~DESIGN AND CONSTRUCTION.~--The main points to be kept in mind in the

original design and construction of forms are: Economy in lumber,

economy in carpenter work, and economy in taking down, carrying and

re-erecting. Economy in lumber is not merely the matter of using the

least amount of lumber that will serve the purpose considering the form

as an isolated structure. It may be possible to build a column form, for

example, of very light material which will serve to mold a single

column, but it is evident that we could better afford to use twice this

amount of lumber if by doing so we obtained a form which could be used

over again to mold a second column; no more lumber per column would be

used while the cost of erecting a form already framed is less than the

cost of framing a new form. Economy in lumber in form construction

involves, therefore, recognition of the economies to be gained by

repeated use of the lumber. A certain amount of additional sturdiness is

required in the shape of heavier form lumber and stronger framing to

provide for the wear and tear of repeated use, and it is always economy

to provide it when repeated use is possible. The thing can be overdone,

however; there is an economical limit to repeated use, as we demonstrate

further on. In the matter of economy in carpenter work, a certain amount

of extra work put into framing the forms to withstand the stress of

repeated use is economically justifiable. Also carpenter work put into

framing which substitutes clamps and wedges for nails is sound economy;

generally speaking a skillful form carpenter is recognized by the

scarcity of nails he uses. The possibility of reducing carpenter work by

ordering lumber to length and width from plans has already been

mentioned. It is possible often to go a step further by having certain

standard panels, boxes, etc., made in regular shops. Piece work is often

possible and will frequently reduce framing costs. In designing for

economy in taking down, carrying and re-erecting forms a cardinal point

should be that the work be such that it can be executed by common

laborers. This result can be very nearly approached by careful design,

even for form work that is quite complex, if a special gang is devoted

to the work and trained a little in the various operations. Design the

forms so that they come apart in units by simply removing bolts, clamps

and wedges. They can then be taken down, carried and erected by common

laborers with a skilled man in charge to meet emergencies and to true

and line up the work.

In the matter of details the joints deserve particular attention. In

column and girder forms, generally, joints will be square or butt

joints, and to get them tight the lumber must be dressed true to edge.

Tight joints are considered essential by many not only to avoid joint

marks but for the more important reason that otherwise, with wet

mixtures, a honeycombed concrete is produced by leakage. Where tight

joints are desired tongue and groove stock or stock cut with one edge

beveled and the other square give the best results. The authors believe

that the best general satisfaction will be got from the bevel edge stock

placed so that the bevel edge of one board comes against the square edge

of the next board; undue swelling then results in the bevel edge cutting

into the adjacent square edge without bulging. Tongues and grooves

suffer badly from breakage. As a matter of fact square edged stock, if

well dressed and sized and well filled with moisture, can be used and is

used with entire success in nearly all kinds of work. The leakage will

be very slight with ordinarily good butt joints and so far as surface

appearance goes joint marks are more cheaply and more satisfactorily

eliminated by other means than attempting to get cabinet work in form

construction. Where girder forms join columns or beams connect with

girders and at the angles of floor slabs with beams the edges or corners

of the forms should be rounded. The edges of beams and column corners

will appear better if beveled; a triangular strip in the corners of the

forms will provide this bevel. Forms and mold construction for

ornamental work call for and are given special consideration in Chapter

XXIII. In conclusion, the reader should study the specific examples of

form construction for different purposes that are given throughout the

book for hints as to special practice and details.

~UNIT CONSTRUCTION OF FORMS.~--Unit construction has a somewhat variable

meaning in form work. In wall and tank work and in some other kinds of

work unit construction means the use of form units which are gradually

moved ahead or upward as the concreting progresses or of form units

which are used one after another in continuous succession as the

concreting progresses. In column, girder and floor work unit

construction means the division of the form work as a whole and also of

the individual forms into independent structural units; thus in forms

for a building the column forms may be independent of the girder forms

and also each column and girder form be made up of several separate

units. In all cases unit construction has for its purpose the use of the

same form or at least the same form lumber over and over for molding

purposes. Every time the use of the same form is repeated, the cost of

form work per cubic yard of concrete placed is reduced. The theoretical

limit of economical repetition is then the limit of endurance of the

form, the practical limit, however, is something quite different. Most

concrete work varies in form or dimensions often enough to prevent the

use of the same forms more than a few times, and even if these

variations did not exist the time element would enter to prevent the

same form or form lumber being used more than a certain number of times.

Unit construction to give repeated use of forming has, therefore, its

economic limits. The significance of this conclusion does not lie in any

novelty that it possesses but in the fact that for any piece of work it

determines the labor that may profitably be expended in working out and

constructing form units.

~LUBRICATION OF FORMS.~--All forms for concrete require a coating of some

lubricant to prevent the concrete from adhering to the wood with which

it comes in contact. Incidentally this coating tends to give a smoother

surface to the concrete and to preserve the wood against damage by its

alternate wetting and drying. The great value of lubrication is,

however, that it reduces the cost of removing forms. The requisite of a

good coating material is that it shall be thin enough to spread evenly

and to fill the pores and grain of the wood. Crude oil or petroline

makes one of the best coatings, but various other greasy substances will

serve. Where the forms are not to be removed until the concrete has set

hard a thorough wetting of the wood just before the concrete is placed

is all the coating necessary. Any concrete adhering to forms should be

thoroughly cleaned off before they are used again and the wood

underneath given a special heavy coating.

~FALSEWORKS AND BRACING.~--The falseworks which support the forms proper

and stagings for workmen, runways, material hoists, etc., do not call

for any striking differences in construction and arrangement from such

work elsewhere. For wall forms inclined props reaching from ground to

studding are used for walls of moderate height such as retaining walls,

wing walls, and abutments. For building walls of some height a gallows

frame arrangement or the common braced staging used by masons and

carpenters is used. In building construction, however, movable forms are

commonly employed for walls more than one story high and should always

be employed above one story to save staging timber. Column forms are

seldom braced unless erected without connecting girder or floor forms at

their tops, and then only by diagonal props to the floor or ground.

Girder and floor supports usually consist of uprights set under the

girder form at intervals and occasionally under floor slab forms. The

spacing of props and uprights will be regulated by the judgment of the

foreman and boss carpenter; no general rule is applicable, except that

enough lumber must be used to hold the forms rigid and true to line and

level. The various illustrations of actual formwork which follow are the

best guides to good practice.

~TIME FOR AND METHOD OF REMOVING FORMS.~--No exact time schedule for

removing forms is wise in concrete work. Concrete which is mixed wet

sets slower than dry concrete and concrete sets slower in cold weather

than it does in warm weather. Again the time of removal is influenced by

the risk taken by too early removal, and also by the nature of the

stresses in the member to be relieved of support. In all cases the forms

should be removed as soon as possible so that they can be used over

again and so that the concrete may be exposed to the air to hasten

hardening. The following suggestions as to time of removal are general

and must be followed with judgment.

Using dry concrete in warm weather the forms for retaining walls,

pedestals, isolated pillars, etc., can be removed in 12 hours; using wet

or sloppy concrete the time will be increased to 24 hours. In cold

weather the setting is further delayed and inspection is the only safe

guide to follow. Very cold weather delays setting indefinitely. Forms

for small arch work like sewers and culverts may be removed in 18 to 24

hours if dry concrete is used, and in 24 to 48 hours if wet concrete is

used. The time for removing large arch centers should not be less than

14 days for spans up to 50 ft. if the arch is back-filled at once; when

the center is not to be used again it is better to let it stand 28 days.

For very large arches the problem becomes a special one and is

considered in Chapter XVII. In building construction the following

schedule is a common one. Remove the column forms in 7 days and the

sides of the girder forms and the floor lagging in 14 days leaving the

bottom boards of the girder forms and their supports in place for 21

days.

As an example of individual practice the following requirements of a

large firm of concrete contractors are given:

Walls in mass work, 1 to 3 days, or until the concrete will bear

pressure of the thumb without indentation.

Thin walls, in summer, 2 days; in cold weather, 5 days.

Slabs up to 6-ft. span, in summer, 6 days; in cold weather, 2 weeks.

Beams and girders and long span slabs, in summer, 10 days or 2 weeks; in

cold weather, 3 weeks to 1 month. If shores are left without disturbing

them, the time of removal of the sheeting in summer may be reduced to 1

week.

Column forms, in summer, 2 days; in cold weather, 4 days, provided

girders are shored to prevent appreciable weight reaching columns.

Conduits, 2 or 3 days, provided there is not a heavy fill upon them.

Arches, of small size, 1 week; for large arches with heavy dead load, 1

month.

The method of removing forms will vary in detail with the character of

the structure. With proper design and lubrication of forms they will

ordinarily come away from the concrete with a moderate amount of sledge

and bar work. If the work will warrant it, have a special gang under a

competent foreman for removing forms. The organization of this gang and

the procedure it should follow will vary with the nature of the form

work, and they are considered in succeeding chapters for each kind of

work.

~ESTIMATING AND COST OF FORM WORK.~--It is common practice to record the

cost of forms in cents per cubic yard of concrete, giving separately the

cost of lumber and labor. This should be done, but the process of

analysis should be carried further. The records should be so kept as to

show the first cost per 1,000 ft. B. M. of lumber, the number of times

the lumber is used, the labor cost of framing, the labor cost of

erecting and the labor cost of taking down, all expressed in M. ft. B.

M. In this way only is it possible to compare the cost of forms on

different kinds of concrete work, and thus only can accurate predictions

be made of the cost of forms for concrete work having dimensions

differing from work previously done. It is well, also, to make a note of

the number of square feet of exposed concrete surface to which the forms

are applied.

Some of the items mentioned demand brief explanation. Framing and

erecting costs are kept separate for the reason that the framing is done

only once, whereas the erecting occurs two or more times. The lumber

cost, where the material is used more than once, can be computed in two

ways. An example will illustrate the two modes of procedure. In one of

the buildings described in Chapter XIX the lumber cost $30 per M. ft. B.

M. and was used three times. As 34,000 ft. B. M. were required to encase

the 200 cu. yds. of concrete in one floor, including columns, it would

have required 34,000 ÷ 200 = 170 ft. B. M. of lumber at $30 per M. per

cubic yard of concrete if it had been used only once. But since it was

used three times we may call it 170 ft. B. M. at $10 per M. per cubic

yard of concrete, or we may call it 170 ÷ 3 = 57 ft. B. M. at $30 per M.

per cubic yard of concrete. The authors prefer the first method, due to

the fact that it is 170 ft. B. M. that is handled and taken down each

time and it is more consistent to have the lumber cost on the same basis

thus:

170 ft. B. M. of lumber at $10 per M $1.70

170 ft. B. M. handled at $2 per M 0.34

170 ft. B. M. erected at $7 per M 1.19

-----

Total 170 ft. B. M. per cu. yd $3.23

Returning to our main thought, there are three ways of recording the

cost of form work: (1) In cents per cubic yard of concrete; (2) in cents

per square foot of concrete face to which forms are applied, and (3) in

dollars per 1,000 ft. B. M. of lumber used. In all cases the cost of

materials and of labor should be kept separate. It is well if it can be

done to attach a sketch of the forms to the record. So much for the

general method of recording costs in form work.

In estimating the probable cost of forms for any job the following

method will be found reliable: Having the total cubic yards of concrete

in the work and the time limit within which the work must be completed

determine the number of cubic yards that must be placed per day, making

liberal allowances for delays. Next estimate the number of thousands of

feet board measure of forms required to encase the concrete to be placed

in a day. This will give the minimum amount of lumber required, for it

is seldom permissible to remove the forms until the concrete has

hardened over night. Now we come to the very important and puzzling

question of the time element, particularly in work where it is possible

to use the same forms or the same form lumber two or more times.

It has already been pointed out that wet concrete sets more slowly than

dry concrete; that all concrete sets more slowly in cold than in warm

weather, and that the support of forms is necessary a longer time for

pieces subject to bending stress like arches and girders. General

suggestions as to specific times for removing forms have also been

given. Where the specifications state the time of removal the contractor

has a definite guide, but where they do not, as is most often the case,

he must depend very largely on judgment and previous experience. Another

matter which deserves consideration is the use of the forms as staging

for runways or tracks. Such use may result in forms having to stand on

work for sake of their service as trestles much longer than there is any

necessity so far as supporting the concrete is concerned. A derrick or

cableway may often prove cheaper than tieing up form lumber by trying to

make it serve the double purpose of a trestle.

The possibilities of repeated use of forms and of unit construction of

forms have already been noted. This is the next point to be considered

in estimating form lumber. At the expense of a little planning movable

forms can be used to materially reduce the amount of lumber required.

The reader is referred particularly to the chapters on retaining wall,

conduit and building work for specific data on movable form work.

Having estimated the amount of lumber required and the number of times

it can be used the labor cost of framing, erecting and taking down can

be figured. In ordinary retaining wall work forms will cost for framing

and erection from $6 to $7 per M. ft. B. M. To tear down such forms

carefully and to carry the lumber a short distance will cost some $1.50

to $2 per M. ft. B. M. We have then a cost of $7.50 to $9 per M. ft. B.

M. for each time the forms are erected and torn down. Where movable

panels are used and the forms not ripped apart and put together again

each time there is of course only the cost of moving, which may run as

low as 50 cts. per M. ft. B. M. Framing and erecting centers for piers

will run about the same as for retaining wall. At this point it may be

noted that in estimating the cost of forms for plain rectangular piers

the following method will give very accurate results. Ascertain the

surface area of the four sides of the pier. Multiply this area by 2, and

the product will be the number of feet board measure of 2-in. plank

required. Add 40 per cent. to this, and the total will be the number of

feet board measure of 2-in. plank and of upright studs (4×6), spaced 2½

ft. centers. Sometimes 3×6-in. studs are used, and spaced 2 ft. centers,

which requires practically the same percentage (40 per cent.) of timber

for the studs as where 4×6-in. studs are used and spaced 2½ ft. centers.

