open at least one track for the temporary accommodation of traffic; (2)
To remove permanently the causes which had produced the collapse; (3) To
build a new and much stronger lining. Close to the western side wall,
which was still standing, the débris was removed, and the opening
strongly strutted in order to allow the laying of a single track to
reëstablish communication. At the same time a shaft was sunk from the
surface above the caved portion of the tunnel, for the double purpose of
facilitating the removal of the fallen material and of affording
ventilation. The depth of the surface above the tunnel was 41.6 ft.,
which made the construction of the shaft a comparatively easy matter.
The shaft itself was 6¹⁄₂ ft. wide and 18 ft. long, with its longer
dimensions parallel to the tunnel, and it was lined with a rectangular
horizontal frame and vertical-poling board construction. After
temporary communication had been opened on the western track of the
tunnel, the remainder of the fallen earth was removed and the excavation
strutted. The new masonry lining was then built.
To remove permanently the cause of the cave-in, which was the
percolation of water from a close-by stream, this stream was diverted to
a new channel constructed with a concrete bed and side walls.
The failure of the original lining occurred by cracks developing at the
crown, haunches, and springing lines. The new lining was made
considerably thicker than the original lining, and at the points where
failure had first occurred in the original arch cut-stone _voussoirs_
were inserted in the brickwork of the new arch as described in Chapter
XIII.
=Chattanooga Tunnel.=--The Western & Atlantic Ry. passes through the
Chattanooga mountains by means of a single-track tunnel 1,477 ft. long,
constructed in 1848-49. The lining consisted of a brickwork roof arch
and stone masonry side walls. After the tunnel had been opened to
traffic, this lining bulged inward at places, contracting the tunnel
section to such an extent that it was decided to reconstruct the
distorted portions. After careful surveys and calculations had been
made, it was decided to take down and reconstruct about 170 ft. of the
lining.
Owing to contracted space in the tunnel, it was necessary to remove all
men, tools, and material, whenever trains were to pass through; and in
order to do this a work-train of three cars was fitted up with necessary
scaffolds, and supplied with gasoline torches for lighting purposes.
Mortar was mixed on the cars, and all material remained on them until
used. Débris torn out of the old wall was loaded on the cars, and hauled
to the waste dump. A siding was built near the West end of the tunnel
for the use of this train, and a telephone system was installed between
the entrances and the working-train. On account of the contracted
working-space and the greater ease with which brick could be handled,
it was decided to rebuild the walls out of brick instead of stone.
In tearing out the old wall a hole was first cut through the three
bottom courses of the arch and gradually widened. When the opening
became four or five feet long, a small jack was placed near the center
of it and brought to a bearing against the arch to sustain it. After
cutting the opening to a length of from 7 to 10 ft. depending on the
stability of the earth backing, the jack was removed and a piece of 8×16
in. timber placed under the arch and brought up to a bearing with jacks.
One end of the timber rested on the old wall, the other on a seat built
into the adjoining section of new wall. Wedges were then driven under
the ends of timber and the jacks removed. With this timber in place, the
old wall could be taken down with ease, the only trouble being that
small stones and earth fell in from above and behind the arch. This was
obviated by placing a 2 in. plank across the opening and just back of
the 8×16 in. timber. At several points, however, the earth backing was
saturated with water, and it became necessary to put in lagging as the
old wall was removed. This timbering would be taken out as the new work
was built up.
A suitable foundation for the new wall was secured at a depth from 2 to
4 ft., and a concrete footing was used. The section of the new wall was
then built up as near as possible to the 8×16 in. timber; the timber was
then removed and the new wall built up and keyed under the arch.
The new wall had a minimum width of 2¹⁄₂ ft. at the top, and 4 ft. at
the base of rail, and was provided with weep holes at intervals. To
facilitate matters, work was carried on simultaneously at two or three
different places, the intention being to get one place torn out and
ready for the bricklayers by the time they completed a section of the
new wall at another place.
In rebuilding the arch, sections extending from the springing line up as
far as was necessary to obtain the desired clearance, and from 2¹⁄₂ to
4 ft. in length, were removed. Near the sides, the earth above the arch
was a stiff clay, which was self-sustaining; but near the center there
occurred a stratum of gravel and clay saturated with water. This gave
considerable trouble, falling through almost continuously until
timbering could be placed. One end of this timber rested on the old
arch, the other on the adjoining section of the new work. As the new
work was to be set 6 to 13 ins. back from the old, it was necessary to
block up this distance on top of the old arch, to carry the end of the
lagging timber, in order that the timber should be clear of the new
arch.
Owing to the small clearance between the car roof and the arch, a
special form of centering was required, one that would occupy as small
space as possible. Bar iron 1 in. thick, 4 ins. wide, and 20 ft. long
was curved to a radius of 6¹⁄₂ ft., and on the underside of this was
riveted a 6-in. plate ¹⁄₄ in. thick. This plate projected 1 in. on the
sides of the centering, and carried the ends of the 1 in. boards used
for lagging. The rivets were counter-sunk on the outside of the
centering to present a smooth surface next the arch.
In keying up a section of the new work, a space about 18 ins. square had
to be left open for the use of the workmen. As soon as the next section
had been torn out, this space was built up. In building up the last
section, this space had to be filled from below, which proved to be a
tedious undertaking. The opening was gradually reduced to a size of 10 ×
18 in., and the top ring then completed and keyed up, the adhesion of
mortar holding the bricks in place until the key could be driven home.
The next ring was treated in a similar manner, and so on to the face
ring. Altogether 412 lin. ft. of the walls and 178 lin. ft. of the arch
were taken down and rebuilt, amounting in all to 607 cu. yds. of masonry
at the total cost of $7,440, or about $12.25 per cu. yds.
The regular trains arrived so frequently at the tunnel that slightly
over two hours was the longest working-time between any two trains, and
usually less than one hour at a time was all that it could be worked. In
addition to the regular trains, a large number of extra trains, moving
troops, had to be accommodated. Work was in progress eight months, and
during that time there was no delay to a passenger train. The repairs
were completed in August, 1899. The work was under the direction of Mr.
W. H. Whorley, engineer of the Western & Atlantic R. R., and foreman of
construction, A. H. Richards. A recent examination failed to reveal any
sign of settlement cracks at the junction points of the new and old
work.
CHAPTER XXIII.
RELINING TIMBER-LINED TUNNELS WITH MASONRY.
The original construction of many American railway tunnels with a timber
lining to reduce the cost and hasten the work has made it necessary to
reline them, as time has passed, with some more permanent material. In
most cases the work of removing the old lining and replacing it with the
new masonry has had to be done without interfering with the running of
trains, and a number of ingenious methods have been developed by
engineers for accomplishing this task. Three of these methods which have
been employed, respectively, in relining the Boulder tunnel on the
Montana Central Ry., in Montana, the Mullan tunnel on the Northern
Pacific Ry., in Montana, and the Little Tom tunnel on the Norfolk &
Western R. R., in Virginia, have been selected as fairly representative
of this class of tunnel work.
=Boulder Tunnel.=--This tunnel penetrates a spur of the main range of
the Rocky Mountains, at an elevation at the summit of grade of 5,454
ft., and is 6,112 ft. in length. Its alignment is a tangent, with the
exception of 150 ft. of 30′ curve at the north end. The material
penetrated is blue trap-rock with seams for 4,950 ft. from the north
end, and syenitic boulders with the intervening spaces filled with
disintegrated material for the remaining 1,160 ft. The dimensions and
character of the old timber lining and of the new masonry lining
replacing it are shown in Figs. 159 and 160.
The form of masonry adopted consisted of coarse rubble side walls of
granite, 13 ft. 8 ins. high, and generally 20 ins. thick, with a full
center circular arch of four rings of brick laid in rowlock form. When
greater strength was needed the thickness of the side walls was
increased to 30 ins. and that of the arch to six rings of brick.
[Illustration: ~Cross Section.~
~Longitudinal Section.~
~Cross Section.~
~Cross Section.~
FIGS. 159 and 160.--Relining Timber-Lined Tunnel.]
The first plan adopted in putting in the masonry was to remove all the
timbering; but owing to the large number of falls and slides this was
abandoned, and the plan followed was to leave in the three roof segments
of the timbering with the overlying cord-wood packing and débris. In
carrying on the work the first step was to remove the side timbers. This
was done by supporting the roof timbers, as shown in Fig. 159; that is,
the first and fourth arch rib of an 8-ft. section containing four arch
ribs were supported by temporary posts. The intermediate arch ribs were
supported against the downward pressure by 6 × 6 in. timbers, extending
from the side ribs near the tops of the temporary posts to the opposite
sides of the intermediate roof segments, as shown in the longitudinal
section, Fig. 160. To resist the pressure from the sides, 4 × 6 in.
braces were placed across the tunnel from near the center of the
intermediate segments to the upper ends of the hip segments, as shown in
the cross-section, Fig. 159. The hip segments were then sawed off below
the notch, and the side timbering removed and the masonry built.
