisting engine. The output of this crusher averaged 210

cu. yds. per day of 10 hrs. The crushed stone was hauled in dump cars,

drawn by a locomotive, to the mixers. Spiral screw mixers mounted on

flat cars were used, and they delivered the concrete to belt conveyors

which delivered the concrete into the forms.

The forms on Section 15 (and on Section 14 as well) consisted of upright

posts set 8 ft. apart and 9 ins. in front of the wall, held at the toe

by iron dowels driven into holes in the rock, and held to the rear posts

by tie rods. The plank sheeting was made up in panels 2 ft. wide and 16

ft. long, and was held up temporarily by loose rings which passed around

the posts which were gripped by the friction of the rings. These panels

were brought to proper line and held in place by wooden wedges. After

the concrete had set 24 hrs. the wedges were struck, the panels removed

and scraped clean ready to be used again.

The cost of quarrying and crushing the stone, and mixing the concrete on

Section 15 was as follows:

Typical Wages per Cost per

General force-- force. 10 hrs. cu. yd.

Superintendent 1.0 $5.00 $0.024

Blacksmith 0.9 2.75 0.011

Teams 1.7 3.00 0.025

Waterboy 4.5 1.00 0.022

Wall force--

Foreman 1.1 2.50 0.010

Laborers 14.4 1.50 0.105

Tampers 0.1 1.75 0.001

Mixer force--

Foreman 2.1 2.50 0.026

Enginemen 2.1 2.50 0.022

Laborers 23.1 1.50 0.180

Mixing machines 2.1 1.25 0.022

Timber force--

Carpenters 0.8 3.00 0.013

Laborers 0.7 1.50 0.005

Helpers 10.2 2.50 0.125

Hauling force--

Foreman 0.7 2.50 0.009

Enginemen 1.4 2.50 0.019

Fireman 0.4 1.75 0.003

Brakeman 2.2 2.00 0.018

Teams 0.4 3.25 0.007

Laborers 1.5 1.50 0.010

Locomotives 1.4 2.25 0.015

Crushing force--

Foreman 1.0 2.50 0.014

Enginemen 1.0 2.50 0.014

Laborers 11.1 1.50 0.081

Firemen 1.0 1.75 0.008

Gyratory crusher 1.0 2.25 0.011

Quarry force--

Foreman 1.2 2.50 0.012

Laborers 19.0 1.50 0.140

Drillers 1.8 2.00 0.017

Drill helpers 1.8 1.50 0.013

Machine drills 1.8 1.25 0.011

------

$0.993

The first cost of the plant for this work on Section 15 was $25,420,

distributed as follows:

1 crusher, No. 7 Gates $12,000

Use of locomotive 2,200

Car and track 5,300

3 mixers 3,000

Lumber 1,200

Pipe 720

Small tools 1,000

-------

Total $25,420

This $25,420 distributed over the 44,811 cu. yds. of concrete amounts to

57 cts. per cu. yd.

It will be noted that 2 mixers were kept busy. Their average output was

100 cu. yds. each per day, which is the same as for the mixers on

Section 14.

The total cost of concrete on Section 15 was as follows:

Per cu. yd.

Labor quarrying, crushing and mixing $0.991

Explosives 0.083

Utica cement, at $0.60 per bbl. 0.930

Portland cement, at $2.25 per bbl. 0.180

Sand, at $1.35 per cu. yd. 0.476

------

Total $2,660

First cost of plant $0.567

It is not strictly correct to charge the full first cost of the plant to

the work as it possessed considerable salvage value at the end.

_Comparison._--For the purpose of comparing Sections 14 and 15 the

following summary is given of the cost per cubic yard of concrete:

Sec. 14. Sec. 15.

