TUNNEL LINING.

_Preliminary Considerations._--For the placing of the concrete lining, a

sub-contract was given to Messrs. King, Rice and Ganey, by Mr. Bradley,

which provided substantially that all materials should be supplied by

him, and delivered to the sub-contractors at track level, at or near the

point in the tunnel at which they were to be placed, and that he would

supply light and power; the sub-contractors were to supply the plant,

forms, and labor necessary for placing the concrete and water-proofing,

building the conduit lines, manholes, etc., etc., to complete the

lining, the general form of which is shown on Plate VIII of the paper by

Mr. Jacobs, and in Fig. 10. The latter also shows the different sections

into which the lining was divided for purposes of construction, and the

nomenclature adopted for each. It may be noted, incidentally, that the

cubic contents of the lining per linear foot of tunnel is almost exactly

half the quantity excavated, out to the standard section lines, and as

there was some excavation outside of these lines, all of which had to be

replaced, the actual quantity of material which had to be brought back

into the tunnel was quite a little more than half the quantity taken

out. It will be evident, therefore, that the question of transportation

was an important one.

[Illustration: Fig. 10.

SKETCH SHOWING DIVISION OF LINING FOR PURPOSES OF CONSTRUCTION,

AND NAMES OF SECTIONS]

An essential part of the agreement with the sub-contractors provided

that the operations incident to the placing of the lining should be

carried on so as to provide at all times space for a single track of

3-ft. gauge, running through the work, and the necessary clearance for

the locomotives and cars used in hauling out the muck. A clearance

diagram of one of the "dinkys" used in the tunnels, and its relation to

the forms used, is shown by Fig. 12 and also by Fig. 16, the 4-yd.

Allison cars, used for handling the muck, taking practically the same

width, although they were not quite as high. This requirement and the

limited space available must be kept in mind in considering the design

finally adopted for the forms and plant required in placing the lining.

It should also be kept in mind that, with the rolling stock used, there

was only room for a single track through that part of the tunnel where

any concrete had been built. As the concrete progressed, therefore, the

length of single track was necessarily lengthened, and the problem of

transportation was made increasingly difficult.

In working out a design for the bench-wall forms, another highly

important and controlling factor, which had to be considered, was the

arrangement of the conduit lines, as shown in the general

cross-section.[2]

[Footnote 2: Plate VIII of the paper by Mr. Jacobs.]

The quantities of the various materials in the lining, per linear foot

of tunnel, were as follows:

Concrete 7.64 cu. yd.

Rock packing: Paid for 1.48 cu. yd.

Outside standard section line 1.74 " "

------------ 3.22 " "

Iron and steel 44.2 lb.

Vitrified conduits 84.0 duct ft.

Water-proofing 13.0 sq. ft.

Flags 3.3 " "

_General Methods._--The lining was started at both ends of the tunnels

before the headings were finally holed through, so that there was

practically a separate organization at each end, each in charge of one

of the members of the firm. The work at the Weehawken end was started

first, and the plant and scheme of working adopted there was thoroughly

tried out before the plant for the western end was built, consequently,

the latter was somewhat more efficient, being designed in the light of

the experience gained at the Weehawken end.

The general sequence of the plan first adopted in placing the concrete

is shown by Fig. 10. The concrete was first placed in the foundations up

to the elevation of the bottom of the conduit bines, this work, of

course, being kept well in advance; next followed, in the order named,

the sand-walls, water-proofing, conduits, bench-walls, and finally the

arch. The foundation was built in any convenient lengths, multiples of

16 ft., the length of one section of form, the sand-walls in lengths of

from 25 to 35 ft., the bench-walls in 25-ft. lengths, and the arch in

10-ft. lengths. Concrete was placed during the day shift only, the forms

being moved partly at night, and partly on the alternate days when

concrete was not being placed in them.

Five gangs were organized at each end, the first placed concrete in the

foundations in both tunnels, as the excavation was ready. In each tunnel

there was a gang which built sand-wall one day and bench-wall the next,

the two tunnels alternating so that only one bench-wall was built each

day, and finally a gang in each tunnel building arches, a 10-ft. section

being completed each day. During the night shift, the arch forms and

travelers were moved, and all other forms, etc., were made ready for the

concrete to be placed the following day. Some of the conduit laying was

done by the night shift, but part of it was necessarily done during the

day, as the concrete was built up. A small gang was kept busy in both

tunnels, during the day shift, laying conduits and water-proofing. The

latter two operations were generally performed by the same gang.

