METHODS OF EXCAVATION.

The distribution of materials to be excavated, as previously outlined,

divided the excavation into three distinct classes, for which different

methods had to be developed.

These three classes were:

_First._--All-rock section.

_Second._--Rock in the bottom, earth in the top.

_Third._--All-earth section.

The extent of the second and third classes was much greater than that of

the first, and they, of course, determined the use of the shield.

Shields had not previously been used extensively in rock work, either

where the face was wholly or partly in rock, and it was necessary to

develop the methods by experience. The specifications required that

where rock was present in the bottom, a bed of concrete should be laid

in the form of a cradle on which to advance the shield.

_All Rock._--At different times, three general methods were used for

excavating in all-rock sections. They may be called: The bottom-heading

method; the full-face method; and the center-heading method.

The bottom-heading method was first tried. A heading, about 8 ft. high

and 12 ft. wide, was driven on the center line, with its bottom as

nearly as possible on the grade line of the bottom of the tunnel. It was

drilled in the ordinary manner by four drills mounted on two columns.

The face of the headings varied from 10 to 30 ft. in advance of the

cutting edge. After driving the heading for about 10 ft., the bottom was

cleared out and a concrete cradle was set. The width of the cradles

varied, but was generally from 8 to 10 ft.

The excavation was enlarged to full size as the shield advanced, the

drills being mounted in the forward compartments of the shield, as

shown by Fig. 1, Plate LXVII, which represents the conditions after the

opening had been cut in the bulkhead, but before the new methods,

mentioned later, had been developed.

[Illustration: PLATE LXVIII]

The sides and top were shot downward into the heading. The area of the

face remaining behind the heading was large, and a great number of holes

and several rounds were required to fire the face to advantage. As soon

as firing was started at the face, the heading was completely blocked,

and operations there had to be suspended until the mucking was nearly

completed. The bottom-heading method was probably as good as any that

could be devised for use with the shields as originally installed. All

the muck had to be taken from the face by hand and handled through the

chutes or doors. By drilling from the shield, some muck was blasted on

to the extensions of the floors and could be handled from the upper

compartments. At best, however, the shield with the closed transverse

bulkhead was a serious obstacle to rapid work in rock sections.

The full-face method was only used where the rock was not considered

safe for a heading. A cut was fired at the bottom, together with side

holes, in a manner quite similar to that adopted in the first set of

holes for a bottom heading. The cradle was then placed, in lengths of

either 2.5 or 5 ft., after which the remainder of the face was fired in

the same manner as for the bottom-heading method. The closed transverse

bulkhead with air-locks, as shown in Fig. 1, Plate LXVI, was placed in

the shield in the hope that it would only be necessary to maintain the

full air pressure in the working compartments in front of the bulkhead.

It was also thought that some form of bulkhead which could be closed

quickly and tightly would be necessary to prevent flooding the tunnel in

case of blows. While no attempt was ever made to reduce the pressure

behind the shield bulkhead, it was obvious from the experience with

Tunnels _B_ and _D,_ while working in the sand between Manhattan and the

reef, that the plan was not practicable, and that the closed bulkhead in

the bottom was a hindrance instead of a safeguard. As soon as rock was

encountered in those tunnels at the west edge of the reef, the

contractor cut through the bulkheads and altered them, as shown in Fig.

2, Plate LXVI.

Taking advantage of the experience gained, openings were cut through the

bulkheads in Shields _A_ and _C_, while they were shut down near the

edge of the Manhattan ledge. In erecting the shields at Long Island

City in May and June, 1906, openings were also provided. These shields

had to pass through about 700 ft. of rock at the start, the greater

portion of which was all-rock section. It was at that point that

openings were first used extensively and methods were developed, which

would not have been possible except where ears could be passed through

the shield. The bottom-heading method was first tried, but the working

space in front of the shield was cramped, and but few men could be

employed in loading the cars. To give more room, the heading was

gradually widened. The enlargement at the top, when made from the

shield, blocked all work at the face of the heading while the former

operation was in progress. To reduce the delays, the heading was raised,

thus reducing the quantity of rock left in the top, and the bottom was

taken out as a bench. To avoid blocking the tracks when firing the top,

a heavy timber platform was built out from the floors of the middle

working compartments. Most of the muck from the top was caught on the

platform and dropped into cars below. This method of working is shown by

Fig. 2, Plate LXVII. The platforms were not entirely satisfactory, and,

later, the drills in the heading were turned upward and a top bench was

also drilled and fired, as shown by Fig. 3, Plate LXVII. There was then

so little excavation left in the top that the muck was allowed to fall

on the tracks and was quickly cleared away. The method just outlined is

called the center-heading method, and was the most satisfactory plan

devised for full-rock sections.

