LABOR.

Key: cm = centimeter, in = inch, m = meter

+-----------+------+------+------+------+-------+-------+----

| | | | | | |Total |

| DIAMETER | | | Cubic| Cost |Back- |cost, |

| OF PIPE: | Width|Depth |meters| of |filling|exca- |

| | of | | per |exca- |and re-|vation |

+------+----+trench| |linear|vation|moving |back- | Continues

| | | | | meter| per |surplus|filling|

| cm | in | m | m | |lin. m|Pesos |etc. |

| | | | | | | |Pesos |

+------+----+------+------+------+------+-------+-------+----

| 10 | 4 | 0.55 | 0.90 | 0.50 | 0.60 | 0.18 | 0.78 |

| 15 | 6 | 0.60 | 1.00 | 0.60 | 0.72 | 0.22 | 0.94 |

| 30.5 | 12 | 0.65 | 1.20 | 0.78 | 0.94 | 0.29 | 1.23 |

| 38 | 15 | 0.70 | 1.30 | 0.91 | 1.10 | 0.34 | 1.44 | Below

| 45.7 | 18 | 0.80 | 1.40 | 1.12 | 1.34 | 0.41 | 1.75 |

| 61 | 24 | 1.00 | 1.50 | 1.50 | 1.80 | 0.55 | 2.35 |

| 76 | 30 | 1.10 | 1.60 | 1.76 | 2.11 | 0.65 | 2.76 |

+------+----+------+------+------+------+-------+-------+----

--+----------------+--------+--------+--------+

| HAULING PER | Cost | Total | Total |

| | of |hauling |excava- |

| LINEAR METER | laying | and |tion and|

| | per |laying |laying, |

+--------+-------+ linear | per |labor, |

| Haul- | Misc. | meter |linear |complete|

| ing | Pesos | | meter | |

| Pesos | | Pesos | Pesos | Pesos |

--+--------+-------+--------+--------+--------+

| 0.0275 | 0.005 | 0.06 | 0.0925 | 0.8725 |

| 0.45 | 0.005 | 0.825 | 0.1325 | 1.0725 |

| 0.18 | 0.0075| 0.1475 | 0.335 | 1.565 |

| 0.2725 | 0.01 | 0.19 | 0.4775 | 1.9125 |

| 0.2725 | 0.01 | 0.245 | 0.5275 | 2.2775 |

| 0.825 | 0.08 | 0.41 | 1.315 | 3.665 |

| 0.83 | 0.10 | 0.53 | 1.46 | 4.22 |

--+--------+-------+--------+--------+--------+

NOTE.--The above costs of earthwork are based on the following rates and

percentages over the whole city:

Earth, per cubic meter | 0.35 pesos | 50%

Soft sillar | 0.75 " | 20%

Hard sillar | 1.50 " | 20%

Rock (chiefly conglomerate) | 4.00 " | 10%

ASCE 1193: The Water-Works and Sewerage of Monterrey, N. L., Mexico The 4th article from the June, 1911, Volume LXXII, Transactions of the American Society of Civil Engineers. Paper No. 1193, Feb. 1, 1911. · 第 30 / 48 题