TABLE 4.

-----------+----------------+-----------------+---------------------+

Location. | Number of days | Total length of | Average length of |

| worked. | heading, in | heading driven per |

| | feet. | day worked, in feet.|

-----------+----------------+-----------------+---------------------+

| | | |

N.E. | 227 | 446 | 1.96 |

S.E. | 168 | 346 | 2.06 |

N.W. | 272 | 768 | 2.82 |

S.W. | 234 | 698 | 2.98 |

-----------+----------------+-----------------+---------------------+

_Progress at Hackensack._--At Hackensack the total number of days worked

on the tunnels proper, all in trap rock (omitting the cut and cover) was

about 792, divided as shown in Table 5.

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The Bergen Hill Tunnels. Paper No. 1154 · 第 5 / 15 题