The stone was conveyed into the tunnel on flat cars, and laid by means
of small derricks located on the cars. Two derricks were used, one for
each side wall, and the work on both walls was carried on
simultaneously.
The arch was built upon a centering, the ribs of which were 5¹⁄₂ ins.
less in diameter than the distance between the side walls, so as to
permit the use of 2³⁄₄ ins. lagging. Each center had three ribs, made in
1-in. or 2-in. board segments, 10 ins. thick and 14 ins. deep. These
ribs were mounted on frames, which followed the opposite walls, and were
4 ft. apart, making the total length of the center out to out about 9
ft. The frames, upon which the ribs were supported, are shown in Fig.
161. As will be seen, they were mounted on dollys to enable the center
to be moved from one section to another. Jacks were used to raise and
lower the center into its proper position.
[Illustration: ~Cross Section.~
~Longitudinal Section.~
FIG. 161.--Relining Timber-Lined Tunnel, Great Northern Ry.]
The arch was built up from the springing lines on both sides at the same
time, four masons being employed. The rings were built beginning with
the intrados, which was brought up, say, a distance of about 2 ft. from
the springing line. Then the back of the ring was well plastered with
from ³⁄₈ in. to ¹⁄₂ in. of mortar, and the second ring brought up to the
same height and plastered on the back, and so on until the last ring was
laid. After bringing the full width of the arch up some distance, new
laggings were placed on the ribs for an additional height of 2 ft. and
the same process was repeated. All the space between the extrados of the
masonry arch and the old lining was compactly filled with dry rubble.
When high enough so that the hip segments had a foot or more bearing on
the masonry the segments were securely wedged and blocked up against the
brickwork, and the longitudinal 4 × 6 in. timbers removed. The
remaining space was now clear for completion of the arch, and both sides
were brought up until there was not sufficient space for four masons to
work, when the keying was completed by two masons beginning at the
completed and working back toward the toothed end. The brickwork was
built from the top of a staging-car.
[Illustration: ~Cross Section.~
~Longitudinal Section.~
FIG. 162.--Relining Timber-Lined Tunnel, Great Northern Ry.]
In a few instances where slides occurred after the removal of the slide
timbering, the method of re timbering the tunnel shown in Fig. 162 was
adopted. Two side drifts were first run 2¹⁄₂ ft. wide by 4 ft. high, and
the plate timbers placed in position and blocked. Cross drifts were then
run, and the roof segments placed, and the core down to the level of the
bottoms of the side drifts taken out. The lower wall plates were then
placed and the hip segments inserted. The bench was then taken down by
degrees, the side plates being held by jacks, and the posts placed one
at a time. As the masonry at the points where slides occur consists of
30-in. walls and six-ring arch, the timbering was 22 ft. wide in the
clear, with other dimensions as shown in Fig. 162.
Only a single crew of brick and stone masons was employed. In order to
prepare the sections for these masons it was necessary to have timber
and trimming crews at work throughout the whole day of 24 hours, so that
an engine and two train crews were in constant attendance. The single
mason crews were able to complete 8 ft. of side wall and arch in 24
hours. The number of men actually employed at the tunnel was 35. This
included electric-light maintenance, and all other labor pertaining to
the work. The tunnel was lighted by an Edison dynamo of 20 arc light
capacity, one arc light being placed on each side of the tunnel at all
working-places. Each lamp carried a coil of wire 20 or 30 ft. long to
allow it to be shifted from place to place without delay.
=Mullan Tunnel.=--This tunnel is 3,850 ft. long, and crosses the main
range of the Rocky Mountains, about 20 miles west of Helena, Mont. The
tunnel is on a tangent throughout, and has a grade of 20% falling toward
the east. The summit of the grade, west of the tunnel, is 5,548 ft.
above sea level, and the mountain above the line of the tunnel rises to
an elevation of 5,855 ft. Owing to the treacherous nature of the
material through which the tunnel passed, it had been a constant menace
to traffic ever since its construction in 1883, and numerous delays to
trains had been caused by the falls of rock and fires in the timber
lining. For these reasons it was finally decided to build a permanent
masonry lining, and work on this was begun in July, 1892.
[Illustration: ~_With Wall Plates._~
~_Without Wall Plates._~
~Old Timber Sections.~
~_Minimum Section._~
~_Average Section._~
~Permanent Work.~
FIG. 163.--Relining Timber Lined Tunnel, Great Northern Ry.]
The original timbering consisted of sets spaced 4 ft. apart _c._ to
_c._, with 12 × 12 in. posts supporting wall plates, and a five-segment
arch of 12 × 12 in. timbers joined by 1¹⁄₂-in. dowels. The arch was
covered with 4-in. lagging, and the space between this and the roof was
filled with cordwood. Except where the width had been reduced by
timbering placed inside the original timbering to increase the strength,
the clear width was 16 ft., and the clear height 20 ft. above the top of
the rail. Fig. 163 shows the timbering and also the form of masonry
lining adopted. The side walls are of concrete and the arch of brick.
This new masonry, of course, required the removal of all the original
timbering. The manner of doing this work is as follows: A 7-ft. section,
_A B_, Fig. 164, was first prepared by removing one post and supporting
the arch by struts, _S S_. After clearing away any backing, and
excavating for the foundation of the side wall, two temporary posts, _F
F_, were set up, and fastened by hook bolts. Fig. 146, _L_, and a
lagging was built to form a mold for the concrete. Several of these
7-ft. sections were prepared at a time, each two being separated by a
5-ft. section of timbering.
[Illustration: ~Section, with Concrete Car.~
~With Wall Plate.~
~Without Wall Plate.~
~Longitudinal Section.~
FIG. 164.--Construction of Centering Mullan Tunnel.]
The mortar car was then run along, and enough mortar (1 cement to 3
sand) was run by the chute into each section to make an 8-in. layer of
concrete. As the car passed along to each section, broken stone was
shoveled into the last preceding section until all the mortar was taken
up. The walls were thus built up in 8-in. layers, and became hard enough
to support the arches in about 10 to 14 days. The arches were then
allowed to rest on the wall, and the posts of the remaining 5-ft.
sections were removed, and the concrete wall built up in the same way as
before.
The average progress per working-day was 30 ft. of side wall, or about
45 cu. yds.; and the average cost, including all work required in
removing the timber work, train service, lights and tools, engineering
and superintendence, and interest on plant, was $8 per cubic yard.
[Illustration: FIG. 165.--Centering Mullan Tunnel.]
The centering used for putting in the brick arches is shown in Fig. 165.
From 3 ft. to 9 ft. of arch was put in at a time, the length depending
upon the nature of the ground. To remove the old timber arch, one of the
segments was partly sawed through; and then a small charge of giant
powder was exploded in it, the resulting débris, cordwood, rock, etc.,
being caught by a platform car extending underneath. From this car the
débris was removed to another car, which conveyed it out of the tunnel.
The center was then placed and the brickwork begun, the cement car shown
in Fig. 164 being used for mixing the mortar. The size of the bricks
used was 2¹⁄₂ + 2¹⁄₂ + 9 ins., four rings making a 20-in. arch and
giving 1.62 cu. yds. of masonry in the arch per lin. ft. of tunnel. The
bricks were laid in rowlock bond, two gangs, of three bricklayers and
six helpers each, laying about 12 lin. ft. per day. The brickwork cost
about $17 per cu. yd. The total cost of the new lining averaged about
$50 per lin. ft.
[Illustration: ~Cross Section.~
~Longitudinal Section.~
FIG. 166.--Relining Timber-Lined Tunnel, Norfolk and Western Ry.]
=Little Tom Tunnel.=--The tunnel has a total length of 1,902 ft., but
only 1,410 ft. of it were originally lined with timber. This old timber
lining consists of bents spaced 3 ft. apart, and located as shown by the
dotted lines in the cross-section, Fig. 166. Instead of renewing this
timber, it was decided to replace it with a brick lining. Although the
tunnel was constructed through rock, this rock is of a seamy
character, and in some portions of the tunnel it disintegrates on
exposure to the air. In removing the timber to make place for the new
lining some of the roof was found close to the lagging, but often also
considerable sections showed breakages in the roof extending to a height
varying from 1 ft. to 12 ft. above the upper side of the timbering. This
dangerous condition of the roof made it necessary that only a small
section of the timber lining should be removed at one time. It made it
necessary, also, that the brick arch should be built quickly to close
this opening, and finally that all details of centers, etc., should be
arranged so as to furnish ample clearance to trains. The accompanying
illustrations show the solution of the problem which was arrived at.
[Illustration: FIG. 167.--Relining Timber-Lined Tunnel, Norfolk and
Western Ry.]
Referring to the transverse and longitudinal sections shown by Fig.