This organization, of course, required considerable regularity in the

work, and this was finally attained, but at the beginning many sections

were often not finished on time, thus creating considerable confusion.

The progress possible with this organization (finally maintained with

great regularity) was 75 ft. of bench-wall and 60 ft. of arch per week

at each of the two working faces in each tunnel. This allowed the

bench-wall to gain considerably on the arch, and therefore at a suitable

point, as shown on the progress diagram, Fig. 9, a third pair of arches

was started, one in each tunnel, increasing the progress on the arches

to 180 ft. per week in each tunnel.

_Mixing and Transportation._--All the concrete used on this section was

mixed in Hains mixers, one being at each end. At the Weehawken shaft the

mixer was installed in the framework supporting the head-house and

elevators; and storage bins were arranged above, as shown by Fig. 11,

_A_, the whole structure being somewhat strengthened to allow this to be

done. At the western end the mixer was placed immediately under the bins

of the stone crusher, as shown by Fig. 11, _B_, the track below being

connected directly with the tunnels. The stone bin under the screen of

the crusher plant at the Hackensack end was divided into three parts,

the center being filled with sand by a derrick having a clam-shell

bucket, the other two with stone directly from the screen above.

This type of mixer proved very efficient on this work. The largest

number of full batches (0.8 cu. yd.) mixed in one plant per hour was

about 35; the largest number per day of 10 hours was about 240; but the

apparatus was never worked to its full capacity, the quantity of

concrete which it was possible to use being limited by other

considerations.

[Illustration: Fig. 11.

_A_ CROSS-SECTION OF HAINS MIXER INSTALLATION, AT WEEHAWKEN SHAFT

_B_ CROSS-SECTION OF HAINS MIXER INSTALLATION,

STONE AND SAND BINS ABOVE AND SCREEN OF CRUSHER, AT HACKENSACK

PORTAL]

The concrete for the foundations was hauled in steel, =V=-shaped,

dumping cars holding about 1 cu. yd., and the concrete for the

bench-walls and arches in Stuebner, 1-yd., bottom-dumping buckets placed

on small flat cars, as shown by Fig. 1, Plate XXIV. Rock packing was

handled in Allison 4-yd. cars and also in the cars shown by Fig. 5,

as well as in the Stuebner buckets, the latter, however, being most

generally used. Mules were used for a short time at the Weehawken end to

haul the concrete in, but proved entirely inadequate to haul the loaded

cars up the 1.3% grade, and locomotives were substituted after the

headings were holed through. At the western end the cars were allowed to

coast in, and, up to the time the headings were holed through, were

hauled back by mules; after that they were pushed out by a locomotive

which had gone in ahead of them. As a rule, from 8 to 10 cars of

concrete and rock packing were sent in, one after the other, in proper

order, a boy riding on each car and stopping it at the proper place; all

these cars were pushed out together when empty.

[Illustration: Plate XXIV.

Fig. 1: K 131. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels) Weehawken Shaft, North Tunnel. Rear view of conveyor for

concrete, showing method of hoisting bucket from car on track in

hopper over belt. June 7, 07.

Fig. 2: K 130. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels) Weehawken Shaft, South Tunnel. View showing waterproofing

(extreme left) portion of completed sand wall, sand wall forms,

traveller and end of conveyor overhead. July 22, 07.

Fig. 3: K 148. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels) Weehawken. View showing method of placing concrete in

forms. Hoisting apparatus and bucket in background. Sept. 24, 07.

Fig. 4: K 154. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels) Weehawken Shaft, North Tunnel. Method of placing concrete

in bench walls. Top of waterproofing suspended from top of sandwall.

Oct. 21, 07.]

During the time the excavation was being carried on simultaneously with

the lining at the Weehawken end, the rock packing was loaded at the

working face and sent out to the point where it was to be used; after

that the rock packing was sent in from outside from the reserve pile on

the north side of Baldwin Avenue.

At the western end the larger part of the rock packing was sent in from

outside, but occasionally, during the time the excavation was going on,

the cars from the heading were stopped at convenient points, generally

under the gantries, where the lining was being placed, and whatever

stone could be utilized was sorted from the top and passed up to the

platforms above.

