CHAPTER XV.

SPECIAL TREACHEROUS GROUND METHOD; ITALIAN METHOD; QUICKSAND TUNNELING;

PILOT METHOD.

ITALIAN METHOD.

The Italian method of tunneling was first employed in constructing the

Cristina tunnel on the Foggia & Benevento R.R. in Italy. This tunnel

penetrated a laminated clay of the most treacherous character, and after

various other soft-ground methods of tunneling had been tried and had

failed, Mr. Procke, the engineer, devised and used successfully the

method which is now known as the Italian or Cristina method. The Italian

method is essentially a treacherous soil method. It consists in

excavating the bottom half of the section by means of several successive

drifts, and building the invert and side walls; the space is then

refilled and the upper half of the section is excavated, and the

remainder of the side walls and the roof arch are built; finally, the

earth filling in the lower half of the section is re-excavated and the

tunnel completed. The method is an expensive one, but it has proved

remarkably successful in treacherous soils such as those of the Apennine

Mountains, in which some of the most notable Italian tunnels are

located. It is, moreover, a single-track tunnel method, since any soil

which is so treacherous as to warrant its use is too treacherous to

permit an opening to be excavated of sufficient size for a double-track

railway, except by the use of shields.

=Excavation.=--The plan of excavation in the Italian method is shown by

the diagram Fig. 99. Work is begun by driving the center bottom heading

No. 1, and this is widened by taking out parts No. 2. Finally part No. 3

is removed, and the lower half of the section is open. As soon as the

invert and side wall masonry has been built in this excavation, parts

No. 2 are filled in again with earth. The excavation of the center top

heading No. 4 is then begun, and is enlarged by removing the earth of

part No. 5. The faces of this last part are inclined so as to reduce

their tendency to slide, and to permit of a greater number of radial

struts to be placed. Next, parts No. 6 are excavated, and when this is

done the entire section, except for the thin strip No. 7, has been

opened. At the ends of part No. 7 narrow trenches are sunk to reach the

tops of the side walls already constructed in the lower half of the

section. The masonry is then completed for the upper half of the

section, and part No. 7 and the filling in parts No. 2 are removed. The

various drifts and headings and the parts excavated to enlarge them are

seldom excavated more than from 6 ft. to 10 ft. ahead of the lining.

[Illustration: FIG. 99.--Diagram Showing Sequence of Excavation in

Italian Method of Tunneling.]

[Illustration: FIG. 100.--Sketch Showing Strutting for Lower Part of

Section.]

=Strutting.=--The bottom center drift, which is first driven, is

strutted by means of frames consisting of side posts resting on floor

blocks and carrying a cap-piece. Poling-boards are placed around the

walls, stretching from one frame to the next. As soon as the invert is

sufficiently completed to permit it, the side posts of the strutting

frames are replaced by short struts resting on the invert masonry as

shown by Fig. 100. To permit the old side posts to be removed and the

new shorter ones to be inserted, the cap-piece of the frame is

temporarily supported by inclined props arranged as shown by Fig. 103.

When parts No. 2 are excavated the roof is strutted by inserting the

transverse caps _a_, Fig. 100, the outer ends of which are carried by

the system of struts _b_, _c_, _d_, and _e_. The longitudinal

poling-boards supporting the ceiling and walls are held in place by the

cap _a_ and the side timber _e_. To stiffen the frames longitudinally of

the tunnel, horizontal longitudinal struts are inserted between them.

The excavation of the upper half of the tunnel section is strutted as in

the Belgian method, with radial struts carrying longitudinal roof bars

and transverse poling-boards. On account of the enormous pressures

developed by the treacherous soils in which only is the Italian method

employed, the radial strutting frames and crown bars must be of great

strength, while the successive frames must be placed at frequent

intervals, usually not more than 3 ft. After the masonry side walls have

been built in the lower part of the excavation, longitudinal planks are

laid against the side posts of the center bottom drift frames, to form

an enclosure for the filling-in of parts No. 2. The object of this

filling is principally to prevent the squeezing-in of the side walls.