166, it will be seen that two side trestles were built to carry an
adjustable centering for the roof arch. Two sections of these trestles
and centerings were used alternately, one being carried ahead and set up
to remove the timbering while the masons were at work on the other. The
manner of setting up and adjusting the trestles and centerings is shown
by Fig. 166 and also by Fig. 167, which is an enlarged detail drawing of
the set screw and rollers for the centering ribs. The following is the
bill of material required for one set of trestles and one center:
Trestles:
Caps and sills 8 pieces 8 × 8 ins. × 20 ft.
Posts 18 „ 8 × 8 „ × 11 „
Braces 16 „ 6 × 4 „ × 7 „
Centerings:
Ribs 27 „ 2 × 18 „ × 7 „
Bracing 12 „ 2 × 8 „ × 7 „
Support to crown lagging 2 „ 6 × 6 „ × 10 „
Crown lagging 20 „ 3 × 6 „ × 2 „
Side lagging 30 „ 3 × 6 „ × 10 „
Side strips 2 „ 2 × 12 „ × 9 „
Blocking for rollers 1 „ 5 × 8 „ × 12 „
6 screw and roller castings complete with bolts and lever; 114 bolts
³⁄₄-ins. in diameter; 7¹⁄₂ U. H. hexagonal nut and 2 cast washers
each.
With this arrangement the progress made per day varied from 2 lin. ft.
to 3 lin. ft. of lining complete. By work complete is meant the entire
lining, including stone packing between the brickwork and the rock. On
Feb. 23, 1900, 363 ft. of lining had been completed, at a cost of $33.50
per lin. ft. This cost includes the cost of removing the old timber, the
loose rock above it, and all other work whatsoever.
CHAPTER XXIV.
THE VENTILATION AND LIGHTING OF TUNNELS DURING CONSTRUCTION.
VENTILATION.
In long tunnels, especially when excavated in hard rock, proper
ventilation is of great importance, because the air cannot be easily
renewed, and the amount of oxygen consumed by miners horses and lamps
during construction is very large. The gases produced by blasting also
tend to fill the head of excavation with foul air. Pure atmospheric air
contains about 21% of oxygen and only 0.04% of carbonic acid; when the
latter gas reaches 0.1% the fact is indicated by the bad odor; at 0.3%
the air is considered foul, and when it reaches 0.5% it is dangerous. It
is generally admitted that the standard of purity of the air is when it
contains 0.08% of carbonic acid.
A large quantity of carbonic acid in the air is easily detected by
observing the lamps, which then give out a dim red light and smoke
perceptibly; the workmen also suffer from headache and pains in the
eyes, and breathe with difficulty. Naturally, miners cannot easily work
in foul air and, therefore, make very slow progress. It is, therefore,
to the interest of the engineer to afford good ventilation, not only
because of his duty to care for the safety and health of his men, but
also for reasons of economy, so that the men may work with the greatest
possible ease, thus assuring the rapid progress of the work.
It would be impossible to change completely the atmosphere inside a
tunnel, as the gases developed from blasting will penetrate into all the
cavities and gather there, but the fresh air carried inside by
ventilation has a very small percentage of carbonic acid, mixes with
that which contains a greater quantity, and dilutes it until the air
reaches the standard of purity. We have not here considered the gases
developed from the decomposition of carboniferous and sulphuric rocks,
which may be met with in some tunnels, and which render ventilation
still more necessary. Tunnels may be ventilated either by natural or
artificial means.
=Natural Ventilation.=--It is well known that if two rooms of different
temperatures are put in communication with each other, e.g., by opening
a door, a draft from the colder room will enter the other from the
bottom, and a similar draft at the top, but with a contrary direction,
will carry the hot air into the colder room, thus producing perfect
ventilation, until the two rooms have the same temperature. Now, during
the construction of tunnels the temperature inside may be considered as
constant, or independent of the outside atmospheric variations; hence
during summer and winter, there will always be a draft affording
ventilation, owing to the difference of temperature inside and outside
the tunnel. In winter time the cold air outside will enter at the bottom
of the entrances and headings, or along the sides of the shafts, and the
hot air will pass out near the top of the headings or entrances or the
center of the shafts; in summer the air currents will take the contrary
direction.
Natural ventilation in tunnels is improved when the excavation of the
heading reaches a shaft, because the interior air can then communicate
with the exterior at two points, at different levels. In such cases a
force equal to the difference in weight between a column of air in the
shaft and a similar one of different density at the entrance of the
tunnel, will act upon the mass of air in the tunnel and keep it in
movement, thus producing ventilation. Consequently, during winter, when
the outside air has greater weight than that inside, the air will come
in by the headings and go out by the shaft, and in the summer it will
enter at the shaft and pass out at the entrance. Sometimes to afford
better ventilation shafts 8 or 12 in. in diameter are sunk exclusively
for the purpose of changing the air. When the inside temperature is
equal to that outside, as often happens during the spring and autumn,
there are no drafts, and consequently the air in the excavation is not
renewed and becomes foul; then fires are lighted under the shaft and a
draft is artificially produced. The hot air going out through the shaft,
as through a chimney, allows the fresh air to come in as in ordinary
ventilation.
When the head of the excavation is very far from the entrances, or when
the mountain is too high to allow excavation by shafts, it is quite
impossible to secure good natural ventilation, especially during the
spring and autumn months, and the engineer has to resort to some
artificial means by which to supply fresh air to the workmen.
=Artificial Ventilation.=--Artificial ventilation in tunnels may be
obtained in two different ways, known as the vacuum and plenum methods.
Their characteristic difference consists in this, that in the vacuum
method the air is drawn from the inside and the vacuum thus produced
causes the fresh air from the outside to rush in, while the plenum
method consists in forcing in the fresh air which dilutes the carbonic
air produced inside the tunnel by workingmen and explosives. In the
vacuum method the pressure of the atmosphere inside the tunnel is always
less than the pressure outside, while in the plenum method the pressure
within is always greater than that outside. Ventilation is the result of
this difference of pressure, as the tendency of the air toward
equilibrium produces continuous drafts. Both these methods have their
advantages and disadvantages; but in the presence of hard rock, when
explosives are continually required, the vacuum method is considered the
best, because the gases attracted to the exhaust pipes are expelled
without passing through the whole length of the tunnel, thus avoiding
the trouble that a draft of foul air will give to the workmen who are
within the tunnel. In both these methods it is necessary to separate
the fresh air from the foul one; and this is done by means of pipes
which will exhaust and expel the foul air in the vacuum method, or force
to the front a current of fresh air when the plenum method is used.
Artificial ventilation may also be obtained by compressed air which is
set free after it has driven the machines, especially in tunnels
excavated through rock, when rock drilling machines moved by compressed
air are employed.
=Vacuum Method Contrivances.=--The most common of the vacuum appliances
consists in the simple arrangement of a pipe leading from the head of
the tunnel out through the fire of a furnace. The air in the pipe is
rarefied by the heat of the furnace and then set free from the other end
of the pipe, thus creating a partial vacuum in the pipe, into which the
foul air of the head rushes, the fresh air from the entrance taking its
place, and thus ventilating the tunnel. A similar arrangement may be
used with shafts, and the foul air may be driven out by a furnace which
is placed either at the top or bottom of the shaft. Such furnaces act
the same as those commonly used for heating purposes in the houses, with
this difference, that, instead of fresh air being forced in, foul air is
expelled. Another simple arrangement for producing a vacuum is by means
of a steam jet which is thrown into the pipe, and which helps the
expulsion of the air by heating it, thus producing a different density
which originates a draft besides that mechanically originated by the
force of the steam jet, which tends to carry out the foul air of the
pipes.
Foul air may also be expelled by means of exhaust fans which are
connected with pipes near the entrance of the tunnel. The fan consists
of a box containing a kind of a paddle wheel turned by steam or water
power and arranged so as to revolve at a high speed. The air inside the
pipe is forced out by blades attached to the wheel, and thus the foul
air of the front is driven away and fresh air from the entrance rushes
in to take its place, and perfect ventilation is obtained.
The best manner of expelling foul air from tunnels, according to the
vacuum method, is by means of bell exhausters. This consists of two sets
of bells connected by an oscillating beam and balancing each other. Each
set consists of a movable bell, which covers and surrounds a fixed bell
with a water joint. In the central part of the fixed bell there are
valves which open upwards, and on the bottom of each movable bell there
are valves which open from the outside. When one bell ascends, the
valves at the bottom are closed, the air beneath is then rarefied, and a
vacuum is produced; the valves in the central part of the fixed bell
filled with water are opened, and there is an aspiratory action from the
pipe leading to the headings, and the foul air is thus carried away. The
apparatus makes about ten oscillations per minute, and the dimensions of
the bells depend upon the quantity of air to be exhausted in a minute.
In the St. Gothard tunnel, where these bell exhausters were used, they
exhausted 16,500 cu. ft. of air per minute.