After the headings were holed through, there was considerable difficulty

at times in getting a sufficient supply of concrete and rock packing

into the tunnel at the time it was required, and while undoubtedly the

transportation facilities may have had some influence in this, the

principal trouble lay in the difficulty of securing a sufficient supply

of proper stone for rock packing, and for the crusher.

While the excavation was progressing, the cars of muck, as they came

from the headings, were taken directly to the crusher and dumped into

it, the proportion of fine material being fairly constant and the supply

regular. At this time, also, a portion of the rock not required at the

crusher was dumped along the edge of the bank on the south side of the

approach, the larger stones rolling to the bottom where they were easily

available to be loaded into cars for rock packing, being entirely free

from the fine material; as this stone at the bottom of the bank was used

up, the supply was renewed, the rock suitable for rock packing being

automatically separated from the fine material as it rolled to the foot

of the slope.

After the excavation was completed, however, it was necessary to go into

the bulk of the storage piles to get material for the crusher and for

rock packing, and then the difficulties were materially increased by the

large quantity of fine material encountered, the proportion remaining

after the rock packing had been sorted out being too large to send

through the crusher. It was not only the handling over of this fine

material which caused delay, but the difficulty of disposing of it. On

rainy days the trouble was increased by the difficulty of getting men to

work in the open.

The delays due to transportation were usually caused by derailments,

which were more numerous than they should have been, and were due to the

condition of the rolling stock rather than to that of the track. These

delays, especially when they occurred in the early part of the day,

greatly increased the cost, by necessitating over-time work; a delay of

1 hour in the forenoon generally meant 2 hours' work after 6 o'clock to

finish the day's work.

The average number of cars handled (round trips of 1 car) during a day

(two 10-hour shifts) at the Hackensack end during January, 1908, when

the excavation and lining were in full swing, was about 125 cars of muck

and 200 cars of lining material, the former being hauled by locomotives

and the latter by mules.

_Methods of Handling Concrete in the Tunnels._--The concrete for the

floor, ditches, and foundations, was brought into the tunnel in

=V=-shaped steel, dumping cars, and dumped as near as possible to the

place it was to occupy.

The concrete for the arches and bench-walls was loaded at the mixers

into 1-yd., Stuebner, bottom-dumping buckets which just held a 4-bag

batch. These buckets were placed on small flat cars, hauled into the

tunnel, placed beneath the traveling gantry, as shown by Fig. 1, Plate

XXIV, and hoisted to the platform above.

These traveling gantries, the details of which are shown by Fig. 12,

consisted essentially of platforms at each end of which an =A=-frame was

erected; the latter supported at their apexes two =I=-beams, from the

lower flanges of which was suspended a traveling block, shown at _A_,

Fig. 12, and through which the hoisting rope was rigged. The buckets

were hoisted through an opening in the platform and then moved along to

where they could be dumped. The platforms were supported on wheels

traveling on rails laid on the concrete of the foundation (for the

bench-wall gantries) or on top of the bench-wall (for the arch

gantries).

Each of the first two of these traveling gantries used was equipped with

a belt conveyor working on a cantilever arm, as shown by Figs. 3 and 4,

Plate XXI, and Figs. 1 and 2, Plate XXIV. In using these belt conveyors,

the concrete was dumped from the Stuebner bucket into a hopper, Fig. 1,

Plate XXIV, with an adjustable slot in the bottom, under which the belt

ran.

[Illustration: Fig. 12. [Full Page]

DETAILS OF TRAVELING GANTRY USED IN THE CONSTRUCTION OF THE TUNNEL

LINING:

SECTIONAL ELEVATION

CROSS-SECTION

A. DETAIL OF TRAVELING BLOCK

B. DETAIL OF TOP SHEAVE

C. DETAIL OF LOWER SHEAVE.]

It was the original intention, in designing the conveyor, that the end

of the cantilever arm should be swung from one side of the tunnel to the

other, and that the traveler should be moved backward or forward, as

might be required, and thus deliver the concrete from the end of the

belt directly over the place in which it was to be deposited in the

bench-walls. As a matter of fact, it was found impractical in operation

to move the gantry readily, owing to its great weight, which was

supported on only four ordinary car wheels and their bearings, and it

was found more convenient to leave the arm in one position near the

center, letting the concrete drop on the platform above the bench- or

sand-wall forms, whence it could be shoveled into place, than to attempt

to move it as had been intended. Both of these difficulties might

possibly have been overcome by modifications in the design of the gantry

and conveyor, had this method of handling the concrete seemed otherwise

desirable.

