CHAPTER XI.

STRENGTHENING OF RIVETED BRIDGES BY CENTRE GIRDERS.

The addition of distributing girders, described in the last chapter, as

a means of strengthening a bridge floor, while sufficient in many cases

so far as the cross-girders are concerned, does not in any appreciable

way assist the main girders. When for a two-line bridge, having outer

main girders only, this result also is desired, together with a more

complete relief of the floor structure, centre main girders may be used,

placed either above or below the cross-girders, on the centre line of

the bridge.

There are two principal ways in which such a girder may be brought into

use; the easier, but generally less economical, is by making a simple

attachment to the cross-girders, the old girder work still taking the

whole dead load. By this method the new girder does no work but carry

itself till the live load comes upon the bridge, and must be made very

stiff to take any sensible portion of the running load; the second

method is to make the connection adjustable, so that a part of the floor

weights may be imposed upon the new girder as an initial load. In doing

this the old outer girders will rise slightly, being relieved of stress,

and the cross-girders also lifted at the middle, whilst the new girder

is depressed as the load is brought upon it. With some part of the live

load a very considerable proportion of the total may in this way be

carried by a centre girder of moderate section. The whole question, by

either method, turns upon deflections; and it is in determining the

relative movements of the girders that the problem chiefly lies.

It is convenient first to determine the percentage of load relief to be

effected in the main girders, as to which it is to be observed that as

this relief (distributed) is induced by the upward reaction of the new

girder acting at the centre of the cross-girders, the stress relief of

these will, as a rule, greatly exceed that of the outside girders. For

the generality of cases, it may be taken that the relief suitable for

the outside girders will be satisfactory in its effects upon the

cross-girders, even though it is desired to reduce the stress in these

to a greater degree.

If, however, it be thought desirable to check this, it may be done by

considering a cross-girder subject to its dead and live loads acting

downwards, and to reactions at the centre and ends. At the centre the

reaction will be the load of which the two main girders are relieved on

a length equal to the pitch of the cross-girders, or as here given:--

_c_ × _t_ × P = reaction at centre (1)

_c_ being the percentage of relief; _t_ the total load per foot run of

the bridge; and P the pitch of cross-girders. The live loads carried by

the cross-girders are for this purpose taken at per foot run, as for the

main girders. With these data it will be easy to construct a diagram of

moments, making it evident whether the relief proposed for the main

girders will give a sufficient percentage of relief to the floor beams.

Granting that this proportion has been decided, and dealing first with

the case in which the centre girder is simply attached to the

cross-girders, and takes no dead load other than its own weight, then

the live load carried by the outside girders, and previously borne

wholly by them, will be reduced by the amount it is intended to transfer

to the centre girder, and will become

L{_l_} - (_c_ × L{_t_}) = live load on outer girders (2)

L{_l_} being the total live load, and L{_t_} the total dead and live

load carried by the bridge. From this the deflection of the outer

girders corresponding to this modified live load may be derived.

[Illustration: FIG. 70.]

It is next necessary to ascertain the vertical movement, commonly a

depression, of the cross-girders at the centre relative to their ends,

when subject to the running load only, and supported at the middle and

ends, the centre reaction being obtained as before indicated (1). This

movement will be the difference (if any) between the deflection on the

whole span of the cross-girder due to the live load, and the upward

flexure of the girder due to the centre reaction, considered as separate

effects. Stress values having been estimated for the two conditions,

these results may readily be deduced by simple flexure formulæ,

observing that while the curve of moments due to live load sufficiently

approximates to that for a distributed load to justify, for this, the

use of a distributed load formula as given in the chapter “Deflections,”

the flexure due to the centre reaction will be but 0·80 of that which

corresponds to the same stress for distributed loading. Or, the curve

assumed by the girder under live load may be plotted by a method to be

later explained.