=Plenum Method Contrivances.=--Fresh air may be driven into tunnels to
dilute the carbonic acid by two different ways, viz., by water blast and
by fans. Water when running at a great velocity produces a movement in
the air which may be sometimes usefully and economically employed for
ventilating tunnels. Water falling vertically is let run into a large
horizontal zinc pipe having a funnel at the outer end; into this the air
attracted by the velocity of the water is forced. By an opening at the
bottom the water is afterward withdrawn from the pipe, and there remains
only the air which is pushed forward by the air which is being
continually sucked in by the velocity of the water.
The best and most common means of ventilation by the plenum method is by
fans. There are numerous varieties of these fans in the market, but they
all consist of a kind of fan wheel which by rapid revolution forces the
fresh air into the pipe leading to the headings of the tunnel or to the
working places. Instead of a large single fan, such as is used for
mining purposes, it is better to have a number of small fans acting
independently of each other, conveying the fresh air where it is needed
through independent pipes.
=Saccardo’s System.=--A new method of ventilating tunnels was devised by
Mr. Saccardo for the ventilation of the Pracchia tunnel along the
Bologna and Lucca Railway in Italy. At the highest end of the tunnel the
mouth was contracted inward in a funnel shaped form so as to just admit
a train. Immediately at this contraction, a lateral tunnel, 50 feet
long, branched off from one side of the main tunnel. At the mouth of
this lateral tunnel was installed a fan which forced air into the tunnel
and with 70 revolutions per minute delivered 3.532 cu. ft. of air per
second at a water pressure of 1 in. This air current was directed inward
through a second contraction or funnel, parallel to the one at the
entrance and 23 ft. beyond it. In operation the action of the artificial
air current was to suck in a considerable volume of outside air, while
the air pressure was sufficient to counterbalance the movement of air
produced by a train moving at a velocity of 16.1 ft. per second. Mr.
Saccardo’s method was employed in ventilating a tunnel on the Norfolk
and Western Railway with satisfactory results.
=Compressed Air.=--In the excavation of tunnels in hard rock a number of
rock drilling machines are employed which are moved by compressed air at
a pressure of not less than five atmospheres. At each stroke about 100
cu. ins. of compressed air are set free, and at an average of 10 strokes
per minute there would be 5000 cu. ins. of air at five atmospheres or
25,000 cu. ins., or a little more than 175 cu. ft. of fresh air at
normal pressure set free every minute by each of the machines employed.
But the air exhausted from the drilling machine is foul.
Regarding ventilation by compressed air, Mr. Adolph Sutro, in a lecture
delivered to the mining students of the University of California, said:
“I will note a curious fact which I have never seen explained, and
which is worthy of close investigation by means of experiments. In the
Sutro tunnel we found that the compressed air used for driving the
machine drills, after having been compressed and expanded and
discharged from the drills, was not wholesome to breathe, and the men
and mules would all crowd around the end of the blower pipe to get
fresh air. Whether the air in being compressed has parted with some of
its oxygen or because vitiated from some other cause, I do not know,
and I hope that this subject will at some future day be carefully
examined into.”
In the December, 1901, number of “_Compressed Air_,” a magazine
especially devoted to the useful application of compressed air, is read:
Compressed air wasted from power drills is so contaminated with oil
from the cylinders that it cannot be taken into consideration as
ventilation. It is as important to displace it with pure air as it is
to drive out or draw off other vitiated air. The ventilation should be
an independent supply provided by fan or blower, delivering by pipe at
the point where miners are working.
=Quantity of Air.=--The quantity of air to be introduced into tunnels
must be in proportion to the oxygen consumed by the men, the animals,
and the explosions. It is allowed that the quantity of air required for
breathing purpose and explosions is as follows:
1 workman with lamp needs 240 cu. yds. of fresh air in 24 hours.
1 horse „ 850 „ „ „ „
1 lb. gunpowder 100 „ „ „
1 lb. dynamite 150 „ „ „
In a long tunnel excavated through hard rock the number of workmen all
together may be assumed at 400 at each end, and each workman is supposed
to be furnished with a lamp. No less than ten horses are employed, and
the average quantity of dynamite consumed is 600 lbs. per day. From the
data given the consumption of air by workmen and lamps would be: 240 ×
400 = 96,000 cu. yds.; the consumption of air by horses would be 850 ×
10 = 8500 cu. yds.; the consumption of air by dynamite would be 150 ×
600 = 90,000 cu. yds.; making a total consumption of air per day of
194,500 cu. yds., or about 8000 cu. yds. per hour.
To obtain good ventilation, then, it will be necessary to furnish every
hour a quantity of fresh air amounting to not less than 8000 cu. yds.
Since, however, a large quantity of pure air is expelled with the foul
air, it is necessary greatly to increase this quantity.
It may be observed, in closing, that the water having its particles
divided, as in a fog or mist, rapidly precipitates the gases produced by
explosions. Now, when hydraulic machines are used, there is a hollow
ball pierced by holes that are almost imperceptible, from which the
compressed water spreads in very subtile particles, and this causes the
fall of the gases from explosions. Such a method of precipitating gases
is very good, but does not have the advantage of supplying new oxygen to
replace that consumed by the men, animals, lamps, and explosions;
besides, it has the defect of increasing the quantity of water to be
removed. In tunnels the pipes used either for conveying the fresh air or
for carrying away the foul air, are of iron, having a diameter of about
8 in.; they are fixed along the side walls about 3 ft. above the
inverted arch.
LIGHTING.
The object and necessity of a perfect lighting of the tunnel-workings
during construction are so obvious that they need not be enlarged upon.
Comparatively few tunnels require lighting after completion; and these
are generally tunnels for passenger traffic under city streets, of which
the Boston Subway is a representative American example. Considering the
methods of lighting tunnels during construction, we may, for sake of
convenience, chiefly, divide the means of supplying light into (1) lamps
and lanterns usually burning oil; (2) coal-gas lighting; (3) acetylene
gas lighting; and (4) electric lighting.
=Lamps and Lanterns.=--Lamps and lanterns are commonly employed by
engineers for making surveys inside the tunnel, and to light the
instrument. For ranging in the center line, a convenient form of lamp
consists of an oil light inclosed in glass chimney covered with sheet
metal, except for a slit at the front and back through which the light
shines, and on which the observer sights his instrument. To direct the
operations of his rodmen the engineer usually employs a lantern, either
with white or colored glass, much like the ordinary railway trainman’s
lantern, which he swings according to some prearranged code of signals.
Lamps and lanterns are used by the workmen both for signaling and for
lighting the workings. For signaling purposes red lanterns are usually
placed to denote the presence of unexploded blasts or other points of
possible danger; and colored or white lights are usually placed on the
front and rear of spoil and material trains. For lighting purposes, two
forms of lamps are employed, which may be somewhat crudely designated as
lamps for individual use and lamps for general lighting. Individual
lamps are usually of small size, and burn oil; they may be carried in
front of the miner’s helmet, or be fixed to standards, which can be set
up close to the work being done by each man. Miners’ safety lamps should
be employed where there is danger from gas. A great variety of lamps for
mining and tunneling purposes are on the market, for descriptions of
which the reader is referred to the catalogues of their manufacturers.
Lamps for general lighting are always of larger size than lamps for
individual use. A common form consists of a cylinder ten or twelve
inches in diameter, provided with a hook or bail for suspension, and
filled with benzine, gasolene, or other similar oil. Connected with this
cylinder is a pipe of considerable length and small diameter through
which the benzine or gasolene vapor runs, and burns when lighted with a
brilliant flame. Lamps of this type burning gasolene were extensively
employed in building the Croton Aqueduct tunnel. Various patented forms
of lamps for burning coal-oil products are on the market, for
descriptions of which the manufacturers’ catalogues may be consulted.
=Coal-gas Lighting.=--A common method of lighting tunnel workings is by
piping coal-gas into the headings and drifts from some nearby permanent
gas plant, or from a special gas works constructed especially for the
work. Gas lighting has the great advantage over lamps and lanterns of
giving a light which is more brilliant and steady. Its great objection
is the danger of explosion caused by leaks in the pipes, by breaks
caused by flying fragments of rock, and by the carelessness of workmen
who neglect to turn off completely the burners when they extinguish the
lights. In nearly every tunnel where gas has been used for lighting, the
records of the work show the occurrence of accidents which have
sometimes been very serious, particularly when fire has been
communicated to the tunnel timbering.
=Acetylene Gas Lighting.=--The comparatively recent development of
acetylene gas manufactured from carbide of calcium has given little
opportunity for its use in tunnel lighting, and the only instance of its
use in the United States, so far as the author knows, is the water-works
tunnel conduit for the city of Washington, D. C. Col. A. M. Miller, U.
