Part III.--Disposition of Material.

Loading the Material for Transportation.--The material excavated by a

steam shovel is loaded on cars, wagons or carts. On railway work it is

usually loaded on dump or flat cars. On other construction work small

dump cars are most generally used, and sometimes wagons or carts.

[Illustration: Fig. 66.]

[Illustration: Fig. 67.]

[Illustration: Fig. 68.]

[Illustration: Fig. 69.]

[Illustration: Fig. 73.]

Standard gage railway dump cars, Figs. 66 and 67, have nearly gone out

of use. They were replaced by the center ridge flat car, Figs. 68 and

69, and it in turn has been replaced by the ordinary flat car. Dump

cars are of two styles, dumping either by tipping, Fig. 66, or by means

of a hinged sideboard opening on an inclined floor, Fig. 67. Both are

heavy, clumsy, costly and can be used for scarcely any other purpose,

often standing idle from six to eight months of the year. They dump

dry materials very rapidly, but are often slow in discharging damp,

tenacious materials, especially in the hinged sideboard car, whose

floor slope is often not sufficient to permit the material to slip

out quickly, and the material must then be pushed out, thus causing

much delay. The greatest objection to these cars is that they can be

used for scarcely any other purpose, on most railways for no other

purpose; and there is not sufficient work for them to justify keeping

the necessary number on hand for the ordinary work in this line. They

were replaced by the center ridge car, Figs. 68 and 69, as above noted,

which is merely an ordinary flat car with a timber 4 by 6 ins. bolted

on its floor along the center line, serving as a guide for a plow, Fig.

70, drawn over it by the locomotive, thereby unloading the material.

The ridge timber is slightly pointed at both ends to assist in guiding

the plow onto the car as it passes from one car to another. The top

edges of the ridge are sometimes protected by angle irons, as in Fig.

71, and the points by cast iron caps, Fig. 72. By taking off the

center ridge this car can readily be restored to general service after

completing the steam shovel work. The center dump car, shown in Fig.

73, is used only for gravel ballasting where the material is wanted

delivered between the rails.

[Illustration: Fig. 70.]

[Illustration: Fig. 71.]

[Illustration: Fig. 72.]

The brakes are placed on one side of the car, as shown in Figs. 74 and

75. When boulders, loose rock, etc., are to be unloaded, the brake

staff is set in a socket, Fig. 76, and taken out before the plow is

started. This avoids bending or breaking the staff in case any stone

should be wedged between it and the moving plow. Sometimes the socket

is used with the brake at its ordinary place at the end of the car; in

such a case it must always be taken out before the plow reaches it.

The plow, Fig. 70, is built of heavy plate and angle iron, strongly

braced, and headed by a cast steel point, to which the cable is

attached. The sides are curved outward at the bottom, working under the

material and pushing it aside as the plow is drawn along, and held down

on the car by the weight of the material and the partly downward pull

of the cable at its point. Short pieces of old rails and other scrap

iron are also often placed on the plow to help hold it down on the car

when very tenacious materials are to be unloaded. The groove extending

along the center line on the bottom fits over the ridge timber on the

car, and forms the guide by which its movement is directed. Small

stones, protruding bolts, slivered ridge timbers and other obstructions

in the groove of the plow sometimes wedge the point fast, and before

the engine can be stopped, the plow is turned up on its point, and

falling to either side, tumbles off the car. The weight and elasticity

of the cable is often sufficient to draw the plow half a car-length

after the engine has been stopped, and it is often difficult to stop

the plow quick enough to prevent upsetting when obstructions occur,

although the speed is usually only two to three miles per hour. The

unloading nearly always occurs on trestles or embankments, and when

the plow is thrown off the car, its replacement often requires much

time and labor, sometimes even making the services of the wrecking car

necessary. This difficulty is very likely to occur when unloading on

curves, where one side of the point of the groove presses against the

ridge timber. This plow unloads the material equally on both sides of

the car, as it is wanted in filling trestles, raising embankments,

tracks, etc.; but it cannot be used to advantage where the material is

wanted on one side only, as in widening embankments for double track,

side tracks, yards, station grounds, etc.

[Illustration: Fig. 74.]

[Illustration: Fig. 75.]

[Illustration: Fig. 76.]

