LONG ISLAND SHAFTS.

The river shafts were designed to serve both as working shafts and as

permanent openings to the tunnels, and were larger and more substantial

than would have been required for construction purposes. Plate X of Mr.

Noble's paper shows their design. They consist of two steel caissons,

each 40 by 74 ft. in plan, with walls 5 ft. thick filled with concrete.

A wall 6 ft. thick separated each shaft into two wells 29 by 30 ft.,

each directly over a tunnel. Circular openings for the tunnel, 25 ft. in

diameter, were provided in the sides of the caissons. During the sinking

these were closed by bulkheads of steel plates backed by horizontal

steel girders. The shafts were sunk as pneumatic caissons to a depth of

78 ft. below mean high water. There have been a few caissons which were

larger and were sunk deeper than these, but most large caissons have

been for foundations, such as bridge piers, and have been stopped at or

a little below the surface of the rock. The unusual feature of the

caissons for the Long Island shaft is that they were sunk 54 ft. through

rock.

It had been hoped that the rock would prove sound enough to permit

stopping the caissons at or a little below the surface and continuing

the excavation without sinking them further; for this reason only the

steel for the lower 40 ft. of the caissons was ordered at first.

The roof of the working chamber was placed 7 ft. above the cutting edge.

It was a steel floor, designed by the contractors, and consisted of

five steel girders, 6 ft. deep, 29 ft. long, and spaced at 5-ft.

centers. Between were plates curved upward to a radius of 4 ft. Each

working chamber had two shafts, 3 ft. by 5 ft. in cross-section, with a

diaphragm dividing it into two passages, the smaller for men and the

larger for muck buckets. On top of these shafts were Moran locks.

Mounted on top of the caisson was a 5-ton Wilson crane, which would

reach each shaft and also the muck cars standing on tracks on the ground

level beside the caissons. Circular steel buckets, 2 ft. 6 in. in

diameter and 3 ft. high, were used for handling all muck. These were

taken from the bottom of the working chamber, dumped in cars, and

returned to the bottom without unhooking. Work was carried on by three

8-hour shifts per day. The earth excavation was done at the rate of

about 67 cu. yd. per day from one caisson. The rock excavation,

amounting to about 6,200 cu. yd. in each caisson, was done at the rate

of about 44.5 cu. yd. per day. The average rate of lowering, when the

cutting edge of the south caisson was passing through earth, was 0.7 ft.

per day. In rock, the rate was 0.48 ft. per day in the south caisson,

and 0.39 ft. per day in the north caisson.

At the beginning all lowering was done with sixteen hydraulic jacks.

Temporary brackets were fastened to the outside of the caisson. A

100-ton hydraulic jack was placed under each alternate bracket and under

each of the others there was blocking. The jacks were connected to a

high-pressure pump in the power-house. As the jacks lifted the caisson,

the blocking was set for a lower position, to which the caisson settled

as the jacks were exhausted. After the caisson had penetrated the earth

about 10 ft., the outside brackets were removed and the lowering was

regulated by blocking placed under brackets in the working chamber. The

caisson usually rested on three sets of blockings on each side and two

on each end. The blocking was about 4 ft. inside the cutting edge. In

the rock, as the cutting edge was cleared for a lowering of about 2 ft.,

6 by 8-in. oak posts were placed under the cutting-edge angle. When a

sufficient number of posts had been placed, the blocking on which the

caisson had rested was knocked or blasted out, and the rock underneath

was excavated. The blocking was then re-set at a lower elevation. The

posts under the cutting edge were then chopped part way through and the

air pressure was lowered about 10 lb., which increased the net weight to

more than 4,000,000 lb. The posts then gradually crushed and the

caissons settled to the new blocking. The tilt or level of the caisson

was controlled by chopping the posts more on the side which was desired

to move first.

The caisson nearly always carried a very large net weight, usually about

870 tons. The concrete in the walls, which was added as the caisson was

being sunk, was kept at about the elevation of the ground. There was

generally a depth of from 5 to 20 ft. of water ballast on top of the

roof of the working chamber. The air pressure in the working chamber was

usually much less than the hydrostatic head outside the caisson. For

example, the average air pressure in the south caisson during January,

1906, was 16-1/2 lb., while the average head was 62.5 ft., equivalent to

27 lb. per sq. in. Under these conditions, there was a continued but

small leakage into the caisson of from 15,000 to 20,000 gal. per day.