S. Engineer Corps, who is in charge of this work, describes the method
adopted in his annual report for 1899 as follows:--
“It had been the practice to do all work underground by the light of
miners’ lamps and torches. This means of illumination is very poor for
mechanical work. The fumes and smoke from blasting, added to the smoke
from torches and lamps, render the atmosphere underground, especially
when the barometer conditions were unfavorable to ventilation, very
offensive and discomforting to the workmen. An investigation of the
subject of lighting the tunnel by other means, more especially at the
locality where the mechanics were at work,--brick and stone masons,
and the workmen on the iron lining,--resulted in the selection of
acetylene gas as the most available and economical in this special
emergency. Accordingly, an acetylene gas plant for 300 burners was
erected at Champlain-Avenue shaft, and one for 60 lights at Foundry
Branch. The engine-houses at the shafts, the head-houses, and
localities in the tunnel, when required, are lighted by these plants.
“Gas pipes were carried down the Champlain-Avenue shaft and along the
tunnel both in an easterly and westerly direction, with cocks for
burners at proper intervals every 30 feet; and this system sufficed
for illumination from Hock Creek to Harvard University, a distance of
over two miles. The plant erected at Foundry Branch was in like manner
utilized for the illumination from that point in both directions.
“By connecting with the stopcocks by means of a rubber hose, a
movable light, chandelier, or ‘Christmas-tree’ of any required number
of burners is used, thus concentrating the light in the immediate
vicinity of the work, and also enabling the illumination to be carried
into the cavities or ‘crow-nests,’ so called, behind the defective old
lining.
“This method of illuminating has proved very satisfactory and quite
economical. It is especially valuable as enabling good work to be
done, and facilitating a thorough inspection of the same.”
=Electric Lighting.=--By far the most perfect, and at present the most
commonly employed means for lighting tunnel workings, is electricity.
The light furnished by electric lamps is steady and brilliant, and does
not consume oxygen or give off offensive gases. The wires are easily
removed and extended, and the lamps are easily put in place and removed.
About the only objection to the method is the fragility of the lamps,
which are easily broken by the flying stones and the concussion produced
by blasting.
CHAPTER XXV.
THE COST OF TUNNEL EXCAVATION AND THE TIME REQUIRED FOR THE WORK.
=Cost.=--The cost of a tunnel will depend upon the cost of the two
principal operations required in its construction, viz., the excavation
of the cross section and the lining of the excavation with masonry,
metal, or timber. These two operations may in turn be subdivided, in
respect to expense, into cost of labor and cost of materials. It is a
comparatively simple matter to calculate the cost of the building
materials required to construct a tunnel; but it is very difficult to
estimate with accuracy what the cost of labor will be. The reason for
this is that it is impossible to foresee exactly what the conditions
will be; the character of the material may change greatly as the work
proceeds, increasing or decreasing the cost of excavation; water may be
encountered in quantities which will materially increase the
difficulties of the work, etc. Nevertheless, while accurate preliminary
estimates of cost are not practicable, it is always desirable to attempt
to obtain some idea of the probable expense of the work before beginning
it, and the more usual means of getting at this point will be discussed
here.
Two methods of estimating the cost of tunnel work are employed. The
first is to calculate the probable expense of the various items of work,
based upon the available data, per unit of length, and then add to this
a margin of at least 10% to allow for contingencies; the second is to
apply to the new work the unit cost of some previous tunnel built under
substantially the same conditions. In the first method it is usual to
consider the strutting and hauling as constituting a part of the work
of excavation. To estimate the cost of excavation involves the
consideration of three general items, viz., the excavation proper, the
strutting of the walls of the excavation, and the hauling of the
excavated materials and the materials of construction.
The cost of excavating the preliminary headings or drifts is greater per
unit of material removed than that of excavating the enlargement of the
section. The cost of bottom drifts is also always greater than that of
top headings, the material penetrated remaining the same. Mr. Rziha
gives the comparative unit costs of excavating drifts, headings, and
enlargement of the profile as follows:--
Bottom drifts $9.20 per cu. yd.
Top headings 4.80 „ „ „
Enlargement of profile 2.84 „ „ „
The cost of hauling increases with the length of the tunnel. This fact
and amount of this increase are indicated by the following actual prices
for the Arlberg tunnel:--
Top heading $6.76 per cu. yd., increasing 37 cts. per mile
Bottom drift 7.40 „ „ „ „ 26 „ „ „
Enlargement of profile 2.70 „ „ „ „ 10 „ „ „
In all the prices given above, the cost of strutting and hauling is
included in the cost of excavation.
The cost of excavation is not always the same for the same character of
materials in different tunnels. The following figures show the prices
paid for the excavation of calcareous rock in four different German
tunnels:--
Berliner Nordhausen Wetzler R.R. $1.24 per cu. yd.
Ofen 1.30 „ „ „
Stafflach 2.76 „ „ „
Gries 1.92 „ „ „
The method of tunneling has little influence upon the cost of the work,
as shown by the following figures from tunnels excavated through
calcareous rock by different methods:--
Ofen tunnel Austrian method $93.19 per lin. ft.
Dorremberg tunnel Belgian method 86.08 „ „ „
Stafflach tunnel English method 91.69 „ „ „
The Martha and Merten tunnels, excavated through soft ground by the
Austrian and German methods respectively, cost $87.95 and $87.55 per
lin. ft. respectively. In the excavation of the various sections of the
tunnel for the new Croton Aqueduct in America, the following prices were
paid:--
Excavation of heading $8 to $10.00 per cu. yd.
Tunnel in soft ground 8 to 9.00 „ „ „
Tunnel in rock 7 to 8.50 „ „ „
Brick masonry 10.00 „ „ „
Timber in place $40 per M. ft. B. M.
It is the practice in America to include the work of hauling under
excavation, but not to include the strutting, which is paid for
separately. In some cases only the market price of the timber is paid
for separately, the cost of setting up being included in the price of
excavation. The writer prefers the European practice of including the
total cost of timbering under excavation, since the two operations are
so closely connected, and since the contractor employs the same timber
over and over again. Knowing the dimensions of the several members of
the strutting, it is a simple, although somewhat tedious,
process to calculate the total quantity required. An idea of the
quantity of timber required for strutting in soft ground may be had from
the data given on page 55. The quantity will decrease as the cohesion of
the material penetrated increases, until it becomes so small in hard
rock-tunnels as to cut very little figure in the total cost.
The cost of hoisting excavated materials through shafts depends upon the
depth from which it is hoisted, and upon the character of hoisting
apparatus employed. The following table, showing the cost of hoisting
for different lifts and by different methods, is given by Rziha, the
cost being in francs per cubic meter:--
+-------+----------+----------------------+-------------+
| HEIGHT| WINDLASS.| HORSE GINS. |STEAM HOISTS.|
| IN +----------+----------+-----------+-------------+
|METRES.| |ONE HORSE.|TWO HORSES.| |
| | Francs | Francs | Francs | Francs |
| |per Cu. M.|per Cu. M.| per Cu. M.| per Cu. M. |
+-------+----------+----------+-----------+-------------+
| 15 | 0.172 | 0.077 | 0.062 | 0.035 |
| 30 | 0.212 | 0.087 | 0.070 | 0.045 |
| 45 | 0.257 | 0.100 | 0.080 | 0.050 |
| 60 | 0.305 | 0.112 | 0.092 | 0.082 |
| 90 | 0.410 | 0.152 | 0.110 | 0.087 |
| 120 | 0.535 | 0.195 | 0.135 | 0.092 |
| 150 | 0.722 | 0.240 | 0.157 | 0.112 |
+-------+----------+----------+-----------+-------------+
Mr. Séjourné, a French engineer, who has been connected with the
construction of numerous tunnels by the Belgian method where he was in
position to secure comparative figures, has given the following rules
for calculating the cost of tunnels. Assuming _A_ to represent the cost
of excavating a cu. yd. in the open air, the cost of excavating the same
quantity underground in driving headings will be from 9 _A_ to 11 _A_,
and in enlarging the profile it will be about 5 _A_. The cost of
constructing single-track tunnels varies with the thickness of the
lining, and may be calculated by the following formulas:
Without lining, _C_ = 5.5 _A_.
With roof arch only, _C_ = 6.4 + 6.4 _A_.
With lining 18 in. thick, _C_ = 9.4 + 7 _A_.
With lining 2 ft. thick, _C_ = 11 + 8 _A_.
In these formulas _C_ is the cost per cu. yd. of excavation, including
the masonry. For double-track tunnels the amounts given by the above
formulas may be used by reducing them about 7¹⁄₂% or 8%.
The second method of estimating the cost of tunnel work consists in
assuming as a unit the unit cost of tunnels previously excavated under
similar conditions. Mr. La Dame gives the following unit prices for a
number of tunnels driven through different materials:
+-------------------+--------+-------------+--------+----------------+
| NATURE OF SOIL. |TUNNELS,| EXCAV. PER |COST PER| MAX. AND MIN. |
| | NO. OF | CU. YD. |LIN. FT.| PER LIN. FT. |
+-------------------+--------+-------------+--------+----------------+
|Granite-gneiss | 56 |$3.07 @ $3.85| $100. |$61.46 @ $190.40|
|Schist | 39 | 1.38 @ 1.53| 75.42| 43.11 @ 70.68|
|Triassic | 3 | ... | 90.85| 84.75 @ 93.33|
|Jurassic | 69 | 1.23 @ 1.38| 77.86| 35.24 @ 157.2 |
|Cretaceous | 34 | 0.61 @ 0.77| 59.60| 27.37 @ 92.25|
|Tertiary and modern| 39 | 0.33 @ 0.61| 105.80| 51.52 @ 188.36|
+-------------------+--------+-------------+--------+----------------+
In the following table is given a list of tunnels excavated through
different soils, from the most compact to very loose materials, and
driven according to the various methods which have been illustrated.