The principal difficulty with its use, however, was the inability to

take care of more than one batch of concrete at a time. When one batch

had been dumped into the hopper, a second could not be disposed of until

the first had nearly all run through on the belt, and this took from 7

to 20 min., varying with the consistency of the concrete, etc. In a few

instances, where there happened to be some fairly dry batches, the

concrete could not be started through the slot at all, and had to be

shoveled out of the hopper. On the other hand, it is stated that some

batches, under favorable conditions, passed through in about 2 min., but

this was quite exceptional, and the operation was irregular and

uncertain.

Before the final method of handling the concrete was adopted, a trial

was made of two forms of cars and buckets, to be used on the top

platform, as shown by Figs. 3 and 4, and Plate XXIV. In the method shown

by Fig. 3, Plate XXIV, the concrete was hoisted in the regular Stuebner

buckets, one of which can be seen suspended in the background of this

photograph, and dumped into the car shown, which was mounted so that it

could be revolved in a horizontal plane. It was intended to move this

car on the tracks to the point at which the concrete was required, and

dump it directly through a chute into the bench-walls. This car was

abandoned, as there was a great deal of difficulty in turning it when it

was loaded, and in several instances it had to be dumped straight ahead

in the middle of the platform and the concrete shoveled into the forms.

This method was also objectionable when the bucket was dumped, inasmuch

as the force of the impact of a whole batch of concrete dumped from such

a height into the forms, not only tended to throw the conduits out of

line, and to break them, but also caused considerable strain on the

forms.

The bucket shown by Fig. 4, Plate XXIV, was next tried. It had a

slanting bottom and a door opening at the side. It was filled at the

mixer, came into the tunnel on a small flat car, and was hoisted and

placed on a similar car on top, as shown. This bucket was not

successful, as its great weight made it difficult to handle, and it

generally required a man to shovel the concrete out, which latter, of

course, had been pretty well compacted in the bottom of the bucket by

its trip from the mixer. All these cars were hauled backward and forward

on the top platform by a rope running to the winch on the hoisting

engine on the traveling gantry.

Aside from the fact that neither type was a success, neither of these

schemes was much improvement over the belt, inasmuch as only one batch

could be handled at a time, owing to the necessity of using the engine

to haul the cars back and forth on the platform. The final solution was

found in the use of the traveling gantry, shown by Fig. 12 and Fig. 1,

Plate XXVI, the latter being one of the arch gantries. The gantry used

for the bench- and sand-walls was supported on framed bents on wheels

running on rails laid on the foundation; that for the arch was the same,

except that the high-framed bent was dispensed with, the side-sills

resting directly on the journals of wheels traveling on rails on top of

the finished bench-wall.

These gantries were used only as a means of hoisting the buckets and

moving them along to where they could be dumped directly on the

platform, whence the concrete was shoveled into wheel-barrows, which

could be dumped directly into the bench-walls; or, in the case of the

arches, shoveled from the platform of the gantry to the intermediate

platform on the arch ribs, and thence directly into the arch. This use

of wheel-barrows, though apparently a somewhat crude method and a

retrogression from the use of the belt conveyor, proved very successful,

and really involved no more labor than did the conveyors, although this

might not have been the case had these latter worked as they were

originally designed to.

The method finally adopted allowed as many as four buckets to be dumped

on the platform on one end of the arch gantry at one time, and eight on

one end of that used for the bench-walls, the workmen handling about

three of these latter into the forms by the time the last of the eight

was dumped. It required about 1½ min. to place a car under the gantry,

hoist the bucket, dump, close it, and return it to the car below.

Rock packing was stored at the other end of the platform, for use as

required, when it was not handled directly from the end nearest the

work. This method allowed the concrete and other materials to be brought

in in trains at infrequent intervals, and provided a sufficient supply

of material on hand so that the men handling it on top could be kept

steadily at work.

Each hoisting engine on these gantries had 7 by 10-in. cylinders, and a

double drum; some of them were Lamberts and some Mundys, operated by

compressed air.