The many objections to the center ridge car are almost entirely avoided

by the use of the Barnhart plow, Fig. 77, employing the ordinary flat

car without any preparations except changing the brake staffs to one

side or placing them in sockets at their ordinary places and inserting

short stakes in the stake pockets, permitting the immediate use of the

car for general service if necessity should so require. This plow is

also built of heavy plate and angle irons, strongly braced, and headed

by a cast steel point to which the cable is attached; it is preceded

and followed by guiding sleds attached to it by adjustable hinges and

guided over the car by the stakes in the stake pockets, which are

indicated by the dotted lines. The usual speed at which it is drawn

over the car is about four miles per hour, but in loose gravel it can

safely be drawn at a speed of six miles per hour. On straight track

it is scarcely ever thrown off the car unless carelessly handled,

and it works equally well on curves when the usual means are adopted

to maintain a tangential pull of the cable, as will be subsequently

described. Two styles of the Barnhart plow are in use: One unloading

on both sides of the car, and called the center plow, Fig. 77; and the

other unloading on one side only and called the side plow, Fig. 78.

[Illustration: Fig. 77.]

[Illustration: Fig. 78.]

[Illustration: Fig. 79.]

On all but very small pieces of work the cars should be provided with

hinged drop sideboards, Fig. 79, using either of the arrangements shown

in Figs. 80 and 81, which will enable them to carry 12 to 14 cu. yds.

instead of 6 or 7. The side boards are made in two pieces on each side

of the car, Fig. 79. Those shown in Fig. 80 are used for both center

and side plows; they can be quickly dropped by a man walking along the

train, after arriving at the unloading place and striking the hook A an

upward blow with a light hammer. The boards are hooked up again after

the cars have been returned to the steam shovel pit. The side boards

shown in Fig. 81 are used where the side plow only is used. Here the

board on one side only (the unloading side) is hinged (or chained),

and dropped by pulling out the pin B, thus leaving that side of the

car entirely unobstructed for unloading the material; the board on the

other side of the car is bolted to the stake pocket and is not moved.

[Illustration: Fig. 80.]

[Illustration: Fig. 81.]

The cars should also be provided with sheet iron aprons, Figs. 82 and

83, extending from the end of one car onto the floor of the next, to

prevent the material from falling on the track between the cars as the

plow is drawn over them, and delaying the departure of the train until

it can be shoveled out. These aprons are made either in two pieces,

Fig. 82, or in one piece only, Fig. 83. The former are more easily

handled, and permit access to the coupling of the cars without lifting

the apron. Very little material drops on the track when the aprons and

the center plow are used. The single apron is used mostly in connection

with the side plow.

The number of cars and engines required for each steam shovel to keep

it in nearly constant operation depends upon the nature of the material

excavated, the length of haul, and the density of other traffic

upon the main line. This number must be determined by accompanying

circumstances in each case; ordinarily, however, it averages about as

given in Table III.:

TABLE III.

In the steam (--------------On the road up to-------------)

(shovel pit.) 10 miles. 25 miles. 50 miles. 75 miles.

Loco. Cars. Loco. Cars. Loco. Cars. Loco. Cars. Loco. Cars.

Loose gravel 1 30 1 30 2 60 3 90 4 120

Dry clay 1 22 1 22 2 40 - - - -

Damp stiff

clay 1 18 1 18 2 36 - - - -

Hardpan, cemented

gravel, etc.,

loosened

by explosives 1 16 1 16 2 32 - - - -

The length of haul usually ranges from 2 to 15 miles; it seldom

exceeds 25 miles for any material except gravel ballast,

where hauls of 75 miles are frequent, and sometimes reach 200

miles.

[Illustration: Fig. 82.]

[Illustration: Fig. 83.]

[Illustration: Fig. 84.]

[Illustration: Fig. 85.]

On hauls exceeding 25 miles the full number of cars and engines

required can seldom be obtained, and the output of the

steam shovel is correspondingly decreased. The delay in returning

empty cars due to detentions from other trains is the

great trouble most keenly felt in steam shovel work on railways

in operation. The so-called "mud train" is generally considered

an outcast, and is usually the last train to receive the dispatcher's

attention for an order to the road. These delays are

daily occurrences, and it is quite an exceptional case when the

machine is amply supplied with empty cars. The record of

most steam shovels on such work is therefore a rather poor one,

when the machine really made a good showing for the crippled

condition of its car service. Some of these delays can be

avoided or shortened by stationing a telegraph operator at the

outgoing end of the pit, and on all but very small pieces of work

his wages will be many times balanced by the time gained in

keeping the whole plant moving, by obtaining train orders

quicker, and remaining constantly informed of the whereabouts

of the construction and other trains, and regulating the work in

the pit accordingly.