In the rock the excavation was always carried from 2 to 5 in. outside

the cutting edge. As soon as the cutting edge was cleared, bags of clay

were placed under it in a well-tiered, solid pile, so that when the

caisson was lowered the bags were cut through and most of the clay, bags

and all, was squeezed back of the cutting edge between the rock and the

caisson.

Table 1 shows the relation of the final position of the caissons to that

designed.

The cost of rock excavation in the caisson was $4.48 per cu. yd. for

labor and $10.54 for top charges.

The bottom of the shaft is an inverted concrete arch, 4 ft. thick,

water-proofed with 6-ply felt and pitch. As soon as the caisson was down

to its final position and the excavation was completed, concrete was

deposited on the uneven rock surfaces, brought up to the line of the

water-proofing, and given a smooth 1-in. mortar coat. The felt was stuck

together in 3-ply mats on the surface with hot coal-tar pitch. These

were rolled and sent down into the working chamber, where they were put

down with cold pitch liquid at 60 deg. Fahr. Each sheet of felt overlapped

the one below 6 in. The water-proofing was covered by a 1-in. mortar

plaster coat, after which the concrete of the 4-ft. inverted arch was

placed. While the water-proofing and concreting were being done, the air

pressure was kept at from 30 to 33 lb. per sq. in., the full hydrostatic

head at the cutting edge. After standing for ten days, the air pressure

was taken off, and the removal of the roof of the working chamber was

begun. The water-proofing was done by the Union Construction and

Waterproofing Company.

TABLE 1.--RELATION OF THE FINAL POSITION OF THE CAISSONS TO THAT

DESIGNED.

================================================================

LOCATION.| LONG ISLAND CITY. |

----------------------------------------------------------------

Shaft. | North. | South. |

----------------------------------------------------------------

Corner. | High. | East. | North. | High. | East. | North. |

----------------------------------------------------------------

Northeast|0.21 ft.|0.08 ft.|0.05 ft.|0.32 ft.|0.15 ft.|0.28 ft.|

Northwest|0.22 " |0.08 " |0.02 " |0.00 " |0.15 " |0.12 " |

Southwest|0.27 " |0.14 " |0.02 " |0.18 " |0.45 " |0.12 " |

Southeast|0.23 " |0.14 " |0.05 " |0.39 " |0.45 " |0.28 " |

================================================================

=============================================================================

LOCATION.| MANHATTAN. |

-----------------------------------------------------------------------------

Shaft. | North. | South. |

-----------------------------------------------------------------------------

Corner. | High. | East. | South. | High. | East or West.|North or South.|

-----------------------------------------------------------------------------

Northeast|0.23 ft.|0.74 ft.|0.38 ft.|0.00 ft.|0.06 ft. east.|0.04 ft. south.|

Northwest|0.00 " |0.74 " |0.22 " |0.08 " |0.06 " " |0.13 " north.|

Southwest|0.11 " |0.31 " |0.22 " |0.21 " |0.45 " west.|0.13 " " |

Southeast|0.46 " |0.31 " |0.38 " |0.04 " |0.45 " " |0.04 " south.|

=============================================================================

The cost of labor in compressed air chargeable to concreting was $3.40

per cu. yd.

After the roof of each working chamber had been removed, the shield was

erected on a timber cradle in the bottom of the shaft, in position to be

shoved out of the opening in the west side of the caisson. Temporary

rings of iron lining were erected across the shaft in order to furnish

something for the shield jacks to shove against.

The roof of the working chamber was then re-erected about 35 ft. above

its original position and about 8 ft. above the tunnel openings. This

time, instead of the two small shafts which were in use during the

sinking of the caisson, a large steel shaft with a T-head lock was

built. This is illustrated in Fig. 2, Plate LXIV. The shaft was 8 ft. in

diameter. Inside there was a ladder and an elevator cage for lowering

and hoisting men and the standard 1-yd. tunnel cars. At the top, forming

the head of the T, there were two standard tunnel locks.

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 The New York Tunnel Extension of the Pennsylvania Railroad. The East River Tunnels. Paper No. 1159 · 第 13 / 35 题