_Excavation in Part Rock and Part Earth._--This was probably the most

difficult work encountered, particularly when the rock was covered with

boulders and coarse sharp sand which permitted a free escape of air. It

was necessary, before removing the rock immediately under the soft

ground, to excavate the earth in advance of the shield to a point beyond

where the rock was to be disturbed, and to support, in some way, the

roof, sides, and face of the opening thus made. The hoods were designed

mainly for the purpose of supporting the roof and the sides. With the

fixed hood it was necessary either to excavate for the distance of the

desired shove in front of it or else to force the hood into the

undisturbed material. To avoid this difficulty, the sliding hoods were

tried as an experiment.

In using the sliding hood, which will be described in detail in Mr.

Japp's paper, the segments commencing at the top were forced forward by

the screw rod, one at a time, as far as possible into the undisturbed

material. Just enough material was then removed from underneath and in

front of the section to free it, and it was again forced forward. These

operations were repeated until the section had been extended far enough

for a shove. As soon as two or three sections had been pushed forward in

this way, the face near the advance end of the sliding hood was

protected by a breast board set on edge and braced from the face.

Gradually, all the segments were worked forward, and, at the same time,

the whole soft ground face was sheeted with timber. At times polings

were placed over the extended segments in order to make room for a

second shove, as shown on Plate LXVIII. When the shield was advanced the

nuts on the screw rods were loosened and the sections of the hoods were

telescoped on to the shield. The idea was ingenious, but proved

impracticable, because of the unequal relative movements of the top and

bottom of the shield in shoving, bringing transverse strains on the hood

sections.

[Illustration: PLATE LXIX]

With the fixed hood, poling boards were used to support the roof and

sides, and the face was supported in the manner described for the

sliding hoods. The polings were usually maple or oak planks, 2 in.

thick, about 8 in. wide, and 6-1/2 ft. long. In advancing the face, the

top board of the old breast was first removed, then the material was

carefully worked out for the length of the poling. The latter was then

placed, with the rear end resting over the hood and the forward end

forced as far as possible into the undisturbed material. When two or

three polings had been placed, a breast board was set. After several

polings were in position, their forward ends were supported by some form

a cantilever attached to the hood. Plate LXIX shows one kind of

supports. In this way all the soft material was excavated down to the

rock surface, and the roof, sides, and face were sheeted with timber. In

shoving, the polings in the roof and sides were lost. It was found that

the breast could usually be advanced 5 ft. with safety. The fixed hood

made it possible to set the face about 7 or 8 ft. in front of the

cutting edge without increasing the length of the polings. This distance

was ample for two shoves, and was generally adopted, although a great

many faces were set for one shove only.

Fixed hoods were substituted for those of the sliding type, originally

placed on Shields _B_ and _D_ at Manhattan, at about the time the latter

encountered the rock at the reef.

In placing the polings and breasting, all voids behind them were filled

as far as possible with marsh hay or bags of sawdust or clay. To prevent

loss of air in open material, the joints between the boards were

plastered with clay especially prepared for the purpose in a pug mill.

The sliding extensions to the floors of the working compartments were

often used, in the early part of the work, to support the timber face or

loose rock, as shown in Fig. 1, Plate LXVIII. At such times the front of

the extensions was held tightly against the planking by the pressure of

the floor jacks. While shoving, the pressure on the floor jacks was

gradually released, allowing the floors to slide back into the shield

and still afford support to the face. The extensions also afforded

convenient working platforms. They were subject to severe bending

strains while the shield was being shoved, however, and the cast-iron

rams were frequently broken or jammed. The extensions did not last

beyond the edge of the ledge at Manhattan, nor more than about half

through the rock work at Long Island City. The fixed extensions

originally placed on Shields _A_ and _C_ at Manhattan were not

substantial enough, and lasted only a few days.