For general construction work where the excavated material

is not loaded on standard gage railway cars, small dump cars,

Figs. 84 and 85, are generally used. They are more economical

than wagons or carts, which are employed only in special

cases, mostly in cities, where the material must be hauled some

distance over several intersecting streets, and where a track will

not be allowed; or for very small jobs with a long haul which

would not justify building a track.

The gage of these tracks is usually 2-1/2 or 3 ft., sometimes

2 ft. or even 1-1/2 ft. only; the latter gages are not often used,

and the 3-ft. gage is usually preferred.

The rails most generally used weigh 20 lbs. per yd. Although

these tracks are only temporary their construction should

be fairly substantial; but they are often built in an exceedingly

careless and insecure manner, causing a great waste of power

in pulling the cars over them, and resulting in frequent delays,

due to derailments. The grade is usually arranged so that the

loaded cars will run downhill by gravity, and only the empty

cars need be drawn back to the pit. On small work, horses or

mules are used to pull the cars, but on large jobs small locomotives

are employed. Small dump cars vary in capacity from

1 to 3 cu. yds., the latter size being most generally used. The

side dump car, Fig. 84, dumps on either side. The rotary dump

car, Fig. 85, unloads on either side or end; the box can be

turned around horizontally, revolving about a vertical pin in a

turntable on the frame; they are used mostly in dumping off the

end of a fill.

In making fills it is nearly always the best plan to build a

temporary trestle of round pieces of beech, cottonwood or other

cheap trees, old bridge or building timber, or other second-class

lumber, and then filling in with the side dump cars. By adopting

this plan the unloading will progress much more rapidly

than by dumping from the end of a fill, where only one car at a

time can be unloaded. These trestles are inexpensive, and the

saving in labor and time in making the fill will amply repay

their cost.

[Illustration: Fig. 86.]

[Illustration: Fig. 87.]

[Illustration: Fig. 88.]

[Illustration: Fig. 89.]

Unloading the Material.--On railways the unloading is seldom

done by slow and expensive hand labor with the shovel;

sometimes dump cars are employed, but in most cases flat cars

and the plow are used. The trains consist of 10 to 30 cars. The

car carrying the plow is attached to the rear of the train at the

nearest side track to the unloading place, if it is not over 10

miles from the steam shovel pit this car is generally carried

back and forth to avoid an extra stop to couple it on the train

at the side track. One end of a steel wire cable is then hooked

to the plow and the other end (which is attached to an ordinary

car coupling link) coupled to a car or the engine. Usually this

cable is about 400 ft. long and extends over 12 cars. The

brakes on these cars are then set up tight and the engine started

with the forward cars, Fig. 86. In very tenacious or partially

frozen material the rear cars are sometimes pulled along by the

plow; the wheels are then blocked with pieces of wood or with

stones; sometimes it is even necessary to chain a few of these

cars to the track to prevent the rear lot of cars from moving.

After the plow has been started, it is drawn along slowly until

it arrives on the last car, Fig. 87. The engine is then stopped

and backed up a few feet to permit the cable to be thrown on

one side of the track, Fig. 88. The train is then backed up

again and coupled to the unloaded cars, when four to six men

throw the cable on the next loaded cars, Fig. 89, coupling its

forward end to a car or to the engine if the cable is long

enough. The operation is then repeated until all but the car

next to the engine is unloaded; this car carries the plow and is

the first car to be unloaded by the next train. The ends of the

cable are then detached from engine and plow, thrown to one

side of the track, and left there for the next train to pick up

and use in the same manner.

[Illustration: Fig. 90.]

[Illustration: Fig. 91.]

When filling a trestle the cable cannot be thrown on one

side, as described, but must be unhooked from the plow (the rear

lot of cars being left standing on the trestle), dragged across

the trestle, and there thrown to one side. The forward lot of

cars is then backed up until its rear car is opposite the rear end

of the cable, when it is loaded, the train backed up, coupled and

unloaded, as before described. After unloading the train the

cable must again be dragged beyond the trestle, and there

thrown to one side of the track and left for the next train. The

time required for unloading varies from 10 to 30 minutes, depending

upon the nature of the material and the number of

cars, and averages about 20 minutes, doing as much work

in that time as 20 men can do in a day.

