PROGRESS.

The total time elapsed from the time of starting work at the Weehawken

end, in May, 1905, to the completion of the excavation, in May, 1908,

was almost exactly three years. Of this time about 40 days were lost in

February and March, 1906, when work was stopped by the Receiver of the

Shields Company, the total number of days actually worked being about

940, giving an average progress of 6.26 ft. per working day in each of

the two tunnels, which, omitting the Central Shaft headings, gives an

average rate of progress for each working face, of 3.13 ft. per day.

These 940 days include practically all the time elapsed, except Sundays

and such few holidays as were observed. For some of this time, work was

being carried on at only one or two points; the time, therefore,

represents practically the total possible working time during the period

covered.

_Progress at Weehawken._--At Weehawken the total number of days worked

was 763, divided as follows:

186 days in timbered section, about 426 ft., an average rate of 2.3 ft.

per day in each tunnel;

176 days in hard sandstone, about 563 ft., an average rate of 3.2 ft.

per day in each tunnel;

112 days in hard trap, about 267 ft., an average rate of 2.4 ft. per

day in each tunnel;

289 days in ordinary trap, about 1,316 ft., an average rate of 4.55 ft.

per day in each tunnel.

_Progress at Central Shaft._--At Central Shaft the average length driven

per day in each of the four headings is shown by Table 4.

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The Bergen Hill Tunnels. Paper No. 1154 · 第 4 / 15 题