No allowance is made for timber to brace the studs, since, in pier work,

it is customary to hold the forms together either with bolts or with

ordinary No. 9 telegraph wire, which weighs 0.06 lb. per foot. The

foregoing data can be condensed into a rule that is easily remembered:

_Multiply the number of square feet surface area of the sides and ends

of a concrete pier by 2.8, and the product will be the number of feet

board measure required for sheet plank and studs for the forms._

If the form lumber can be used more than once, divide the number of feet

board measure by the number of times that it can be used, to ascertain

the amount to be charged to each pier. Forms can be erected and taken

down for $8 per M. carpenters being paid $2.50 and laborers $1.50 a day.

Since there are 2.8 ft. B. M. of forms per square foot of surface area

of concrete to be sheeted, it costs 2¼ cts. for the labor of carpenters

per square foot of surface area to be sheeted. If lumber is worth $24

per M., and is used three times, then the lumber itself also costs 2¼

cts. per sq. ft. of surface area of concrete. By dividing the total

number of cubic yards of concrete into the total number of square feet

of area of surface to be sheeted with forms, the area per cubic yard is

obtained. Multiply this area by 4½ cts., and the product is the cost per

cubic yard for material in the forms (assumed to be used three times)

and the labor of erecting it and taking it down.

The cost of framing and erection of forms for building work and of

centers for large arches is a special problem in each case and is

considered in the chapters devoted to those classes of work.

CHAPTER X.

METHODS AND COST OF CONCRETE PILE AND PIER CONSTRUCTION FOR FOUNDATIONS.

Two general methods of concrete pile construction are available for

engineering work. By one method a hole is formed in the ground by

driving a steel shell or by other special means and this hole is filled

with concrete. By the other method the pile is molded in suitable forms

and after becoming hard is driven as a wood or steel pile is driven.

Piles constructed by the first method may be either plain or reinforced,

but piles constructed by the second method are always reinforced to

strengthen them for handling and driving. Concrete piers for foundation

work are simply piles of enlarged diameter.

~MOLDING PILES IN PLACE.~--Molding piles in place requires the use of

special apparatus, and this apparatus is to a very large degree

controlled by patents. Pile work of this kind is thus generally done by

concerns which control the use of the apparatus employed and the general

contractor can undertake it only by permission of the proprietary

companies. The methods of work followed and the cost of work are thus of

direct interest only as general information.

~Method and Cost of Constructing Raymond Piles.~--The machinery and

processes employed in the construction of Raymond concrete piles are

patented and all piling work by this method is controlled by the Raymond

Concrete Pile Co. As detail costs of construction are not given out by

the company the following figures collected by the authors are subject

to revision. They are believed to be fairly approximate, having in one

case been obtained by personal watch on the work and in the other case

from authentic records of the engineers on the work.

The pile is made as follows: A collapsible steel core 30 ft. long, 20

ins. diameter at the top and 6 ins. diameter at the bottom, encased in

a thin sheet steel shell, is driven into the ground by an ordinary pile

driver. When it has reached the proper depth, a wedge is loosened,

permitting the two sections of the core to come closer together so that

the core can be pulled out of the hole, leaving the steel shell behind

as a casing to prevent the sides from caving in. The shell is made of

No. 20 gage steel, usually in four or more sections, which telescope one

over the other. A nest of sections is slipped over the lower end of the

core as it hangs in the leads, a rope is hitched around the outer

section and the engine hoists away until the sections are

"un-telescoped" and drawn snug onto the core. The rope is then

unfastened and the driving begins. Figure 49 shows the usual pile

driving rig used. The following are examples of pile construction in

actual work:

_Example I._--In this work, for a building foundation in New York City,

the pile driver was mounted on a turntable, the framework of the

turntable in turn resting on rollers traveling on timbers laid on the

ground. The driver was moved along and rotated when necessary by ropes

passing around the winch head of the engine. The driver had 50-ft. leads

and a 3,100-lb. hammer operated by an ordinary friction clutch hoisting

engine. The hammer blow was received by an oak block fitting into a

recess at the top of the steel core. This block was so battered by the

blows that it had to be renewed about every five or six piles driven. A

¾-in. wire rope passing over a 10-in. sheave lasted for the driving of

130 piles and then broke. When the work was first begun the crew

averaged 10 piles per 10-hour day, but the average for the job was 13

piles per day, and the best day's work was 17 piles. The cost of labor

and fuel per pile was as follows:

5 men on driver at $1.75 $ 8.75

2 men handling shells at $1.75 3.50

1 engineman 3.00

6 men mixing and placing concrete 10.50

1 foreman 5.00

Coal and oil 2.50

-------

Total, 13 piles, at $2.55 $33.25

[Illustration: Fig. 49.--Pile Driver Rigged for Constructing Raymond

Concrete Piles.]

Deducting the cost of placing the concrete we get a cost of $1.75 for

driving the cores. The pile, 25 ft. long, 6 ins. at the point and 18

ins. at the head, contains 21¼ cu. ft., or 0.8 cu. yd., of concrete, and

has a surface area of 77 ft. As No. 20 steel weighs 1.3 lbs. per sq.

ft., each shell weighed approximately 100 lbs. The cost per pile may

then be summarized as follows:

1.2 bbls. cement in 0.8 cu. yd., at $1.75 $2.10

0.8 cu. yd. stone at $1.25 1.00

1/3 cu. yd. sand at $1.05 0.35

100 lbs. steel in shell at 3½ cts. 3.50

Labor and fuel as above 2.55

-----

Total per pile (38 cts. per lin. ft.) $9.50

_This cost, it should be carefully noted, does not include cost of

moving plant to and from work or general expenses._

_Example II._--In constructing a building at Salem, Mass., 172

foundation piles, 14 to 37 ft. long, 6 ins. diameter at the point and 20

ins. diameter at the top, were constructed by the Raymond process. The

general contractor made the necessary excavations and provided clear and

level space for the pile driver, braced all trenches and pier holes, set

stakes for the piles and gave all lines and levels. The piles were

driven by a No. 2 Vulcan steam hammer with a 3,000-lb. plunger having a

drop of 3 ft., delivering 60 blows per minute. Figure 49 shows the

driver at work. Sixteen working days were occupied in driving the piles

after the driver was in position. The greatest number driven in one day

was 20, and the average was 11 piles per day. When in position for

driving, the average time required to complete driving was 12 minutes.

The total number of blows varied from about 310 to 360, the average

being about 350. The piles were driven until the penetration produced by

8 to 10 blows equaled 1 in. When in full operation, a crew of 5 men

operated the pile driver. Seven men were engaged in making the concrete

and 5 men working upon the metal shells.

Assuming the ordinary organization and the wages given below, we have

the following labor cost per day:

1 foreman at $5 $ 5.00

1 engineman at $3 3.00

4 laborers on driver at $1.75 7.00

6 laborers making concrete at $1.75 10.50

5 laborers handling shells at $1.75 8.75

------

Total $34.25

As 172 piles averaging 20 ft. in length were driven in 16 days, the

total labor cost of driving, given by the figures above, is 16 × $34.25

= $548, or practically 16 cts. per lineal foot of pile driven.

The concrete used in the piles was a 1-3-5 Portland cement, sand and

1½-in. broken stone mixture. A 20-ft. pile of the section described

above contains about 20 cu. ft. of concrete, or say 0.75 cu. yd. We can

then figure the cost of concrete materials per pile as follows:

0.85 bbl. cement at $1.60 $1.36

0.36 cu. yd. sand at $1 0.36

0.60 cu. yd. stone at $1.25 0.75

-----

Total per pile $2.47

The steel shell has an area of about 72 sq. ft., and as No. 20 gage

steel weighs 1.3 lbs. per sq. ft., its weight for each pile was about 94

lbs. Assuming the cost of coal, oil, etc., at $2.50 per day, we have the

following summary of costs:

Per lin. ft.

of pile.

Labor driving and concreting $0.16

Concrete materials 0.123

94 lbs. steel shell at 3 cts. 0.145

Coal, oil, etc. 0.011

------

Total $0.439

_The cost does not include interest on plant, cost of moving plant to

and from work and general expenses._

[Illustration: Fig. 50.--Sketch Showing Method of Constructing Simplex

Concrete Piles.]

~Method of Constructing Simplex Piles.~--The apparatus employed in driving

Simplex piles resembles closely the ordinary wooden pile driven, but it

is much heavier and is equipped to pull as well as to drive. A 3,300-lb.

hammer is used and it strikes on a hickory block set in a steel drive

head which rests on the driving form or shell. This form consists of a

¾-in. steel shell 16 ins. in diameter made in a single 40-ft. length.

Around the top of the shell a ½-in. thick collar or band 18 ins. deep is

riveted by 24 1-in. countersunk rivets. This band serves the double

purpose of preventing the shell being upset by the blows of the hammer

and of giving a grip for fastening the pulling tackle. The bottom of the

form or shell is provided with a point. Two styles of point are

employed. One style consists of two segments of a cylinder of the same

size as the form, so cut that they close together to form a sort of clam

shell point. In driving, the two jaws are held closed by the pressure of

the earth and in pulling they open apart of their own weight to permit

the concrete to pass them. This point, known as the alligator point, is

pulled with the shell. It is suitable only for driving in firm, compact

soil, in loose soil the pressure inward of the walls keeps the jaws

partly closed and so contracts the diameter of the finished pile. The

second style of point is a hollow cast iron point, 10 ins. deep and 16½

ins. in diameter, having a neck over which the driving form slips and an

annular shoulder outside the neck to receive the circular edge of the

shell. The projected sectional area of this point is 1.4 sq. ft. It is

left in the ground when the form is withdrawn. The form is withdrawn by

means of two 1-in. cables fastened to a steel collar which engages under

the band at the top of the form. The cables pass in the channel leads on

each side over the head of the driver and down in back to a pair of

fivefold steel blocks, the lead line from which passes to one of the

drums of the engine. In this manner the power of the drum is increased

ten times and it is not unusual to break the pulling cables when the

forms are in hard ground. The general method of construction is about as

shown by Fig. 50, being changed slightly to meet varying conditions. The

form resting on a cast iron point is driven to hard ground. A heavy

weight is then lowered into the form to make sure the point is loose.

While the weight is at the bottom of the form a target is placed on its

line at the top of the form, the purpose of which will be apparent

later. The weight is then withdrawn. Given the length of the pile and

sectional area, it is an easy matter to determine the volume of concrete

necessary to fill the hole.

This amount is put into the form by means of a specially designed bottom

dump bucket, which permits the concrete to leave it in one mass,

reaching its destination with practically no disintegration. It will be

noticed that when the full amount of concrete is in the form its surface

is considerably above the surface of the ground. This is due to the fact

that the thickness of the form occupies considerable space that is to be

occupied by the concrete. The weight is now placed on top of the

concrete and the form is pulled. The target previously mentioned now

becomes useful. As the form is withdrawn the concrete settles down to

occupy the space left by the walls of the form. Obviously this

settlement should proceed at a uniform rate, and as it is difficult to

watch the weight, the target on its line further up is of considerable

help. By watching this target in connection with a scale on the leads of

the driver, it can be readily told how the concrete in the form is

acting. As another check, the target, just as the bottom of the form is

leaving the ground should be level with the top of the form. This would

indicate that the necessary amount of concrete has gone into the ground

and that, other conditions being all right, the pile is a good one. In

some grounds where the head of concrete in the form exerts a greater

pressure than the back pressure or resistance of the earth, the concrete

will be forced out into the sides of the hole, making the pile of

increased diameter at that point and necessitating the use of more

concrete to bring the pile up to the required level.

~Method of Constructing Piles with Enlarged Footings.~--A pile with an

enlarged base or footing has been used in several places by Mr. Charles

R. Gow of Boston, Mass., who has patented the construction. A single

pipe or a succession of pipes connected as the work proceeds is driven

by hammer to the depths required. The material inside the shell is then

washed out by a water jet to the bottom of the shell and then for a

further distance below the shell bottom. An expanding cutter is then

lowered to the bottom of the hole and rotated horizontally so as to

excavate a conical chamber, the water jet washing the earth out as fast

as it is cut away. When the chamber has been excavated the water is

pumped out and the chamber and shell are filled with concrete. The

drawings of Fig. 51 show the method of construction clearly. The

chambering machine is used only in clay or other soil which does not

wash readily. In soil which is readily washed the chamber can be formed

by the jet alone. The practicability of this method of construction is

stated by Mr. Gow to be limited to pipe sizes up to about 14 ins. in

diameter.

[Illustration: Fig. 51.--Sketch Showing Method of Constructing Concrete

Piles with Enlarged Footings.]

~Method of Constructing Piles by the "Compressol" System.~--The compressol

system of concrete pile or pillar construction is a French invention

that has been widely used abroad and which is controlled in this country

by the Hennebique Construction Co., of New York, N. Y. The piles are

constructed by first ramming a hole in the ground by repeatedly

dropping a conical "perforator" weighing some two tons. This perforator

is raised and dropped by a machine resembling an ordinary pile driver.

The conical weight gradually sinks the hole deeper and deeper by

compacting the earth laterally; this lateral compression is depended

upon so to consolidate the walls of the hole that they do not cave

before the concrete can be placed. The concrete is deposited loose in

the hole and rammed solid by dropping a pear-shaped weight onto it as it

is placed. The view Fig. 52 shows the "perforator" and the tamping

apparatus at work. Very successful work has been done abroad by this

method.

[Illustration: Fig. 52.--View of Apparatus Used in Constructing

Compressol Piles.]

~Method of Constructing Piers in Caissons.~--For piles or pillars of

diameters larger than say 18 ins. the use of driving shells and cores

becomes increasingly impracticable. Concrete pillars of large size are

then used. They are constructed by excavating and curbing a well or

shaft and filling it with concrete. This construction has been most used

in Chicago, Ill., for the foundations for heavy buildings, but it is of

general application where the sub-soil conditions are suitable. The

method is not patented or controlled by patents in any particular,

except that certain tools and devices which may be used are proprietary.

