Note

End pipe connections may be changed to suit connections of rodding

outfit, care being taken to use a connection which will not split and

expand the mandrel if it should be driven back into it, in attempting

to ram the mandrel back when stuck in a duct.

Connection at Head End may be dispensed with, if the mandrel is

threaded through ducts by rods attached to the trailing end.]

Wooden rods were used at first, but proved entirely too light, as the

mandrels used were a close fit, and it required considerable effort to

push them through 400 ft. of conduit. Iron pipe with ordinary couplings

was next tried, but the couplings broke quite often, as the threads

became worn in uncoupling the sections to move the rods from one line to

another, and the break was generally inside a duct line. The long

couplings were finally adopted, and a set of rods was put in each line,

that is, six sets in all, so that when coupled up they remained in the

line until it was finished. The expense of the extra quantity of pipe

thus required was more than offset by the decreased labor cost.

It was thought necessary at first to run a cutter, Fig. 15, _E_, through

the conduits ahead of the final rodding mandrel, but this was soon found

to be unnecessary except in a very few instances, and, after a short

experience, the cutter was only used at places where an obstruction was

encountered by the mandrel.

At such times as the pipe became uncoupled inside the duct line, the

part remaining inside was recovered by the use of the tool shown at _D_,

Fig. 15, called a "weasel." In two instances, the mandrel became stuck

in such a manner that the duct line had to be cut into in order to take

it out.

The best day's work of the rodding gang (1 foreman and 4 men) was 20,400

duct ft. of the 4-way conduit in the telegraph and telephone line, and

19,200 duct ft. of single conduit on the low-tension line, an average

day's work under ordinary conditions being about 10,000 duct ft. The

cost, including labor, material, and all tools, for rodding for the

whole work was slightly less than 0.2 cent per duct ft. The average cost

of the single conduit was about 0.25 cents per ft., and of the 4-way,

0.15 cents per ft. About 10% of the conduit lines were rodded twice,

owing to partial sections having been rodded once before completion. The

best continuous work on rodding was done between October 22d and 29th,

1908, when in 7 working days, 105,600 duct ft. were rodded, an average

of a little more than 15,000 ft. per day.

_Bench-walls._--The original design for the tunnels provided for the

construction of a brick arch above a point 22° above the springing line,

that is, the part above the side-walls (Fig. 10). It was thought

desirable, therefore, in designing the bench-wall forms, to provide for

placing the concrete in the side-walls and bench-walls at one operation.

These forms, as first designed, are shown by Fig. 2, Plate XXV, and the

details in Fig. 16, _A_ and _A'_; they were built of steel, the facing

plates being 5/16 in. thick, in pieces 4 ft. 6 in. wide, and in length

about 6 in. more than the height of the bench-wall.

[Illustration: Fig. 16. [Full Page]

DETAILS OF TRAVELING FORMS USED IN THE CONSTRUCTION OF THE BENCH WALLS

A'. CROSS-SECTION OF STEEL FORM

A. LONGITUDINAL SECTION AND ELEVATION OF STEEL FORM USED AT

WEEHAWKEN END

B. DETAILS OF SCREW-JACKS FOR ADJUSTING FORM TO LINE

C. SECTION _C_-_D_ SHOWING CONNECTION OF FACE PLATES TO I-BEAM

UPRIGHTS

D. DETAILS OF WOODEN FORMS USED AT WESTERN END: CROSS-SECTION,

PART LONGITUDINAL SECTION

No chutes were used with these forms, the wheel-barrows being dumped

from the runways on the sides.]

The design was controlled very largely by the necessity of providing the

requisite clearance for the locomotives and muck cars, and the principal

feature was the support of the forms on two trusses, one at either side,

the front ends of which were supported from the foundation on a long

leg, as shown in Fig. 3, Plate XXV, and the rear ends directly on the

journal-boxes of wheels traveling on a rail on the top of the finished

bench, as shown in Fig. 2, Plate XXV.

Although it had been decided to substitute concrete for brick in the

arch before any of the lining was actually placed, two sets of forms for

the Weehawken end had already been ordered and delivered, so it was

decided to use them as designed, and place the side-wall with the bench.

