PIERS AND TRESTLE FOR DISPOSAL.

The most rapid and economical handling of all excavated material to

scows was made possible by the Tunnel Company procuring from the New

York Central and Hudson River Railroad Company the pier at the foot of

32d Street, North River, known in the earlier stages of the work as Pier

No. 62, but subsequently changed to Pier No. 72, and thus referred to in

this paper. This pier was occupied by a freight-shed used by the New

York Central Railroad Company, under a long-term lease from the City,

and that Company had to make numerous changes in their tracks and

adjoining piers before No. 72 could be turned over; the contract for

the excavation, therefore, required the contractor to procure any piers

needed previous to and in addition to it. Under this clause of the

agreement, the contractor procured one-half of the pier at 35th Street,

North River, which was used for the disposal of all material excavated

previous to May 22d, 1905, on which date Pier No. 72 was first put in

service.

As the type of plant the contractor would elect to use could not be

determined, previous to the letting of the contract, a general plan for

Pier No. 72 and the trestle approach, suitable for either trains or

wagons, was attached to the contract, and the details were worked out

afterward. The method adopted was by train, and a two-track approach to

the pier was provided. Beginning on the east side of Ninth Avenue, at

the south line of 32d Street, at an elevation of 20 ft. below the

surface, crossing under Ninth Avenue and to the center line of 32d

Street, it rose on a 1.5% grade in open cut to the surface of 32d Street

at a point 500 ft. west of Tenth Avenue, from which point it rose above

the surface of the street on a timber trestle to Tenth Avenue, which was

crossed overhead. West of Tenth Avenue the line changed by a reverse

curve to the south sidewalk of 32d Street, and continued on a timber

trestle, practically level, to the New York Central Yard tracks near

Eleventh Avenue. These tracks and Eleventh Avenue were crossed overhead

on a through-truss, steel bridge, and a column-and-girder construction

on which the two tracks separated to a distance of 29 ft, between center

lines, so as to bring them directly over the posts of special timber

bents which spanned the two house tracks of the New York Central

south-bound freight shed, which the trestle here paralleled. This

position was held to a point 25 ft. west of the east house line of

Twelfth Avenue, where, by a system of cross-overs and turn-outs, access

was had from either track to six tracks on the pier. Four of these were

on upper decks, two on the north and two on the south edge of the pier,

at an elevation of 41 ft. above mean high tide, to carry earth and small

rock to chutes from which it was dumped into barges. The other two

tracks proceeded by a 5.3% grade down the center of the pier to the

lower deck where, at a distance of 540 ft. from the bulkhead, and beyond

the upper deck construction, they diverged into six, two on the north

and two on the south edge of the pier for standing tracks to serve

derricks, and two down the center for shifting purposes. A siding to the

north of the two running tracks just west of the bottom of the incline

served a bank of eight electric telphers. The arrangement of the pier is

shown by Fig. 4.

The trestle east of the steel structure at Eleventh Avenue had simple

four-post bents, as shown by Bent "_A_," on Fig. 5, all posts being

vertical, to save room at the street level; the outside posts and the

caps and sills were of 12 by 12-in. timber; the intermediate posts were

of 8 by 12-in. timber; and single or double decks of 3 by 8-in. bracing

were used, depending on the height of the bents. These bents were framed

on the ground in position and raised by hand. West of Tenth Avenue, the

sills of the bents rested on four 12 by 12-in. longitudinal timbers,

each spanning two bays and breaking joints, for convenience in

supporting the trestle while the tunnels were constructed in open cut

beneath. These bents were placed 12 ft. on centers, with one 8 by 16-in.

stringer under each rail, and one 6 by 16-in. jack-stringer supporting

the overhang of the floor on either side.

The bents along the New York Central freight shed had but two posts of

12 by 14-in. yellow pine varying from 26 ft, to 31 ft. 9 in. from center

to center; they had double caps of 12 by 14-in. yellow pine on edge, no

bottom sills or bracing, and the vibration and wind pressure were taken

care of by the top bracing and anchorage, as shown by Bent "_G_," on

Fig. 6.

[Illustration:

Fig. 4.