The sum of the movements now determined--that is, the live-load

deflection of the outer girders, and depression, as is commonly the

case, of the cross-girders--will give the extreme depression (marked _m_

in Fig. 70), from the dead-load condition of the middle cross-girders,

when supported to the extent desired by a centre girder whose

proportions are not yet known, but which, carrying the required

percentage of the total load, must, subject to a reservation presently

stated, deflect only this amount. The unit stress in the flanges of the

new girder, governed by this flexure, will for a plate girder be

D × C × _m_

----------- = _f_, unit stress on gross section (3)

S^{2}

D and S being, as before (see “Deflections”), the depth and span

respectively in feet, C a constant, _m_ the deflection in inches, and

_f_ the stress per square inch on the gross section of flange.

The gross area A, of the flange, is given by

S × _c_ × L{_t_}

---------------- = gross area of flange (4)

8 × D × _f_

_c_ × L{_t_}, being, as in (2), the load transferred to and carried by

the centre girder.

The actual stress in the flanges will, of course, be greater by an

amount due to the girder’s own weight; but this does not affect the

question of relief. For any ordinary case the stress per square inch

will be low; but it will manifestly be useless to assume a greater

stress with a view to economy, as the effect of reducing the section

will simply be to make the girder too flexible, thus causing it to be

less effective than primarily intended. If, as is seldom the case, there

is freedom as to the depth of girder permissible, it is evident the unit

stress may be made a condition, and the depth deduced by a suitable

modification of formula (3); the relief desired being in this way

equally well assured. Indeed, in the rare instances in which any depth

may be adopted, this method is--contrary to the general rule--distinctly

economical, particularly if the girder may be placed below the

cross-girders, which simply rest upon it, without elaborate attachments.

[Illustration: FIG. 71.]

Considering now the second method of applying centre girders by which

the new girder is made initially to carry part of the dead load, by

adjustment, it will at once be recognised as a more complex matter. The

measure of relief by which the old girderwork shall benefit need not be

affected by the method of applying the centre girder, and may be decided

on the principles already considered. The outer girders carrying a

reduced load, when the bridge is fully loaded, and the cross-girders

being in part supported at their centres in the manner already

described, will give a resulting depression _m_ (see Fig. 71) of the

centre cross-girders, below the original dead-load position, of a

similar amount determined in the same way. This extreme depression

determines also the lowest position of the new centre girder, which may

be designed to carry the required percentage of the total bridge loads

with the maximum stress and depth, as conditions, leaving the initial

dead load and necessary adjustments to be ascertained. This is the

common case and will be here dealt with, it being assumed to avoid

ambiguity in description that the new girder lies above the

cross-girders.

The centre girder of fixed depth being then required to carry a definite

load at a definite flange stress, will deflect a definite amount at this

stress. If this deflection equalled the extreme depression _m_ of the

old girder work, no adjustment would be necessary, the centre girder

then carrying no initial dead load, as by the first method; but for

centre girders designed for economical flange stress the deflection will

in ordinary cases greatly exceed this, the depth generally being small,

and in order to ensure that the new girder shall do its full work, some

dead load must be put upon it. In the act of adjustment the

cross-girders must be lifted and the centre girder depressed, till the

joint movement equals the excess _s_ of the centre girder deflection

over _m_, when the new girder will carry the proper amount of initial

load, and upon further deflection under live load give the full measure

of relief. The amount of “lift” or upward flexure of the old girder

work, and the depression or “drop” of the new girder, during adjustment,

will depend upon relative stiffness, and may be ascertained as

follows:--

For unit reactions at the centre of the cross-girders the upward flexure

of these may be ascertained, as also the upward flexure of the two outer

girders when subject to forces of the same total amount (one-half to

each) applied at the cross-girder ends. The sum of these movements will

give the total lift of the centre cross-girders, when all are subject to

unit lifting forces; similarly, the depression of the centre girder for

unit loads applied at the cross-girders may be determined. There will

then be known the movements upwards and downwards of the old and new

work when being drawn together by unit forces applied as stated.