When unloading on curves the operations are delayed by

the necessity of using snatch blocks on the cars to insure a nearly

tangential pull of the cable and avoid pulling the plow off the

car. These blocks are applied as shown in Fig. 90, and at A,

Fig. 91. They are hooked to long chains extending over the

car and fastened to the bolster or arch bar of the truck. The

number of snatch blocks required depends upon the degree of

the curve and the length of the cable; generally four to six

blocks, one to every third car, are enough. As the plow approaches

one of these blocks it must be stopped, block and

chain removed and transferred forward for use at that end of

the train. The other operations of unloading are the same as

when on straight track. The time required in unloading on

curves varies from 20 minutes to an hour, and averages about

40 minutes, doing as much work in that time as 20 men can do

in a day.

The steel wire cables used vary from 1 in. to 1-1/2 ins. diameter.

The former are used for unloading loose gravel and

sandy material; they are light and easily handled, but cannot

bear much jerking. The most usual size is 1-1/4 ins. diameter.

Heavier cables require too many men (six to eight) to load them

on the car preparatory to starting the plow.

One of the heaviest locomotives on the road (preferably one

of the consolidation type) should be used for drawing the plow

over the cars. These engines are generally able to keep the

plow moving with a strong steady pull, avoiding the necessity

of taking a run to start the plow, and all injurious jerking of

the cable, which frequently breaks it. For tenacious materials

and where the haul is not more than 25 miles, it is often good

policy to keep one heavy engine at this work, the other engines

merely hauling the trains; this can generally be arranged so that

no more engines are used than if each engine were to unload

its own train. Sometimes two light engines are used for this

purpose, but they can seldom move in perfect unison and more

or less jerking is the result. Unfortunately the engines for the

"mud trains" are not always in the best working order; they

are mostly those which are about to go into the shops for turning

down the tires or for general repairs, and are not in fit

condition for general traffic, but still considered good enough

for this service. Expensive delays due to badly working engines

are frequently the result.

The locomotive in the steam shovel pit should always be

equipped with a steam or air driver brake to assist in quickly

stopping the cars at exactly the right place when setting them

for loading by the steam shovel. For the same reason the

brakeman should be allowed to use short sticks in the brake-wheels

to obtain a greater leverage in turning them.

Both engine and train crews should be changed as little as

possible and they should retain their respective trains in the pit

on the road or at the dump. Most of the men dislike the "mud

train" service, but some (especially the older ones) are glad to

get a steady job with a full night's rest, and these are the men

to be chosen. They take an interest in the success of the work,

and soon acquire an expertness in handling cars, plows, etc.,

that makes them worth twice as much as the inexperienced or

unwilling ones. The wages of these men should be equalized

to average the same as the men on the road in other service,

otherwise dissatisfaction and indifference are sure to result.

[Illustration: Fig. 92.]

The machine shown in Fig. 92 has lately come into use for

pulling the plow over the cars to unload them. This is merely

a double cylinder (10 by 12 ins.) reversible hoisting engine,

resting on a heavy cast iron bedplate attached to the floor of a

box car. Steam is supplied to the engine from the locomotive

of the train, which is coupled to this car when the unloading is

to begin. With this machine there is no injurious jerking of

the cable, and consequently very little breakages or delays, and

heavy loads of 15 cu. yds. of tenacious material are readily

plowed off the cars in a more satisfactory manner than can be

done by any one or two locomotives. Blocking the wheels or

chaining cars to the track need not be resorted to; the cars cannot

move, for the machine pulls the plow toward itself and the

strain is resisted by the cars between them. If it is desired to

scatter small quantities of material along the track, as it is often

wanted in surfacing or raising track, both plow and train are

moved in the same direction at the same or varying speeds, as

may be necessary to unload the required amount of material.

If a large quantity of material is wanted within a short distance,

as usually happens on washouts, train and plow are moved in

opposite directions. By moving them in this manner at the

same speed, a whole train can be unloaded at any desired spot.

Where two locomotives must be used to pull the plow over the

cars, the use of this machine will dispense with one of them,

and do the work in half the time. On large jobs it should not

be missing. The cable is wound around the drum, A, Fig. 92,

and must be long enough to extend over the whole length of

the train. A steel wire cable 1-1/8 ins. diameter is generally

used; but for loose gravel a 1 in. cable is amply strong enough.