General force $0.078 $0.082

Wall force 0.108 0.116

Mixing force 0.121 0.250

Timbering force 0.150 0.140

Hauling force 0.142 0.081

Crushing force 0.073 0.128

Quarry force 0.303 0.275

Cement, natural 0.863 0.930

Cement, Portland 0.305 0.180

Sand 0.465 0.476

Plant (full cost) 0.407 0.567

------ -------

Total $3.015 $3.225

It should be remembered that on Section 14 there was no drilling and

blasting of the rock, but that the "quarry force" not only loaded but

hauled the stone to the crusher. The cost of mixing on Section 15 is

higher than on Section 14 because the materials were dumped on platforms

and shoveled into the mixer, instead of being discharged from bins into

the mixer as on Section 14.

[Illustration: Fig. 108.--Cross Section of Retaining Wall. New York

Central Terminal Work.]

[Illustration: Fig. 109.--Portable Concrete Mixing Tower, N. Y. Central

Terminal Work.]

~GRAND CENTRAL TERMINAL, NEW YORK, N. Y.~--In building a retaining wall of

the cross-section, shown in Fig. 108, a traveling tower moving on tracks

parallel to the wall contained the concrete mixing plant. The

construction of the tower is shown in Fig. 109. The tower had two

platforms, one at the top carrying two 10-cu. yd. bins for sand and

stone and the other directly below carrying 40 cu. ft. (4 cu. ft.

cement, 12 cu. ft. sand and 24 cu. ft. stone) Ransome mixer driven by a

30 H.P. motor and a Lidgerwood motor hoist. The elevator tower carried

two 40-cu. ft. Ransome dumping buckets traveling in guides and dumping

automatically into the bins. These buckets were operated by the

Lidgerwood motor hoist on the mixer platform. Sand and broken stone on

flat cars were brought alongside the tower. The sand was shoveled direct

from the car into the sand bucket, but the broken stone was shoveled

into wheelbarrows which were wheeled over a light bridging from car to

bucket and dumped. Wheelbarrows were used for handling the stone chiefly

because the capacity of the plant was so great that enough men could not

be worked in the limited space around the bucket to keep up the supply

by shoveling. The wheelbarrow work added materially to the cost. Cement

was carried from the cars to the sand bucket, hoisted and stored on the

mixer platform which provided storage room for 100 bags. A 1-3-6 mixture

was used; the sand and stone were chuted directly from the bins to the

charging hopper and the cement was charged by hand. The mixed concrete

was delivered to two 1 cu. yd. dump cars running on a 2-ft. gage track

laid in sections on the cross pieces connecting the uprights of the

forms. The track had no switches, so that one car had to wait for the

other. Four men were required to push each car and two more men assisted

in dumping the car and kept the track clear. The wall was built in

sections 51 ft. long, each containing 250 cu. yds. One of these sections

was filled in 8 hours with ease and by a little hustling a section was

filled in 6¾ hours, which is at the rate of 37 cu. yds. of concrete per

hour. Working 8 hours per day the cost of mixing, transporting and

placing concrete with this mixing plant, with wages for common labor of

$1.50 per day, was as follows:

Total. Per cu. yd.

2 men carrying cement $ 3.00 $0.012

6 men shoveling sand 9.00 0.036

17 men shoveling stone 25.00 0.100

11 men wheeling stone 16.00 0.064

2 men at stone and sand bins 3.00 0.012

2 men opening cement bags 3.00 0.012

1 man dumping hopper 1.50 0.006

1 man dumping mixer 1.50 0.006

1 man cleaning chute, mixer, etc. 1.50 0.006

1 motorman or engineer 3.00 0.012

------- -------

Total labor mixing $66.50 $0.266

8 men pushing 2 cars 12.00 0.048

2 men cleaning track, etc. 3.00 0.012

7 men spading concrete 10.50 0.042

------- -------

Total labor transporting, placing $ 25.50 $0.102

1 foreman 5.00 0.020

Electricity estimated 7.00 0.028

------- -------

Total general $ 12.00 $0.048

Grand total $104.00 $0.416

It will be noted that the cost of shoveling and wheeling the broken

stone amounts to 16.4 cts. per cu. yd., or nearly 40 per cent. of the

total cost of mixing and placing. The cost of spading the concrete is

also high for a sloppy mixture, but is probably accounted for by the

fact that the concrete had to be spaded so as to have 2 or 3 ins. of

clear mortar next the forms. The forms used in constructing the wall

are shown by Figs. 110 and 111. They were made in panels 51 ft. long and

a locomotive crane was used to shift the panels. This crane worked

handling forms only a small part of the time, but a form gang of 10

carpenters was kept busy all of the time moving and reassembling.