The forms were designed so that 30-ft. lengths could be built, and this

was done at the start, but owing to the occurrence of the refuge niches,

ladders, etc., at 25-ft. intervals, it was soon seen that it would be

advisable to build the bench-wall in sections of that length (25 ft.),

or multiples of it, and as the clearance conditions seemed to preclude

the possibility of making the forms 50 ft. long, 25 ft. was adopted.

This permitted the removal of one of the panels, 4 ft. 6 in. wide, and

at the same time it was decided to remove the side-wall forms. This

decreased the load on the trusses considerably, but being still a trifle

weak, they were strengthened by the substitution of 1¼-in. truss rods

instead of the ¾-in. rods used originally. The top platform and the

cross-bracing were also stiffened a little and tightened up to prevent

racking.

The construction of the side-walls in conjunction with the bench-wall

was abandoned for three reasons: First, it was found that there would be

a much more even distribution of the work by including the side-wall

with the arch rather than with the bench; second, there was difficulty

in getting a good finish for the top of the bench-wall, as of course a

top form for the latter had to be placed to prevent the concrete from

squeezing up when the side-wall was built above it, which prevented

troweling; the third reason was the weakness of the whole form as

designed, and the increasing difficulty of adjusting it to line as the

work progressed, the principal difficulty being with the curved

side-wall forms.

The bench-wall forms were set in position, after they had been moved

ahead, by first blocking the bottom against the face of the foundation,

as shown by Fig. 13. As previously noted, this foundation face had been

built very carefully to line. The back end of the form, of course, was

blocked tightly against the end of the previously finished section, and

the top was made plumb by the adjusting screwjacks shown in Fig. 16,

_B_. At first these screws were ¾-in., but they were afterward changed

to 1¼-in. The only points which it was necessary for the alignment corps

to give in setting these forms was a grade at each of the front ends for

the top of the finished bench.

The steel face forms in both tunnels gave excellent results, as far as

smoothness of finish was concerned, but, owing to the imperviousness of

the steel, small air holes were formed in the surface, though not in

sufficient numbers or size to cause trouble or disfigure the work in any

way.

The design of the bench-wall forms used at the western end, where this

differs from the steel form, is shown by Fig. 16, _D_. The principal

features in which they differed from those used at the Weehawken end was

in the substitution of 2½-in. tongued and grooved hard pine for the

face. This timber was of the very best quality obtainable, each piece

being especially selected and as nearly clear and free from knots or

other defects as it was possible to get it. The edges of each piece were

planed at the back so as to insure a tight joint on the face, and all

joints were shellacked. These forms were used, without renewal of the

face timber and with only two planings, for a length of 2,500 ft., or

100 separate sections, and gave good satisfaction.

In order to obtain a surface to which the face lagging could be

fastened, wooden uprights were used and were reinforced on either side

by light channels bolted together through the timber, in place of the

=I=-beams used on the steel forms. The lagging was nailed to these

uprights by 6-in. wire nails driven through the top edges of each piece

as it was placed in position, thus leaving the surface entirely clear

and free from any marks or nail holes, and in condition for planing when

this became necessary. Runways for wheeling the concrete were built one

either side over the bench-walls instead of having a center platform

with chutes, as was used at Weehawken.

When the original lagging had become too much worn for further use, it

was resurfaced with strips of 7/8 by 2½-in., clear, tongued and grooved,

hard pine, placed vertically, which did fairly well and lasted to the

end (about 1,000 ft.), although it was not altogether satisfactory, and

the last eight or ten sections built had to be rubbed down with a wooden

float in order to obtain a suitable finish.

In designing the forms for all exposed surfaces in the tunnels, it was

the desire of the contractors to obtain directly from them a surface

which would be satisfactory to the engineers without further finishing

than the patching of minor defects. In this they were generally quite

successful, and excellent results were obtained, as shown in the view of

the finished tunnel, Fig. 2, Plate XXVII. The surface of the bench-walls

was obtained solely by spading the face with a flat spade as the work

progressed. No after treatment was resorted to, except for the few

sections where the forms became worn. The top of the bench-wall was

finished with a float about 2 or 3 hours after the concrete was placed.