_General Description._--The caisson method of construction is simple in

principle. A well is dug by successive excavations of about 5 ft. each.

After each excavation of 5 ft. is completed, wood lagging is placed

around the sides and supported by internal steel rings, so that the soft

ground around the excavation is maintained in its former position. The

methods of excavating and removing the soil and of constructing the

lagging are considered in detail further on. The caissons vary in

diameter according to the load; some as large as 12 ft. in diameter have

been sunk, but the usual diameter is 6 ft.; a caisson of 3 ft. in

diameter is as small as a man can get into and work. When the pier goes

to bed rock the caisson is made of uniform diameter from top to bottom,

but where the pier rests on hardpan the bottom portion of the well is

belled out to give greater bearing area. It is customary to load the

piers about 20 tons per square foot.

[Illustration: Fig. 53.--Curbing for Concrete Piers (Usual

Construction).]

_Caisson Construction._--The caisson construction, or more correctly the

form of curbing most commonly used, is that indicated by the sketch,

Fig. 53. The lagging is 2×6 in. or 3×6 in., stuff 5 ft. 4 ins. or 4 ft.

long set vertically around the well and held in place by interior

wrought iron rings. For a 6-ft. diameter caisson these hoops are ¾ by 3

ins.; they are made in two parts, which are bolted together as shown by

Fig. 53. Generally there are two rings for each length of lagging; for

5-ft. lagging they are placed about 9 ins. from each end. In some

cases, however, engineers have specified three rings for the upper

sections in soft clay and two rings for the sections in the hard ground

lower down. The lagging used is not cut with radial edges, but is rough,

square cut stuff; the rings, therefore, take the inward pressure

altogether.

[Illustration: Fig. 54.--Curbing for Concrete Piers (Jackson Patent).]

In some recent work done by the inventor use has been made of the

caisson construction shown by Fig. 54 and patented by Mr. Geo. W.

Jackson. In place of the plain rings a combination of T-beam ribs and

jacks is used; this construction is clearly shown by the drawing. The

advantages claimed for the construction are that it gives absolute

security to the workmen and the work, that the lagging can be jacked

tightly against the outer walls of the well, that the braces form a

ladder by which the workmen can enter and leave the well, and that the

possibility of shifting the bracing easily permits the concrete to be

placed to the best advantage. On the other hand the braces abstruct the

clear working space of the caissons.

[Illustration: Fig. 55.--Layout of Plant for Concrete Pier Construction.

Cook County Court House Foundations.]

_Excavating and Handling Material._--The excavation of the wells is done

by hand, using shovels and picks, and, in the hardpan, special grubs

made by A. J. Pement and George Racky, Chicago blacksmiths. The

excavated material is hoisted out of the well in buckets made by the

Variety Iron Works, of Chicago. For caissons which are not specified to

go to rock it is considered more economical to do the hoisting by

windlass derricks operated by hand. These derricks have four 6×6-in.

legs and a 3×6-in. top piece. When the caissons go to rock the hoisting

is done by power, so-called "cable set-ups" being used in most cases. To

illustrate this method the following account of the foundation work for

the Cook County Court House is given:

The Cook County Court House foundations consist of 126 caissons varying

from 4 ft. to 10½ ft. in diameter and averaging$ 7½ ft. in diameter.

They were sunk to rock at a depth of 115 ft. below street level. The

work involved 22,000 cu. yds. of excavation and the placing in the

caissons of 17,000 cu. yds. of concrete. Over 1,000 piles about 40 ft.

long, that had formed the foundation of the old Court House built in

1875, were removed. These piles were found to be in good condition. The

work was done by the George A. Fuller Co., of Chicago, Ill.,

Contractors, with Mr. Edgar S. Belden Superintendent in Charge. The

details which follow have been obtained from Mr. Belden.

[Illustration: Fig. 56.--Section Showing Arrangement of Hoist for

Concrete Pier Construction.]

The foundation area was 157×375 ft., and was excavated to a depth of 15

ft. below the street surface before the caissons were started. The

caissons, of which there were 126, were arranged in rows across the lot,

there being from six to eight caissons in a row. The arrangement of the

plant for the work is indicated by Fig. 55. One row of caissons formed a

unit. A platform or "stand" was erected over each caisson and carried in

its top a tripod fitted with a "nigger head" operated by a rope sheave.

This arrangement is shown by Fig. 56. An engine on the bank operated by

a rope drive all the tripod sheaves for a row of six or eight caissons.

The arrangement is indicated by Fig. 55. The clay hoisted from the pits

was dumped into 1 cu. yd. hoppers with which the stands were fitted, as

shown by Fig. 56; when a hopper was full it was dumped into a car

running on a 24-in. gage portable track. Side dump Koppel cars of 1 cu.

yd. capacity were used; they dumped their load into an opening connected

with the tracks of the Illinois Tunnel Co., where the material passed

into tunnel cars and was taken to the lake front about one mile away. As

soon as one row of caissons was completed the stands, tripods, etc.,

which were made portable, were shifted to another row. At times as many

as five units were in operation, sinking 40 caissons.

[Illustration: Fig. 57.--Details of Working Platform for Concrete Pier

Construction.

Side Elevation.

End Elevation.

Bottom Plan.

Section.]

Fig. 56 shows the arrangement in detail at one caisson. In this work the

lagging used was 3×6-in. maple, 5 ft. 4 ins. long, and was supported by

3×¾-in. steel hoops. The lagging was matched and dressed. The "nigger

head," as will be seen, is operated by a rope sheave on the same axle.

As stated above, an endless rope drive operated all the "nigger heads"

on a row of caissons. A 26-in. driving sheave was attached to an

ordinary hoisting engine equipped with a governor. The driving rope was

5/8-in. steel. It was wrapped twice around the driving sheave and once

around the "nigger head" sheaves. These latter were 18 ins. in diameter.

For the hoists 1-in. Manila rope was used. The other details, the

bucket, bucket hook, swivel block, etc., are made clear by the drawing.

The platforms, tripods, etc., were of the standard dimensions and

construction adopted by the contractors of the work. Detail drawings of

the standard platform are given by Fig. 57. One of these platforms

contains about 1,000 ft. B. M. of lumber. As will be seen, all

connections are bolted, no nails being used anywhere. A platform can

thus be taken down and stored or shipped and erected again on another

job with very little trouble.

The plant described handled some 22,000 cu. yds. of excavated material

on this work. Work was kept up night and day, working three 8-hour

shifts. It took an average of 35 shifts to excavate one row of caissons.

No figures of the working force or the cost of excavation of this work

are available.

_Mixing and Placing Concrete._--The placing of the concrete in the

excavated wells is done by means of tremies, or, which is more usual, by

simply dumping it in from the top, workmen going down to distribute it.

The manner of mixing the concrete and of handling it to the caisson

varies of course with almost every job. As an example of the better

arranged mixing and handling plants the one used on the Cook County

Court House work may be described. This plant is shown by the sketch,

Fig. 58.

Bins for the sand and stone were built at one side of the lot on the

sloping bank; their tops were level with the street surface and their

bottoms were just high enough to permit their contents to be delivered

by chutes into 1 cu. yd. cars. Wagons dumping through traps in the

platform over the bin delivered the sand and stone. The sketches

indicate the arrangement of the bins and mixer and the car tracks

connecting them. The raw material cars were first run under the stone

bin and charged with the required proportion of stone, and then to the

sand bin, where the required proportion of sand was chuted on top of the

stone. The loaded car was then hauled up the incline and dumped into the

hopper, where cement and water were added. A No. 2½ Smith mixer was used

and discharged into cars which delivered their loads on tracks leading

to the caissons. The same cars and portable tracks were used as had been

used to handle the excavated material. In operation a batch of raw

materials was being prepared in the hopper while the previous batch was

being mixed and while the concrete car was delivering the still previous

batch to the caissons. An average of 40 batches an hour mixed and put

into the caissons was maintained with a force of 25 men. In all some

17,000 cu. yds. of concrete were mixed and deposited.

[Illustration: Fig. 58.--Arrangement of Concrete Making Plant, Concrete

Pier Construction.]

_Cost of Caisson Work._--The following attempt to get at the cost of

caisson work is based largely upon information obtained from Mr. John M.

Ewen, John M. Ewen Co., Engineers and Builders, Chicago, Ill. Mr. Ewen

says:

"My experience has taught me that it is almost impossible to determine

any definite data of cost for this work. This is due to the fact that no

two caisson jobs will average the same cost, notwithstanding the fact

that the cost of material used and the labor conditions are exactly the

same. This condition is due to the great variety in texture of the soil

gone through. For instance, it has come under my experience that in

caissons of the same diameter on the same job it required but fifteen

8-hour shifts to reach bedrock in some of these, while it required as

many as 21 to 25 shifts to reach rock in the others, rock being at the

same elevation. In fact, the digging all the way to rock in some was the

best that could be wished for, while in the others boulders and

quicksand were encountered, and the progress was slower, and the cost

consequently greater.

"Again, we have known it to require eight hours for two men to dig 8

ins. in hardpan in one caisson, while on a job going on at the same time

and on the opposite corner of the street two men made progress of 2 ft.

in 8 hours through apparently the same stuff, the depth of hardpan from

grade being 61 ft. 6 ins. in both instances, and the quality of labor

exactly the same.

"There have been more heavy losses among contractors due to the

unexpected conditions arising in caisson digging than in any other item

of their work, and I predict a loss to some of them that will be serious

indeed if an attempt be made to base future bids for caisson work

entirely upon the data kept by them on past work. If a contractor is

fortunate enough to find the ordinary conditions existing in his caisson

work, and by ordinary conditions I mean few boulders, no quicksand,

ordinary hardpan and no gas, the following items may be considered safe

for figuring caisson work:

"Figure that it will require from 22 to 25 shifts of 8 hours each to

strike bedrock, bedrock being from 90 to 95 ft. below datum, and datum

being 15 ft. below street grade; figure 2 diggers to the shift in all

caissons over 5 ft. in diameter, 45 cts. per hour for each digger;

figure 1 top man at 40 cts. per hour, and 1 mucker or common laborer at

30 cts. per hour for all caissons in which there are two diggers, and 1

top man less if 1 digger is in the caisson, which condition exists

generally in caissons less than 5 ft. in diameter. Add the cost of

5/8-in. cable, tripods, sheaves, 1-in. Hauser laid line, nigger heads,

ball-bearing blocks, etc., for rigging of the job. Lagging, which is 2×6

ins. and 3×6 ins. hemlock or some hard wood, in length of 5 ft. 4 ins.

and 4 ft., is priced all the way from $20 to $22.50 and $21 to $24.50

per M. ft. B. M., respectively. The price of caisson rings is $2.40 per

100 lbs. The cost of specially made grubs for digging in hardpan is

about $26 per dozen. Shovels are furnished by the diggers themselves in

Chicago, Ill. The cost of temporary electric light is $10 per caisson.

This includes cost of cable, lamps, guards, etc. Add the cost of or

rental of engine or motors for power.

"Some engineers specify three rings to be used to each set of lagging

below the top set until hardpan is reached, then two rings for each of

the remaining sets from hardpan to rock. This is, of course, to insure

against disaster from great pressure of the swelling clay above the

hardpan strata, and may or may not be necessary. These rings are ¾×3

ins. wrought iron.

"For caissons which are not specified to go to rock, it is not

considered economical to rig up cable set-ups, but rather to use

windlass derricks. In this case 1-in. Hauser laid line is used as the

means of hoisting the buckets of clay out of the caisson, as is the case

in cable set-ups, hand power being used on the windlass derricks instead

of steam or electricity. The windlass derricks are made with four legs

out of 6×6-in. yellow pine lumber. The top piece is generally a piece of

3×6-in. lagging. The cost of windlass and boxes is about $35 per dozen.

Hooks for caisson buckets cost 45 cts. each. Caisson buckets cost $8

each.

"With the above approximate units as a basis, I have seen unit prices

given per lineal foot in caisson work which ranged all the way from $12

to $16.50 for 6-ft. diameter caissons, larger and smaller sized caissons

being graded in price according to their size. This unit price included

rings, lagging, concrete, power, light, labor, etc."

From the above data the following figures of cost can be arrived at,

assuming a 6-ft. caisson:

Labor. Per day.

2 diggers in caisson, at $3.60 $ 7.20

1 top man, at $3.20 3.20

1 mucker, at $2.40 2.40

------

$12.80

The depth sunk varies from 3½ to 8 ft. per 8-hour day, depending on the

material. Assuming an average of 4 ft., we have then 4 lin. ft. of

caisson, or 2.8 cu. yds. excavated at a labor cost of $12.80, which is

at the rate of $3.20 per lin. ft., or $4.57 per cu. yd. We now get the

following:

Per lin. ft.

Caisson.

40 ft. B. M. (2×6-in. lagging) at $25 $1.00

60 lbs. iron (¾×3-in. rings) at 2½ c. 1.50

0.7 cu. yd. excavation at $4.57 3.20

0.7 cu. yd. muck hauled away at $1 0.70

0.7 cu. yd. concrete at $5 3.50

Electric light 0.10

------

Total $10.00

If 3×6-in. lagging is used add 50 cts. per lin. ft. of caisson.

~MOLDING PILES FOR DRIVING.~--Piles for driving are molded like columns in

vertical forms or like beams in horizontal forms. European constructors

have a strong preference for vertical molding, believing that a pile

better able to withstand the strain of driving is so produced; such

lamination as results from tamping and settling is, in vertical molding,

in planes normal to the axis of the pile and the line of driving stress.