Assuming the work of the crane to amount to $5 per day and the wages of

the carpenter gang to amount to $25, we get a cost of 12 cts. per cubic

yard of concrete for shifting forms. It should be noted carefully that

the costs given for this work do not include cost of materials, interest

on plant, superintendence and other items.

[Illustration: Fig. 110.--End View of Forms for Retaining Wall, New York

Central Terminal Work.]

~WALL FOR RAILWAY YARD.~--For building a retaining wall 7 ft. high, forms

were made and placed by a carpenter and helper at $8 per M., wages being

35 cts. and 20 cts. an hour, respectively. Concrete materials were

dumped from wagons alongside the mixing board. Ramming was unusually

thorough. Foreman expense was high, due to small number in gang; 2 cu.

yds. were laid per hour by the gang.

[Illustration: Fig. 111.--Corner Detail of Retaining Wall Forms, New

York Central Terminal Work.]

Per day. Per cu. yd.

7 mixers, 15 cts. per hour $10.50 $0.53

2 rammers, 15 cts. per hour 3.00 0.15

1 foreman 30 cts. per hr., 1 waterboy 5 cts. 3.50 0.17

------- ------

Total labor $17.00 $0.85

The total cost was as follows per cubic yard:

Per cu. yd.

0.8 bbls. Portland cement, at $2 $1.60

Sand 0.30

Gravel 0.70

Labor mixing and placing 0.85

Lumber for forms, at $16 per M. 0.56

Labor on forms, at $8 per M. 0.28

------

Total, per cubic yard $4.29

The sheathing plank for the forms was 2-in. hemlock.

~CONCRETE FOOTING FOR RUBBLE MASONRY RETAINING WALL.~--In constructing a

footing for a retaining wall at Grand Rapids, Mich., a 1-2½-5 natural

cement concrete was used. It was found that 1 cu. yd. of concrete was

equivalent to 29.8 cu. ft. of material composed of 3.6 cu. ft. or 1.1

bbls. of cement, 8.4 cu. ft. or 2.7 bbls. of sand and 17.8 cu. ft. or

5.5 bbl. of broken stone. The labor cost of 15.5 cu. yds. of concrete

was as follows:

Item. Total. Per cu. yd.

Foreman, 14 hours at 40 cts. $ 5.60 $0.3613

Foreman, 20 hours at 22.5 cts. 4.50 0.2903

Laborers, 49 hours at 12.5 cts. 6.11 0.3942

Mason, 2 hours at 35 cts. 0.70 0.0451

------ --------

Total labor $16.91 $1.0909

All material was furnished by the railway company, the contractor

furnishing labor only; his contract price for this was $1 per cu. yd.

~TRACK ELEVATION, ALLEGHENY, PA.~--The wall was 6,100 ft. long and 75 per

cent. was on curves. The first wall built had a top width of 2½ ft. and

a bottom width of 0.4 the height with the back on a smooth batter. Later

the back was stepped and last the wall was proportioned as follows:

Calling the height from top of foundation to under coping, then width of

base was 0.45 (h + 3), the top measuring 2½ ft. The back was arranged

in steps 24 ins., 30 ins. and 36 ins. high, and the thickness of wall at

each step was, calling h equal to height of step from base, 0.45 (h + 3).

Several forms of expansion joints were tried. The first was tarred

paper extending through the wall every 50 ft.; the second was ½-in.

boards running through the wall every 50 ft.; the third was ½-in. board

extending 2 ft. into the wall, with a ¼-in. cove at the angles, every 25

ft. The third construction gave perfect satisfaction.