Wherever the rock face was sufficiently sound and high, a bottom heading

was driven some 20 or 30 ft. in advance of the shield. The heading was

driven and the cradle placed independently of the face of the soft

ground above, and in the manner described for all-rock sections. The

remainder of the rock face was removed by firing top and side rounds

into the bottom heading after the soft ground had been excavated. Great

care had to be taken in firing in order not to disturb the timber work

or break the rock away from under the breast boards. If either occurred,

a serious run was likely to follow. The bottom-heading method is shown

by Figs. 1, 2, and 3, Plate LXVIII, and the breasting and poling by Fig.

2, Plate LXX.

In the early part of the work, where a bottom heading was impracticable,

the soft ground was first excavated as described above, and the rock was

drilled by machines mounted on tripods, and fired as a bench. By this

plan no drilling could be done until the soft ground was removed. This

is called the rock-bench method.

Later the rock-cut method was devised. Drills were set up on columns in

the bottom compartments of the shield, and the face was drilled while

work was in progress on the soft ground above. The drilling was done

either for a horizontal or vertical cut and side and top rounds. The

drillers were protected while at work by platforms of timber built out

from the floors of the compartments above. This plan, while probably not

quite as economical of explosives, saved nearly all the delay due to

drilling the bench.

[Illustration: PLATE LXX, FIG. 1.--SMALL SHAFT SUNK TO ROCK.]

[Illustration: PLATE LXX, FIG. 2.--BREASTING AND POLING IN FRONT OF

SHIELD.]

[Illustration: PLATE LXX, FIG. 3.--SHUTTERS ON FRONT OF SHIELD.]

[Illustration: PLATE LXX, FIG. 4.--HYDRAULIC ERECTOR PLACING SEGMENT.]

_All-Earth Section._--As described by Messrs. Hay and Fitzmaurice, in a

paper on the Blackwall Tunnel,[C] the contractor had used, with marked

success, shutters in the face of the shield for excavating in loose open

material. He naturally adopted the method for the East River work. When

the shields in Tunnels _B_ and _D_, at Manhattan, the first to be driven

through soft ground, reached a point under the actual bulkhead line,

work was partly suspended and shutters were put in place in the face of

the top and center compartments. The shutters in the center compartments

in Shield _D_ are shown in Fig. 3, Plate LXX, while the method of work

with the shutters is shown by Figs. 4, 5, 6, and 7, Plate LXVIII. Fig. 4

on that plate shows the shield ready for a shove. As the pressure was

applied to the shield jacks, men loosened the nuts on the screws holding

the ends of the shutters, and allowed the latter to slide back into the

working compartments. At the end of the shove, the shutters were in the

position shown in Fig. 5, Plate LXVIII. In preparing for a new shove,

the slides in the shutters were opened, and the material in front was

raked into the shield. At the same time, the shutters were gradually

worked forward. The two upper shutters in a compartment were generally

advanced from 12 to 15 in., after which the muck could be shoveled out

over the bottom shutters, as shown on Fig. 6, Plate LXVIII, and Fig. 3,

Plate LXX. No shutters were placed in the bottom compartments, and as

the air pressure was not generally high enough to keep the face dry at

the bottom, these compartments were pretty well filled with the soft,

wet quicksand. Just before shoving, this material was excavated to a

point where it ran in faster than it could be taken out. Much of the

excavation in the bottom compartment was done by the blow-pipe. During

the shove the material from the bottom compartment often ran back

through the open door in the transverse bulkhead, as shown by Fig. 5,

Plate LXVIII.

In the Blackwall Tunnel the material was reported to have been loose

enough to keep in close contact with the shutters at all times. In the

East River Tunnels this was not the case. The sand at the top was dry

and would often stand with a vertical face for some hours. In advancing

the shutters, it was difficult to bring them into close contact with the

face at the end of the operation. The soft material at the bottom was

constantly running into the lower compartment and undermining the stiff

dry material at the top. The latter gradually broke away, and, at times,

the actual face was some feet in advance of the shutters. Under those

circumstances, the air escaped freely through the unprotected sand face.