Vertical molding has been rarely employed in America and then only for

molding round piles. The common belief is that horizontal molding is the

cheaper method. In the ordinary run of work, where comparatively few

piles are to be made, it is probably cheaper to use horizontal molds,

but where a large number of piles is to be made, the vertical method has

certain economic advantages which are worth considering.

[Illustration: Fig. 59.--Plant for Vertical Molding of Concrete Piles.]

Vertical molding necessitates a tower or staging to support the forms

and for handling and placing the concrete; an example of such a staging

is shown by Fig. 59. To counterbalance this staging, horizontal molding

necessitates a molding platform of very solid and rigid construction if

it is to endure continued and repeated use. In the matter of space

occupied by molding plant, vertical molding has the advantage. A tower

40 ft. square will give ample space around its sides for 80 vertical

forms for 12-in. piles and leaves 1 ft. of clear working space between

each pair of forms. The ground area occupied by this tower and the forms

is 1,764 sq. ft. With the same spacing of molds a horizontal platform

at least 25 × 160 ft. = 4,000 sq. ft., would be required for the molds

for the same number of piles 25 ft. long. For round piles, vertical

molding permits the use of sectional steel forms; horizontal forms for

round piles are difficult to manage. For square piles vertical molding

requires forms with four sides; horizontal forms for square piles

consist of two side pieces only, the molding platform serving as the

bottom and no top form being necessary. Thus, for square piles

horizontal molding reduces the quantity of lumber per form by 50 per

cent. The side forms for piles molded on their sides can be removed much

sooner than can the forms for piles molded on end, so that the form

material is more often released for reuse. The labor of assembling and

removing forms is somewhat less in horizontal molding than in vertical

molding. Removing the piles from molding bed to storage yard for curing

requires derricks or locomotive cranes in either case and as a rule this

operation will be about as expensive in plant and labor in one case as

in the other. In the ease and certainty of work in placing the

reinforcement, horizontal molding presents certain advantages, the

placing and working of the concrete around the reinforcement is also

easier in horizontal molding. Mixing and transporting the concrete

materials and the concrete is quite as cheap in vertical molding as in

horizontal molding. If anything, it is cheaper with vertical molding,

since the mixer and material bins can be placed within the tower or

close to one side where a tower derrick can hoist and deposit the

concrete directly into the molds. Car tracks, cars, runways and

wheelbarrows are thus done away with in handling the concrete from mixer

to molds. Altogether, therefore, the choice of the method of molding is

not to be decided off-hand.

~DRIVING MOLDED PILES.~--Driving molded concrete piles with hammer drivers

is an uncertain operation. It has been done successfully even in quite

hard soils and it can be done if time is taken and the proper care is

exercised. The conditions of successful hammer driving are: Perfect

alignment of the pile with the line of stroke of the hammer; the use of

a cushion cap to prevent shattering of the pile-head, and a heavy hammer

with a short drop. The pile itself must have become well cured and

hardened. At best, hammer driving is uncertain, however; shattered piles

have frequently to be withdrawn and the builder is never sure that

fractures do not exist in the portion of the pile that is underground

and hidden. The actual records of concrete pile work given in succeeding

sections illustrate successful examples of hammer driving. The plant

required need not vary from that ordinarily used for driving wooden

piles, except that more power must be provided for handling the heavier

concrete pile and that means must be provided for holding the pile in

line and protecting its head.

Sinking concrete piles by means of water jets is in all respect a

process similar to that of jetting wooden piles. Examples of jetting are

given in succeeding section. In rare cases, driving shells, or sheaths

have been used for driving molded piles.

~Method and Cost of Molding and Jetting Piles for an Ocean Pier.~--In

reconstructing in reinforced concrete the old steel pier at Atlantic

City, N. J., some 116 reinforced concrete piles 12 ins. in diameter were

molded in air and sunk by jetting. The piles varied in length with the

depth of the water, the longest being 34½ ft. Their construction is

shown by Fig. 60, which also shows the floor girders carried by each

pair of piles and forming with them a bent, and the struts bracing the

bents together. In molding and driving the piles the old steel pier was

used as a working platform.

[Illustration: Fig. 60.--Concrete Pile for Pier at Atlantic City, N. J.]

The forms for the piles were set on end on small pile platforms located

close to the positions to be occupied by the piles and were braced to

the old pier. The forms were of wood and the bulb point, the shaft and

the knee braces were molded in one piece. Round iron rods were used for

reinforcement. The concrete was composed of 1 part Vulcanite Portland

cement, 2 parts of fine and coarse sand mixed and 4 parts of gravel 1

in. and under in size. The mixture was made wet and was puddled into the

forms with bamboo fishing rods, which proved very efficient in working

the mixture around the reinforcing rods and in getting a good mortar

surface. The concrete was placed in small quantities; it was mostly all

hand mixed. The forms were removed in from 5 to 7 days, depending on the

weather.

The piles were planned to be sunk by water jet and to this end had

molded in them a 2-in. jet pipe as shown. They were sunk to depths of

from 8 ft. to 14 ft. into the beach sand. Water from the city water

mains at a pressure of 65 lbs. per sq. in. was used for jetting; this

water was furnished under special ordinance at a price of $1 per pile,

and a record of the amount used per pile was not kept. The piles were

swung from the molding platforms and set by derricks and block and fall.

The progress of jetting varied greatly owing to obstructions in places

in the shape of logs, old iron pipes, etc. In some cases several days

were required to get rid of a single pipe. In clear sand, with no

obstruction, a 12-in. pile could be jetted down at the rate of about 8

ft. per hour, working 1 foreman and 6 men. The following is the itemized

actual cost of molding and sinking a 26-ft. pile with bulb point and

knee braces complete:

Cost per

Forms-- pile.

Lumber, 340 ft. B. M. @ $30 $10.20

Labor (carpenters @ $2.50 per day) 12.00

Oil, nails, oakum, bolts, clamps, etc. 1.20

-------

$23.40 $ 3.90

Times used 6

Reinforcement--

275 lbs. of plain ¾-in. steel rods @ 2 cts. per lb. $ 5.50

Preparing and setting, 4/10 ct. per lb. 1.10 6.60

Jet Pipe--

26½ ft. of 2-in. pipe @ 10 cts. per ft. in place. 2.65

Setting Forms--

6 men @ $2.50 per day = $15, set 4 piles 3.75

Material--

90/100 Cu. yds. gravel @ $1.50 per yd. 1.35

45/100 cu. yds. sand @ $1.50 per yd. .67

1.50 bbls. cement @ $1.60 2.40 4.42

Labor--

Concrete and labor foreman 3.00

6 laborers, mixing and placing by hand, $1.75

each 10.50

-------

$13.50 3.38

Average number of piles concreted per day 4

Removing Forms--

4 men @ $2.50 remove and clean in half day 4

columns 1.25

1 man @ $2.25 plastering column with cement

grout (4 per day) .56

Jetting 10 ft. into Sand--

Foreman $ 3.00

4 men, $2.25 each, handling hose and traveler 9.00

-------

$12.00 3.00

Average number of piles jetted per day 4

City water pressure used for jetting @ $1 per pile 1.00

Superintendence @ $5.00 per day 1.25

Caring for trestle, traveler, material, etc. 4.84

-------

Total cost per pile $36.60

The pile being 26 ft. long, the cost in place was $1.41 per foot.

Subtracting the cost of sinking amounting to $7.09 per pile, we have the

cost of a 26-ft. pile molded and ready to sink coming to about $1.10 per

foot. It should be noted that this is the cost for a pile of rather

complicated construction; a plain cylindrical pile should be less

expensive.

~Method of Molding and Jetting Square Piles for a Building

Foundation.~--The foundation covered about an acre. The soil was a

deposit of semi-fluid mud and quicksand overlying a very irregular rock

bottom and encircled by a ledge of rock. The maximum depth of the mud

pocket was 40 ft., and interspersed were floating masses of hard pan.

Soundings were made at the locations of all piles; a ½-in. gas pipe was

coupled to a hose fed by city pressure and jetted down to rock, the

depth was measured, the sounding was numbered and the pile was molded to

length and numbered like the sounding. In all 414 piles were required,

ranging in length from 1½ to 40 ft.; all piles up to 6 ft. were built

in place in wooden forms. The piles were 13 ins. square and were of

1-2½-4 concrete reinforced with welded wire fabric. A tin speaking tube

was molded into each pile at the center. This tube was stopped about 10

ins. from the head and by means of an elbow and threaded nipple

projected through the side of the pile to allow of attaching a pressure

hose. The piles were handled to the pile driver, the hose attached and

water supplied at 100 lbs. pressure by a pump. Churning the pile up and

down aided the driving. A hammer was used to force the piles through the

hard pan layers. A wooden follower was used to protect the pile head. A

2,800-lb. hammer falling 20 ft. did not injure the piles. One pile was

given 300 blows with a 2,800-lb. hammer falling 12 ft., and when pulled

was unbroken. It was found that 30 ft. piles and under could be picked

up safely by one end; longer piles cracked at the center when so

handled. These long piles were successfully handled by a long chain, one

end being wrapped around the pile at the center and the other end

similarly wrapped near the head; the hook of the hoisting fall was

hooked into the loop of the chain and as the pile was hoisted the hook

slipped along the chain toward the top gradually up ending the pile. The

piles weighed 175 lbs. per lin. ft. It was attempted to mold the piles

directly on the ground by leveling it off and covering it with tar

paper, but the ground settled and the method proved impracticable.

~Method of Molding and Jetting Piles for Building Foundations.~--In a

number of foundations Mr. Frank B. Gilbreth has used a polygonal pile,

either octagonal or hexagonal, with the sides corrugated or fluted as

indicated in Fig. 61. In longitudinal section these piles have a uniform

taper from butt to point and have flat points. Each pile is cored in the

center, the core being 4 ins. in diameter at the top and 2 ins. at the

bottom end. On each of the octagon or hexagon sides the pile has a

half-round flute usually from 2½ to 3 ins. in diameter. The principal

object of these flutes or "corrugations" is to give passage for the

escape to the surface of the water forced through the center core hole

in driving the pile. They are also for the purpose of increasing the

perimeter of the pile and thereby gaining greater surface for skin

friction.

The piles are reinforced longitudinally and transversely. On this

particular job the reinforcement was formed with Clinton Electrically

Welded Fabric, the meshes being 3 ins.×12 ins.; the longer dimension

being lengthwise with the pile and of No. 3 wire; the horizontal or

transverse reinforcement being of No. 10 wire. The meshes being

electrically welded together, the reinforcement was got out from a wide

sheet taking the form of a cone. No part of the reinforcement was closer

than 1 in. from the outside of the concrete. In general only sufficient

sectional area of material is put in the reinforcement to take the

tensile stresses caused by the bending action when handling the pile

preparatory to driving; more reinforcement than this only being

necessary when the piles are used for wharves, piers or other marine

structures, where a considerable length of pile is not supported

sidewise or when they are subjected to bending stresses.

[Illustration: Fig. 61.--Cross-Section of Corrugated Reinforced Concrete

Pile.]

_Molding._--The forms for molding the piles are made from 2-in. stuff,

gotten out to the required dimensions, the corrugations being formed by

nailing pieces on the inside whose section is the segment of a circle.

The sides of the octagon are fastened to the ends through which the core

projects some 6 or 8 ins. At times while the molding of the pile is in

progress, the central core is given a partial turn to prevent the

setting of the cement holding it fast and thereby preventing the final

removal.

The stripping of the forms from the piles is usually done from 24 to 48

hours after molding, and from this time on great care is taken that

there is a sufficient amount of moisture in the pile to permit of the

proper action for setting of the cement. This is usually accomplished by

covering the piles over with burlaps and saturating with water from a

hose; the operation of driving the pile not being attempted until the

concrete is at least ten days old.

_Driving._--The operation of driving corrugated concrete piles is

somewhat similar to that for driving ordinary wooden piles by water jet,

but a much heavier hammer with less drop is used. The jetting is

accomplished by inserting a 2-in. pipe within the pile. This pipe is

tapered at the bottom end to 1-in. diameter, forming a nozzle, and the

water pressure used is about 120 lbs. per sq. in. As a rule, this

pressure is obtained by the use of a steam pump which may be connected

with the boiler which operates the pile driver, or with a separate steam

supply. At the upper end of this 2-in. pipe an elbow is placed and a

short length of pipe is connected to this and to the hose from the water

supply.

[Illustration: Fig. 62.--Cushion Cap for Driving Gilbreth Corrugated

Pile.]

As it is not practicable to drop the hammer directly on the head of the

concrete piles, the driving is accomplished by the use of a special cap,

Fig. 62. This cap is about 3 ft. in height and the bottom end fits over

the head of the pile. In one side of this cap is a slot from the outside

to the center, which permits the 2-in. pipe, which supplies the water

jet for driving the pile, to project. The outside of this cap is formed

with a steel shell, the inside has a compartment filled with rubber

packing and the top has a wooden block which receives a blow from the

hammer. In this way the head of the pile is cushioned, which prevents

the blow of the hammer from bruising or breaking the concrete.

During the operation of driving, the water from the jet comes up on the

outside of the pile and carries with it the material which it displaces

in driving. This, with the assistance of the hammer, allows the pile to

be driven in place, and, contrary to what might be supposed, after the

operation of driving when the water has saturated into the ground or

been drained away, this operation puddles the earth around the pile, so

that after a few hours' time the skin friction is much more than it

would be with the pile driven into more compact soil without the use of

a jet.

[Illustration: Fig. 63.--View Showing Method of Fabricating

Reinforcement for a Round Pile with Flattened Sides.]