[Illustration: FIGS. 101 and 101A.--Sketches Showing Construction of

Centers, Italian Method.]

=Centers.=--Owing to the great pressures to be resisted in the

treacherous soils in which the Italian method is used, the construction

of the centers has to be very strong and rigid. Figs. 101 and 101A show

two common types of center construction used with this method. The

construction shown in Fig. 101 is a strong one where only pressures

normal to the axis of the tunnel have to be withstood, but it is likely

to twist under pressures parallel to the axis of the tunnel. In the

construction shown by Fig. 101A, special provision is made to resist

pressures normal to the plane of the center or twisting pressures, by

the strength of the transverse bracing extending horizontally across the

center.

[Illustration: FIG. 102.--Sketch Showing Invert and Foundation Masonry,

Italian Method.]

=Masonry.=--The construction of the masonry lining begins with the

invert, as indicated by Fig. 100, and is carried up to the roof of parts

No. 2, as already indicated, and is then discontinued until the upper

parts Nos. 4, 5, and 6 are excavated. The next step is to sink side

trenches at the ends of part No. 7, which reach to the top of the

completed side walls. This operation leaves the way clear to finish the

side walls and to construct the roof arch in the ordinary manner of such

work in tunneling. Since this method of tunneling is used only in very

soft ground which yields under load, the usual practice is to construct

the invert and side walls on a continuous foundation course of concrete

as indicated by Fig. 102. The lining is usually built in successive

rings, and the usual precautions are taken with respect to filling in

the voids behind the lining. The thickness of the lining is based upon

the figures for laminated clay of the third variety given in Table II.

=Hauling.=--The system of hauling adopted with this method of tunneling

is very simple, since the excavation of the various parts is driven only

from 6 ft. to 10 ft. ahead, and the work progresses slowly to allow for

the construction of the heavy strutting required. To take away the

material from the center bottom drift, narrow-gauge tracks carried by

cross-beams between the side posts above the floor line are employed.

This same narrow-gauge line is employed to take away a portion of parts

No. 2, the remaining portion being left and used for the refilling after

the bottom portion of the lining has been built, as previously

described. The upper half of the section being excavated, as in the

Belgian method, the system of hauling with inclined planes to the tunnel

floor below, which is a characteristic of that method, may be employed.

It is the more usual practice, however, since the excavation is carried

so little a distance ahead and progresses so slowly, to handle the spoil

from the upper part of the section by wheelbarrows which dump it into

the cars running on the tunnel floor below. Hand labor is also used to

raise the construction materials used in building the upper section. The

tracks on the tunnel floor, besides extending to the front of the

advanced bottom center drift, have right and left switches to be

employed in removing the refilling in parts No. 2, the spoil from the

upper part of the section, and the material of part No. 7. Fig. 103 is a

longitudinal section showing the plan of excavation and strutting

adopted with the Italian method.

[Illustration: FIG. 103.--Sketch Showing Longitudinal Section of a

Tunnel under Construction, Italian Method.]

=Modifications.=--It often happens that the filling placed between the

side walls and the planking, which is practically the space comprised by

parts No. 2, is not sufficient to resist the inward pressure of the

walls, and they tip inward. In these cases a common expedient is to

substitute for the earth filling a temporary masonry arch sprung

between the side walls with its feet near the bottom of the walls, and

its crown just below the level of their tops, as shown by Fig. 107. This

construction was employed in the Stazza tunnel in Italy. In this tunnel

the excavation was begun by driving the center drift, No. 1, Fig. 104,

and immediately strutting it as shown by Fig. 105. The other parts, Nos.

2 and 3, completing the lower portion of the section, were then taken

out and strutted. While part No. 2 was being excavated at the bottom,

and the center part of the invert built, the longitudinal crown bars

carrying the roof of the excavation were carried temporarily by the

inclined props shown by Fig. 106. After completing the invert and the

side walls to a height of 2 or 3 ft., a thick masonry arch was sprung

between the side walls, as shown in transverse section by Fig. 107, and

in longitudinal section by Fig. 106. This arch braced the side walls

against tipping inward, and carried short struts to support the crown

bars. The haunches of the arch were also filled in with rammed earth.