When the work was well organized, a bench-wall was built at each end

each day, one day in the North Tunnel, and the following day in the

South. During the time sand-walls were being built, a sand-wall and

bench-wall were built on alternate days in each tunnel, care being taken

that when a bench-wall was being built in one tunnel, the sand-wall was

being built in the other, this being necessary in order to equalize the

work of the night gang and the conduit layers as well as the

transportation.

The conduit layers on the day shift, two or three men and a foreman,

required about 2 hours in the forenoon and 1 hour in the afternoon to

lay their portion of the conduits, and usually finished this work by 3

P.M. At other times during the shift they were utilized at those points

where rock packing was heaviest, and when the packing was brought in in

the large cars, as shown in Fig. 1, Plate XXVI, these men helped unload

it so that the track could be cleared as soon as possible. When

water-proofing was to be done, the number of men in this gang was

increased, so as to enable them to do that work also.

[Illustration: Plate XXVI.

Fig. 1: K 167. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels.) View of form for circuit breaker chamber at Sta. 286, and

travelling gantry for placing concrete in arches, looking Easterly

from near Sta. 280+85, South Tunnel. Oct. 3, 08.

Fig. 2: K 166. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels.) View of forms for storage chamber at Sta. 294+24, looking

Southward. Sept. 17, 08.

Fig. 3: K 163. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels.) Tunnel lining. Rock packing over arches, South tunnel Sta.

???+?? end of completed section. May 19, 08.

Fig. 4: K 168. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels.) Showing method of waterproofing in timbered tunnel section

at Weehawken end. Oct. 21, 08.]

A gang of four rough carpenters and a foreman was employed on the day

shift; they moved and set the bench-wall forms or sand-wall forms, as

the case might be, and moved the traveling gantry into position. This

was done in the afternoon, and required about 3 hours. They also took

out, cleaned, repaired, and set all ditch forms, all passenger forms,

circuit-breaker forms, and did all other repair work. The ladder forms,

the refuge-niche forms, and overhead conductor pocket forms were

attended to by one man, who set, removed, cleaned, and repaired them.

The carpenters on the night shift set the arch centers and gantries,

also the manhole forms when needed. The conduit layers on the night

shift laid up half the 4-way conduits (3-high) and one-third of the

single ducts (4-high). This one gang laid the conduits in two sections

of bench-wall each night, that is, one section at Weehawken and the

other at the western end.

In concreting the bench-walls, the concrete was first placed on the side

containing the single conduit until it reached the top of the four tiers

laid, then the concrete gang was turned over to the side with the 4-way

conduits while four more tiers of single conduits were laid, the work

thus progressing, the conduits being laid on one side while concrete was

placed on the other. On the side of the 4-way conduits the concrete was

built in two layers while that on the side of the single ducts was built

in three; the interval between the different layers was not sufficiently

long to prevent a complete bond being obtained, and there were only one

or two instances where there was any mark on the face to indicate a

break.

After the work had been in progress some time, it was found to be quite

feasible to build all the 4-way conduits at night and half the single

conduits, that is, 6 ducts high, as the mandrels proved amply sufficient

to hold them in place; in fact, had it been necessary, the writer has no

doubt that all the ducts might have been laid and held in place with

very little extra precaution, by the use of the expanding mandrels,

as described under the head of conduit laying. A =V=-shaped joint about

½ in. deep was made between each section of bench-wall so that the

expansion cracks would follow this joint rather than show irregularly on

the face. These joints divided the face into the even 25-ft. panels, and

were very effectual in concealing what few cracks there were.

After the construction of the sand-walls was discontinued, the space

behind the bench-walls, between the neat line and the rock, was filled

with rock packing, which was generally built, part way up at least, as a

dry wall ahead of the construction of the bench-wall, or it was put in

place simultaneously with the concrete, care being taken to keep it as

free as possible for the drainage of any water there might be. Toward

the latter part of the work, owing to the difficulty of getting

sufficient rock packing during the day, a rough back form for the

bench-wall was built at the neat line, in places where the section was

at all large, and the space was filled with rock afterward, generally at

night or on Sundays.