If

_l_ = lift due to unit loads,

_l{t}_ = total lift due to adjustment,

_d_ = drop due to unit loads,

_d{t}_ = total drop due to adjustment,

_s_ = deflection excess = gross adjustment,

there will then be

_d_

--------- × _s_ = _d{t}_,

_l_ + _d_

total drop of centre girder under adjustment,

_l_

--------- × _s_ = _l{t}_,

_l_ + _d_

total lift of centre cross girders under adjustment,

_d{t}_

------ × unit load =

_d_

initial load put upon centre girder at each cross-girder.

The rise of the two outer girders for upward forces together equal to

those depressing the centre girder may readily be deduced.

[Illustration: FIG. 72.]

[Illustration: FIG. 73.]

The act of adjustment may conveniently be effected by the arrangement

shown in Fig. 72, in which each cross-girder is hung up at its centre by

four bolts. At the middle of the centre girder the total amount to be

screwed up will be that corresponding to the deflection excess _s_, but

towards the ends this amount decreases, and may advantageously be

represented by a diagram as Fig. 73, in which, if _s_ represents to

scale the amount to be screwed up at a centre cross-girder, the

corresponding amounts for other girders may be read off direct. It will

be apparent that it must be necessary to place the centre girder at

such a height as to leave a space between the old and the new work

greater than the amount to be screwed up, this excess clearance being

ultimately filled by a packing.

The precautions to be observed in carrying out this kind of work, and

the practical methods of adjustment adopted by the author after some

little experience, may here be given.

Great care is necessary at the outset to ascertain the true spacing of

the cross-girders, to ensure that the bolt-holes in the bottom flange of

the centre girder shall come where desired. The fixing of the

cross-girder brackets also needs close attention to avoid after trouble,

the bolt-holes in the brackets being preferably drilled on the site

after fixing. It will, for masonry abutments, be necessary to fix

bedstones to receive the new centre girder, which, being carried out

quite possibly under adverse traffic conditions, will perhaps leave the

stones liable to settle slightly when the full load is carried. To

eliminate the bad effect of this upon the ultimate adjustment, and to

take up any initial set of the new girder work, which would be

prejudicial in the same way, it is desirable, the centre girder being in

place, to screw up the bolts temporarily and leave the work for a week

or two. To ensure regularity in the screwing up process, it is

convenient to prepare, for use at the bridge, a diagram somewhat similar

to Fig. 73, giving the amount by which the new and old work are to be

brought together at each cross-girder, with the number of turns for each

nut to effect this. With a man at each side of the girder, the whole

length is traversed, giving a half-turn to each nut; this is repeated as

often as necessary, and so managed as to bring all up proportionately to

the final requirement, keeping tally with chalk marks over each

cross-girder as a check. The preliminary screwing up should be conducted

with little less care than that adopted for the later adjustment, to

avoid damage to the old work. This later adjustment having in due course

been effected, it is then necessary to measure for packings to fill the

spaces remaining between the old cross-girders and the new centre

girder. These spaces should be callipered at each of the four corners,

care being taken to avoid after-confusion. The measurements ascertained

will, however, be too great for the finished packings, as an allowance

of not less than 1/10 inch (total), will commonly be wanted to cover

irregularities in the surfaces. The packings, having been prepared and

checked, may be slipped into place after slacking all the bolts a small

amount to permit this to be done, finally screwing up tight and securing

the nuts by split-pins, through holes drilled as the last operation.

As a check upon the calculations and adjustment, the “lift” of the outer

girders and cross-girders, and the “drop” of the centre girder may be

observed by levelling. For this purpose the author has used a staff of

inches divided into tenths, with which, and a good level, very accurate

readings may be taken for short distances.