The upper half of the section was excavated, strutted, and lined as in

the standard Italian method previously described. When the lining was

completed, the arch inserted between the side walls was broken down and

removed.

[Illustration: FIG. 104.--Sketch Showing Sequence of Excavation, Stazza

Tunnel.]

[Illustration: FIG. 105.--Sketch Showing Method of Strutting First

Drift, Stazza Tunnel.]

[Illustration: FIGS. 106 and 107.--Sketches Showing Temporary Strutting

Arch Construction, Stazza Tunnel.]

=Advantages and Disadvantages.=--The great advantage claimed for the

Italian method of tunneling is that it is built in two separate parts,

each of which is separately excavated, strutted, and lined, and thus can

be employed successfully in very treacherous soils. Its chief

disadvantage is its excessive cost, which limits its use to tunnels

through treacherous soils where other methods of timbering cannot be

used.

QUICKSAND TUNNELING.

When an underground stream of water passes with force through a bed of

sand it produces the phenomenon known as quicksand. This phenomenon is

due to the fineness of the particles of sand and to the force of the

water, and its activity is directly proportional to them. When sand is

confined it furnishes a good foundation bed, since it is practically

incompressible. To work successfully in quicksand, therefore, it is

necessary to drain it and to confine the particles of sand so that they

cannot flow away with the water. This observation suggests the mode of

procedure adopted in excavating tunnels through quicksand, which is to

drain the tunnel section by opening a gallery at its bottom to collect

and carry away the water, and to prevent the movement or flowing of the

sand by strutting the sides of the excavation with a tight planking.

The sand having to be drained and confined as described, the ordinary

methods of soft-ground tunneling must be employed, with the following

modifications:

(1) The first work to be performed is to open a bottom gallery to drain

the tunnel. This gallery should be lined with boards laid close and

braced sufficiently by interior frames to prevent distortion of the

lining. The interstices or seams between the lining boards should be

packed with straw so as to permit the percolation of water and yet

prevent the movement of the sand.

(2) As fast as the excavation progresses its walls should be strutted

by planks laid close, and held in position by interior framework; the

seams between the plank should be packed with straw.

(3) The masonry lining should be built in successive rings, and the work

so arranged that the water seeping in at the sides and roof is collected

and removed from the tunnel immediately.

=Excavation.=--The best and most commonly employed method of driving

tunnels through quicksand is a modification of the Belgian method. At

first sight it may appear a hazardous work to support the roof arch, as

is the characteristic of this method, on the unexcavated soil below,

when this soil is quicksand, but if the sand is well confined and

drained the risk is really not very great. Next to the Belgian method

the German method is perhaps the best for tunneling quicksand. In these

comparisons the shield system of tunneling is for the time being left

out of consideration. This method will be described in succeeding

chapters. Whenever any of the systems of tunneling previously described

are employed, the first task is always to open a drainage gallery at the

bottom of the section.

Assuming the Belgian method is to be the one adopted, the first work is

to drive a center bottom drift, the floor of which is at the level of

the extrados of the invert. This drift is immediately strutted by

successive transverse frames made up of a sill, side posts, and a cap

which support a close plank strutting or lining, with its joints packed

with straw. Between the side posts of each cross-frame, at about the

height of the intrados of the invert, a cross-beam is placed; and on

these cross-beams a plank flooring is laid, which divides the drift

horizontally into two sections, as shown by Fig. 108; the lower section

forming a covered drain for the seepage water, and the upper providing a

passageway for workmen and cars. The bottom drift is driven as far ahead

as practicable, in order to drain the sand for as great a distance in

advance of the work as possible. After the construction of the bottom

drainage drift the excavation proper is begun, as it ordinarily is in

the Belgian method by driving a top center heading, as shown by Fig.