In the sections where water-proofing was required, where no sand-wall

was built, the rock was taken out for 2 ft. outside the neat line,

if the excavation was not already that far out (at the expense of the

contractors, who preferred to do this rather than build the sand-walls

for the short sections required), so that there would be sufficient room

for placing the water-proofing on the back of the bench-walls, as shown

by Fig. 18, _E_. The water-proofing of these sections was left until

just before the arch was to be built, and after being placed it was

protected by a single row of brick laid on edge before the rock packing

was filled in.

_Arches._--The centering used for the arches is shown very clearly in

Fig. 4, Plate XXV, which is a view of the back end of the first section

built at Weehawken. In this part of the tunnel, the lower part of the

arch, about 5 ft. above the bench-wall, was built first, as previously

referred to, but the centers, as will be seen, were built so that they

could be used for the whole of the arch. The forward bulkhead, and the

shoveling platform on a section being built, are shown in Fig. 3, Plate

XXVI.

The front bulkheads used were made in nine sections, bolted to a 2½ by

2½-in. angle bent to the radius of the arch, as shown in Fig. 3, Plate

XXVI, and fitting on the end of the lagging; when set they were braced

partly against the rock of the roof and partly against the gantry. After

the ribs and part of the lagging had been set by the night gang for a

fresh section of arch, the braces holding the bulkheads were knocked

out, the concrete placed during the day having set sufficiently by this

time; the whole of the bulkhead was then easily moved ahead, sliding

along the lagging to the forward end, and made ready for the next day's

work. The middle section at the top was taken out temporarily, to

facilitate working at the sides, until it was needed.

The traveling gantry used in handling the concrete for the arch is shown

in Fig. 1, Plate XXVI, which also shows the form for the circuit-breaker

chamber, and a car of rock packing on the track beneath.

The arches were built in 10-ft. sections, the ribs being spaced 5 ft.

apart, the end ribs of each section supporting the end of the lagging on

two adjoining sections. Five sets of lagging and ten ribs were used at

each place where the arch was being built, thus giving each section

practically 4 days' set before removing the centers. Probably in the

greater part of the work the centers could have been removed in from 40

to 48 hours after the concrete had been placed, but 3 days was

considered the least time which would certainly be safe at all times,

and the contractors thought that the very slight additional expense

involved in leaving the centers up 4 days was more than warranted by the

additional feeling of security.

The lagging was made from 3 by 6-in. clear, hard pine, 10 ft. long,

dressed to about 2½ in. in thickness, about 5½ in. in width, and the

sides to radial lines. As it was placed, every third or fourth piece was

lightly nailed to the ribs; when the latter were released and taken

down, the nails pulled out, and the lagging was left in place until one

piece was pried out, allowing the others to fall. A light =A=-frame,

about 8 ft. long, spanning the bench-walls, was placed below, in order

to break the fall and allow the lagging to slide to the top of the

bench-walls rather than fall to the track beneath.

Cross-passages between the two tunnels were built every 300 ft., their

form being shown on Plate VIII of the paper by Mr. Jacobs. There were

two circuit-breaker chambers, one at Station 286 and the other at

Station 310. Steel doors are provided so that all the openings between

the two tunnels can be closed. At Station 294+24, the core-wall broke

through for a length of about 40 ft., and instead of filling this in,

a storage chamber 34 ft. long and 11 ft. wide, inside, was built there,

the form for which is shown in Fig. 2, Plate XXVI. This photograph, as

well as Fig. 1, Plate XXVI, a form for a circuit-breaker chamber, shows

the method of setting the steel doors in the forms, so that they were

built into the concrete instead of being fastened in with expansion

bolts afterward, thus showing a perfect fit and a much neater job.

During construction the arches in each tunnel were kept even with each

other, so that when the cross-passages were reached, they, and the

sections of arch which they joined, could be completed at one operation.

By the methods used on this work, one section of arch was easily built

in a shift, so that the monolithic construction of each section was

easily secured, and concrete, as wet as it was possible to handle with

shovels, could be used for all except the last 5 ft. or so at the top,

thus getting a structure which was as nearly impervious as possible

under the circumstances.