~Method of Molding and Driving Round Piles.~--In constructing a warehouse

at Bristol, England, some 600 spirally-reinforced piles of the Coignet

type were used. Coignet piles are in section circles with two

longitudinal flat faces to facilitate guiding during driving; this

section is the same as would be found by removing two thin slabs from

opposite sides of a timber pile. The reinforcement consists of

longitudinal bars set around the periphery and drawn together to a point

at one end and then inserted into a conical shoe; these longitudinal

bars are wound spirally with a ¼-in. rod wire tied to the bars at every

intersection. This spiral rod has a pitch of only a few inches, but to

bind it in place and give rigidity to the skeleton it is wound by a

second spiral with a reverse twist and a pitch of 4 or 5 ft. As thus

constructed, the reinforcing frame is sufficiently rigid to bear

handling as a unit. The piles used at Bristol were 14 to 15 ins. in

diameter and 52 ft. long, and weighed about 4 tons gross each. The

mixture used was cement, river sand and crushed granite.

_Molding._--In molding Coignet piles the reinforcement is assembled

complete as shown by Fig. 63 and then suspended as a unit in a

horizontal mold constructed as shown by the cross-section Fig. 64. The

concrete is deposited in the top opening and rammed and worked into

place around the steel after which the opening is closed by the piece

A. After 24 hours the curved side pieces B and C are removed and

the pile is left on the sill D until hard enough to be shifted; a pile

is considered strong enough for driving when about six weeks old.

[Illustration: Fig. 64.--Form for Molding Round Pile with Flattened

Sides.]

_Driving._--Coignet piles at the Bristol work were handled by a

traveling crane. The material penetrated was river mud and they were

driven with a hammer weighing 2 tons gross; in driving the pile head was

encircled by a metal cylinder into which fitted a wooden plunger or

false pile with a bed of shavings and sawdust between plunger and pile

head.

~Molding and Driving Square Piles for a Building Foundation.~--The Dittman

Factory Building at Cincinnati, O., is founded on reinforced concrete

piles varying from 8 to 22 ft. in length. The piles were square in

cross-section, with a 2-in. bevel on the edges; a 16-ft. pile was 10

ins. square at the point and 14 ins. square at the head, shorter or

longer piles had the same size of point, but their heads were

proportionally smaller or larger, since all piles were cast in the same

mold by simply inserting transverse partitions to get the various

lengths. Each pile was reinforced by four ¾-in. twisted bars, one in

each corner, bound together by ¼-in hoops every 12 ins.. The bars were

bent in at the point and inserted in a hollow pyramidal cast iron shoe

weighing about 50 lbs. The concrete was a 1-2-4 stone mixture and the

pile was allowed to harden four weeks before driving. They were cast

horizontally in wooden molds which were removed after 30 hours.

_Driving._--Both because of their greater weight and because of the care

that had to be taken not to shatter the head, it took longer to adjust

and drive one of these concrete piles than it would take with a wooden

pile. The arrangement for driving the piles was as follows: A metal cap

was set over the head of the pile, on this was set the guide cap having

the usual wood deadener and on this was placed a wood deadener about 1

ft. long. The metal cap was filled with wet sand to form a cushion, but

as the pile head shattered in driving the sand cushion was abandoned and

pieces of rubber hose were substituted. With this rubber cushion the

driving was accomplished without material damage to the pile head. The

hammer used weighed 4,000 lbs. and the drop was from 4 to 6 ft. The

blows per pile ranged from 60 up. The average being about 90. In some

cases where the driving was hard it took over 400 blows to drive a

14-ft. pile. An attempt to drive one pile with a 16-ft. drop resulted in

the fracture of the pile.

~Method of Molding and Driving Octagonal Piles.~--The piles were driven in

a sand fill 18 ft. deep to form a foundation for a track scales in a

railway yard. They were octagonal and 16 ins. across the top, 16 ft.

long, and tapered to a diameter of 12 ins. at the bottom. They were also

pointed for about a foot. The reinforcement consisted of four ½-in.

Johnson corrugated bars spaced equally around a circle concentric with

the center of the pile, the bars being kept 1½ ins. from the surface of

the concrete. A No. 11 wire wrapped around the outside of the bars

secured the properties of a hooped-concrete column. The piles were cast

in molds laid on the side. They were made of 1:4½ gravel concrete, and

were seasoned at least three weeks before being driven.

An ordinary derrick pile driver, with a 2,500-lb. hammer falling 18 ft.,

was used in sinking them. A timber follower 6 ft. long and banded with

iron straps at both ends was placed over the head of the pile to receive

directly the hammer blows. The band on the lower end was 10 ins. wide

and extended 6 ins. over the end of the follower. In this 6-in. space a

thick sheet of heavy rubber was placed, coming between the head of the

pile and the follower. Little difficulty was experienced in driving the

piles in this manner, although 250 to 300 blows of the hammer were

required to sink each pile. The driving being entirely through fine

river sand there is every probability that any kind of piles would have

been driven slowly. The heads of the first 4 or 5 piles were battered

somewhat, but after the pile driver crew became familiar with the method

of driving, no further battering resulted and the heads of most of the

piles were practically uninjured.

[Illustration: Fig. 65.--Cross-Section of Chenoweth Rolled Pile.]

[Illustration: Fig. 66.--Diagram Showing Method of Rolling Chenoweth

Pile.]

~Method and Cost of Making Reinforced Concrete Piles by Rolling.~--In

molding reinforced concrete piles exceeding 30 or 40 ft. in length, the

problem of molds or forms becomes a serious one. A pile mold 50 or 60

ft. long is not only expensive in first cost, but is costly to maintain,

because of the difficulty of keeping the long lagging boards from

warping. To overcome these difficulties a method of molding piles

without forms has been devised and worked out practically by Mr. A. C.

Chenoweth, of Brooklyn, N. Y. This method consists in rolling a sheet of

concrete and wire netting into a solid cylinder on a mandril, by means

of a special machine. Fig. 65 is a sketch showing a cross-section of a

finished pile, in which the dotted line shows the wire netting, the

hollow circle is the gas pipe mandril, and the solid circles are the

longitudinal reinforcing bars.

[Illustration: Fig. 67.--Machine for Rolling Chenoweth Piles.]

In making the pile the netting is spread flat, with the reinforcing bars

attached as shown at (a), Fig. 66, and is then covered with a layer of

concrete. One edge of the netting is fastened to the platform, the other

edge is attached to the winding mandril. The winding operation is

indicated by sketch (b), Fig. 66. Fig. 67 shows the machine for

rolling the pile. It consists of a platform and a roll. The platform is

mounted on wheels and is so connected up that it moves back under the

roll at exactly the circumferential speed of the roll; thus the forming

pile is under constant, heavy pressure between the roll and platform.

When the pile has been completely rolled it is bound at intervals by

wire ties; the wire for these ties is carried on spools arranged under

the edge of the platform at intervals of 4 ins. for the first 10 ft.

from the point and of 6 ins. for the remainder of the length. The

binding is done by giving the pile two or three extra revolutions and

then cutting and tying the wire; then by means of a long removable shelf

which contains the flushing mortar, as the pile revolves it becomes

coated on the outside with a covering that protects the ties and other

surface metal. Finally the pile is rolled onto a suitable table to

harden.

An exhibition pile rolled by the process described is 61 ft. long and 13

ins. in diameter. This pile was erected as a pole by hoisting with a

tackle attached near one end and dragging the opposite end along the

ground exactly as a timber pole would be erected. It was also suspended

free by a tackle attached at the center; in this position the ends

deflected 6 ins. Neither of these tests resulted in observable cracks in

the pile. The pile contains eight 1-in. diameter steel bars 61 ft. long,

one 2½-in. pipe also 61 ft. long, 366 sq. ft., or 40.6 sq. yds. ½-in.

mesh 14 B. & S. gage wire netting, and 2 cu. yds. loose concrete. Its

cost for materials and labor was as follows:

Materials--

Gravel, 28.8 cu. ft., at $1 per cu. yd. $ 1.05

Sand, 19.8 cu. ft., at $1 per cu. yd. .73

Cement, 3 bbls., at $1.60 per bbl. 4.80

Netting, 40.6 sq. yds., at 17½ cts. per sq. yd. 7.10

Rods, wire, etc., 1,826 lbs., at 2½ cts. per lb. 45.65

--------

Total $59.33

Mixing 2 cu. yds. concrete, four men one hour, at 15 cts.

per hour $ 0.60

Placing concrete and netting, four men 30 mins., at 15

cts. per hour .30

Winding pile, four men 20 mins., at 15 cts. per hour .20

Removing pile, four men 10 mins., at 15 cts. per hour .10

--------

$1.20

Grand total $60.53

This brings the cost of a pile of the dimensions given to about $1 per

lin. ft.

CHAPTER XI.

METHODS AND COST OF HEAVY CONCRETE WORK IN FORTIFICATIONS, LOCKS, DAMS,

BREAKWATERS AND PIERS.

The construction problem in building concrete structures of massive form

and volume is chiefly a problem of plant arrangement and organization of

plant operations. In most such work form construction is simple and of

such character that it offers no delay to placing the concrete as

rapidly as it can be produced. The same is true of the character of the

structure, it is seldom necessary for one part of the work to wait on

the setting and hardening of another part. As a rule, there is no

reinforcement to fabricate and place and where there is it is of such

simple character as not to influence the main task of mixing, handling,

and placing concrete. Stated broadly, the contractor in such work

generally has a certain large amount of concrete to manufacture,

transport and deposit in a certain space with nothing to limit the

rapidity of these operations, except the limitations of plant capacity

and management. Installation and operation of mixing and conveying

plant, then are matters to be considered carefully in heavy concrete

work.

In the following sections we have given one or more examples of nearly

every kind of heavy concrete work excepting bridge foundations and

retaining walls, which are considered in Chapters XII and XIII, and

except rubble concrete work, which is considered in Chapter VI. In each

case so far as the available records made it possible, we have given an

account of the plant used and of its operation.

~FORTIFICATION WORK.~--Concrete for fortification work consists very

largely of heavy platforms and walls for gun foundations and enclosures

and of heavily roofed galleries and chambers for machinery and

ammunition. The work is very massive and in the majority of cases of

simple form. A large number of data are to be found in the reports of

the Chief of Engineers, U. S. A., on all classes of fortification work,

but the manner in which they are recorded makes close analysis of

relative efficiencies of methods or of relative costs almost impossible.

The following data are given, therefore, as examples that may be

considered fairly representative of the costs obtained in fortification

work done under the direction of army engineers; these data are not

susceptible of close analysis because wages, working force, outputs,

etc., are nearly always lacking.

~Gun Emplacements, Staten Island, N. Y.~--The work comprised 5,609 cu.

yds. of concrete in two 12-in. gun emplacements, and 3,778 cu. yds. of

concrete in two 6-in. gun emplacements. Concrete was mixed in a

revolving cube mixer with the exception of 809 cu. yds. in the 6-in.

emplacements which were mixed by hand at a cost of 56 cts. more per

cubic yard than machine mixing cost. The body of the concrete was a

1-3-5 Portland cement, beach sand and broken trap rock mixture. The

floors and upper surface of the concrete had a pavement consisting of 6

ins. of 1-3-5 concrete surfaced with 2 ins. of 1-3 mortar. Wages are not

given, but for the time and place should have been about $1.50 per

8-hour day for common labor. The cost of materials was:

Alpha Portland cement, per bbl. $1.98

Broken trap rock, per cu. yd. 0.81

12-in. emplacement, hauling sand per cu. yd. 0.175

6-in. emplacement, hauling sand per cu. yd. 0.20

The cost of the concrete in place was as follows:

12-in., per 6-in., per

Body Concrete-- cu. yd. cu. yd.

Cement, at $1.98 per bbl. $2.546 $2.546

Broken stone, at 81 cts. per cu. yd. 1.041 1.041

Sand, at 17½ and 20 cts. per cu. yd. 0.225 0.257

Receiving and storing materials at 11.6 cts. per

cu. yd. and 8.4 cts. per bbl. 0.149 0.180

Mixing, placing and ramming 0.879 1.110

Forms, lumber and labor 0.477 0.950

Superintendence and miscellaneous 0.190 0.150

------ ------

Total $5.507 $6.234

Concrete Pavement--

Materials $2.97 $3.06

Labor 4.63 4.72

------ ------

Total $7.60 $7.78

[Illustration: Fig. 68.--Sketch Plans of Concrete Making Plant for

Mortar Battery Platform.]

~Mortar Battery Platform, Tampa Bay, Fla.~--The platform contained 8,994

cu. yds. of concrete composed of a mixture of Portland cement, sand,

shells and broken stone. The broken stone and cement were brought in by

vessel and the sand and shells were obtained from the beach near by. The

plant for the work was arranged as shown by the sketch, Fig. 68. Sand,

stone and shells were stored in separate compartments in the storage

bins. Box cars, divided into compartments of such size that when each

was filled with its proper material, the car would contain the proper

proportions for one batch of concrete, were pushed by hand under the

several compartments of the bin in succession until charged; then they

were hooked to a cable and hauled to the platform over the mixer and

dumped. The charge was then turned over with shovels and shoveled into

the hopper of a continuous mixer, located beneath. Two cars were used

for charging the mixer, running on separate tracks as shown. The mixer

discharged into buckets set on flat cars, which were hauled by mules

under the cableway, which then lifted and dumped the bucket and returned

it empty to the car. By using three bucket cars, one was always ready

to receive the mixer discharge as soon as the preceding one had been

filled, so that the mixer operated continuously. The cableway had a

working span of 270 ft., the cable being carried by traveling towers 69

ft. high; the cableway was very easily operated back and forth along the

work. The cableway complete, with 497 ft. of six-rail track for each

tower, cost $4,700. The cost of materials and labor for the 8,994 cu.

yds. of concrete was as follows:

Per cu. yd.

1 bbl. cement at $2.46 $2.46

0.89 cu. yd. stone, at $2.95 2.622

0.315 cu. yd. shells, at $0.45 0.142

0.51 cu. yd. sand, at $0.12 0.062

Mixing and placing 0.693

-------

Total $5.979

The above batch tamped in place to 30 cu. ft., or 1-1/9 cu. yds., which

gives the cost as follows:

Per cu. yd.