108. This heading is deepened and widened after the manner usual to the

Belgian method, until the top of the section is open down to the

springing lines of the roof arch. To collect the seepage water from the

center top heading it is provided with a center bottom drain constructed

like the drain in the bottom drift, as shown by Fig. 108. When the top

heading is deepened to the level of the springing lines of the roof

arch, its bottom drain is reconstructed at the new level, and serves to

drain the full top section opened for the construction of the roof arch.

This top drain is usually constructed to empty into the drain in the

bottom drift.

[Illustration: FIG. 108.--Sketch Showing Preliminary Drainage Galleries,

Quicksand Method.]

[Illustration: FIG. 109.--Sketch Showing Construction of Roof Strutting,

Quicksand Method.]

=Strutting.=--The method of strutting the bottom drift has already been

described. For the remainder of the excavation the regular Belgian

method of radial roof strutting-frames is employed, as shown by Fig.

109. Contrary to what might be expected, the number of radial struts

required is not usually greater than would be used in many other soils

besides quicksand. Single-track railway tunnels have been constructed

through quicksand in several instances where the number of radial props

required on each side of the center did not exceed four or five. It is

necessary, however, to place the poling-boards very close together, and

to pack the joints between them to prevent the inflow of the fine sand.

In strutting the lower part of the section it is also necessary to

support the sides with tight planking. This is usually held in place by

longitudinal bars braced by short struts against the inclined props

employed to carry the roof arch when the material on which they

originally rested is removed. This side strutting is shown at the right

hand of Fig. 110.

[Illustration: FIG. 110.--Sketch Showing Construction of Masonry Lining,

Quicksand Method.]

=Masonry.=--As soon as the upper part of the section has been opened the

roof arch is built with its feet resting on planks laid on the

unexcavated material below. This arch is built exactly as in the regular

Belgian method previously described, using the same forms of centers and

the same methods throughout, except that the poling-boards of the

strutting are usually left remaining above the arch masonry. To prevent

the possibility of water percolating through the arch masonry, many

engineers also advise the plastering of the extrados of the arch with a

layer of cement mortar. This plastering is designed to lead the water

along the haunches of the arch and down behind the side walls. In

constructing the masonry below the roof arch the invert is built first,

contrary to the regular Belgian method, and the side walls are carried

up on each side from the invert masonry. Seepage holes are left in the

invert masonry, and also in the side walls just above the intrados of

the invert. At the center of the invert a culvert or drain is

constructed, as shown by Fig. 110, inside the invert masonry. This

culvert is commonly made with an elliptical section with its major axis

horizontal, and having openings at frequent intervals at its top. The

thickness of the lining masonry required in quicksand is shown by Table

II.

=Removing the Seepage Water.=--After the tunnel is completed the water

which seeps in through the weep-holes left in the masonry passes out of

the tunnel, following the direction of the descending grades. During

construction, however, special means will have to be provided for

removing the water from the excavation, their character depending upon

the method of excavation and upon the grades of the tunnel bottom. When

the excavation is carried on from the entrances only, unless the tunnel

has a descending grade from the center toward each end, the tunnel floor

in one heading will be below the level of the entrance, or, in other

words, the descending grade will be toward the point where work is going

on, while at the opposite entrance the grade will be descending from the

work. In the latter case the removal of the seepage water is easily

accomplished by means of a drainage channel along the bottom of the

excavation. In the former case the water which drains toward the front

is collected in a sump, and if there is not too great a difference in

level between this sump and the entrance, a siphon may be used to remove

it. Where the siphon cannot be used, pumps are installed to remove the

water. When the tunnel is excavated by shafts the condition of one high

and one low front, as compared with the level at the shaft, is had at

each shaft. Generally, therefore, a sump is constructed at the bottom of

the shaft; the culvert from the high front drains directly to the shaft

sump, while the water from the low-front sump is either siphoned or

pumped to the shaft sump. From the shaft sump the water is forced up the

shaft to the surface by pumps.

THE PILOT METHOD.