PLANT FOR DISPOSAL OF EXCAVATED MATERIALS PIER NO. 72 N.R.]

The method of erection was as follows: An excavation was made on the

line of each post, 4 ft. deep and from 4 to 5 ft. square, depending on

whether it was for a single or reinforced post; 6 in. of concrete was

placed in the bottom, and on this were laid, at right angles to the

center of the trench, three 8 by 12-in. timbers varying in length with

the excavation from 3 to 4 ft. To these timbers was drifted one 12 by

12-in. timber of the same length as those in the bottom row, but at

right angles to them. Elevations were then taken on top of the 12 by

12-in. timber, and the bent was framed complete and of correct height.

The framing was done south of the line of the trestle and west of the

freight-house. The framed bents were picked up by a small two-boom

traveler carrying two double-drum, electric, hoisting engines, and run

forward into position. A hole had previously been made in the metal

gutter and canopy of the freight-house, by an experienced roofer, and

in the freight platform underneath, and, as soon as the bent had been

dropped into position, it was firmly drifted to the foot-blocks,

previously described, and the excavation made for them was filled with

concrete well rammed about the blocks and rounded off 6 in. above the

surface of the ground. Secure flashings, in two sections, were then made

about the posts to cover the holes made in the gutter and roof, the

bottom sections being firmly soldered to the roof or gutter, and the top

sections, which lapped over the bottom and cleared them 2 in. in all

directions, were firmly nailed to the posts and the joints leaded. This

arrangement allowed the bents to move slightly, and at the same time

made the roof and gutter water-tight. These bents were placed 16 ft. on

centers to correspond with the spacing of the doors of the freight shed.

Under the cross-overs near Eleventh Avenue, where the tracks had to

be supported in different positions on the caps, and could no longer

be kept over the posts, the caps were trussed and the posts were

reinforced, as shown on Bents "_J_," "_H_," and "_K_," Fig. 5.

[Illustration:

Fig. 5.

DETAIL OF BENTS FOR MATERIAL TRESTLE]

The trusses for the through bridge over the tracks were erected on

Sunday, April 16th. The two trusses, one 122 ft. and the other 165 ft. 8

in. from center to center of end posts, had been assembled and riveted,

lying flat on cribwork a few feet above the ground, south of the

permanent position and between the New York Central tracks and Eleventh

Avenue. On the date stated, the contractor, having been given permission

to block the Central's tracks from 5 a.m. to 9 p.m., erected a large

steel gin pole just south of the correct position of the center of the

north truss, which was then dragged, from the place where it had been

assembled, across the railroad tracks until the center of the bottom

chord was vertically under its true position, the truss still lying flat

and about at right angles to the center line of the bridge. Chains were

made fast to the top chord at the middle panel of the truss, which was

then turned up to a vertical plane, raised to its permanent position,

and guyed. The gin pole was then shifted and the operation repeated with

the longer truss, after which, half of the floor beams and a part of the

top laterals were bolted in position and the guys were removed, the

bridge being thus erected without the use of falsework of any kind.

During the lifting there was no sag in either truss that could be

noticed by the eye. Fig. 1, Plate LV, shows the bridge erected, with

the exception of the tight timber fence.

Pier No. 72 is directly over the North River Tunnels. When it was turned

over by the New York Central Railroad Company, the contractor for the

construction of those tunnels tore down the shed and removed the deck

and such piles as were in the path of the tubes. This left standing the

four northernmost, the four southernmost and two centers rows of piles

for the entire length of the pier. An additional row of piles was then

driven on either side of the two center rows, and battered so that at

the elevation of the tunnels they would be close to the center rows

and leave as much clear space as possible. The pier, therefore, was

constructed of three independent lines of four-post bents, which,

however, rested on sills which were continuous throughout the width of

the pier, as shown by Figs. 2 and 3, Plate LV.

[Illustration:

Fig. 6.

DETAIL OF BENTS FOR MATERIAL TRESTLE.]