Cost of concrete tamped in place $5.381

Cost of form work 0.370

-------

Total cost $5.751

In the preceding prices of cement and stone, 59 cts. and 29 cts. per

cubic yard, respectively, are included for storage. The costs of sand

and shells are costs of screening and storing. Rough lumber for forms

cost $10.25, and dressed lumber $12.75 per M. ft. B. M.

~Emplacement for Battery, Tampa Bay, Fla.~--The emplacement contained

6,654 cu. yds. of Portland cement, sand, shells and broken stone

concrete. The plant arrangement is shown by Fig. 69. The sand and shells

were got near the site, using an inclined cableway running from a 40-ft.

mast near the mixer to a deadman at the shell bank. All the sand for the

fill around the emplacement was obtained in the same way. The other

materials were brought by vessel to a wharf, loaded by derrick onto cars

operated by an endless cable, and taken to the work. The storage bins

and mixing plant were operated much like those for the mortar battery

work, previously described. A cube mixer was used, and the concrete was

handled from it to the work by a crane derrick covering a circle of 100

ft. in diameter. The cost of materials and concrete was as follows:

Cement, plus 7 cts. for storage per bbl. $ 2.532

Stone, plus 38 cts. for storage per cu. yd. 3.047

Shells, excavating and storage. 0.481

Sand, excavating and storage. 0.250

Lumber, rough per M. ft. B. M. 10.25

Lumber, dressed per M. ft. B. M. 12.75

[Illustration: Fig. 69.--Sketch Plans of Concrete Making Plant for

Battery Emplacement.]

A batch made up as follows, tamped in place to a volume of 30 cu. ft. or

1-1/9 cu. yds.:

1 bbl. cement, at $2.532. $ 2.532

0.315 cu. yd. shells, at $0.481. 0.151

0.51 cu. yd. sand, at $0.25. 0.130

0.89 cu. yd. stone, at $3.047. 2.710

Mixing and placing. 0.761

--------

Total for 30 cu. ft. $ 6.284

This gives a cost per cubic yard of concrete in place as follows:

Concrete in place, per cu. yd. $ 5.655

Forms, per cu. yd. of concrete. 0.220

--------

Total cost of concrete per cu. yd. $ 5.875

~United States Fortification Work.~--The following methods and cost of

mixing and placing concrete by hand and by cubical mixers is given by

Mr. L. R. Grabill for U. S. Government fortification work done in 1899.

_Hand Mixing and Placing._--The work was done by contract, using a 1

cement, 2 sand, 2 pebbles and 3 stone mixture turned four times. A board

large enough for three batches at a time was used; one batch was being

placed, one being mixed and one being removed at the same time so that

the mixers moved without interval from one to the other. Two gangs were

worked, each mixing 64 batches of 0.75 cu. yd., or 48 cu. yds. of

concrete per day at the following cost:

Per Per

Hand Mixing 9,000 Cu. Yds.-- day. cu. yd.

6 men wheeling materials $ 7.50 $0.16

8 men mixing 10.00 0.21

8 men wheeling away 10.00 0.21

6 men placing and ramming 7.50 0.16

1 pump man 1.25 0.02

1 waterboy 1.00 0.02

1 foreman 2.00 0.04

------- -------

Totals $39.25 $0.82

The entire cost of plant for this work was about $500.

_Machine Mixing and Placing._--The concrete was mixed in a 4-ft. cubical

mixer operated by a 12 hp. engine which also hauled the material cars up

the incline to the mixer. These cars passed by double track under the

material bins where the compartments of the car body were filled through

trap doors; they then passed the cement house where the cement was

placed on the load, then up the incline to the mixer and dumped, and

then empty down an opposite incline. Seven turns of the mixer mixed the

charge which was discharged into iron tubs on cars hauled by horses to

two derricks whose booms covered the work. One gang by day labor mixed

and placed 168 batches of 0.7 cu. yd., or 117.6 cu. yds. per day at the

following cost:

Per Per

Machine Mixing 4,000 Cu. Yds.-- day. cu. yd.

32 men at $1.25 $40.00 $0.34

1 pumpman 1.25 0.01

1 teamster and horse 2.00 0.02

2 waterboys at $1 2.00 0.02

1 engineman 1.70 0.02

1 derrickman 1.50 0.01

1 fireman 1.50 0.01

1 foreman 2.88 0.03

Fuel (cement barrels largely) 1.25 0.01

------- -------

Totals $54.08 $0.47

The cost of the plant was about $5,000.

[Illustration: Fig. 70.--Concrete Making Plant for Constructing Lock

Walls, Cascades Canal.]

~LOCK WALLS, CASCADES CANAL.~--Four-fifths or 70,000 cu. yds. of lock

masonry was concrete, the bulk of which was mixed and deposited by the

plant shown by Fig. 70. The concrete was Portland cement, sand, gravel

and broken stone. Cement was brought in in barrels by railway, stored

and tested; from the store house the barrels were loaded onto cars and

taken 250 ft. to a platform onto which the barrels were emptied and from

which the cement was shoveled into the cement hopper and chuted to cars

which took it to the charging hopper of the mixer. The stone was crushed

from spalls and waste ends from the stone cutting yards, where stone for

wall lining and coping and other special parts was prepared. These

spalls and ends were brought in cars and dumped into the hopper of a

No. 5 Gates crusher, with a capacity of 30 tons per hour. From the

crusher the stone passed to a 2½-in. screen, the pieces passing going to

a bin below and the rejections going to a smaller Blake crusher and

thence to the bin. The dust and small particles were not screened out.

The sand and gravel were obtained by screening and washing pit gravel.

The gravel was excavated and brought in cars to the washer. This

consisted of a steel cylinder 2 ft. 6½ ins. in diameter and about 18 ft.

long, having an inclination of 1 in. per foot. An axial gudgeon

supported the cylinder at the lower end and it rested on rollers at the

other end and at an intermediate point. The gravel was fed by hopper and

chute into the upper end and into this same end a 3-in. perforated pipe

projected and extended to about mid-length of the cylinder. The cylinder

shell was solid and provided with internal fins for about half its

length from the feed end. For the remainder of its length nearly to the

end, the shell was perforated with 2½-in. holes. For a length of 4 ft.

beyond mid-point it was encircled by a concentric screen of 1/8-in.

holes, and this screen for 3 ft. of its length was encircled by another

screen of 30 meshes to the inch. The pit mixture fed into the cylinder

was gradually passed along by the combined inclination and rotation,

being washed and screened in the process. The sand fell into one bin and

the gravel into another, and the waste water was carried away by a

flume. The large stones passed out through openings at the lower end of

the shell and were chuted into cars. The cars came to the mixer as

clearly shown by Fig. 70.

The stone and gravel cars were side dump and the cement car was bottom

dump. The mixers were of the cube type 4 ft. on each edge and operated

by a 7×12-in. double cylinder engine at nine revolutions per minute. The

usual charge was 32 cu. ft. of the several ingredients, and it was found

that 15 revolutions requiring about 1½ minutes were sufficient for

mixing. The average work of one mixer was 17 batches or about 13 cu.

yds. per hour, but this could be speeded up to 20 batches per hour when

the materials were freely supplied and the output freely removed. Two

cars took the concrete from the mixer to the hopper, from which it was

fed to the work by chute. The hopper was mounted on a truck and the

chute was a wrought iron cylinder trussed on four sides and having a

45° elbow at the lower end to prevent scattering. The chute fed into a

car running along the wall and distributing the material. It was found

impracticable to move the chute readily enough to permit of feeding the

concrete directly into place. As the concreting progressed upward the

trestle was extended and the chute shortened. It was found that wear

would soon disable a steel chute so that the main trussed cylinder had a

smaller, cheaply made cylinder placed inside as a lining to take the

wear and be replaced when necessary.

The plant described worked very successfully. Records based on 9,614.4

cu. yds. of concrete laid, gave the following:

Cu. yds.

Concrete mixed by hand 1,777.0

Concrete mixed by machine 7,837.4

Total concrete laid 9,614.4

Concrete placed by derricks 2,372.0

Concrete placed by chute 7,242.4

Concrete 1-2-4 mixture 156.0

Concrete 1-3-6 mixture 1,564.0

Concrete 1-4-8 mixture 6,892.0

The average mixture was 1 cement, 3.7 sand, 4.8 gravel and 2.6 broken

stone. The average product was 1.241 cu. yds. concrete per barrel of

cement and 1.116 cu. yds. of concrete per cubic yard of stone and

gravel. The average materials for 1 cu. yd. of concrete were: Cement

0.805 bbl., sand 0.456 cu. yd., gravel 0.579 cu. yd., and stone 0.317

cu. yd.

The cost of these 9,614.4 cu. yds. of concrete in place was:

Hand Mixed and Placed by Derrick-- Per cu. yd.

Labor mixing 1,777 cu. yds $1,072

Repairs, fuel, etc 0.016

-------

Total cost mixing $1,088

Labor placing 2,372 cu. yds. 0.6025

Fuel, tramways, etc. 0.1958

-------

Total cost placing $0.7983

Machine Mixed and Placed by Chute--

Labor mixing 7,837 cu. yds. $0.388

Repairs, fuel, etc 0.046

------

Total cost mixing $0.434

Labor placing 7,242 cu. yds 0.414

Fuel, tramways, etc. 0.045

------

Total cost placing $0.459

Materials and Supplies 9,614 cu. yds.--

Timbering $0.145

Cement 3.289

Sand and gravel 1.073

Broken stone 0.536

Cement testing, repairs, etc. 0.223

------

Total $5,266

Plant and Superintendence, 9,614 Cu. Yds.--

Engineering, superintendence, repairs, etc. $1,508

20% cost of plant 0.165

------

Total $1,673

The comparative cost of hand and machine mixing and handling was thus:

Item-- Hand. Machine.

Mixing per cu. yd. $1.088 $0.434

Placing per cu. yd. 0.798 0.459

Materials, etc., per cu. yd. 5.466 5.466

Plant, etc., per cu. yd. 1.673 1.673

------ ------

Totals $9.025 $8.032

The average total costs of all the concrete placed were:

Mixing per cu. yd. $0.555

Placing per cu. yd. 0.543

Materials per cu. yd. 5.266

Plant, etc., per cu. yd. 1.673

------

Total $8.037

~LOCKS, COOSA RIVER, ALABAMA.~--The following methods and costs are given

by Mr. Charles Firth for constructing lock No. 31 for the Coosa River

canalization, Alabama. This lock is 420 ft. long over all, 322 ft.

between quoins, 52 ft. clear width, 14.7 ft. lift and 8 ft. depth of

water on sills; it contained 20,000 cu. yds. of concrete requiring

21,500 bbls. cement, half Alsen and half Atlas.

Figure 71 shows the concrete mixing plant, consisting of two 4×4 ft.

cube mixer, driven by a 10×16-in. engine. The top floor of the mixer

house stored the cement, 2,000 bbls. The concrete was a 1-3-5½ stone

mixture. Each mixer charge consisted of 3 cu. ft. cement, 9 cu. ft. sand

and 16.5 cu. ft. stone; the charge was turned over four times before and

six times after watering at a speed not exceeding eight revolutions per

minute. The average output of the plant was 200 cu. yds. per 8-hour day,

or 100 cu. yds. per mixer, but it was limited by the means for placing.

[Illustration: Fig. 71.--Concrete Mixing Plant for Lock Construction,

Coosa River, Alabama.]

The concrete was mixed dry, deposited in 6 to 8-in. layers, and rammed

with 30-lb. iron rammers with 6-in. square faces. For all exposed

surfaces a 6-in. facing of 1-3 mortar was placed by setting 2×12-in.

planks 4 ins. from the laggings, being kept to distance by 2×4-in.

spacers, placing and ramming the concrete behind them, then withdrawing

them, filling the 6-in. space with mortar and tamping it to bond with

the concrete. The walls were carried up in lifts, each lift being

completed entirely around the lock before beginning the next; the first

lift was 10.7 ft. high and the others 6 ft., except the last, which was

4.5 ft., exclusive of the 18-in. coping. The coping was constructed of

separately molded blocks 3 ft. long, made of 1-2-3 concrete faced with

1-1 mortar and having edges rounded to 3 ins. radius.

In constructing the forms a row of 6×8-in. posts 24 ft. long and 5 to 7

ft. apart was set up along the inside of each wall and a similar row of

posts 12 ft. long was set up along the outside. From the tops of the

short posts 6×8-in. caps reached across the wall and were bolted to the

long posts; these caps carried the stringers for the concrete car

tracks. The lagging consisted of 3×10-in. planks dressed on all sides.

The backs of the walls were stepped and as each step was completed the

rear 12-ft. posts were lifted to a footing on its top and carried in the

necessary distance. The front posts remained undisturbed until the wall

was completed. The lagging was moved up as the filling progressed. As no

tie bolts were permitted, these forms required elaborate bracing.

From the mixing plant, which was located on the bank above reach of

floods, the concrete cars were dropped by elevator to the level of the

track over the walls and then run along the wall and dumped onto

platforms inside the forms and just below the track. This arrangement

was adopted, because it was found that even a small drop separated the

stone from the mortar. The concrete was shoveled from the platforms to

place and rammed. The cars were bottom dumping with a single door hinged

at the side; this door when swinging back struck the track stringers and

jarred the form so that constant attention was necessary to keep it in

line. It would have been much better to have had double doors swinging

endwise of the car. Another point noted was that unless the track was

high enough to give good head room at the close of a lift the placing

and ramming were not well done.