No reference has been made to the effect of skew in a bridge on the

above methods, the explanation given applying rather to bridges square

on plan. The influence of skew on the load distribution will largely be

a matter of detailed calculation. The flexure of the girders may also be

sensibly affected, but may be arrived at with sufficient accuracy

without any great trouble. The chief effect of skew is to modify the

amount of screwing up during adjustment, which may be better understood

by reference to Fig. 74, and comparing it with Fig. 73, the adjustment

diagram for a square bridge.

To illustrate how these methods of strengthening work out, and compare

as to weights of centre girders required, the case has been assumed of a

wrought iron bridge of 60-feet span, having outer girders 5 feet deep,

of 39 square inches gross flange area; and cross-girders, at 8-feet

centres, 27-feet span, 1 foot 9 inches deep, with a gross flange area of

twenty square inches. The dead load and live load on either road are

each 1·75 tons per foot run.

The stress in the outer girders previous to the alteration being 6 tons

per square inch gross, it is desired to relieve this to the extent of 33

per cent. by a steel centre girder. In the table here given the

quantities given in italics are fixed as primary conditions:--

CENTRE STRENGTHENING GIRDERS FOR 60-FT. SPAN.

----------------------------+-----------+------------+------------

| Centre | Centre |

| Girder, | Girder, |Adjustments

---- | Stress | Depth | Unknown.

| Unknown. | Unknown. |

----------------------------+-----------+------------+------------

_Outer Girder._ | | |

| | |

Deflection under modified | | |

live load | ·42 in. | ·42 in. | ·42 in.

Lift of adjustment | _nil_ | _nil_ | ·153 „

| | |

_Cross Girders._ | | |

| | |

Depression under live load | | |

--modified conditions of | | |

support | ·13 in. | ·13 in. | ·13 „

Extreme depression (_m_) | ·55 „ | ·55 „ | ·55 „

Lift of adjustment (cross- | | |

girder only) | _nil_ | _nil_ | ·095 „

Total lift of adjustment | | |

(_l{t}_) | _nil_ | _nil_ | ·248 „

| | |

_Centre Girder._ | | |

| | |

Depth | _3·5 ft._ | 8·2 ft. |_3·5 ft._

Unit stress on gross section| | |

(ex girder’s weight) | 2·14 tons | _5·0 tons_ |_5·0 tons_

Total deflection (ex | | |

girder’s weight) | ·55 in. | ·55 in. |1·28 in.

Deflection excess (_s_) | _nil_ | _nil_ | ·73 „

Depression, or “drop” of | | |

adjustment (_d{t}_) | _nil_ | _nil_ | ·482 „

Gross area of flange |105 sq. in.|19·2 sq. in.|44·5 sq. in.

Weight | 20 tons | 10·4 tons |11·4 tons

Net flange stress (including| | |

girder’s weight) | 3·19 tons | 6·87 tons | 6·94 tons

----------------------------+-----------+------------+------------

Girders subject to distributed load are treated as having uniform

stress, but where this is not strictly the case, as in some light

girders, it will be necessary to take the fact into account. For centre

girders of wrought iron, and a unit stress on the gross section of 4

instead of 5 tons, the girder weights are between 9 and 10 per cent.

greater.

[Illustration: FIG. 74.]

In the above treatment of the application of centre strengthening

girders there is a source of error which should be touched upon. If,

under live load, the centre girder deflects more than the outer girders,

as it commonly will, there must be a want of uniformity in the behaviour

of the cross-girders, those near the abutments being more relieved than

the estimated amount of relief of those at the centre, which will have

less than that intended; but the reduction of stress in the

cross-girders will generally be so considerable that any such ambiguity

of excess or defect is commonly unimportant; the effect of this also

upon the main girders is much less than might be supposed, being, for

the third of the cases just given, about 2-1/2 per cent. excess for the

centre girder, and generally a much smaller error. With this

qualification, the method can, however, be regarded as approximate only.