The pilot system of tunneling has been successfully employed in

constructing soft-ground sewer tunnels in America by the firm of

Anderson & Barr, which controls the patents. The most important work on

which the system has been employed is the main relief sewer tunnel built

in Brooklyn, N.Y., in 1892. This work comprised 800 ft. of circular

tunnel 15 ft. in diameter, 4400 ft. 14 ft. in diameter, 3200 ft. 12 ft.

in diameter, and 1000 ft. 10 ft. in diameter, or 9400 ft. of tunnel

altogether. The method of construction by the pilot system is as

follows:

Shafts large enough for the proper conveyance of materials from and into

the tunnel are sunk at such places on the line of work as are most

convenient for the purpose. From these shafts a small tunnel,

technically a pilot, about 6 ft. in diameter, composed of rolled boiler

iron plates riveted to light angle irons on four sides, perforated for

bolts, and bent to the required radius of the pilot, is built into the

central part of the excavation on the axis of the tunnel. This pilot is

generally kept about 30 ft. in advance of the completed excavation, as

shown by Fig. 111. The material around the exterior of the pilot is then

excavated, using the pilot as a support for braces which radiate from it

and secure in position the plates of the outside shell which holds the

sand, gravel, or other material in place until the concentric rings of

brick masonry are built. Ribs of T-iron bent to the radius of the

interior of the brick work, and supported by the braces radiating from

the pilot, are used as centering supports for the masonry. On these ribs

narrow lagging-boards are laid as the construction of the arch proceeds,

the braces holding the shell plates and the superincumbent mass being

removed as the masonry progresses. The key bricks of the arches are

placed in position on ingeniously contrived key-boards, about 12 ins. in

width, which are fitted into rabbeted lagging-boards one after another

as the key bricks are laid in place. After the masonry has been in place

at least twenty-four hours, allowing the cement mortar time to set, the

braces, ribs, and lagging which support it are removed. In the meantime

the excavation, bracing, pilot, and exterior shell have been carried

forward, preparing the way for more masonry. The top plates of the shell

are first placed in position, the material being excavated in advance

and supported by light poling-boards; then the side-plates are butted to

the top and the adjoining side-plates. In the pilot the plates are

united continuously around the perimeter of the circle, while in the

exterior shell the plates are used for about one-third of the perimeter

on top, unless treacherous material is encountered, when the plates are

continued down to the springing lines of the arch. This iron lining is

left in place. The bottom is excavated so as to conform to the exterior

lines of the masonry. The excavation follows so closely to the outer

lines of the normal section of the tunnel that very little loss occurs,

even in bad material; and there is no loss where sufficient bond exists

in the material to hold it in place until the poling-boards are in

position.

[Illustration: ~Bracing.~

~Arch Construction.~

~Longitudinal Section.~

FIG. 111.--Sketch Showing Pilot Method of Tunneling.]

In the Brooklyn sewer tunnel work, previously mentioned, the pilot was

built of steel plates ³⁄₈ in. thick, 12 ins. wide, and 37¹⁄₂ ins. long,

rolled to a radius of 3 ft. Steel angles 4 × 4¹⁄₂ ins. were riveted

along all four sides of each plate, and the plates were bolted together

by ³⁄₄-in. machine-bolts. The plates weighed 136 lbs. each, and six of

them were required to make one complete ring 6 ft. in diameter. In

bolting them together, iron shims were placed between the horizontal

joints to form a footing for the wooden braces for the shell, which

radiate from the pilot. The shell plates of the 15-ft. section of the

tunnel were of No. 10 steel 12 ins. wide and 37 ins. long, with steel

angles 2¹⁄₂ × 2¹⁄₂ × ³⁄₈ ins., riveted around the edges the same as for

the pilot, and put together with ⁵⁄₈-in. bolts. These plates weighed 61

lbs. each, and eighteen of them were required to make one complete ring

15 ft. in diameter. The plates for the 12-ft. section were No. 12 steel

12 ins. wide with 2 × 2 × ¹⁄₄-in. angles. Seventeen plates were required

to make a complete ring.

Tunneling: A Practical Treatise. · 第 15 / 18 章