The cost of 8,710 cu. yds. of concrete placed during 1895 by day labor

employing negroes at $1 per 8-hour day was as follows per cubic yard:

1 bbl. cement $2.48

0.88 cu. yd. stone at $0.76 0.67

0.36 cu. yd. sand at $0.34 0.12

Mixing, placing and ramming 0.88

Staging and forms 0.42

----

Total $4.57

~LOCK WALLS, ILLINOIS & MISSISSIPPI CANAL.~--The locks and practically all

other masonry for the Illinois & Mississippi Canal are of concrete. The

following account of the methods and cost of doing this concrete work is

taken from information published by Mr. J. W. Woermann in 1894 and

special information furnished by letter. The decision to use concrete

was induced by the fact that no suitable stone for masonry was readily

available (the local stone was a flinty limestone, usually without bed,

or, at best, in thin irregular strata, and cracked in all directions

with the cracks filled with fire clay) while good sand and gravel and

good stone for crushing were plentifully at hand. The concrete work done

in 1893-4 comprised dam abutments, piers for Taintor gates and locks.

_Dam Abutments._--Four dam abutments were constructed, three of which

were L-shaped, with sides next to the river 40 ft. long and sides

extending into the banks 20 ft. long; the top thickness was 3 ft., the

faces were vertical and the backs stepped with treads of 14 to 16 ins.,

and the width of base was 0.4 of the height. Each of these abutments was

built in four 30-cu. yd. sections, each section being a day's work. The

forms consisted of 2×8-in. planks, dressed on both sides, 2×8-in. studs

spaced 2 ft. on centers and 4×6-in. braces. For the first two of the

four abutments, the forms were erected in sections, the alternate

sections being first erected and filled. When these sections had

hardened the forms were shifted to the vacant sections and lined up to

and braced against the completed sections. This method did not give well

aligned walls, so in subsequent work the forms were erected all at once.

The concrete was mixed by hand. The sand and cement were mixed dry,

being turned four times and spread in a layer Pebbles and broken stone

previously wetted were spread over the sand and cement and the whole

turned four times, the last turn being into wheelbarrows; about five

common buckets of water were added during the mixing. The mixture sought

was one that would ram without quaking. Two forms of rammers were used;

for work next to forms a 4×6-in. rammer and for inside work 6-in

diameter circular rammer weighing 20 lbs. The gang mixing and placing

concrete consisted usually of:

Item. Per Day. Per Cu. Yd.

2 handling cement and sand $ 3.00 $0.10

3 filling barrows with aggregate 4.50 0.15

8 mixing concrete 12.00 0.40

2 shoveling concrete into barrows 3.00 0.10

5 wheeling concrete to forms 7.50 0.25

1 spreading concrete 1.50 0.05

5 tamping concrete 7.50 0.25

------ -----

Total, 26 men $39.00 $1.30

These cubic yard costs are based on 30 cu. yds. of wall completed per

8-hour day. The cost in detail of two abutments containing 254 cu. yds.

was per cubic yard as follows:

Item. Per Cu. Yd.

1.65 bbls. Portland (Germania) cement $ 5.60

0.5 cu. yd. crushed stone 2.07

0.24 cu. yd. gravel 0.59

0.53 cu. yd. sand 0.24

Lumber, forms, warehouses, platforms[D] 0.55

Carpenter work[E] ($9 per M.) 1.10

Mixing and placing 1.47

20 per cent. first cost of plant 0.31

Engineering and miscellanies 0.31

------

Total $12.24

[Footnote D: Charging ¼ of first cost of $18 per M. ft.]

[Footnote E: Carpenters $3.50, laborers $1.50 per day; there was one

laborer to two carpenters.]

The large amount of cement 1.65 bbls. per cubic yard was due to facing

the abutments with 8 ins. of 1-2 mortar. The concrete in the body of the

wall was 1 cement, 2 sand, 2 gravel and 2 broken stone mixture. A dry

mixture was used and this fact is reflected in the cost of ramming, 25

cts. per cu. yd. The cost of mixing was also high.

[Illustration: Fig. 72.--Concrete Mixing Plant for Lock Walls, Illinois

& Mississippi Canal.]

_Piers for Taintor Gates._--The masonry at this point consisted of three

piers 6×30 ft., and two abutments 30 ft. long, 6 ft. thick at base and 4

ft. thick at top, with wing walls; it amounted to 460 cu. yds. The feet

of the inclined braces were set into gains in the horizontal braces and

held by an 8-in. lag screw; after the posts were plumbed a block was

lag-screwed at the upper end of each brace. These forms proved entirely

satisfactory. The cost of the work per cubic yard was as follows:

Item. Per Cu. Yd.

1.45 bbls. Portland cement $4.330

0.55 cu. yd. crushed stone 0.604

0.252 cu. yd. pebbles 0.328

0.465 cu. yd. sand 0.419

40,000 ft. B. M. lumber (¼ cost of $16 per M.) 0.348

Carpenter work on forms 0.780

Mixing and placing concrete 1.909

20 per cent. cost of plant 0.090

Miscellaneous 0.182

-----

Total $8.99

_Mixing Plant._--The concrete for all the lock work of 1893-4 was mixed

by the plant shown by Figs. 72 and 73. The mixer plant proper consisted

of a king truss carried by two A-frames of unequal height; under the

higher end of the truss was a frame carrying a 4-ft. cubical mixer and

under the lower end a pit for a charging box holding 40 cu. ft. This

charging box was hoisted by ½-in. steel cable running through a pair of

double blocks as shown; the slope of the lower chord of the truss was

such that the cable hoisted the box and carried it forward without the

use of any latching devices. On two sides of the pit were tracks from

the sand and stone piles and on the other two sides were the cement

platform and water tank. The charging box dumped into the hopper above

the mixer and the mixer discharged into cars underneath. A 15-HP. engine

operated the hoist by one pulley and the mixer by the other pulley. Nine

revolutions of the mixer made a perfect mixture. The plant as

illustrated was slightly changed as the result of experience in

constructing the guard lock. The charging hopper was lowered 6 ins. and

the space between the mixer and lower platform reduced by 9 ins.;

diagonal braces were also inserted under the timbers carrying the mixer

axles. This plant cost for framing and erection $300 and for machinery

delivered $706. The crushing plant shown by Fig. 73 consisted of a No. 2

Gates crusher delivering to a bucket elevator.

[Illustration: Fig. 73.--Stone Crushing Plant for Lock Walls, Illinois &

Mississippi Canal.]

[Illustration: Fig. 74.--Forms for Guard Lock, Illinois & Mississippi

Canal.]

_Guard Lock._--The forms employed in constructing the guard lock are

shown by Fig. 74, and in this drawing the trestle and platform for the

concrete cars are to be noted. The walls were concreted in sections. A

batch of concrete consisted of 1 bbl. cement, 10 cu. ft. sand and 20 cu.

ft. crushed stone. The average run per 8-hour day was 40 batches of

facing and 60 batches concrete, representing 100 bbls. cement. The gang

worked was as follows:

Duty. No. Men. P. C. Cost.

Handling cement 3 5.26

Filling and pushing sand car 5 8.77

Filling and pushing stone car 9 15.79

Measuring water 1 1.75

Dumping bucket on top platform 3 5.26

Opening and closing door of mixer 1 1.75

Operating friction clutch 1 1.76

Attending concrete cars under mixer 1 1.76

Dumping cars at forms 2 3.51

Spreading concrete in forms 3 5.26

Tamping concrete in forms 10 17.54

Mixing mortar for facing 6 10.53

Finishing top of wall 2 3.51

Hauling concrete cars with 1 horse 1 3.51

Engineman operating hoist 1 3.51

Engineman operating engine 1 3.51

Foreman in charge of forms 1 3.51

General foreman 1 3.51

-- ------

Total 52 100.00

The percentages of cost in this statement have been calculated by the

authors upon the assumption that each laborer received one-half as much

wages as each engineman, foreman and horse and driver per 8 hours, which

would make the total daily wages equivalent to the wages of 57 men.

Wages of common labor were $1.50 per day. Considering the size of the

gang the output of 40 batches of mortar and 60 batches of concrete per

day was very small. The total yardage of concrete in the guard lock was

3,762 cu. yds., 2,212 cu. yds. in the walls and 1,550 cu. yds. in

foundations, culverts, etc. Its cost per cubic yard was made up as

follows:

Item. Total. Per Cu. Yd.

5,246 bbls. Portland cement $15,604}

} $4.170

152 bbls. natural cement 84}

2,910 cu. yds. stone 2,901 0.771

126 cu. yds. pebbles 113}

} 0.401

1,970 cu. yds. sand 1,398}

145,000 ft. B. M. lumber (¼th cost) 659 0.175

Iron for forms, trestles, etc. 90 0.024

Coal, oil, miscellaneous 327 0.087

Carpenter work 2,726 0.724

Mixing and placing concrete 6,693 1.780

Pumping, engineering, misc. 742 0.197

20 per cent of plant 550 0.146

------- ------

Total $31,887 $8.475

[Illustration: Fig. 75.--Forms for Regular Lock Walls, Illinois &

Mississippi Canal.]

_Lock No. 37._--The character of the forms used in constructing the lock

walls is shown by Fig. 75. The walls were built in sections and work was

continuous with three 8-hour shifts composed about as specified for the

guard lock work except that one or two men were added in several places

making the total number 58 men. The average output per shift was 65

batches of concrete and 31 batches of facing mortar. The cost of the

work, comprising 3,767 cu. yds., was as follows:

Item. Total. Per Cu. Yd.

4,564 bbls. Portland cement $14,181 $3.764

2,460 cu. yds. crushed stone 4,521 1.200

250 cu. yds. pebbles 325 0.086

1,750 cu. yds. gravel 2,335 0.619

450 cu. yds. sand 450 0.119

180,000 ft. B. M. lumber (¼th cost) 990 0.236

Fuel, light, repairs, etc. 1,171 0.311

Carpenter work 2,526 0.671

Pumping 270 0.071

Mixing and placing concrete 6,170 1.632

20% cost of plant 730 0.193

------- ------

Total $33,669 $8.902

_Lock No. 36._--The forms used were of the construction shown by Fig.

75. Three shifts were worked, each composed as specified for the guard

lock, except that the number of tampers and spreaders was doubled,

bringing the gang up to 65 men. The average output per gang per shift

was 76 batches of concrete and 35 batches of facing mortar. The cost of

2,141 cu. yds. of concrete in this lock was as follows:

Item. Total. Per Cu. Yd.

3,010 bbls. Portland cement $9,057 $4.23

1,377 cu. yds. broken stone 1,922 0.90

393 cu. yds. pebbles 354 0.17

459 cu. yds. gravel 310 0.15

500 cu. yds. sand 889 0.42

150,000 ft. B. M. lumber (¼th cost) 600 0.28

Fuel, light, repairs, etc. 253 0.68

Carpenter work 1,472 0.11

Mixing and placing concrete 3,897 1.82

20% cost of plant 650 0.30

------- -----

Total $19,404 $9.06

The preceding data, made public by Mr. Woermann in 1894, are

supplemented by the following information prepared for the authors:

"If any criticism was to be made of the concrete masonry erected in 1893

and 1894, it would probably be to the effect that it was too expensive.

The cost of the masonry erected during those two seasons was $8 to $9

per cu. yd. Our records showed that about 45 per cent. of this cost was

for Portland cement alone, and moreover, that 40 per cent. of the total

cement used at a lock was placed in the 8-in. facing and 5-in. coping.

So in the seven locks erected in 1895 on the eastern section, the facing

was reduced to 3 ins. and the proportions changed from 1-2 to 1-2½.

"In 1898 this cost received another severe cut, and Major Marshall's

instructions stated that the facing should not exceed 1½ ins. in

thickness nor be less than ¾-in., while the layer of fine material on

top of the coping was to be only sufficient to cover the stone and

gravel. The amount of sand was again increased so that the proportions

were 1-3.

"The cost of the Portland cement concrete was likewise cheapened by

increasing the amount of aggregates. On the earlier work the proportions

were 1-2-2-3, while on the work in 1898 the proportions were 1-4-4. The

cost of the walls was further cheapened by using Utica cement in the

lower steps of the wall, with 2 ft. of Portland cement concrete on the

face. The proportions used in the Utica cement concrete were 1-2½-2½.

This lower step is one-third of the height, or about 7 ft.

[Illustration: Fig. 76.--Sketch Showing Method of Attaching Lagging to

Studs, Illinois & Mississippi Canal.]

"The forms were of the same character as those used on the first locks,

except that for lining the inner face, 3×10-in. hard pine planks were

substituted for the 4×8-in. white pine. The hard pine was damaged less

by the continuous handling, and the cost was practically the same. There

was also an important change made in the manner of fastening the plank

to the 8×10-in. posts. A strip 1¾ ins. square was thoroughly nailed to

each post, once for all, with 20d. spikes, and the planking was then

nailed from the outside, as shown in Fig. 76. This kept the face of the

plank in a perfectly smooth condition, and prevented the formation of

the little knobs on the face of the concrete which represented all the

old nail holes. This style of forming was also easier to take apart

after the setting of the concrete. Rough pine planks, 2×12-in., were

used for the back of the form, the same as before.

"In order to keep ahead of the concrete force it was necessary to use

two gangs of carpenters, erecting the forms for the next two locks. Each

gang consisted of about 20 carpenters (at $2.25) and 10 helpers (at

$1.50); but men were transferred from one to the other, according to the

stage of completion of the two locks. In addition to these two gangs,

two carpenters were on duty with each concrete shift to put in the steps

in the back of the forms. Sufficient lumber was required for the forms

for three complete locks, and 14 locks (Nos. 8 to 21) were built.

"The same type of mixer has been used as on the earlier work at Milan,

namely, a 4-ft. cubical steel box mounted on corners diagonally

opposite. On account of the greater number of locks to be built on the

eastern section, however, two mixers were found necessary, so that while

the concrete force was at work at one lock, the carpenters and helpers

were erecting the mixer at the next lock. The facing was mixed by hand.