The bents for the upper floors of the pier were double-decked, with

12 by 12-in. posts, sills, intermediate and top caps, and 3 by 8-in.

longitudinal and cross-bracing. The bents for the incline were similar,

except that those below 16 ft. in height were of single-deck

construction. The spacing of the bents varied from 9 ft. 6 in. to 12

ft., except the three outer bays, which had a span of 23 ft., all to

agree with the position of the pile bents. The double-deck construction

extended for the full length of the original pier. A single-deck

extension, of full width and 180 ft. in length, was subsequently built

for the accommodation of four derricks for handling building material

and large rock. The piles for this extension were driven in three sets

of four rows each, similar to those in the old portion of the pier,

except that the bents were driven with a uniform spacing of 15 ft.

between centers. The three sets of bents were topped separately with

12 by 12-in. caps and 12 by 12-in. dock stringers; they were braced with

both cross and longitudinal low-water bracing, and were tied together by

a continuous 12 by 12-in. timber over the dock stringers and 12 by

12-in. packing pieces from stringer to stringer, each of these ties

being supported in the center of the span over the tunnels by two 2-in.

hog rods, Section "_A-A_," Fig. 4.

The south side of the upper deck of the pier carried three sets of nine

hoppers, each set covering 90 ft., a little less than the full length

between bulkheads of the largest deck scows, with 70 ft. clear between

sets, to allow for the length of a scow outside of the bulkhead and to

permit the free movement of boats. Each hopper occupied the full space

between two bents, and, as the caps were topped by strips of timber of

triangular section, with a width of 12 in. on the base and a height of

6 in., protected by a 6 by 6-in. steel angle, each set of hoppers

presented 90 lin. ft. of continuous dumping room. The bottoms of the

hoppers, set at an angle of 45°, were formed by 12 by 12-in. timbers

laid longitudinally, running continuously throughout each set, and

covered by 3-in. planking. The partitions were formed with 4-in. planks

securely spiked to uprights from the floor of the hoppers to the caps;

these partitions narrowed toward the front and bottom so as to fit

inside the chutes. Each hopper was lined on the bottom and sides with

½-in. steel plates, and the bottoms were subsequently armored with 2 by

1-in. square bars laid 3 in. on centers and bolted through the 12 by

12-in. flooring of the hoppers. The chutes, extending from the bottom of

the hoppers, were 20 ft. long and 7 ft. wide, in the clear; they were

formed entirely of steel plates, channels, and angles, and were

supported from the upper deck of the pier by chains; their lower ends

were 17 ft. above mean high tide and 14 ft. 6 in. from the string piece

of the pier. The hoppers and chutes are shown by Fig. 1, Plate LVI.

[Illustration:

Plate LV.

Material Trestle Over N.Y.C. & H.R.R.R. Co.'s Tracks;

and Construction of Pier No. 72, North River

Fig. 1.--Material Trestle Over N.Y.C. & H.R.R.R. Co.'s Tracks.

Fig. 2.--Material Trestle Under Construction on Pier No. 72,

North River, Showing Clear Water Over Tunnel Location.

Fig. 3.--Pier No. 72, North River, Showing Incline as Reconstructed

For Locomotives.]

A length of 150 ft. of the north side of the pier was for the use of the

contractor for the North River tunnels; it was equipped with a set of

nine chutes similar to those for the south side; they were used but

little, and were finally removed to make room for a cableway for

unloading sand and crushed stone.

At the foot of the incline there was a bank of eight telphers running

on rails securely bolted to the tops of 20-in. I-beams, which were hung

from stringers resting on the upper caps. The beams were erected in

pairs, each pair being securely braced together and to the trestle posts

to prevent swaying. Each telpher occupied the space between two bents,

about 10 ft., so that the entire bank commanded a length of 80 ft.,

which was approximately the length of a rock scow between bulkheads. All

supports for the telphers were provided as a part of the trestle, but

the machines themselves were a part of the contractor's plant.

Four derricks were erected on the extension, two on the north and two on

the south edge of the pier, supported on bents at a sufficient elevation

above the floor to clear a locomotive.

After most of the earth had been excavated, the out-bound set of hoppers

on the south side of the pier was removed, and two derricks were erected

in their place and used for unloading sand, crushed stone, and other

building material.