TABLE 2.

Hrs. _Hours._

Min. _Minutes._

----------------+----------+---------------+----------------

Date. | Place. | Total | Number of feet

| | working time. | drilled.

----------------+----------+---------------+----------------

| | Hrs. Min. |

Jan. 14th, 1907 | Whk. N. | 8 0 | 15

" 15th, 1907 | " N. | 7 32 | 12

| " N. | 7 22 | 14

" 12th, 1907 | " S. | 8 0 | 20

| " S. | 8 0 | 11

| " S. | 8 0 | 10

" 11th, 1907 | Hack. N. | 8 0 | 13

" 17th, 1907 | " N. | 7 10 | 10

| " N. | 7 5 | 11

| " N. | 7 10 | 10

" 16th, 1907 | " S. | 4 20 | 10

| " S. | 6 9 | 10

| " S. | 7 ... | 8

----------------+----------+---------------+---------------

Totals. | | 93 48 | 154

----------------+----------+---------------+---------------

Average: 36.6 min. per ft. drilled, or 1.64 ft. drilled per hour.

As a check on the average figures obtained from various sources, the

following estimate of the cost of drilling per cubic yard was made up

from these average figures, for comparison with the actual average cost

on the whole work. The cost records show this to be about $2.25 per yd.,

exclusive of power for running the drills, almost exactly what the

following estimates give for theoretical average conditions, although no

effort was made to have this latter compare so closely.

_Estimated Cost per Drill per Day._

Drill Runner 1 at $3.50 per day, $3.50

Helper 1 " 2.00 " " 2.00

Nipper 1/5 " 1.75 " " 0.35

Heading foreman 1/12 " 5.00 " " 0.42

Walking boss 1/50 " 7.50 " " 0.15

Blacksmith 1/12 " 4.00 " " 0.34

Blacksmith helper 1/12 " 2.00 " " 0.16

Machinist 1/12 " 3.00 " " 0.25

Machinist helper 1/24 " 1.75 " " 0.07

Pipe fitter and helper 1/50 " 5.00 " " 0.10

Oil, waste, blacksmith coal, etc. 0.24

Drill steel, 6 in. per shift 0.20

-----

$7.78

Average number of feet drilled per cubic yard 3 to 3.5

Number of feet drilled per drill, per shift 10.5 to 12

Number of yards per drill, per shift 3.5±

Cost of drilling, per yard, $7.78/3.5 $2.22±

In all the foregoing tables and computations, the quantities used have

been those paid for. The quantity taken out, however, has been 10% more

than that paid for, and 28% more than the contractor was actually

required to take out.

The specifications required that the excavation should be taken entirely

outside of the neat line, as shown on Plate VIII of the paper by Mr.

Jacobs, but not necessarily beyond this line, but that the contractor

would be paid for rock out to the standard section line, which is 1 ft.

larger on the sides and top and 6 in. deeper in the bottom than the neat

line.

A great deal of the extra quantity was due to rock falling from the

core-wall side whenever one working face was behind the other. Blasting

at the face behind generally loosened more or less rock on the core-wall

side of the tunnel which was ahead, in one or two instances breaking

entirely through, as shown in Fig. 2, Plate XXVI, the hole in the

core-wall in this case being utilized by building a storage chamber in

it.

Table 3 gives some of the statistics of drilling in the Simplon Tunnel,

as compared with the drilling on this work, the figures for the Simplon

being taken from papers read before the Institution of Civil Engineers

of Great Britain.

TABLE 3.

-------------------------------------------+--------------+----------

| |

| Bergen Hill. | Simplon.

-------------------------------------------+--------------+----------

Drills set up in heading, percentage of | |

total elapsed time | 50% | 60%

Actually drilling the rock, percentage of | |

total elapsed time | 25% | 50%

Average advance per round (attack) | 8.5 ft. | 3.8 ft.

Average time for each attack | 36 hours. | 5 hours.

Average advance per day of 24 hours | 5 ft. | 18 ft.**

Depth of holes | 10 ft. | 4.6 ft.

Diameter of holes | 2¾ in. | 2¾ in.

Linear feet drilled per hour, per drill | 2.7 | 7.0

Linear feet drilled per cubic yard | 5.0 | 6.0

Pounds of dynamite per cubic yard | 3.4 to 5.7 | 8½

Average depth drilled with one sharpening | 12 in. | 6½ in.

