| DAY. | NIGHT. |
Title. +-----+-------+--------+-----+-------+---------+
| No. | Rate. | Amount.| No. | Rate. | Amount. |
---------------------+-----+-------+--------+-----+-------+---------+
Walking bosses | 2 | $5.00 | $10.00 | | | |
Timekeeper | 2 | 3.00 | 6.00 | | | |
Watchmen | | | | 5 | $2.00 | $10.00 |
Waterboys | 1 | 1.50 | 1.50 | | | |
Carpenter foremen | 2 | 3.50 | 7.00 | 1 | 4.00 | 4.00 |
Carpenters | 14 | 2.50 | 35.00 | 8 | 2.50 | 20.00 |
Pipe-fitters | 1 | 3.00 | 3.00 | | | |
Pipe-fitter's helper | 1 | 1.75 | 1.75 | | | |
Wheelwright | 1 | 2.75 | 2.75 | | | |
Wheelwright's helper | 1 | 1.75 | 1.75 | | | |
Blacksmith | 1 | 3.00 | 3.00 | | | |
Blacksmith's helper | 1 | 1.75 | 1.75 | | | |
Foremen riggers | 1 | 3.00 | 3.00 | | | |
Riggers | 6 | 1.75 | 10.50 | | | |
Foremen trackmen | 1 | 3.00 | 3.00 | | | |
Trackmen | 6 | 1.50 | 9.00 | | | |
Machinist | 2 | 3.00 | 6.00 | | | |
Machinist's helper | 1 | 1.75 | 1.75 | | | |
Electrician | 2 | 3.00 | 6.00 | 1 | 2.50 | 2.50 |
Electrician's helper | 1 | 1.75 | 1.75 | | | |
Lampman | 1 | 1.50 | 1.50 | | | |
Pumpman | 1 | 1.50 | 1.50 | | | |
Finishers | 3 | 2.50 | 7.50 | | | |
Hoist engineers | 12 | 3.00 | 36.00 | | | |
Dinky engineers | 5 | 2.75 | 13.75 | 1 | 2.75 | 2.75 |
Brakemen | 5 | 1.75 | 8.75 | 1 | 1.75 | 1.75 |
Switchmen | 1 | 1.50 | 1.50 | | | |
Barnmen | 1 | 2.00 | 2.00 | 1 | 2.50 | 2.50 |
Drivers | 9 | 1.50 | 13.50 | | | |
Foremen ductmen | | | | 2 | 2.50 | 2.50 |
Ductmen | | | | 5 | 2.00 | 10.00 |
Foremen laborers | 13 | 3.50 | 45.50 | 2 | 3.50 | 7.00 |
Laborers | 120 | 1.75 | 210.00 | 20 | 1.75 | 35.00 |
Compressor engineer | 1 | 3.50 | 3.50 | 1 | 3.50 | 3.50 |
Firemen | 2 | 2.50 | 5.00 | 1 | 2.50 | 2.50 |
Oiler | 1 | 1.75 | 1.75 | | | |
Coal passers | 2 | 1.75 | 3.50 | 1 | 1.75 | 1.75 |
---------------------+-----+-------+--------+-----+-------+---------+
Totals | 334 | |$469.75 | 50 | | $108.25 |
Total daily labor expense $578.00
---------------------------------------------------------------------
The water finding its way into the side ditches in the approach, which
of course included all rain falling in this area, was intercepted just
inside the portal and carried back to the mouth of the cut through
24-in. cast-iron pipes laid beneath the conduits in the central
bench-wall, thus disposing by natural drainage of a not inconsiderable
quantity of water which would otherwise have flowed through the tunnels
to the sump at the Weehawken Shaft, from which it would have had to be
pumped to the surface.
About 100 ft. of the tunnel immediately east of the Hackensack Portal
was built by the cut-and-cover method, and the arch section used in the
tunnel was modified by widening the haunches, the thickness of the arch
at the crown being gradually increased from 22 in. at the portal,
Station 324, to 34 in. at Station 323, where the regular segmental
timbering at the tunnel commenced. A general view of the approach during
construction is shown by Fig. 1, Plate XXV.