DOUBLE-TRACK TUNNELS.
+--------------+-----------------+--------+-------------+
|NAME OF |QUALITY OF SOIL. |COST PER| METHOD OF |
|TUNNELS. | |LIN. FT.| TUNNELING. |
+--------------+-----------------+--------+-------------+
|Mt. Cenis |Granitic, |$273.73 |Drift. |
|St. Gothard |... | 193.63 |Heading. |
|Stammerich |Granitic, | 157.90 |English. |
|Stalle |Broken schist, | 290.58 |Austrian. |
|Bothenfels |Dolomite, | 115.64 |English. |
|Dorremberg |Calcareous, | 86.08 |Belgian. |
|Stafflach |Calcareous, | 91.69 |English. |
|Ofen |Calcareous, | 93.19 |Austrian. |
|Wartha |Grewack, | 87.95 |Austrian. |
|Mertin |Grewack, | 87.55 |German. |
|Schloss Matrei|Clay schist, | 94.25 |English. |
|Trietbitte |Clay and sand, | 229.0 |German. |
|Canaan |Clay-slate, | 69.50 |Wide heading.|
|Church-Hill |Clay with shells,| 178.0 |... |
|Bergen No. 1 |Trap rock, | 182.31 |... |
+--------------+-----------------+--------+-------------+
SINGLE-TRACK TUNNELS.
+--------------+--------------------+----------+-------------+
| NAME OF | QUALITY OF SOIL. | COST PER | METHOD OF |
| TUNNELS. | | LIN. FT. | TUNNELING. |
+--------------+--------------------+----------+-------------+
|Mt. Cenis |Gneiss, |$82.27 |Heading. |
|Stalletti |Granite and quartz, | 62.75 |Austrian. |
|Marein |Clay schist, | 64.36 |English. |
|Welsberg |Gravel, |165.07 |Austrian. |
|Sancina |Clay of 1st variety,|129.40 |Belgian. |
|Starre |Clay of 2d variety, |191.61 |Belgian. |
|Cristina |Clay of 3d variety, |307.42 |Italian. |
|Burk |... | 83.90 |Wide heading.|
|Brafford Ridge|... | 85.33 |Wide heading.|
|Dunbeithe |Limestone, | 70.47 |Wide heading.|
|Fergusson |Sandstone, | 37.46[16]|Wide heading.|
|Port Henry |Limestone, | 80.00[17]|Wide heading.|
|Points |Granite, | 72.00[16]|Wide heading.|
+--------------+--------------------+----------+-------------+
[16] Are unlined.
[17] Lined with timber.
The Habas tunnel through quicksand, between Dax and Ramoux, France,
cost $118.50 per lin. ft. The cost of the Boston subway was $342.40 per
lin. ft. The Severn and Mersey tunnels, constructed through rock under
water, cost respectively $208.38 and $263 per lin. ft. The First Thames
Tunnel, driven by Brunel’s shield, cost $1661.66 per lin. ft. The Hudson
River and St. Clair River tunnels, excavated through soft ground by
means of shields and compressed air, cost respectively $305 and $315 per
lin. ft. The Blackwall double-track tunnel under the River Thames, which
is the largest tunnel ever built by the shield system, cost $600 per
lin. ft.
In making estimates of the cost of projected tunnel work based on the
cost of tunnels previously constructed through similar materials, it is
important to keep in mind the date and location of the work used as the
basis for calculations. For example, a tunnel excavated in Italy, where
labor is very cheap, will cost less than one excavated in America, where
labor is dear, all other conditions being the same. Other reasons for
variation in cost due to difference of date and location of construction
will suggest themselves, and should be taken into full consideration in
estimating the cost of the new work.
=Time.=--The time required to excavate a tunnel depends upon the
character of the material penetrated and upon the method of work
adopted. Tunnels driven through soft ground by hand require about the
same time to construct as tunnels driven through hard rock by the aid of
machinery. Tunnels can be driven through hard rock at about as great a
speed as through soft or fissured rock, chiefly because the work of
blasting is more efficient in hard rock, and because no time is required
in timbering. The following table shows the average rate of progress in
different parts of the tunnel excavation through both hard and soft
materials in feet per month:--
+---------------+--------------------+--------------------+-----------+
| QUALITY | HEADING. | EXCAVATION |ENLARGEMENT|
| OF SOIL. | | OF SHAFTS. |OF PROFILE.|
| +----------+---------+---------+----------+-----------+
| | By hand. | By | By hand.| By | By hand. |
| | | machine.| | machine. | |
+---------------+----------+---------+---------+----------+-----------+
|Very loose soil|16.7- 26.8| | 6.6-16.7| | 6.6- 16.7|
|Loose soil |33.4-100 | |16.7-33.4| | 16.7- 33.4|
|Soft rock |66.8 |233.8-334|33.4-66.8|66.8-132.6| 33.4- 50 |
|Hard rock |50 - 66.8|233.8-334|33.4-50 |66.8-132.6| 66.8-100 |
|Very hard rock |33.4 |233.8-334|16.7-33.4|66.8-132.6| 66.8-100 |
+---------------+----------+---------+---------+----------+-----------+
The following tables showing the average rate of progress have been
compiled from the actual records made in the tunnels named:
+-------------+-------------+--------+--------------+-------------+
| NAME OF | DIMENSIONS |MONTHLY | CHARACTER OF |OBSERVATIONS.|
| TUNNEL. | IN FEET. |PROGRESS| MATERIAL. | |
| | |IN FEET.| | |
+-------------+-------------+--------+--------------+-------------+
|Excavation of| | | | |
|headings by | | | | |
|hand: | | | | | |
| Mount Cenis |10 × 10 | 65.8 |Schist, |Bottom drift.|
| Sutro | 6.7 × 5.7 | 70.14 |Quartzose, |... |
| St. Gothard | 8.4 × 8.7 | 70.14 |Granite, |Top heading. |
| | | | | |
|Excavation of| | | | |
|headings by | | | | |
|machine: | | | | | |
| Mount Cenis |10 × 10 | 188.7 |Calcareous | |
| | | |schist, |Bottom drift.|
| Sutro | 8.15 × 10 | 227.45 |Quartzose, |... |
| St. Gothard | 8.4 × 8.7 | 339.45 |Granite, |Top heading. |
| Trari | 8 × 9.35| 167 |Gneiss, |Top heading. |
| Arlberg | 8.35 × 9.35| 474.2 |Mica schist, |Bottom drift.|
| Palisades |16 × 7 | 160 |Trap rock, |Top heading. |
| Busk |15 × 7 | 126 |Granite, |Top heading. |
| Cascade |16 × 8 | 180 |Basaltic rock,|Top heading. |
| Franklin |15 × 7 | 240 |... |Top heading. |
+-------------+-------------+--------+--------------+-------------+
The following table shows the monthly progress of completed tunnel in
feet excavated through rock:
+---------------+--------+----------+------------+
|NAME OF TUNNEL.|PROGRESS|MATERIAL. | METHOD. |
| |IN FEET.| | |
+---------------+--------+----------+------------+
|Cascade | 207 |Basalt, |Top heading.|
|Palisades | 186 |Trap rock,|Top heading.|
|Busk | 190 |Granite, |Top heading.|
|Tennessee Pass | 169.5 |Granite, |Top heading.|
+---------------+--------+----------+------------+
The average monthly progress in feet of excavating tunnels through
treacherous ground may be quite generally assumed to be for: (1) clay of
the first variety from 43.4 ft. to 60 ft.; for clay of the second
variety from 33.4 ft. to 43.4 ft.; for clay of the third variety from
23.3 ft. to 33.4 ft., and for quicksand from 30 ft. to 50 ft. The
monthly progress in feet made in sinking the shafts of the Hoosac and
Musconetcong tunnels in America was as follows:--
+---------------+------------+---------+--------+------------+
|NAME OF TUNNEL.| DIMENSIONS | DEPTH |PROGRESS|CHARACTER OF|
| | IN FEET. |IN FEET. |IN FEET.| MATERIAL. |
+---------------+------------+---------+--------+------------+
|Hoosac: | | | | |
| East shaft |15.4 × 27.7| 1035 | 21.7 |Mica schist.|
| West shaft | 8 × 16 | 267 | 16.7 |Gneiss. |
|Musconetcong: | | | | |
| Vertical shaft| 8.35 × 16.7| 113.5 | 100 |Loose rock. |
| Inclined shaft| 8.35 × 26 | 304. | 32 |Loose rock. |
+---------------+------------+---------+--------+------------+
The average monthly progress of sinking shafts in treacherous soils may
be assumed to be as follows: clay of first variety, 50 ft. to 75 ft;
clay of second variety, 36.75 to 50 ft; clay of third variety, 23.4 ft.
to 36.75 ft; quicksand, 16.7 ft. to 33.4 ft.