Total number of men per day of 24 hours* | 450 | 3,300

-------------------------------------------+--------------+----------

[* On Bergen Hill Tunnels, for two full working faces at the

Hackensack end, about 3,000 ft. in from portal (March, 1908). At

Simplon, two full faces and two headings, at a distance of about

5,000 ft. in from the portal (January, 1900). These both include

lining as well as excavation. The lining of the Bergen Hill Tunnels

progressed about twice as fast as the excavation; it is inferred

that on the Simplon it progressed at about the same rate as the

excavation.]

[** At the Italian end, in Antigoric gneiss, which is stated to be

very hard rock.]

The figures in Table 3 are for "heading only" in both cases, except for

the last item (number of men), the heading in the Simplon Tunnels being

about 60 sq. ft., as compared with the heading of Method No 4 (which has

been used for comparison), of 210 sq. ft.

_Mucking and Disposal._--The conditions affecting the disposal of the

muck, after blasting, were quite different at the two ends, the grade

descending in the direction of the loads at Weehawken and ascending at

the Hackensack end. At the Weehawken end the mouth of the tunnels was at

the bottom of a shaft some 80 ft. deep, Fig. 2, Plate XXII, the muck in

the tunnel cars being hoisted by elevators to a platform at the top from

which it was dumped into standard-gauge cars supplied by the Erie

Railroad, as shown by Fig. 7; or later hauled to the crusher or storage

pile, some 500 ft. distant, on the north side of Baldwin Avenue. At the

western end, the cars were hauled directly to the surface through the

approach cut, and the material, except that required for concrete and

rock packing, was deposited in the embankment across the Hackensack

Meadows, a haul of from 1,000 to 3,000 ft. beyond the portal.

All disposal tracks were of 3-ft. gauge, the main running tracks being

generally laid with 60-lb. second-hand rails, although some of lighter

weight were used.

Except for about 1,000 ft. in each tunnel at the Weehawken end, where

the muck was loaded by hand, four steam shovels, operated by compressed

air, were used, one at each working face. One of these was a "Marion,

Model No. 20," weighing 38 tons, the others were "Vulcan Little Giant,"

of about 30 tons each. All these shovels were on standard-gauge track,

and were moved back from 300 to 500 ft. from the working face during

blasting.

[Illustration: Fig. 7.

METHOD OF EMPTYING DUMP CARS AT WEEHAWKEN SHAFT:

FRONT VIEW, SIDE VIEW]

At Weehawken, previous to the time the shovels were installed, the muck

was shoveled by hand into the cars from the bottom of the bench, and the

heading muck was dumped into them from the movable platform (Jumbo)

shown by Fig. 1, Plate XXII. There were three loading tracks at the

face. The cars used at that time were similar to that shown by Fig. 5,

but were about two-thirds the size and had no end door; stop-planks were

supposed to be placed in the ends but seldom were. The loads averaged

about ½ cu. yd. (measured in place). After the shovel was installed the

cars shown by Fig. 5 were used, and the loads averaged nearly 1 cu. yd.

The empty cars were pushed up to the shovel by hand from the storage

track. When loaded, they were given a start with the bucket of the

shovel, and were then allowed to coast by gravity out to the storage

track near the shaft, where they were stopped by placing rolls of cement

bags or burlap on the rails. After the lining was started, the loaded

cars were stopped on the inside of the lining and only sent out over the

single track through this latter at stated intervals, when several cars

followed in close succession, with a long interval which permitted the

concrete to be brought in. The empty cars were hauled back to the

storage track near the working face by mules, one mule usually hauling

two cars at a time.

Up to the time the trap rock was reached, about 1,100 ft. from the

shaft, the excavated material was disposed of by loading it on flat

cars. All the trap, however, was stored to be used later for concrete

and ballast.

When the tunnels were in full working order, sixty muck cars of the type

shown by Fig. 5, were in use, about evenly divided between the two

tunnels. For some time the work was greatly hampered by lack of cars,

and even with the sixty finally obtained, there were many times when

extra cars could have been used to advantage to keep the shovel working.

When mucking by hand, the mucking gangs consisted of from 15 to 20 men.