The joints of the shutters were plastered with clay, but this did not

keep the air from passing out through the lower compartments. This

condition facilitated the formation of blows, which were of constant

occurrence where shutters were used in the sand. In Tunnels _B_ and _D_,

at Manhattan, the shutters were used in the above manner clear across to

the reef. In Tunnel _C_, which was considerably behind Tunnels _B_ and

_D_, the shutters, although placed, were never used against the face,

and the excavation was carried on by poling the top and breasting the

face. The change resulted in much better progress and fewer blows. The

excavation through the soft material in Tunnel _C_ had just been

completed when Tunnel _A_ was started, and the gangs of workmen were

exchanged.

The work in soft ground in Tunnel _A_ thus gained the benefit of the

experience in Tunnel _C_. Shutters were placed only in the top

compartments in this tunnel, and, as in Tunnel _C_, were never used in

contact with the face. The method of work is shown by Figs. 1, 2, and 3,

Plate LXXI. The result was still more rapid progress in Tunnel _A_, and

although the loss of air was fully as great in this tunnel as in the

other three, there was only one blow which caused any considerable loss

of pressure. In Tunnels _A_ and _C_ the diaphragms in the rear of the

center compartments of the lower tiers of working chambers were removed

before the shields entered the soft ground. The change was not of as

much advantage in soft ground as in rock, but it facilitated the removal

of the soft wet sand in the bottom. In Tunnel _A_, after encountering

gravel, a belt conveyor was suspended from the traveling stage with one

end projecting through the opening into the working compartment. The use

of the conveyor made it possible to continue mucking at the face while

the bottom plates of the iron lining were being put in place, and

resulted in a material increase in the rate of progress.

[Illustration: PLATE LXXI]

The shutters were not placed on the Long Island shields at all. Just

before the shields passed into all soft ground, a fixed hood was

attached to each.

The method of working in soft ground from Long Island City is

illustrated by Plate LXXII. The full lines at the face of the shield

show the position of the earth before a shove of the shield, and the

dotted lines show the same after the shove. The face was mined out to

the front of the hood and breasted down to a little below the floor of

the top pockets of the shield. In the middle pocket the earth was

allowed to take its natural slope back on the floor. Toward the rear of

the bottom pockets it was held by stop-planks. The air pressure was

always about equal to the hydrostatic head at the middle of the shield,

so that the face in the upper and middle pockets was dry. In the lower

pockets it was wet, and flowed under the pressure of shoving the shield.

By this method 4,195 lin. ft. of tunnel was excavated by the four Long

Island shields in 120 days, from November 1st, 1907, to March 1st, 1908.

This was an average of 8.74 ft. per day per shield.

The rate of progress, the nature of the materials, and the methods

adopted are shown in Table 2.

_Preparations for Junction of Shields._--As previously mentioned, the

Manhattan shields were stopped at the edge of the reef. Before making

the final shove of those shields, special polings were placed with

unusual care. The excavation was bell-shaped to receive the Long Island

shields. The arrangement of the polings is shown by Figs. 4 and 5, Plate

LXXI. After the shields were shoved into final position, as shown at the

right in Fig. 5, the rear end of the polings rested over the cutting

edge and allowed room for the removal of the hood. After the latter had

been accomplished, the temporary bulkheads of concrete and clay bags

were built as a precaution against blows when the shields were close

together. An 8-in. pipe was then driven forward through the bulkhead for

distances varying from 30 to 100 ft., in order to check the alignment

and grade between the two workings before the shields were actually

shoved together. The errors in the surveys were negligible, but here, as

elsewhere, the shields were not exactly in the desired position, and it

took careful handling to bring the cutting edges together. The Long

Island shields were driven to meet those from Manhattan.

TABLE 2.--RATE OF PROGRESS, NATURE OF MATERIALS, AND METHODS ADOPTED IN

CONSTRUCTION OF EAST RIVER TUNNELS.

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The East River Tunnels. Paper No. 1159 · 第 18 / 35 题