After turning over the dry cement and sand at least twice with shovels,

the mixture was then cast through a No. 5 sieve, after which the water

was incorporated slowly by the use of a sprinkling can so as to avoid

washing. The secret of good concrete, after the selection of good

materials, is thorough mixing and hard tamping. Each batch of concrete,

consisting of about 1.2 cu. yds. in place, was turned in the mixer for

not less than 2 mins. at the rate of 9 revolutions per minute. The

amount of tamping is indicated by the fact that about 16 men out of 72

on each shift did nothing but tamp. The rammers used were 6 ins. square

and weighed 33 lbs. The bottom of the rammer consisted of three ridges,

each 1-in. in height, so as to make more bond between the successive

layers.

"On the eastern section the top of the lock walls was higher above the

ground, as a rule, than at the Milan locks, and the cars were run up an

incline with a small hoisting engine. A 15-HP. portable engine and

boiler operated the bucket hoist from one pulley, the mixer from the

other pulley, and also furnished steam for the hoist which pulled the

cars up the incline. The incline made an angle of about 30° with the

ground. The practice of carrying on two sections at once was continued

the same as on the western section. Each main wall was systematically

divided into 11 sections, making each section about 20 ft. long. The

corners of the coping were dressed to a quadrant of about 3 ins. radius

with a round trowel like those used on cement walks. In fact, the whole

method of finishing the coping was the same as is used on concrete

walks. The mortar was put on rather wet and then allowed to stand for

about 20 mins. before finishing. This allowed the water to come to the

surface and prevented the formation of the fine water cracks which are

sometimes seen on concrete work. After its final set the coping was

covered with several inches of fine gravel which was kept wet for at

least a week.

"The last concrete laid during the season was in November, on Lock No.

21, and Aqueducts Nos. 2 and 3. Portions of these structures were built

when the temperature was below freezing. The water was warmed to about

60° or 70° F., by discharging exhaust steam into the tank. Salt was used

only in the facing, simply sufficient to make the water taste saline.

The maximum amount used on the coldest night when the temperature was

about 20° F. was 1½ per cent.

The concrete force on each shift was as follows:

Men.

Filling and pushing stone car 10

Filling and pushing gravel car 8

Measuring cement 3

Measuring water and cleaning bucket 2

Dumping bucket on top platform 2

Operating mixer 2

Loading concrete cars 1

Pushing and dumping cars on forms 3

Switchmen on forms 2

Spreading concrete in forms 12

Tamping concrete in forms 16

Mixing facing 3

Water boys 2

--

Total laborers 66

Operating hoists 2

Finishing coping 2

Fireman 1

Sub-overseers 2

Overseer 1

--

Total force 74

The cost of material and labor at Lock No. 15 (10-ft. lift), which

contains 2,559 cu. yds. of concrete, was as follows:

Materials. Per cu. yd.

0.56 bbl. Portland cement (0.96 per cu. yd.) $1.42

0.64 bbl. Utica cement (1.58 per cu. yd.) .30

0.58 cu. yd. stone 1.15

0.60 cu. yd. gravel .52

14 ft. B. M. lumber[F] at $15 per M. .21

0.6 lb. spikes .01

Coal (10 tons in all, at $1.70) .01

0.35 gal. kerosene .03

-----

Total materials $3.65

Labor.

Erecting forms ($7 per M.) .45

Removing forms ($2 per M.) .13

Erecting and removing mixer ($161) .06

Loading and unloading materials at yards and lock sites .23

Track laying ($86) .03

Train service (narrow gage road) .09

Delivering materials to mixer .28

Mixing concrete .11

Depositing concrete .21

Tamping concrete .21

Mixing, depositing and tamping, 69 cu. yds. face mortar

($160) .23

General construction ($553) .22

-----

Total labor $2.25

[Footnote F: The lumber was used nearly five times, which accounts for

its low cost per cu. yd.]

There were 1,430 cu. yds. of Portland cement concrete. 69 cu. yds. of

Portland cement mortar facing, and 1,059 cu. yds. of Utica cement

concrete. The Portland concrete cost $6.43 per cu. yd.; the Utica

concrete, $4.77 per cu. yd. The following is the cost of labor on Lock

No. 20 (11-ft. lift.; 2,750 cu. yds.):

Per cu. yd.

Erecting forms ($7 per M.) $.434

Removing forms ($1.70 per M.) .113

Erecting and removing mixer ($151) .058

Loading and unloading at yards, lock sites, etc. .614

Tracks .024

Train service (narrow gage) .016

Pumping .114

Delivering material to mixer .288

Mixing concrete .134

Depositing concrete .205

Tamping concrete .192

Mixing, depositing and tamping, 85 cu. yds. face

mortar .071

General construction .246

------

Total $2.509

~COST OF HAND MIXING AND PLACING, CANAL LOCK FOUNDATION.~--Mr. Geo. P.

Hawley gives the following record of mixing and placing 4,000 cu. yds.

of 1-4½ gravel concrete for the foundation of a lock constructed for the

Illinois and Mississippi Canal in 1897. The concrete was mixed on

14×16-ft. board platforms, from which it was shoveled directly into

place. The materials were brought to the board in wheelbarrows. Two

boards were used, the usual gang for each being 4 men wheeling gravel, 4

men mixing, 1 man sprinkling, 2 men depositing and leveling and 2 men

tamping. The two gangs were worked against each other. Ten hours

constituted a day's work, and the average time and cost per cubic yard

for mixing and placing were:

Cts.

Foreman, 0.21 hr., at 30 cts 6.30

Laborers, 3.339 hrs., at 15 cts 50.09

Pump runner, 0.129 hr., at 20 cts 3.58

Water boy, 0.087 hr., at 7½ cts 0.65

-----

Total labor per cu. yd., cents. 60.62

~BREAKWATER AT MARQUETTE, MICH.~--The breakwater extends out from the

shore and consists of a prism of concrete resting on timber cribs filled

with stone. Originally the cribs carried a timber superstructure; this

was removed to give place to the concrete work. A typical cross-section

of the concrete prism is shown by Fig. 77; the prism is 23 ft. wide on

the base. Farther in shore the base width was reduced to 20 ft., and in

the shore section the prism was changed to a triangular trapezoid by

continuing the first slope to the bottom cutting off the berm and second

slope. The wooden structure was removed to a level 1 ft. below mean low

water and on it a concrete footing approximately 2 ft. thick was

constructed for the prism proper. This footing reached the full width of

the crib and was constructed in various ways during the 5 years through

which the work continued. At first the footing concrete was deposited

loose under water by means of bottom dumping buckets; later the stone

filling of the cribs was simply leveled up by depositing concrete in

bags, and last toe and heel blocks were molded and set flush with the

sides of the crib and filled between. Methods of construction and

records of cost are reported for portions only of the work and these are

given here.

[Illustration: Fig. 77.--Cross Section of Marquette Breakwater.]

_Footing Placed under Water with Buckets._--Besides the material track

which was constructed along the old wooden structure the plant

consisted of a mixing scow and a derrick scow, which were moored

alongside the work. The sand, stone and cement were brought out in cars

between working hours and stored on the mixing scow, enough for one

day's work at a time. The derrick handled a 40-cu. ft. bottom dump

bucket, which sat in a well on the mixing scow with its top flush with

the deck. The concrete was mixed by hand on the deck and shoveled into

the bucket; the bucket was then handled by the derrick to the crib and

lowered and dumped under water. The gang consisted of 24 men, 1 foreman,

1 master laborer, 14 men shoveling and mixing, 3 men wheeling materials,

1 derrick man and 3 men placing and depositing concrete. No record of

output of this gang is available. The cost of the concrete in place with

wages $1.25 to $1.40 per day for common labor is given as follows:

Materials. Per cu. yd.

1.21 bbls. (459 lbs.) cement at $2.20 $2.657

1 cu. yd. stone at $1.58 1.580

0.5 cu. yd. sand at $0.50 0.250

2.02 lbs. burlap at $0.037 0.075

Twine and needles 0.005

------

Total materials $4.567

Labor.

Loading scow with materials $0.4114

Mixing concrete 0.8459

Depositing concrete 0.5242

-------

Total labor $1.7815

Grand total $6.348

These figures are based on some 757 cu. yds. of concrete footing. In

explanation of the items of burlap, etc., it should be said that the

cribs were carpeted with burlap to prevent waste of concrete into the

stone fill.

[Illustration: Fig. 78.--Cross Section of Marquette Breakwater Showing

Manner of Constructing Footing with Bags of Concrete.]

_Leveling Off Cribs with Concrete in Bags._--The sketch, Fig. 78, shows

the method of leveling off the cribs with concrete in bags. The concrete

was mixed by hand on shore and filled into 8-oz. burlap bags, 6 ft. long

and 80 ins. around, holding 2,000 lbs. The bags were filled while lying

in position in a skip holding one bag. A skip was lifted by gallows

frame and tackle onto a car and run out to the work where the derrick

scow handled the skip to the crib, lowered it into the water and dumped

the bag. The cost of making and placing some 375 cu. yds. of concrete in

bags is given as follows:

Materials. Total. Per cu. yd.

453 bbls. cement at $2.627 $1,190.03 $3.173

375 cu. yds. stone at $1.619 607.13 1.619

180 cu. yds. sand at $0.392 70.56 0.188

3,220 yds. burlap at $0.03304 106.39 0.283

Twine and needles 6.36 0.017

--------- ------

Total materials $1,980.47 $5.280

Labor Mixing.

108 hrs. master laborer at $0.21-7/8 $ 23.42 $0.062

1,750 hrs. labor at $0.175 306.25 0.816

Superintendence 12.55 0.033

-------- ------

Total labor mixing $ 342.22 $0.911

Labor transporting.

306 hrs. labor at $0.175 $ 53.55 $0.142

Superintendence 5.25 0.014

-------- ------

Total labor transporting. $ 58.80 $0.156

Labor Depositing.

108 hrs. engineman at $0.25 $ 27.00 $0.072

108 hrs. master laborer at $0.21-7/8 23.42 0.062

510 hrs. labor at $0.175 89.25 0.238

Superintendence 13.25 0.035

-------- ------

Total labor depositing $ 152.92 $0.407

Grand total labor $ 553.94 $1.477

Grand total materials and labor $2,534.41 $6.757

_Molding Footing Blocks._--The blocks used at the toe of the prism were

of the form and dimensions shown by Fig. 79. They were molded in a

temporary shed heated to 50° to 65° F., and provided with a 2×8-in.

dressed plank floor on 12×12-in. sills. The floor formed the bottoms of

the block molds. Four molds were used, each consisting of four sides.

Three laborers molded one block, 2.22 cu. yds. per day, wheeling,

mixing, erecting and removing forms, placing concrete and doing all

other work. The cost of making 40 blocks was recorded as follows:

Materials. Total. Per cu. yd.

126 bbls. cement at $2.75 $346.50 $3.893

88.9 cu. yds. screenings at $1.10 97.79 1.098

40.1 cu. yds. sand at $0.45 18.04 0.203

5 gals. oil at $0.65 3.25 0.036

------- ------

Total materials $465.58 $5.230

Labor.

1,000 hrs. labor at $0.125 $125.00 $1.404

Watchman 29.15 0.327

Labor cutting wood for fuel 23.80 0.267

Superintendence 42.66 0.480

------- ------

Total labor $220.61 $2.478

Total labor and materials $686.19 $7.708

[Illustration: Fig. 79.--Details of Toe Blocks for Footing, Marquette

Breakwater.]

_Molding Concrete Prism in Place._--The concrete prism was molded in

alternate sections 10 ft. long; the form for the isolated sections

consisted of eight pieces so constructed that when assembled in place

and secured with bolts and turnbuckles the form was self-contained as to

strength and required no outside support or bracing. The form once in

place, all that remained to be done was to fill it, the block with the

gallery through it being molded in one operation. The forms for the

connecting blocks consisted of two slope panels, a panel for the harbor

face and the gallery form, the blocks previously molded making the other

sides of the form. The concrete was mixed by hand on shore, conveyed to

the work in 1 cu. yd. cars and shoveled into the forms, where it was

rammed with 35-lb. rammers. The following record covers 1,231 cu. yds.

of concrete prism. In this concrete some 214 cu. yds. of rubble stone

were embedded. The costs given are as follows:

Per

Materials-- Total. cu. yd.

1,780 bbls. natural cement at $1.068 $1,901.04 $1.545

963½ cu. yds. stone at $1.619 1,559.91 1.267

53½ cu. yds. screenings at $0.392 20.97 0.017

485.6 cu. yds. sand at $0.392 190.36 0.154

Miscellaneous materials 78.15 0.063

--------- ------

Totals $3,750.43 $3.046

Labor Mixing--

254 hrs. master laborer at $0.21-7/8 $ 55.56 $0.045

4,470 hrs. labor at $0.175 782.42 0.635

Superintendence 18.20 0.015

-------- ------

Total labor mixing $ 856.18 $0.695

Labor Transporting and Placing--

35 days overseer at $2.33-1/3 $ 81.67 $0.066

1,949 hrs. labor at $0.175 342.07 0.277

Superintendence 34.98 0.028

------- ------

Total labor transporting and placing $ 458.72 $0.371

Grand total, labor $1,314.90 1.066

Total labor and materials $5,065.33 4.112

No charge is made under materials for rubble stone as the only cost for

this was cost of handling and this is included in transporting and

placing.

~BREAKWATER, BUFFALO, N. Y.~--The following methods and costs of mixing

and placing some 2,561 cu. yds. of concrete are given by Mr. Emile Low,

for 10 parapet wall sections and 17 parapet deck sections for a

breakwater at Buffalo, N. Y.

The concrete used was a 1 cement, 1 gravel, 1 sand grit and 4 unscreened

broken stone. One bag of cement was assumed to measure 0.9 cu. ft. The

voids in the sand grit and gravel were 27 per cent. and in the

unscreened stone 39 per cent. The hardened concrete weighed 152 lbs. per

cu. ft.