_Ditches, Floor and Foundations._--The first method of building the

foundation was that shown by Fig. 13, _A_; no attempt was then made to

build the ditch, or floor, the intention being to leave these until the

completion of the remainder of the lining. In building the bench-wall on

this foundation, however, it was found difficult to secure the bottom of

the forms properly (Fig. 2, Plate XXV), so as to prevent any give, as

the material under the track was not solid enough to brace against. It

was decided, therefore, to build the whole of the ditch (see Fig. 13,

_B_) so that the bottom of the forms could be braced against the solid

concrete. At the beginning of the work, the face of the bench-wall was

built up to the level of the bottom of the conduits with the foundation;

if, therefore, in placing the concrete above this level, extreme care

were not taken to get a tight fit between the bench-wall form and the

lower face, and then to hold it rigidly in place, the result was a

rather unsightly horizontal joint high enough to be plainly visible. The

position of this joint may be seen in Fig. 2, Plate XXV, which shows the

first section of bench-wall built. Several subsequent sections showed an

overhang above this joint, amounting in one or two cases to as much as ½

in., due to the fact that the bench-wall form moved or did not fit

tightly. This defect was obviated by building the foundations with an

offset on the face, shown by Fig. 13, _B_, so that the joint came at the

level of the top of the flagging over the ditches, and therefore was

almost entirely concealed; at the same time this allowed a sufficient

surface, on the plane of the face of the bench-wall, against which the

bench-wall forms could be braced and lined up.

[Illustration: Fig. 13.

PLAN SHOWING VARIOUS METHODS OF BUILDING FLOOR AND FOUNDATION,

AND DETAILS OF FORMS]

The ditch forms were set very carefully to line and grade by the

alignment corps, as this formed the starting point of all the rest of

the work, the only other thing which was necessary was to give a level

at the front end of the bench-wall form, after it was set, for the

elevation of the top of the bench, and to check up the stations of the

ends of the sections occasionally to see that they were at the even

25-ft. points (that is +08, +33, +58, and +83).

After a short length had been built with the ditches only, it was

thought desirable to try and put in the floor as well, so that the whole

of the concrete would be put in place as the lining advanced, and leave

less cleaning up to be done over the end of a single track, in the

restricted spaces between the bench-walls. Fig. 13, _C_, shows the

method finally adopted. In this may be seen the three stages in which it

was put in, the details of the ditch forms being shown by Fig. 13, _D_.

In that part of the tunnel where sand-walls were built, a hollow tile

drain was built into the foundation, as shown in Fig. 13, _A_ and _B_,

along the foot of the water-proofing and connected at intervals with the

drains by 4-in. cast-iron pipes. When the sand-walls and water-proofing

were not built, however, the concrete of the foundations was sloped from

the neat line back to the rock, as shown by Fig. 13, _C_3, so that in

case any water found its way down through the rock packing, its tendency

would be to flow back against the rock, or to follow the low part of

this concrete to 4-in. cast-iron pipes leading to the side ditches,

rather than to find its way through the joint between the foundation and

the bench-wall and so into the lower duct lines.

_Sand-Walls._--The sand-wall forms first used are shown in Fig. 2, Plate

XXIV, with a section of the finished sand-wall. As this work was only

intended to give a comparatively smooth surface against which to place

the water-proofing, no particular care was taken with the surface,

except to avoid sharp projections which might cut through the felt and

pitch used for this purpose. A rather porous concrete (with all the rock

which could be safely embedded in it and have the wall stand) was used,

so that it would not act as a dam, but rather tend to allow the water to

find its way to the bottom of the tunnel, and so into the drains.

The traveling gantry for placing the concrete in the sand-walls, as

first designed, with the belt conveyor, could of course only deliver the

concrete at one end. Before setting the forms for a new section, it was

necessary, therefore, to move the gantry ahead, before the cross-bracing

between the tops of the forms, which also held the top platform, could

be placed in position. Fig. 2, Plate XXIV, shows the end of the conveyor

over the top of the cross-braces. In order to hold the bottom of these

forms, small wooden blocks were embedded in the foundation concrete,

against which they could be wedged, as shown by Fig. 13, _A_; these

blocks were cut out after the sand-wall had been built.

