MANHATTAN SHAFTS.

A permanent shaft, similar to the river shafts in Long Island City, was

constructed at Manhattan over each pair of tunnels. Each shaft was

located across two lines, with its longer axis transverse to the

tunnels. Plate XIII shows their relative positions. They were divided

equally by a reinforced concrete partition wall transverse to the line

of the tunnels. On completion, the western portions were turned over to

the contractor for the cross-town tunnels for his exclusive use.

_South Shaft._--Work on the south shaft was started on June 9th, 1904,

with the sinking of a 16 by 16-ft. test pit in the center of the south

half of the south shaft, which reached disintegrated rock at a depth of

about 20 ft.

Starting in August, the full shaft area, 74 by 40 ft., was taken out in

an open untimbered cut to the rock, and a 20 by 50-ft. shaft was sunk

through the rock to tunnel grade, leaving a 10 or 12-ft. berm around it.

(Fig. 1, Plate LXX.)

The erection of the caisson was started, about the middle of January, on

the rock berm surrounding the 20 by 50-ft. shaft and about 15 ft. below

the surface. Fig. 3, Plate LXIV, shows the cutting edge of the caisson

assembled. The excavation of the small shaft had shown that hard rock

and only a very small quantity of water would be encountered, and that

the caisson need be sunk only a short distance below the rock surface.

Therefore, no working-chamber roof was provided, the caisson was built

to a height of only 40 ft., and the circular openings were permanently

closed.

The assembling of the caisson took 2-1/2 months, and on April 2d

lowering was started. Inverted brackets were bolted temporarily to the

cutting-edge stiffening brackets, and the sinking was carried on by

methods similar to those used at Long Island. The jacks and blocking

supporting the caisson are shown in Fig. 4, Plate LXIV. As soon as the

cutting edge entered the rock, which was drilled about 6 in. outside of

the neat lines, the space surrounding the caisson was back-filled with

clay and muck to steady it and provide skin friction. As the friction

increased, the walls were filled with concrete, and as the caisson

slowly settled, it was checked and guided by blocking. The cutting edge

finally came to rest 31 ft. below mean high water, the sinking having

been accomplished in about seven weeks, at an average rate of 0.50 ft.

per day.

The final position of the cutting edge in relation to its designed

position is shown in Table 1.

A berm about 4 ft. wide was left at the foot of the caisson below which

the rock was somewhat fissured and required timbering. The cutting edge

of the caisson was sealed to the rock with grout on the outside and a

concrete base to the caisson walls on the inside, the latter resting on

the 4-ft. berm. Following the completion of the shaft, the permanent

sump was excavated to grade for use during construction.

_North Shaft._--The north shaft had to be sunk in a very restricted

area. The east side of the caisson cleared an adjoining building at one

point by only 1 ft., while the northwest corner was within the same

distance of the east line of First Avenue. As in the case of the Long

Island shafts, the steelwork for only the lower 40 ft. was ordered at

the start. This height was completely assembled before sinking was

begun. The caisson was lowered in about the same manner as those

previously described. The bearing brackets for the hydraulic jacks were

attached, as at the south shaft, to the inside of the cutting-edge

brackets. The east side of the caisson was in contact with the

foundations of the neighboring building, while the west side was in much

softer material. As a consequence, the west side tended to settle more

rapidly and thus throw the caisson out of level and position. To

counteract that tendency, it was necessary to load the east wall heavily

with cast-iron tunnel sections, in addition to the concrete filling in

the walls.

Soon after sinking was begun, a small test shaft was sunk to a point

below the elevation of the top of the tunnels. The rock was found to be

sound, hard, and nearly dry. It was then decided to stop the caisson as

soon as a foundation could be secured on sound rock. The latter was

found at a depth of 38 ft. below mean high water. With the cutting edge

seated at that depth, the top of the caisson was only 2 ft. above mean

high water, and as this was insufficient protection against high tides,

a 10-ft. extension was ordered for the top. Work, however, went on

without delay on the remainder of the excavation. The junction between

the cutting edge and the rock was sealed with concrete and grout. The

caisson was lowered at an average rate of 0.53 ft. per day. The size of

the shaft below the cutting edge was 62 ft. 7 in. by 32 ft. The average

rate of excavation during the sinking in soft material was 84 cu. yd.

per day. The average rate of rock excavation below the final position of

the cutting edge was 125 cu. yd. per day. There were night and day

shifts, each working 10 hours. Excavation in earth cost $3.96 per cu.

yd., of which $1.45 was for labor and $2.51 for top charges, etc. The

excavation of rock cost $8.93 per cu. yd., $2.83 being for labor and

$6.10 for top charges.

The final elevations of the four corners of the cutting edge, together

with their displacement from the desired positions, are shown in Table

1.

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The East River Tunnels. Paper No. 1159 · 第 14 / 35 题