It is possible to eliminate some part of the error by lifting the end

cross-girders during adjustment, a less amount than that given by the

diagrams, Figs. 73 and 74, taking care that the centre girder is

depressed its full amount by lifting the centre cross-girders a little

more; this refinement is hardly necessary, and unless controlled by

calculation cannot be depended upon for precise results.

Particulars are here given of five ordinary cases, comparing the

calculated and observed results of adjustment. The operation of

levelling was conducted by a quick-eyed and capable assistant, who was

not made acquainted with the results expected, in order to avoid any

sub-conscious tendency to match the calculated figures:--

EXAMPLES OF CENTRE GIRDER ADJUSTMENTS.

---------------------------------------+-----------+-----------------

-- |Calculated.| Observed.

---------------------------------------+-----------+-----------------

| in. | in.

| |

No. 1.--56-_Ft. Span._

| |

Depression of centre girder | ·82 | ·84

Lift of cross-girders at centre | ·23 | ·22

Lift of outer girders | ·20 |·10 and ·13

| |

No. 2.--57-_Ft. Span._

| |

Depression of centre girder | ·50 | ·50

Lift of cross-girders at centre | ·18 | ·20

Lift of outer girders | ·11 |·08 and ·10

| |

No. 3.--67-_Ft. Span._

| |

Depression of centre girder | ·70 | ·75

Lift of cross-girders at centre | ·15 | ·17

Lift of outer girders | ·10 | ·09

| |

No. 4.--68-_Ft. Span._

| |

Depression of centre girder | ·70 | ·65

Lift of cross-girders at centre | ·20 | ·18

Lift of outer girders | ·13 | ·14

| |

No. 5.--52-_Ft. and_ 28-_Ft. Spans continuous._

| |

|Long |Short|Long |Short

|Span.|Span.|Span.|Span.

---------------------------------------+-----+-----+-----+-----------

| in. | in. | in. | in.

Depression of centre girder | ·28 | .. | ·29 | ..

Lift of centre girder | .. | ·04 | .. | ·03

Lift of cross-girders (centre of spans)| ·17 | ·09 | ·15 | ·13

Lift of outer girders | ·08 | .. | ·08 | ..

Depression of outer girder | .. | ·01 | .. |negligible.

---------------------------------------+-----+-----+-----+-----------

The method of calculation adopted for these cases was not precisely that

given, though depending upon the same broad principles. The first cannot

be considered a good example. The last, having continuous girders, of

course needed special treatment.

Of about seventeen bridges strengthened in the manner described, the

effect generally was satisfactory, in reducing deflection and vibration;

but in two cases of small span, owing probably to settlement of

bedstones, the results were not so good.

From first to last the work of putting in a centre girder takes some

little time, owing to the slow progress generally made in fixing the

brackets, preparing packings, etc. The cost of a typical case was about

23 per cent. of the cost of a new superstructure, with a 30 per cent.

relief of stress.

[Illustration: FIG. 75.]

[Illustration: FIG. 76.]

A special case of strengthening by a centre girder, having considerable

interest, may be here referred to. The primary idea involved was not the

author’s. The bridge dealt with has already been noticed under “Bracing”

and a section, before alteration, shown in Fig. 26. The span being 85

feet, there was no room for a centre girder of sufficient depth above

the cross-girders and between the roads, nor was it considered

economical to place the girder wholly below the floor, because of the

costly staging this would have necessitated for erection purposes, the

height above ground level being very great. A girder was therefore

designed, having open latticing at an angle of 60 degrees, with a bottom

boom to be below the cross-girders, the top being as high above the

rails as could be permitted (see Figs. 75 and 76). A temporary boom was

arranged at the intersection of diagonals, the lower boom proper not

being fixed till the girder having been lifted into place, with the

diagonal members passing between the cross-girders, allowed this to be

done. The girder for some time carried itself from bearing to bearing,

with the temporary boom in tension, the deflection being then 2 inches.

The permanent boom was then put in place, and the girder restored as

nearly as was practicable to the camber it was intended to have when

complete, but without throwing, during the process, any improper loads

upon the old work.