For the reason that the details change with the various conditions
encountered in every work, all the tunnel operations have been treated
in a general way, purposely avoiding to give any detail. Also the rate
of progress and items of cost of tunnels have been given in a broad
manner because they greatly vary in the different works. This
information, however, can be easily obtained by consulting the
Engineering Magazines, where are reported all the tunnel works of
America and Europe, and where are given so many details which are very
valuable to expert engineers in charge of similar works, but not to
students and people who are looking only for general knowledge.
INDEX
Accidents and Repairs in the Belgian Method, 152
Accidents in Tunnels:
After Construction, 308
Baltimore Belt Line, 165
Chattanooga Tunnel, 311
During Construction, 301
General Discussion, 301
Giovi Tunnel, 309
Repairing of, 304
Acetylene Gas Lighting, 334
Air Compressors, Description of, 87
Air Locks, 264-272
Air Pressure, 268
American Method:
General Description, 172
Excavation, 172
Strutting, 174
Hauling, 175
Arrangement of Drill Holes, 90
Artificial Ventilation, 327
Austrian Method of Tunneling:
Advantages and Disadvantages, 180
Excavation, 176
General Description, 176
Lining, 180
Strutting, 177
Average Progress in Tunnels, 342
Baltimore Belt Line Tunnel, General Description, 160
Barlow’s Shield, 242
Beach’s Shield, 246
Belgian Method:
Accidents and Repairs, 152
Advantages and Disadvantages, 152
Excavation, 145
General Description, 144
Lining, 148
Hauling, 150
Strutting, 146
Bench, 131
Bends, 268
Blackwall’s Tunnel Shield, 248
Blasting-cone, 33
Blickford Match, 31
Boston Subway:
General Descriptions, 203
Roof Shield, 251
Boulder Tunnel Relined, 315
Box-cars, 61
Box Strutting, 51
Brandt Drilling Machine, 28, 112
Brown, W. L., 269
Brunel’s Shield, 240
Caissons, 293
Canals and Pipe Lines, 86
Cascade Tunnel, 98
Center-cut, 91
Center Line:
Curvilinear Tunnels, 14
Determination of, 9
Rectilinear Tunnels, 9
Simplon Tunnel, 106
Submarine Tunnels, 265
Triangulation, 12
Transferred through Center Shafts, 13
Transferred through Side Shafts, 14
Value’s Device, 10
Centers:
For Arches, 68
English Method, 169
Ground Molds, 66
Italian Method, 184
Lagging, 71
Leading Frames, 67
Setting Up, 70
Striking, 71
Chattanooga Tunnel, Accident, 311
City and South London Railway Shield, 250
Classification of Tunnels, 42
Coal-gas Lighting, 333
Cofferdam Method of Tunneling, 281
Van Buren Street Tunnel, Chicago, 282
Collapse of Tunnels, 302
Compressed Air:
For Power, 87
For Ventilation, 330
Concrete Lining, 75
Fort George Tunnel, 139
Murray Hill Tunnel, 126
Cost of:
Double-track Tunnels, 340
Hauling, 338
Headings, 337
Hoisting, 338
Single-track Tunnel, 340
Submarine Tunnels, 341
Subways, 209-217
Tunnels, 336
Craven, Alfred, 39
Craven’s Sunflower, 39
Cross-section:
Dimensions of, 20
Form of, 18
Hudson River Tunnel Pennsylvania Railroad, 277
Crown-bar (see American Method).
Subways, 204-211
Croton Aqueduct Tunnel, 95
Culverts, 80
Detroit River Tunnel, 296
Diamond Drilling Machine, 27
Directing the Shield, 265
Drift, 37
Drift Method:
General Discussion, 102
Murray Hill Tunnel, 123
Simplon Tunnel, 103
Drilling Machines:
Brandt, 112
Ingersoll, 26
Drills:
Diamond, 27
Hand, 23
Mountings for, 25
Percussion, 24
Power, 24
Rotary, 27
Dumping Cars, 60
Electric Firing, 32
Electric Lighting, 335
English Method:
Advantages and Disadvantages, 171
Centers, 169
Excavation, 166
General Discussion, 166
Lining, 170
Strutting, 167
Enlargement of the Profile, 38
Entrances, 81
Erector, 272
Excavation:
American Method, 172
Arrangement of Drill Holes, 90
Austrian Method, 176
Belgian Method, 145
Center-cut, 91
Enlargement of Profile, 38
English Method, 166
Fort George Tunnel, 136
German Method, 155
Headings, 37, 91
Hudson River Tunnel of Pennsylvania Railroad, 273
Italian Method, 182
Murray Hill Tunnel, 124
Quicksand Method, 189
Pilot Method, 193
Shield and Compressed Air Method, 267
Simplon Tunnel, 110
Excavating Machines:
For Earth, 22
For Rock, 23
Explosions, 33
Dynamite, 30
Gunpowder, 28
Nitroglycerine, 29
Quantity of, 34
Storage of, 30
Failure of Tunnel Roof, 305
Forgie, James, 269
Fort George Tunnel, 135
Foundations for Lining, 76
Fox, Charles B., 103
Frame Strutting, 49
Fuses, 31
Geological Survey, 3
German Method:
Advantages and Disadvantages, 159
Excavation, 155
General Description, 155
Hauling, 158
Strutting, 156
Giovi Tunnel Accident, 309
Graveholz Tunnel, 98
Greathead’s Shield, 245
Hand Drills, 23
Harlem River Tunnel, 285
Hauling:
American Method, 175
Belgian Method, 150
Italian Method, 185
German Method, 158
Hudson River Tunnel of Pennsylvania Railroad, 278
Motive Power, 61
By Way of Entrances, 59
Simplon Tunnel, 111
By Way of Shafts, 62
Heading and Bench Method:
Fort George Tunnel, 135
General Discussion, 130
St. Gothard Tunnel, 1
Headings, 37, 91
Hewett, H. B., 269
History of Tunnels, xiii
Hoisting Machines:
General Discussion, 62
Elevators, 64
Horse Gins, 63
Windlass, 63
Hoosac Tunnel, 93
Hopkins, Stephen W., 135
Hudson River Tunnel of Pennsylvania Railroad, 269
Hydraulic Jacks, 260, 271
Hydraulic Rams, 271
Illumination:
Acetylene Gas, 334
Coal-gas, 333
Electric, 335
Hudson River Tunnel of Pennsylvania Railroad, 280
Lamps and Lanterns, 330
Inclination of Strata, 6
Ingersoll Drilling Machine, 26
Inverted Arch Lining, 77
Iron and Masonry Lining, 74
Iron Lining, 73, 261, 276
Iron Strutting, 55
Full Section, 56
Headings, 56
Shafts, 57
Italian Method:
Advantages and Disadvantages, 188
Excavation, 182
General Description, 182
Modifications, 186
Strutting, 183
Jacks, 260, 271
Joining the Caissons, 295
Lagging, 71
Lamps and Lanterns, 330
Lighting (see Illumination).
Lining:
Austrian Method, 180
Belgian Method, 148
Concrete, 126, 139
English Method, 170
Foundations, 76
General Observations, 78
German Method, 158
Hudson River Tunnel Pennsylvania Railroad, 276
Invert, 77
Iron, 73, 261, 276
Iron and Masonry, 74
Italian Method, 185
Masonry, 74
Quicksand Method, 191
Roof Arch, 77
Side Tunnels, 79, 83
Side Walls, 77
Subways, 207-213
Timber, 72
Thickness of Masonry, 78, 83
Little Tom Tunnel Relined, 321
Loose Soil (see Soft Ground).
Masonry (see Centers).
Masonry Culverts, 80
Masonry (see Lining).