The maximum output was 50 cu. yd., and averaged about 35 cu. yd. per

shift; there was a great deal of trouble in keeping the gangs full, as

labor at that time was very scarce, and the tunnels were quite wet. The

maximum output of either of the shovels was 159 cu. yd. in one shift,

and the best average in any month--which was between July and December,

1907, during which time only the enlargement and bench of the Central

Shaft headings was being taken out from the western end--was 60 cu. yd.

per shift. As the shovels were generally idle for one shift out of

three, the quantity actually handled averaged 90 cu. yd. per shift

during the shifts the shovel worked. All these quantities were "measured

in place," and, as previously noted, would be about equal to twice as

much measured loose in the cars.

The shovels at both ends were usually worked with three crews for the

two tunnels; two day crews, one at each shovel, and a night crew which

was used in either tunnel as occasion required. The day crews generally

averaged from 45 to 60 hours overtime during the month, one of them

working during the early part of the evenings in the opposite tunnel to

the night crew. For a short time, when the ventilation at the western

end was very bad, four crews were worked, day and night crews in each

tunnel; but, as a general rule, the method of working three crews was

preferred by the men, and was less expensive for the contractor.

At the Hackensack end, 4-yd., Allison, one-way, dump cars were used,

being handled by "dinky" locomotives, of which there were three in use

up to October, 1907, and four after that. One 15-ton Porter engine, with

10 by 16-in. cylinders, was used outside the tunnels for handling the

trains (from 6 to 8 cars) on the dumps and to the crusher; the other

three, 12-ton Vulcans, 9 by 14-in., were used in the tunnels. About 30

dump cars were in use, and of these there were generally from 3 to 6

under repair.

Generally, 4 cars were hauled out together, although 5 and occasionally

6 were handled. The work was generally arranged so that the heavy

mucking shift alternated in the two tunnels, the two engines being

worked there and a single engine in the other tunnel.

The tunnel engines left the cars on a track just outside the portal,

from which they were made up into trains of from 6 to 8 cars and taken

to the dump or crusher by the large "dinky."

The muck from the Central Shaft headings was loaded by hand into cars

similar to that shown by Fig. 5, but smaller and having no door at the

forward end. A double elevator took the cars to a platform about 20 ft.

above the surface, where they were dumped by revolving platforms,

similar to those at Weehawken, into storage bins or directly into

wagons. The muck was all hauled away in wagons; part of it was used to

fill some vacant lots, and part was hauled to the crusher at the Western

Portal.

The method under which the best results were obtained was that in which

a full round was blasted every 36 hours, securing an advance of

practically 9 ft. of full section. During the first shift of the three,

as soon as the blasting had been completed and lights strung, the shovel

was moved forward, and cleaned up the floor to the main pile of muck,

the material from the blast being scattered from 150 to 300 ft. back

from the face; during this shift, also, the drillers mucked the heading

and set up their drills, the muckers helping to carry in the columns and

drills. During the second shift the main pile of muck was disposed of,

leaving not more than 2 or 3 hours' work for the shovel on the third

shift. This left nearly the whole of the third shift for drilling the

lift holes.

_Ventilation._--At Weehawken considerable difficulty was caused by fog

and smoke accumulating in the tunnels after blasting. This was generally

worse on days when the barometric pressure was low outside, and worse in

the North than in the South Tunnel. A 6-ft. fan, driven by an electric

motor, was installed in the cross-passage at Station 274, 900 ft. from

the shaft, the headings at that time being about 300 ft. in advance of

this point, to force the air from the South into the North Tunnel,

drawing it in at the mouth of the South Tunnel and discharging it at the

mouth of the North Tunnel, thus insuring a circulation in both tunnels,

as shown in plan by Fig. 8.

[Illustration: Fig. 8.]

This necessitated, of course, that the cross-passages between that in

which the fan was placed and the mouths of the tunnels should be blocked

tight. There was some difficulty in keeping this blocking tight, owing

to the force of the blasting blowing out the bulkheads. The fan,

however, did good service when it and the bulkheads were in good order.