The gangs placing the arches were paid over-time when they were required

to work after 6 o'clock to finish their section, which was generally

only necessary when the quantity of rock packing to be placed was very

large. If they finished their section before 6 o'clock, however, they

were allowed to quit when this was done, and were given a full day's

pay. The difference in time, when there was any, was usually due to the

greater or less quantity of rock packing, as the excavation varied from

the standard section line.

In building the arches, the night gang set the two ribs (one at the

center and one at the forward end of the section to be built), placed

the lagging on the sides, 4 or 5 ft. high, built the shoveling platform

on the horizontal cross-braces of the ribs, and placed the traveling

gantry in position for use. The forward end of the gantry (that is, the

end farthest from the arch being built), as shown in Fig. 1, Plate XXVI,

was loaded with rock packing to be used as required. As the concrete was

brought into the tunnel it was hoisted and dumped on the end of the

gantry next the arch, and shoveled from there to the platform on the

ribs and from there into place. The rock packing brought in during the

day was dumped on the front or back end of the gantry, as was most

convenient, and handled into the work in the intervals between batches

of concrete. The concrete and rock packing, with the back-lagging and

water-proofing, where these were used, were placed simultaneously, or

nearly so, and brought up the sides together until the key was reached;

the latter was then worked from the back toward the front. The key was

usually made about 5 ft. wide, the lagging for this width was made 5 ft.

long and put up in two sections. It was found to be more convenient to

have the key of this width than narrower.

The method used in making the closures where two sections of the arch

came together is shown by Fig. 17.

[Illustration: Fig. 17. [Full Page]

SKETCH SHOWING METHOD OF MAKING ARCH CLOSURE

CROSS-SECTION OF TUNNEL SHOWING JACK PARTLY EXTENDED

LONGITUDINAL SECTION OF TUNNEL SHOWING JACK PARTLY EXTENDED

PLAN OF BOX; END VIEW

PLAN OF PLUNGER, BOTTOM OF BOX; END VIEW OF PLUNGER,

JACK FULLY EXTENDED]

_Water-proofing._--As already pointed out, the original design for the

lining of these tunnels provided for a brick arch. It was intended to

cover this arch with water-proofing, this latter extending over the

whole of the roof and down the sides as far as the bottom of the conduit

lines. The water-proofing was to be placed against the sand-walls on the

sides, up to the top of the side walls, Figs. 10 and 14. Over the arch,

after being placed, it was to be protected by an armor course of brick,

laid flat, the space between the brick and the excavation, which was

required to be not less than 4 in. (and, as a matter of fact, was

actually a great deal more), being filled with rock packing. Besides

filling the space, this latter was designed to allow any water from the

roof of the tunnel to find its way easily to the top of the sand-wall,

from there being carried through the 4-in. cast-iron pipes, shown on

Plate VIII[4] to the side ditches in the floor of the tunnel.

[Footnote 4: Of the paper by Mr. Jacobs.]

All the water-proofing placed in these tunnels was of felt and pitch,

six-ply felt and seven layers of pitch. The felt was required to be

Hydrex, or of equal quality, and the pitch, "Straight run coal-tar pitch

which will soften at 60° Fahr., of a grade in which the distillate oils

will have a specific gravity of 1.05."

In addition to tests as to the above qualities, the pitch was analyzed

to determine the amount of free carbon it contained, and was not

accepted if this fell below 20 per cent.

It was considered quite important that there should be absolutely free

drainage on the outer side of the lining, so that there would be no

chance for any water to acquire a head. More than three-quarters of the

length of these tunnels is below the level of mean high water, and while

it was hardly expected that there would be any direct connection between

the water in the Hudson River and the groundwater of the section

penetrated, it was thought wise to provide ample drainage.

Before the lining was started, however, the excavation had progressed

sufficiently to show that the tunnels, while very wet in places, and

varying from that to quite damp, would be, on the whole, much dryer than

had been anticipated. It was then decided to substitute concrete for the

brick in the arch and omit the water-proofing over the top, except at

places where water came into the tunnels in sufficiently large

quantities to form practically a continuous stream. Three general types

of construction for the arch were decided on, as shown in Fig. 18. The

first, as shown at _A_, was to be used where the tunnel was quite dry.

