HACKENSACK PORTAL AND APPROACH.

The approach cut at the western end is 300 ft. long, the alignment being

a 2° curve, as shown in Fig. 19. The bench-walls and conduit lines built

throughout the length of the tunnels are extended through the approach

cut, the top of the former gradually sloping from the portal to the

mouth of the cut, where they are just level with the top of the rail,

the conduits also being depressed to the same relative position with the

tops of the benches.

[Illustration: Fig. 19. [Full Page]

BERGEN HILLS TUNNELS.

Hackensack Portal and Approach.

SECTIONS AND ELEVATIONS.

PLAN OF APPROACH.

PROFILE THROUGH APPROACH.

SECTION SHOWING METHOD OF MAKING JOINT BETWEEN COPING AND WALL.

PLAN SHOWING METHOD OF MAKING JOINT BETWEEN ADJOINING SECTIONS.

SECTION OF BENCH AND RETAINING WALLS AND HALF ELEVATION OF PORTAL.]

The top of the rock at the mouth of the cut, Station 327, was from 4 to

6 ft. below the top of the rail, and gradually rose through the approach

until at the portal it was about 6 or 8 ft. above the roof of the

tunnel. The rock was covered with hardpan. A profile of this part of the

work is shown on Fig. 19. The rock throughout the approach was

water-bearing to a considerable extent, and a face-wall was built at the

sides with free drainage, through rock packing and vitrified and

cast-iron drains behind it, to keep this water from flowing over the

tops of the bench-walls, and also to keep the lines of conduits dry.

The retaining walls were built in 25-ft. sections, the joints

corresponding to those in the benches, being at the even stations, +08,

+33, +58, and +83. =V=-shaped joints were made down the face, and the

ends of the sections were made as shown by Fig. 19. The back part of the

joint was mopped with hot pitch before the next section was built, so

that there was practically no bond between any two adjoining sections.

The concrete in these walls was placed late in the season, and the

expansion cracks, which were entirely confined to the =V=-shaped joints,

were quite small even in the coldest weather of the following winter,

nor were there any indications during the past summer of any stresses

due to expansion. The coping and drain at the top of the wall were built

together, but separate from the rest of the wall, the joint being made

as shown in the sketch on Fig. 19. Thus far, there has seemed to be no

seepage through either the vertical or horizontal joints.

The portal is built of granite, a half elevation being shown on Fig. 19,

the stone being supplied by the Millstone Granite Company, Millstone

Point, Conn. Fig. 3, Plate XXVII, shows the portal and the cut-and-cover

section after the arches were completed but not covered.

The forms for the concrete in the approach were made of ordinary dressed

lumber, and the surface was rubbed twice after the forms were removed,

which was as soon as possible after the concrete had set. The surface

was first very lightly rubbed with a piece of soft, light-colored,

sandstone to remove any irregularities, being wetted slightly if

necessary while being rubbed. After the concrete had become fairly hard

and dry, it was rubbed a second time and a uniform texture and color

obtained. The completion of this work was delayed until the second week

in January, and considerable difficulty was encountered in obtaining a

good finish of that part which was built after cold weather set in, when

it was necessary to protect it from frost. Unless extreme care was taken

to prevent freezing after the rubbing, the entire surface was likely to

scale off, although no cement or other material was added to it after

the removal of the forms. A general view of the completed approach is

shown by Fig. 4, Plate XXVII.

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The Bergen Hill Tunnels. Paper No. 1154 · 第 12 / 15 题