After the forms had been filled, the conveyor could not be moved back to

the bench-wall until the concrete had set sufficiently so that these

cross-braces could be removed, and, on account of the overhang at the

top, the set had to be fairly good in order to prevent this overhang

from breaking off. This arrangement, therefore, for placing the concrete

was found to be impractical, if the proposed schedule of a section of

bench-wall and a section of sand-wall to be built on alternate days, was

to be carried out. In a few instances, where the sand-wall was finished

fairly early in the afternoon, the forms were released next morning, and

the conveyor was moved back, but, even then, 2 or 3 hours at least were

lost at the beginning of the shift. The conveyor, however, was

abandoned, for the reasons previously given, and the traveling gantry

was rearranged to allow concrete to be delivered at either end; it was

then only necessary to move it backward and forward between the bench-

and sand-wall forms instead of through these forms. This permitted the

construction of the much more substantial type of forms shown by Fig.

14.

After being moved ahead on the track on top of the foundation, the form

was first blocked up to grade, and then adjusted to line by the screws

and slotted cleats shown at _B_, Fig. 14, after which it was secured by

the braces from the ditches, as shown. The face lagging was placed in

separate pieces and held against the uprights by lightly nailing every

third or fourth piece; the whole was removed each time the form was

moved, and built up again as the concrete was placed.

Considerable care was taken to slope the top of the sand-wall back

toward the rock, as shown by Fig. 14, and to allow free drainage along

the top (which ran parallel to the grade of the tunnel) to the 4-in.

cast-iron drain pipes which carried the water from the rock packing

above the arch to the drains beneath the track.

Sand-walls were built for a length of about 1,100 ft. in each tunnel at

the Weehawken end, and about 700 ft. in each tunnel at the western end,

the remainder of the work, with the exception of a few short stretches,

not being considered wet enough to require water-proofing.

[Illustration: Fig. 14.

TRAVELING FORM FOR BUILDING SAND-WALL;

DETAIL SHOWING METHOD OF HANGING WATER-PROOFING FROM TOP OF SAND-WALL]

_Conduits._--The arrangement of the conduit lines is shown in the

general cross-section.[3] On the core-wall side there are 48 lines for

telegraph and telephone cables, built of 4-way multiple conduit, each

piece of which is 3 ft. long and about 10 in. square outside. On the

other side there are the high- and low-tension lines, built of single

conduit 18 in. long and a little more than 5 in. square outside.

Manholes or splicing chambers are built every 400 ft., and are about

8 ft. long and 4 ft. wide. General views of the conduits as built are

shown in Fig. 4, Plate XXV, which shows all the lines in one tunnel, and

in Fig. 1, Plate XXV, which shows the telegraph and telephone lines,

with the expanding mandrels used in laying them.

[Footnote 3: Plate VIII in the paper by Mr. Jacobs.]

[Illustration: Plate XXV.

Fig. 1: K 173. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels.) Hackensack Portal and Approach. Telephone and Telegraph

ducts and mandrels. Nov. 20, 08.

Fig. 2: K 125. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels) Weehawken Shaft, North Tunnel. View showing general

construction of tunnel lining forms, and clearance to allow disposal

of excavated material. June 17, 07.

Fig. 3: K 156. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels) Weehawken Shaft, South Tunnel. North side looking East,

showing method of placing waterproofing. Oct. 22, 07.

Fig. 4: K 147. P.R.R. Tunnels, N. R. Div. Sect. K. (Bergen Hill

Tunnels) Weehawken. General view showing center and first section of

arch and completed lining, North Tunnel. Sept. 24, 07.]

In attempting to plan the work of placing the lining, two methods of

building the bench-wall were considered. One was to build the wall in

longitudinal sections, each section separated by a line of ducts; and

the other was to attempt to build the wall in the manner called for by

the specifications, which required the concrete to be carried up in

layers as the conduits were laid. In this latter method, it was proposed

to bond the concrete together with the forked bonds, the details of

which are shown by Fig. 15, _A_, but, as it might have been impractical

to use these if the wall had been built in sections, provision was made

in the contract to place expanded metal, as shown by Fig. 15, _B_, if

this was thought advisable. The method of construction necessary, if the

wall had been built in sections, is shown graphically by the five

sketches, Fig. 15, _B_, 1, 2, 3, 4, and 5.

The form and details of the expanding mandrel which was finally designed

to meet the conditions, and proved so satisfactory in every way, are

shown by Fig. 15, _C_. The mandrel consisted of two triangular pieces of

hard pine, separated by wedges attached to one piece which fitted into

slots in the other; these, when expanded, practically filled the whole

of the inside of the ducts. One of these mandrels was placed in each

line of single ducts and two in each 4-way duct, placed diagonally, as

shown in Fig. 1, Plate XXV. This required 60 mandrels at each working

point, or 240 for the whole work. The mandrels were 35 ft. long, so that

they easily covered the whole of a 25-ft. section, projected

sufficiently far back into the previously finished work to assure the

continuity of the alignment, and allowed the ends to be racked out at

the forward end to secure proper breaks between the joints.