In this type, the sand-wall was omitted entirely, and the concrete and

rock packing were built up together, the rock packing impinging to a

certain extent on the concrete, and the concrete squeezing somewhat into

the rock packing, as shown by Fig. 4, Plate XXV. The section shown at

_B_ was used where the tunnels were damp, or where there were slight

droppers not forming a continuous stream. The back lagging, of 1-in.

boards, which was left in place, provided a practically smooth outer

surface on the concrete arch, and allowing the concrete and rock packing

to be built almost simultaneously. It was considered that the free

drainage through the rock packing, the surface of the boards, and the

smooth outer surface of the concrete in the arch would allow the

comparatively small quantity of water in these parts of the tunnel to

find its way to the sides, and thence to the ditches at the bottom,

rather than to percolate through the concrete, and this proved to be

very generally the case, as is shown by the dry condition of the tunnel

as built. The back lagging was used over the arch, both where the

sand-wall was built and where it was omitted, as well as being placed

over the water-proofing of the arch as an armor course where

water-proofing was required. Where the sand-walls were built and

water-proofed, and where the water-proofing was not carried over the

arch, the water-proofing was turned in at the top, as shown at _C_, Fig.

18.

[Illustration: Fig. 18. [Full Page]

VARIOUS TYPES OF ARCHES, AND WATER-PROOFING USED

Method of Lapping Mats over Arch

Method of making joint when work on section was not continuous. Part

of joint on radial line, part sloping slightly toward outside of

arch.

DETAILS OF WATER-PROOFING

One layer of felt with 4" overlap to be nailed to lagging of inch

boards, using tin washers on nails over the whole of the intrados

of the arch before starting any concrete or placing any of the

permanent felt and pitch water-proofing. The water-proofing over

the arch can be laid in mats of three thicknesses of felt properly

joined together with pitch made as shown diagrammatically at "_x_"

Each of these mats of three-ply felt will be overlapped half the

width of the mat, as shown diagrammatically at "_y_"]

The third method provided for water-proofing the whole of the arch, and

was the same as _B_ except for the addition of the water-proofing inside

the back lagging. In placing this water-proofing, the felt was cut in

strips about 11 ft. long (about 1 ft. longer than the length of a

section of arch), and six thicknesses were cemented together with hot

pitch. These mats were then laid shingle-fashion, as shown at _D_, Fig.

18, up the sides of the arch until a space about 5 ft. wide remained at

the crown; shorter mats were then brought out over this, laying them

perpendicular to the axis of the tunnel. Care was taken in making all

laps, irrespective of the direction in which the arch was built, so that

they would lay with the grade, that is, so that the water would tend to

flow over the edges of the laps rather than against them.

Most of the wet sections of the tunnel were at the ends, where

sand-walls had been built for the purpose of providing a smooth surface

against which the water-proofing was to be placed; there were several

wet places at isolated points in the tunnels, however, and, in order to

avoid building sand-walls at these points, the method shown at _E_, Fig.

18, was adopted. This involved a slightly larger excavation, 2 ft.

outside of the neat line, up to the height of the top of the bench,

where there was not already that much room. The bench-wall was built

with a back form on the neat line, the water-proofing was placed as

shown, protected by an armor course of brick, and then continued over

the arch when this latter was built. The excavation and refilling with

rock packing were done at the contractor's expense, which he was willing

to assume rather than build these short sections of sand-wall.

[Illustration: Plate XXVII.

Fig. 1: K 181. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels.) Timbered section near Weehawken Shaft, showing method of

placing waterproofing and keying arch. Dec. 8, 08.

Fig. 2: K 184. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels). View of completed tunnel looking Eastward from Sta.

323+60. South Tunnel. Feb. 8, 09.

Fig. 3: K 149. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels) Hackensack Portal, general view of completed Portal, and

arches through cut and cover section looking East. Oct. 15, 07.

Fig. 4: K 190. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels.) Hackensack Approach. General view, looking East. March 16,

09.]