Masonry Lining, 74
Masonry Niches, 81
McBean, Daniel, 285
Mechanical Installations for Tunnel Work, 84
Milwaukee Tunnel, 226
Mont Cenis Tunnel, 92
Monthly Progress of Tunnels, 342
Mullan Tunnel Relined, 319
Murray Hill Tunnel, 123
Natural Ventilation, 326
New York Rapid Transit Subway, 209
Niagara Falls Power Tunnel, 97
Niches, 81
Open Cut or Tunnel, 1
Open-cut Tunneling:
General Discussion, 195
Parallel Longitudinal Trenches, 197
Single Trench, 196
Single Narrow Trench, 197
Transverse Trenches, 200
Tunnels on the Surface, 200
Palisade Tunnel, 94
Pennsylvania Railroad Shield, 270
Percussion Drills, 24
Pilot Method of Tunneling, 192
Plank Centers, 69
Platform Cars, 59
Plenum Method of Ventilation, 329
Pneumatic Caissons, 287
Polar Protractor, 39
Portals, 81
Power Drills, 24
Power Plants:
Air Compressors, 87
Canals and Pipe Lines, 86
Cascade Tunnel, 98
Croton Aqueduct Tunnel, 95
General Description, 84
Graveholz Tunnel, 98
Hoosac Tunnel, 93
Hudson River Tunnel Pennsylvania Railroad, 279
Mont Cenis Tunnel, 92
Murray Hill Tunnel, 128
Niagara Falls Power Tunnel, 97
Palisades Tunnel, 94
Receivers, 89
Reservoirs, 86
Simplon Tunnel, 117
Sonnstein Tunnel, 99
St. Clair River Tunnel, 99
St. Gothard Tunnel, 133
Steam, 85
Strickler Tunnel, 96
Turbines, 86
Prelini’s Shield, 251
Presence of Water, 7
Prevention of Collapse, 303
Progress in Sinking Shafts, 343
Progress of Excavation, 342
Progress of the Work, 342
Progress in Simplon Tunnel, 122
Quantity of Air for Ventilation, 331
Quicksand Tunneling:
General Discussion, 188
Removing the Seepage Water, 191
Quantity of Timber in Strutting, 54
Receivers, 89
Relining Tunnels, 315
Boulder Tunnel, 315
Little Tom Tunnel, 321
Mullan Tunnel, 319
Repairing of Accidents in Tunnels, 308
Reservoirs, 86
Roof Arch Lining, 77
Roof Shield for Boston Subway, 251
Roof of Caissons, 287-291
Rotary Drills, 27
Ryder, B. H., 296
Saccardo System of Ventilation, 330
Saunders, W. L., 88
Seepage Water, 191
Seine River Tunnel, 293
Setting up Centers, 70
Severn Tunnel, 221
Shafts, Description of, 40
Shaler, Ira A., 142
Shield and Compressed Air Method, 263
Shield Construction:
Diaphragm, 256
Cellular Division, 255
Dimensions of Shields, 259
Front End, 254
General Form, 252
Rear End, 257
Shell, 253
Shield Method:
Barlow Shield, 242
Beach’s Shield, 245
Blackwall Tunnel Shield, 248
Brunel Shield, 240
City and South London Railway Shield, 250
Greathead’s Shield, 245
History, 238
Prelini’s Shield, 251
St. Clair River Tunnel Shield, 247
Side Shafts, 41
Side Tunnels Lining, 79
Side Walls Lining, 77
Simplon Tunnel, 103
Soils Encountered in Tunnels, 3
Sonnstein Tunnel, 99
Stations of Subways, 207-216
St. Clair River Tunnel Shield, 247
St. Gothard Tunnel, 132
Steam Power Plant, 85
Stratification of the Soils, 6
Strickler Tunnel, 96
Striking the Centers, 71
Strutting:
American Method, 174
Austrian Method, 177
Belgian Method, 146
Dimensions of Timber, 54
English Method, 167
Fort George Tunnel, 137
Full Section, 51
German Method, 156
Headings, 48
Italian Method, 183
Murray Hill Tunnel, 125
Pilot Method, 193
Quantity of Timber, 54
Shafts, 52
Iron: Full Section, 56
Headings, 56
Shafts, 57
Submarine Tunneling:
Cofferdam Method, 281
Compressed Air Method, 225
Detroit River Tunnel, 296
General Discussion, 218
Harlem River Tunnel, 285
Hudson River Tunnel Pennsylvania Railroad, 269
Lining, 261
Milwaukee Water-Works Tunnel, 226
Pneumatic Caisson Method, 284
Seine River Tunnel, 293
Severn Tunnel, 221
Shield and Compressed Air Method, 263
Shield System, 238
Sinking and Joining Sections Built on Land, 293
Van Buren Street Tunnel, 282
Subways:
Boston, 203
Cost of, 209-217
Cross-sections, 204-211
General Discussion, 195-202
Lining, 207-213
New York Rapid Transit Railway, 209
Stations, 207-216
Sutro, Adolph, 330
Tamping, 32
Thickness of Lining Masonry, 78, 83
Thomson Excavating Machine, 22
Timber Lining, 72
Timbering (see Strutting).
Tremies, 299
Trussed Centers, 70
Tunnel or Open Cut, 1
Tunnels:
Baltimore Belt Line, 160
Classification of, 42
Fort George, 135
Murray Hill, 123
Simplon, 103
St. Gothard, 132
Hard Rock, 84
Drift Method, 102
Comparison of Methods, 141
Heading and Bench Method, 152
Heading Method, 130
Soft Ground:
American Method, 172
Austrian Method, 176
Belgian Method, 144
English Method, 166
German Method, 155
Italian Method, 182
Pilot Method, 192
Quicksand Method, 188
Submarine:
Detroit River Tunnel, 296
Harlem River Tunnel, 285
Hudson River Tunnel of Pennsylvania Railroad, 269
Milwaukee Tunnel, 226
Seine River Tunnel, 293
Severn Tunnel, 221
Van Buren Street Tunnel, Chicago, 282
Under City Streets:
General Description, 201
Boston Subway, 203
Turbines, 86
Vacuum Method of Ventilation, 328
Value, Beverley R., 10
Van Buren Street Tunnel, 282
Ventilation, 325
Artificial, 327
Compressed Air, 330
Natural, 326
Plenum Method, 329
Quantity of Air, 331
Saccardo’s System, 330
Simplon Tunnel, 120
Vacuum Method, 328
Vernon-Harcourt, L. F., 221
Working Platforms, 286
Wyman, Erastus, 293
Transcriber’s Notes
Inconsistencies in spelling and hyphenation have been retained except
as mentioned below; non-English words and phrases have not been
corrected except as listed below. The (minor) differences between the
Table of Contents and the chapter headings have not been rectified.
Page 36/132: Figs. 14 and 61 are identical.
Page 92/93, Sommeilier: possibly an error for Sommeiller.
Page 134, Soummelier: possibly an error for Sommeiller.
Page 174, Footnote 11: presumably Fig. 92, indicating the planes of
the sections, is from the same publication.
Page 176, Austrian method: Dresden and Leipsic, and the Oberau Tunnel,
are (and were in 1837) in Saxony, Germany (or Prussia).
Page 179, The short transverse beam _c_, Fig. 90: there is no short
transverse beam visible in Fig. 90, nor is it clear which other figure
might be intended; there is therefore no hyperlink to the
illustration.
Page 279, Stirtling boiler: possibly an error for Stirling boiler.
Pages 337 and 342, Arlberg: possibly an error for Aarlberg.
Page 340, Wartha: possibly an error for Martha; Mertin: possibly an
error for Merten.
Changes made
Footnotes, tables and illustrations have been moved out of text
paragraphs; some table data have been re-arranged for better
legibility. In some of the formulas brackets have been added for
clarity.
Several obvious minor typographical and punctuation errors have been
corrected silently.
Page 12, footnote 3: Chapter IX. changed to Chapter X.
Page 35: on page 155 changed to on page 135
Page 36: on page 34 changed to on page 35
Page 53: The lagging plank may be ... changed to The lagging planks
may be ...
Page 113: (1) changed to (_I_) (2×)
Page 117: ... and it in this clearing ... changed to ... and it is in
this clearing ...
Page 130: as indicated by Fig. 58 changed to as indicated by Fig. 61
Page 136: as indicated in the Fig. 63 changed to as indicated in the
Fig. 65
Page 146: as shown by Fig. 63 changed to as shown by Fig. 69
Page 149: underpining changed to underpinning
Page 150: Since the roof arch rests for some time ... changed to Since
the roof arch rests are for some time ...; as shown by Fig. 66 changed
to as shown by Fig. 72
Page 172: illustrated in Fig. 12 changed to illustrated in Fig. 11
Page 175: page 127 changed to page 123
Page 179: as at _b_, Fig. 90 changed to as at _b_, Fig. 97
Page 204: The third type of section is shown by Fig. 116 changed to
The third type of section is shown by Fig. 117
Page 218: Malinö changed to Malmö
Page 261: Fig. 118 shows the hydraulic jacks changed to Fig. 136 shows
the hydraulic jacks
Page 282: shown by Fig. 119 changed to shown by Fig. 141
Page 297: towed down to the tunnel side changed to towed down to the
tunnel site
Page 315: shown in Figs. 141 and 142 changed to shown in Figs. 159 and
160
Page 324: shown by Fig. 148 changed to shown by Fig. 166
Page 338: given on page 50 changed to given on page 55
Page 340: Scloss Matrei changed to Schloss Matrei
Page 341: _Time._ changed to =Time.=
Page 348, entry Ryder: page number 296 added; Sounstein changed to
Sonnstein (2×).