The compressed air discharged from the drills kept the headings fairly

clear, as well as that part of the tunnel between the headings and the

fan. The fan was moved ahead to the next cross-passage at Station 277

when the work had progressed far enough, and was used there for some

time; it was found, however, that by the time the excavation had reached

Station 280, about 1,500 ft. from the shaft, there was practically no

further difficulty from fog and smoke. No satisfactory explanation was

found for this, as it would rather be expected that the ventilation and

trouble with smoke and fumes from blasting would be worse as the

distance increased between the mouth of the tunnel and the working face.

One explanation was offered: That the blasting of the softer sandstone

tended to create more and lighter dust than the heavier trap rock;

whether or not this was so, it is a fact that there was far less trouble

with fog and smoke after the sandstone was passed.

At Hackensack, the principal cause of trouble was the smoke from the

"dinky" locomotives. As the tunnels progressed, this gradually became

worse, until a connection was made with the Central Shaft headings.

A fan was installed in the cross-passage at Station 316 (700 ft. in from

the portal), but was never worked properly. Apparently, the men, at

least the walking bosses and foremen, had little faith in the fan as a

means of ventilation; no real attempt was made to keep it in order or

operate it properly, and a great deal of time and money was lost groping

around in the smoke and fog, the density of which increased, not only

with the state of the atmosphere, but also with the direction of the

wind. On some days the tunnels easily cleared themselves, and on others

the smoke was so thick that a candle held at arm's length could not be

seen. At this end, the South Tunnel was generally worse than the North.

After the headings were holed through between the portal and the Central

Shaft there was very little trouble, there being usually a strong

up-draft through the shaft. This was so pronounced when the wind was

blowing toward the portal, that the moisture-laden air, as it ascended

from the mouth of the shaft, presented the appearance of a heavy

rainstorm with the rain ascending instead of descending. When the wind

was blowing away from the portal, that is, from the southeast, the

effect of the shaft as a chimney was neutralized, and, consequently, the

smoke accumulated in the tunnels. To overcome this, a large blower, with

a fan 9 ft. in diameter, and with blades 4 ft. wide and 2 ft. 3 in.

long, operated by a vertical 12-h.p. engine, was installed at the top of

the shaft, and this kept the tunnels reasonably clear of smoke at all

times. After the bench and enlargement had passed the bottom of the

shaft, the use of the fan was abandoned, as it was found that the

tunnels cleared themselves fairly well, probably owing to the larger

cross-section reaching all the way to the Shaft. What little fog and

smoke there might be did not cause enough trouble to warrant the cost of

running the fan, which, owing to its location, required the whole time

of a mechanic in attendance day and night.

_Lighting._--During the earlier stages of the work, gasoline lamps and

Kitson lights were used. The former, of the familiar banjo type, and a

modification of this, with a section of wrought-iron pipe for the

reservoir, were very unsatisfactory, and were out of repair and leaking

a large proportion of the time. The Kitson lights were given only a

short trial, but were found unsatisfactory, owing to the necessity of

moving them frequently and having to set them up in insecure positions.

Electric lights were installed by Mr. Bradley, on his assumption of the

contract.

The number of lamps maintained in each of the tunnels for the excavation

was approximately as follows:

At the main working face From 8 to 10

On and around the shovel " 9 to 12

Between the portal and the working face " 60 to 80

The cost of lighting for the whole work averaged about 15 cents per

cu. yd., which is quite large. This was mainly due to the fact that

current was bought from outside sources during a large part of the time

(one-third of the yardage). Part of this current cost 5 cents per

kw-hr., and there were fairly heavy charges for connecting the tunnel

wiring system with the source of supply. Current bought from the Public

Service Corporation cost from 10 to 12 cents per kw-hr. delivered at the

mouth of the tunnel.

_Pumping._--The quantity of water encountered during the excavation of

the tunnels, measured somewhat roughly, was approximately as follows:

At Weehawken 74 gal. per min.

At Central Shaft 1 " " "

At Hackensack 18 " " "

The water at the Weehawken end had to be pumped from the bottom of the

shaft, a lift of about 90 ft., while at the Hackensack end it had to be

pumped back from the face up grade to the portal.

The cost of pumping was about $100 to $125 per month for labor for the

whole work, besides the cost of the plant (about $1,200) and the power

for running it.

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The Bergen Hill Tunnels. Paper No. 1154 · 第 3 / 15 题