The lower boom being finally riveted up, the cross-girders were made to

bear upon it by suitable packings. There were, in addition to the new

girder, two stiff frames between the old main girders, to which the new

was secured.

The girder was designed with the intention that under dead load only the

cross-girders should just rest, but throw no weight, upon the new work,

the latter assisting to carry live load only. The floor beams being of

small span, and securely riveted to the old girder tops, the centre

girder was required to deflect, under its share of live load, the same

amount as the old main girders under the remaining portion, the three

points of support of the cross-girders thus not altering their relative

levels. That this resulted was evident from the fact that, previous to

connecting the cross-frames to the centre-girder, the work being

otherwise complete, a space between the two of about 1/2 inch,

afterwards filled by a packing, showed no alteration, the closest

measurement failing to disclose any relative movement upon the passage

of live load. The reduction of vibration was, as might be expected, very

marked.

In the conduct of that class of strengthening work which has been dealt

with in this chapter, it is essential, in the author’s judgment, that

the man responsible for the detailed calculations and design should

himself see the operations of adjustment carried out, or delegate it

only to one equally familiar with the requirements.

Before dismissing the subject, it will be well to refer to a method of

approximately determining flexure curves, of occasional use in dealing

with centre girder or similar questions. The figure assumed is plotted

to an exaggerated scale, with which object the actual radius of

curvature at points along the girder’s length are first ascertained by

the formula

E × D

------- = R, radius of curvature in feet,

_f_ × 2

and the radius of curvature for the diagram by

12 × R × F^2 = _r_, radius for plotting, in inches (5)

E being the modulus of elasticity, D the girder’s depth in feet, _f_ the

mean of the extreme flange stresses per square inch of gross area, and F

the fraction indicating scale as 1/48, where 1/4 inch = 1 foot. The

curve, being plotted, shows by direct scaling the movement of any point

relative to its original position. Near the ends of the curve where the

radii may be of considerable length, the arcs may be drawn with the help

of template curves, or even set out as pieces of “straight.”

When the curve is laid down so that its chord equals the span to scale,

the method involves an error of excess in the resulting deflection or

droop which is as much as 7 per cent. when the mean radius for plotting

equals the span as drawn, or when the droop of curve approaches

one-eighth of the span. As the exaggeration of curvature is made less

pronounced, this error rapidly diminishes, till for a droop of about

one-sixteenth the percentage is one-fourth part of that above given.

This excess in the droop of curve may be amended by the following

expression:--

(droop^3 )

droop - (------- × 3·73) = corrected droop, or deflection.

(chord^2 )

For some purposes it may be preferable to amend the radii for plotting,

so that the curve, as laid down, shall be correct, which may be

effected by the formula here given, to be applied to each value of r, as

first ascertained:--

(chord^2 )

_r_ + (------- × ·0625) = corrected plotting radius.

( _r_ )

If, however, the length of curve is made equal to the span (the chord

then being less), and the radii for plotting as given by (5) are used,

the result will for most purposes be sufficiently precise, though there

will now be an error of a contrary kind, which, for a curve having a

droop of one-eighth, will be about 2 per cent. too little. A somewhat

similar method of setting out deflection curves is described by

Professor Fleeming Jenkin in the article “Bridges” of the “Encyclopædia

Britannica,” but without corrections.

A careful comparison of results by the above means, with those

calculated, shows that with good draughtsmanship they may be relied upon

for considerable accuracy. Equally applicable to girders of varying

depth and flange stress, they have also a limited use in cases of

continuity.

[Illustration: FIGS. 77 and 78.]

Figs. 77 and 78 illustrate the deflection and stress diagrams for the

cross-girders of the bridge supposed to have been strengthened by a

centre-girder, when under the influence of live load and a centre

reaction of a definite amount. As a matter of convenience, each radius

length has been halved, before correction, so that the resulting droop

of the curve is twice the true amount.