The steam shovel can be operated continuously throughout

the year in all kinds of weather, though operations are often suspended

in extremely cold weather. When working in cold

weather the face of the bank sometimes freezes during the night

to the depth of 3 to 6 ins., but this crust is easily broken in the

morning by a few small charges of powder, and then the material

can be excavated as easily as at any other season.

[Illustration: Harris & Carter

Spreader.

Fig. 93.

Fig. 94.]

In freezing weather the floors of the cars should be sprinkled

with brine just before loading; the brine is kept in barrels at the

head of the machine, and one man using an ordinary garden

sprinkling can is detailed for the work. This prevents the material

from freezing to the floor of the car for three to four

hours, and allows it to slip off readily when the plow is put in

operation. No train should be left standing over night without

unloading. The brine will not prevent freezing for this length

of time, and to unload one car of the frozen stuff requires a day's

labor of four to six men.

Distributing the Material After Unloading.--In widening

embankments for side tracks, double track, yard and station

grounds, etc., the material is unloaded, as described above, forming

a ridge on both sides of the track if unloaded with the

center plow, or on one side of the track only if unloaded with the

side plow. This material is sometimes leveled off by hand, a

very slow and expensive job, but generally it is done with a leveler

or spreader, Figs. 93 to 96.

[Illustration: Edson

Spreader.

Fig. 95.

Fig. 96.]

In the Harris & Carter spreader, Figs. 93 and 94, the car

body is cut away between the trucks to receive the two wings

which level or spread the material. One or both wings can be

used, and they can be raised and lowered to adjust them to any

height of new embankment wanted. They will spread the material

for a distance of 3 ft. from the rail. When shipping the

spreader over the road the wings are drawn up by a hand windlass,

revolving about hinges fixed to the braces under the floor

of the car, as shown in Fig. 94. In this position the clearance

is the same as that of an ordinary passenger car.

The Edson spreader, Figs. 95 and 96, has only one wing,

attached to an ordinary flat car, and arranged to raise and

lower to adjust it to any height of new embankment wanted.

The wheel, A, bears against the head of the rail, forming a brace

where one is most needed, and greatly assists in preventing a

derailment when hard or tenacious materials are suddenly encountered.

The wing, braces, windlass, etc., are so constructed

that they can be readily removed from the car, thereby restoring

it to general service on completion of the work in hand. This

spreader is used mostly in connection with the side plow; it will

level the material for a distance of 15 ft. from the rail, wide

enough to permit laying a side track from which the embankment

can be further widened. Only one side at a time can be

widened with this spreader. If it is desired to widen the embankment

on both sides of the track, one side is completed first;

the cars and spreader are then turned around on the nearest

turntable or Y-track, and the other side widened by drawing

the spreader in the opposite direction. If the cars are not provided

with aprons they need not be turned around. This

spreader is generally arranged to cut about 6 ins. below the

bottom of the ties of the main track, thereby forming the subgrade

for the side track, and maintaining proper drainage of

the main track. The apron, B, is bolted on the spreader, and

serves to remove any loose material which may fall on the

track between the rail and the ends of the ties. When shipping

the spreader over the road, Fig. 96, it is drawn up by a hand

windlass revolving about hinges on the side sill of the car and

folded down on it; in this position it will clear anything that

other cars can pass.

The cars of both styles of spreaders are loaded with old rails,

frogs, scrap iron, etc., to hold them down and prevent derailments

when hard or tenacious materials are suddenly encountered.

Loads of five to ten tons are generally sufficient, though

loads up to 15 tons are sometimes required.

Spreaders are usually drawn at a speed of six to eight miles

per hour; in loose gravel the speed often reaches 10 miles per

hour. They will level off a ridge a mile in length in six to

ten minutes, doing as much work in that time as 100 men can do

in a day.

The spreader is usually stationed in the nearest side track to

the unloading place. Frequently it can be hauled between this

track and the dump without raising it, or raising it only partially

to clear depot platforms, switch stands and other obstructions

and thereby avoid the necessity of folding it down on the

car while passing between these points.

Ordinarily the spreading is done by the last train before the

close of the day. In cold weather or on short dumps it must

be done oftener; either to prevent freezing, or to make room for

the unloading material which would otherwise pile up too high

for easy spreading, or be liable to roll back on the track and

obstruct it for the next train. In using the spreader it is coupled

to the rear of the car carrying the plow, and after the train has

been unloaded it is pulled over the length of the ridge of material

unloaded from its own and preceding trains, as shown

in Figs. 97 and 98.