The method of water-proofing that part of the timbered section which was

very wet, is shown at _F_, Fig. 18, and in Fig. 4, Plate XXVI, and

Fig. 1, Plate XXVII. A lagging of 1-in. boards was nailed up the sides

and to the soffit of the segmental timbering, all the spaces outside of

this lagging being carefully filled with rock packing. Before starting

any concrete work, a single thickness of water-proofing felt was nailed

to the inner side of the lagging, which not only served to protect the

finished surfaces of the concrete from the water which fell copiously

from the roof, but also provided a comparatively dry surface to which

the regular six-ply water-proofing could be cemented with pitch and held

in position, while the concrete was placed against it.

In placing the water-proofing in this section on the sides, the strips

of felt were placed vertically, nailed at the top to the wall-plate, to

support their weight, and lapped and cemented with pitch to the sides as

on the sand-walls, except that there was no trouble from the overhang.

After the bench-wall had been built, the felt was cut just below the

nails and about 2 ft. above the top of the bench, so that the mats which

were placed over the arch could be inserted behind it. The roof was

covered with three-ply mats and lapped over a little more than half, as

shown diagrammatically on the drawing.

When the upper part of the arch was reached, where the cementing

strength of the pitch was not sufficient to hold the felt in place, the

mats were braced temporarily from the centering, as shown by Fig. 1,

Plate XXVII, until the concrete could be packed against it.

Where the water-proofing was placed against the sand-wall, the method of

securing the sheets at the top is shown in the small sketch on Fig. 14

and by Figs. 3 and 4, Plate XXIV. Fig. 3, Plate XXV, shows the laps of

the sheets and the method of hanging. At the start an attempt was made

to stick the water-proofing to the sand-wall, but this could not be done

on account of its dampness and the overhang at the top.

The sand-wall water-proofing was kept about 35 ft. ahead of the finished

bench-wall, as shown by Fig. 3, Plate XXV. As the bench-wall form was

moved ahead and set, the mat was braced back against the sand-wall from

the forms at a point just above the top of the finished bench, care

being taken to avoid wrinkles, as, if these were once formed, it was

practically impossible to straighten them out.

The completion of the bench-wall left the upper part of this

water-proofing stretched taut across the curved top of the sand-wall,

forming a chord of the arc. As the arch was built up, the top was

gradually slackened so as to allow the concrete to press the mat back

into place until the top of the sand-wall was reached, when the end was

turned in, as shown at _C_, Fig. 18, or the water-proofing was continued

over the arch, if that was necessary.

The desire to obtain a dry tunnel, and the methods adopted to secure it,

were responsible in a great measure for the decision to build the arch

in short lengths, as well as the reasons given under the head of arches.

Had the tunnels been dry throughout, the method shown at _A_, Fig. 18,

could have been used exclusively, and, except for the fact that

monolithic concrete might not have been obtained, there would have been

no objection to building longer lengths.

The quantity of water reaching the tunnel drains and flowing out of

their lower ends after the completion of the lining was about 100,000

gal. per day, or 75 gal. per min.; of this it is estimated that

considerably less than 1% comes through the lining in the form of leaks.

The very general distribution of this water over the roof is indicated

by the fact that, during the excavation of the first 1,000 ft. of both

tunnels from the Weehawken end, oilskins had to be provided for the

laborers to induce them to work at all. The success, therefore, of the

rock packing as a means of diverting this water to the side drains, is

shown, especially in view of the fact that, excluding the cut-and-cover

section, only 10% of the length of the arch, 1,189 ft., was

water-proofed.

Considerable care was taken to make all joints in the concrete which

were in such a position that water might follow through them to the

inside of the tunnel lining, in such a manner that they would slope

outward toward the rock. The top of the sand-wall is shown by Figs. 14

and 18. The slope of the back of the foundation may be noted in Fig. 18,

and the method of making the joint in the arch, in the few instances

where a section was not completed at one operation, is shown at _A_,

Fig. 18. These joints in the arch were not allowed to be made above a

point 60° above the springing line.

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The Bergen Hill Tunnels. Paper No. 1154 · 第 11 / 15 题