In laying the single conduits, as a rule, the (collapsed) mandrels were

pulled ahead from the previous section as each line was laid, and the

conduits were strung on it until the whole length was completed; the

conduits were then pushed up tight together, so as to close the joints

as tightly as possible, and then the mandrel was expanded. The conduits

were thus held firmly in position, and the forward end of the line was

lifted slightly so that the wraps could be placed around the joints. The

4-way conduits were generally laid in the ordinary way, except that no

laying mandrel was necessary. One dowel was used between each of the

pieces of conduit, at the center, and the joints were wrapped. When a

line was finished, two mandrels were placed diagonally in each line and

expanded simultaneously, so that any inequalities in the ducts

themselves were divided as far as possible. In connection with the use

of these mandrels, one of the points which was most carefully watched

was that they projected back into the last completed section, thus

insuring the continuity of the alignment.

It was originally intended to wrap the joints of the 4-way ducts only,

but it was found to be impractical to keep the grout from the wet

concrete entirely out of the single ducts, and, after a short trial, it

was decided to wrap these also. The expanding mandrel kept out a great

deal of the cement, and, in the sections laid without wraps, the only

difficulty from this cause seemed to be that a slight film of grout,

from 1/16 to 1/8 in. thick, was deposited on the bottom of the inside of

the ducts at some places, and although this was not considered a serious

defect, it was thought that the slight extra cost of placing the wraps

would undoubtedly be justified by the practically perfect results

obtained by using them.

Considerable attention was given to breaking the joints of the ducts

properly, so as to maintain throughout the conduit lines the greatest

break possible. The joints in each superimposed line were broken at half

the length of the individual pieces of conduit, the joints in lines in

the same horizontal plane being broken at one-quarter the length, thus

preventing any joints from touching one another either at the sides or

corners, which tended to prevent a burn-out on one line from being

communicated to another. There was some little difficulty at first in

maintaining the breaks, owing to slight variations in the lengths of the

conduit, but after a very short time both the workmen and the inspectors

became very expert at this and in the proper use of short lengths to

maintain the spacing; after the first few weeks there was little if any

difficulty in attaining at all times almost perfect results. The method

of making the breaks is shown in the photographs and by the isometric

sketch at _F_, Fig. 15.

All the conduits used on this work were furnished by the Great Eastern

Clay Company, and were made at its factory at South River, N.J., where

they were inspected before shipment.

The mandrel used in the final rodding was made as shown at _G_, Fig. 15,

the larger size being used for all lines. The rods for pushing it

through the conduit lines were made of 6½-ft. lengths of ordinary 1-in.

wrought-iron pipe with extra long (3-in.) couplings. The lines were

rodded in both directions from alternate manholes, thus avoiding

uncoupling the rods and allowing every pull to be effective in pushing

the mandrel through the ducts.

[Illustration: Fig. 15. [Full Page]

ELECTRICAL CONDUITS: METHODS OF LAYING, RODDING, ETC.

A. FORK ENDED STEEL BONDS FOR CONDUITS.

B. SEQUENCE OF METHODS OF BUILDING BENCH-WALL PROPOSED WHEN USING

EXPANDED METAL BONDS.

C. ISOMETRIC DRAWING OF EXPANDING MANDREL.

D. DETAILS OF "WEASEL" Used for gripping disconnected pipe rods in

conduit

E. CUTTER FOR REMOVING OBSTRUCTIONS IN CONDUITS.

F. ISOMETRIC SKETCH SHOWING METHOD OF BREAKING JOINTS AND POSITION

FORKED BONDS.

G. PLAN AND SECTIONS OF EXPANDING MANDREL.

INDEX

+-----+------------+----------------+

| | Multi-Duct | Single-Duct |

| | Mandrel | Mandrel |

+-----+------------+----------------+

| _A_ | 3¼" | 3-3/8" |

| _B_ | ¾" | 7/8" |

| _C_ | 2½" | 2-5/8" |

+-----+------------+----------------+

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The Bergen Hill Tunnels. Paper No. 1154 · 第 10 / 15 题